AL UDEID POWER PLANT GT5 Installation | Page 1 of 3 Report#: PROJ/14/GT5/12-034 Start Date: 17 Nov 2014

Day / Date: Sunday,28/12/2014 Weather: Sunny,windy Ambient condition: C Working Hours: 7.30 19.00hrs Prepared by: Raghuram Reviewed by: Afsal

Workforce: 1. Al-Dana-4 Equipment / Tools: 1. Phase E-Piping (Client Scope) by Powertech. 70% completed a) Excavation(Hand digging) 100%completed b) Gas pipe line 80%completed Fabrication 100%completed Radiography 100%completed Hydro test - Nitrogen purging - Air blow Sand Bedding & Back Filling -50%completed - Tie-in

c) Compressed air and service water & Deminlines 95%completed d) Drain lines To be started Current Work Activity Piping 1. Fabrication and erection of compressed air line(1) to ventilation and combustion filters. 2. Compressed air line Pre fabrication (Final spool from main header to turbine nozzle). 3. Sand Bedding. 4. Radiography. Status / % completed: 100%completed 100%completed 50%completed 100%completed Planned Work Activity (Monday). Piping. 1. Compressed air line erection .(Till turbine Nozzle.) 2. Installation of gas line final spool. 3. Hydro test (If RT result finds good)

Delays & Stoppage of Work Issues 1.

HSE Issues 1. Nil

Remarks: 1.

Photos 1. Please refer to next page.

\ Doc#: PROJ/14/GT5/12-034 AL UDEID POWER PLANT GT5 Installation | Page 2 of 3

Figure 1 Sand Bedding

Figure 2 Prefabrication of compressed air line final spool (From main header to turbine nozzle) Doc#: PROJ/14/GT5/12-034

AL UDEID POWER PLANT GT5 Installation | Page 3 of 3

Figure 3 All dropins (Compressed air, Demin , Service water)

Figure 3 Compressed air line(1) connection to Combustion air Filter Doc#: PROJ/14/GT5/12-034