26
Progress Report – 20 th November 2013

Progress Report – 20 th November 2013

  • Upload
    rian

  • View
    46

  • Download
    0

Embed Size (px)

DESCRIPTION

Progress Report – 20 th November 2013. OBJECTIVE To complete the fund raising for a community hydro scheme at Harlaw Reservoir and ‘make it happen’. Agenda. What‘s happened since June Our Finances Your Finances Provisional Schedule Questions Wine, juice and nibbles. - PowerPoint PPT Presentation

Citation preview

Page 1: Progress Report –  20 th  November  2013

Progress Report – 20th November 2013

Page 2: Progress Report –  20 th  November  2013

OBJECTIVE

To complete the fund raising for

a community hydro scheme at

Harlaw Reservoir and

‘make it happen’.

Page 3: Progress Report –  20 th  November  2013

AgendaWhat‘s happened since JuneOur FinancesYour FinancesProvisional ScheduleQuestionsWine, juice and nibbles

Page 4: Progress Report –  20 th  November  2013

What‘s happened since JuneExpanded team

5 members with substantial engineering and project experienceTechnical team meeting fortnightly

Meetings with CEC Flood Prevention / Panel Engineer Grid Connection offered and acceptedHydrology re-analysedVAT RegistrationDesign Contract AwardedPipe Liner Repaired

Page 5: Progress Report –  20 th  November  2013

Design Contract Awarded5 Designers Approached3 Quotations ReceivedPotential Designers Met the committeeUnanimous selection of Adrian Laycock Limited

Extensive experience with micro-hydro schemes, dams, canals, irrigation . . Both in Scotland and across the World

http://www.adrianlaycock.com/index.htm

Page 6: Progress Report –  20 th  November  2013
Page 7: Progress Report –  20 th  November  2013
Page 8: Progress Report –  20 th  November  2013
Page 9: Progress Report –  20 th  November  2013
Page 10: Progress Report –  20 th  November  2013
Page 11: Progress Report –  20 th  November  2013
Page 12: Progress Report –  20 th  November  2013
Page 13: Progress Report –  20 th  November  2013
Page 14: Progress Report –  20 th  November  2013
Page 15: Progress Report –  20 th  November  2013
Page 16: Progress Report –  20 th  November  2013

Another idyllic country scene

– or – potential for

another hydro scheme?

Page 17: Progress Report –  20 th  November  2013

The FinancesIncome

Capital (5 July 2013) £334,750Interest to date £271

£335,021Expenditure

SPN - Grid Connection £18,835Mark Sproule (Website) £600Launch Expenses (BVT) £1,375FCA Annual Fee £55

£20,865

Balance £314,156

Commitments

Adrian Laycock Limited £19,200 50% on appointment of contractor, 50% when turbine is operational

Page 18: Progress Report –  20 th  November  2013

Seed Enterprise Investment Scheme (SEIS)Harlaw Hydro Limited

SEIS is administered by the Small Companies Enterprise Centre (SCEC) in HM Revenue & Customs (HMRC)

The company must submit form SEIS1 to the SCEC The company cannot submit an SEIS1 until either:

it has been trading for at least four months orit has spent at least 70 per cent of the monies raised by the

relevant issue of sharesIf the SCEC accepts that the company, its activities, and the

shares all meet the requirements of the scheme, it will issue the company with a certificate to that effect, and will supply claim forms (SEIS3s) for the company to send to the investors so they can claim tax relief

The company issues SEIS3s to qualifying Investors.

Page 19: Progress Report –  20 th  November  2013

Seed Enterprise Investment Scheme (SEIS)The Investor

Using the SEIS3 supplied by the company the investor claims on their Self Assessment tax return for the tax year in which the shares were issued (i.e. 2013/2014)

Investors can claim relief up to five years after the 31 January following the tax year in which the investment was made.

Page 20: Progress Report –  20 th  November  2013

Enterprise Investment Scheme (EIS)Harlaw Hydro Limited

EIS is administered by the Small Companies Enterprise Centre (SCEC) in HM Revenue & Customs (HMRC)

The company must submit form EIS1 to the SCEC The company cannot submit an EIS1 until it has been

trading for at least four months (confirmed using form EIS2).

The company then has 2 years to submit the formIf the SCEC accepts that the company, its activities, and

the shares all meet the requirements of the scheme, it will issue the company with a certificate to that effect, and will supply claim forms (EIS3s)

The company issues EIS3s to qualifying Investors.

Page 21: Progress Report –  20 th  November  2013

Enterprise Investment Scheme (EIS)The Investor

Using the EIS3 supplied by the company the investor claims on their Self Assessment tax return for the tax year in which the shares were issued (i.e. 2013/2014)

Investors can claim relief up to five years after the 31 January following the tax year in which the investment was made.

Page 22: Progress Report –  20 th  November  2013

Who are our investors?241 investors in total:Average size of investment - £1,588Investments range from £250 to £10,000Most Common - £500 or £1000 Just over half from immediate Balerno area17% from surrounding area17% from wider Edinburgh Area14% anywhere else

Page 23: Progress Report –  20 th  November  2013

Where we LiveShareholders / Society Members

52%

13%

4%

13%

17%

BalernoCurrieJuniper GreenEdinburghOther

Page 24: Progress Report –  20 th  November  2013

What next?Apply to pre-accredit FiT (Feed in Tariff) for 67kw Design accepted by CECs Panel EngineerOrder Turbine / generator – December 2013Lease FormalisedSelect contractor January 2014Submit SEIS1 Spring 2014Start Build – Spring 20141st AGM – May/June 2014 Generate Electricity – Autumn 2014

Page 25: Progress Report –  20 th  November  2013
Page 26: Progress Report –  20 th  November  2013

QuestionsWine and ‘nibbles’