3
PROGRESS REPORT As of September 22, 2011

PROGRESS REPORT As of September 22, 2011. I.Project StatusProject Status II.S-CurveS-Curve III.Revised Construction ScheduleRevised Construction Schedule

Embed Size (px)

Citation preview

Page 1: PROGRESS REPORT As of September 22, 2011. I.Project StatusProject Status II.S-CurveS-Curve III.Revised Construction ScheduleRevised Construction Schedule

PROGRESS REPORTAs of September 22, 2011

Page 2: PROGRESS REPORT As of September 22, 2011. I.Project StatusProject Status II.S-CurveS-Curve III.Revised Construction ScheduleRevised Construction Schedule

PRESENTATION OUTLINE

I. Project StatusII. S-CurveIII. Revised Construction ScheduleIV. Manpower ProfileV. Monthly ReportVI. Progress Photos:– Earthworks– Barge Pier Construction– Seawall Construction

Page 3: PROGRESS REPORT As of September 22, 2011. I.Project StatusProject Status II.S-CurveS-Curve III.Revised Construction ScheduleRevised Construction Schedule

-END- THANK YOU