Dubai Police - PROGRESS

Dubai Police Forensic Lab26th Aug 2014

PROGRESS HIGHLIGHTS 1)STRUCTURE STRUCTURAL STEEL Wing D completed. STAIRCASES- Completed STAIRCASE/ LIFT CORE TOP SLABS- Completed2)EXTERNAL CLADDING WORKS STATUS

External Glazing works in progress

Completed 3526 / 3663 Nos (96.26 %) of glass panels as of 23 Aug 14

Number of glass panels installed during the week 91 Nos

Installation of frames , Alpolic Panels

Completed 838/ 857 Nos (97.78 % ) of frames as of 23 Aug 14

Completed 2416 / 2442 Nos (98.93% ) of brackets as of 23 Aug 14

Completed 922 / 1305 Nos (70.65 % ) of A.Panels as of 23 Aug 14PROGRESS HIGHLIGHTS 1)STRUCTURE STRUCTURAL STEEL STAIRCASES STAIRCASE/ LIFT CORE TOP SLABS2)EXTERNAL CLADDING WORKS STATUS3)MAIN BUILDING INTERNAL FINISHES WORKS STATUSMajor activities during the weekFire rated glazed partitions work continued.Media ceiling grid installation work in progress at 1st & 2nd floor.Wall & Floor tiling at Ground floor & First floor and Wing B & D of 2nd floor in progress.Marble flooring works continued in B wing Ground floor, First floor, 2nd floor and 3rd floor.Marble wall cladding works continued in the Ground floor, First floor & Second floor B wing.Lift installation work continued in wing B wing for lift no 7 & commenced for lift no 1 & 2.Space frame works continued.

Ground FloorWing- a: 22 rooms cleared by MEP for suspended ceiling grid installation. Floor & wall tiling works in wet areas in progress.

Wing- b: 27 rooms cleared by MEP for suspended ceiling grid installation. Marble flooring & cladding work in progress. Floor & wall tiling works in wet areas in progress. False ceiling grid installation in progress. Fire stop works is in progress.

Wing- c: 36 rooms cleared by MEP for suspended ceiling grid installation. Floor & wall tiling works in wet areas in progress. Grouting for wall and floor tile in progress. Glass Fixing in progress. Fire stop works is in progress.

Wing- d: 18 rooms cleared for suspended ceiling grid installation. Primer coat & stucco application on walls in progress. Grouting for wall and floor tile in progress. Fire stop works is in progress. Plastering in progress for new electrical room.

GROUND FLOOR

FIRST FLOOR

First Floor

Wing- a: 30 rooms cleared by MEP for suspended ceiling grid installation. False ceiling grid installation in progress. Fire rated partition works in progress.

Wing- b: 47 rooms cleared by MEP for suspended ceiling grid installation. Dry wall partition wall works and MEP high level works are in progress. Marble flooring works in progress. Marble wall cladding works continued.Lift installation works in progress. Floor & wall tiling works in wet areas in progress. Primer & Stucco paint application in progress. Fire stop works is in progress. False ceiling grid installation in progress.

Wing- c: 50 rooms cleared by MEP for suspended ceiling grid installation. Media ceiling grid works in progress. Lift installation works in progress. Fire stop works is in progress.

Wing- d: 48 rooms cleared by MEP for suspended ceiling grid installation. Media ceiling grid works in progress. Floor & wall tiling works in wet areas in progress. Fire stop works is in progress. False ceiling grid installation in progress. Glass Fixing in progress.

SECOND FLOOR

Second Floor

Wing- a: 15 Rooms cleared for ceiling grid installation; MEP services in walls & ceilings are in progress. Primer coat & Stucco application in progress on dry wall partitions. Fire stop works is in progress. Fire rated partition works in progress.

Wing- b: 22 Rooms cleared for ceiling grid installation; Block work in progress in auditorium area. Drywall partition works in progress. Marble flooring works continued. Lift installation works in progress. Floor & wall tiling works in wet areas in progress. Fire stop works is in progress. Marble wall cladding works in progress.

Wing- c: 56 Rooms cleared for ceiling grid installation. Dry wall partition and MEP services in walls & ceilings are in Progress. Primer coat & Stucco application in progress on dry wall partitions. Media ceiling works in progress. Fire rated glazed partition works in progress. Lift installation works in progress.

Wing- d: 44 rooms cleared for suspended ceiling grid installation. Dry wall partition works in progress at wet area. False ceiling grid installation in progress. MEP services in walls & ceilings are in Progress. Fire stop works is in progress. Media ceiling grid works in progress. Primer & Stucco paint application in progress. Floor & wall tiling works in wet areas in progress.

THIRD FLOORThird FloorWing- a: 4 Rooms cleared for ceiling grid installation. MEP services on ceiling are in progress. Dry wall partition is in progress. Primer coat & stucco application in progress on dry wall partitions. Media ceiling works in progress. Fire stop works is in progress.

Wing- b: 24 Rooms cleared for ceiling grid installation. Block work, dry wall partition, MEP services in walls and ceilings are in progress. Lift installation works in progress. Fire stop works is in progress. Marble flooring works in progress.

Wing- c: 32 Rooms cleared for ceiling grid installation. Block work, Dry wall partition and MEP services in walls & ceilings are in Progress. Primer coat & Stucco application in progress on dry wall partitions. Media ceiling works in progress. Lift installation works in progress. Fire rated glazed partition works in progress. Fire stop works is in progress.

Wing- d: 26 Rooms cleared for ceiling grid installation. Dry wall partition works, MEP services in walls & ceilings are in progress. Primer coat & Stucco application in progress on dry wall partitions. Fire rated glazed partition works in progress. Fire stop works is in progress.

10PROGRESS HIGHLIGHTS 1)STRUCTURE STRUCTURAL STEEL STAIRCASES STAIRCASE/ LIFT CORE TOP SLABS2)EXTERNAL CLADDING WORKS STATUS3)

MAIN BUILDING INTERNAL FINISHES WORKS STATUS4)UTILITY BUILDINGS& EXTERNAL SERVICES STATUS

HV Area Building B

HV room : Transformer installation completed by DEWA.

Building BMEP works in Chiller Hall in progress.Remaining area cladding works in progress.External services in progress.

Building CMEP works in progress. External faade works in progress.Building DOn hold due to external road contractors work.Building EInternal plaster completed.Parapet wall plaster completed.Structural steel works completed.Building FTie Beam works in progress.

External services between Main building & utility buildings in progress.

Excavation of boundary wall in progress in wing c area.

External services manhole casting completed in between building E and wing D & between building B and C.

PROGRESS HIGHLIGHTS 1)STRUCTURE STRUCTURAL STEEL STAIRCASES STAIRCASE/ LIFT CORE TOP SLABS

2)EXTERNAL CLADDING WORKS STATUS

3)

MAIN BUILDING INTERNAL FINISHES WORKS STATUS4)UTILITY BUILDINGS& EXTERNAL SERVICES STATUS5)PROGRESS SUMMARY /SNAP SHOT

PROGRESS SNAPSHOTActivitiesGround floorFirst floorSecond floorThird floorRoof FloorInternal finishesabcdabcdabcdabcdabcdScreed(Dry Area)100%100%100%100%100%100%100%100%100%91%100%100%85%100%100%100%30%-30%-Screed(Wet Area)100%100%100%100%100%100%100%100%100%100%100%100%-90%100%100%Block work100%100%100%100%100%100%100%100%100%85%100%100%91%100%100%100%Internal Plastering100%100%100%100%100%100%100%100%100%90%100%100%90%89%100%100%Partitions in dry area except above glass partition

99%95%95%90%99%91%100%100%87%67%99%100%65%77%93%98%----Internal Paint70%60%70%61%58%30%66%65%56%39%28%52%40%25%45%46%Floor tiling(Wet Area)95%90%95%75%90%75%30%----Wall Tiling90%75%85%75%-65%-2%-50%-2%------Marble & Granite Works87%--72%---40%---------Media ceiling works30%---13%-20%32%--22%17%--7%-----Fire Rated Glazed Partition-95%100%-60%100%100%25%95%80%30%60%25%----Roof Canopy Steel Works----------------31%14%100%MEP worksHVAC96%93%93%93%93%92%89%90%88%80%75%89%79%71%64%79%39%92%36%32%Electrical95%94%94%90%92%84%86%84%76%69%75%72%59%53%61%57%12%Plumbing98%93%95%94%93%93%92%93%92%83%85%90%79%63%66%72%PROGRESS FOR THE WEEKActivitiesGround floorFirst floorSecond floorThird floorRoof FloorInternal finishesabcdabcdabcdabcdabcdScreed(Dry Area)----------------Screed(Wet Area)--------------Block work--------------Internal Plastering---------5%----Partitions in dry area except above glass partition

1%1%-6%1%1%1%4%4%----Internal Paint3%5%1%1%2%3%4%3%3%5%3%2%Floor tiling(Wet Area)10%----Wall Tiling10%-5%-2%-15%-2%------Marble & Granite Works10%----Media ceiling works----4%--3%------Fire rated Glazed partition---27%10%2%5%10%6%30%11%----Roof Canopy Steel Works----------------1%-MEP worksHVAC7%3%9%5%Electrical1%4%5%1%2%2%2%5%2%Plumbing4%1%MEDIA CEILING PROGRESS

Progress Summary

Engineering DelayStructural steel-(-335)AV system Nomination-(-262)Glazed partitions-(-308)Shooting range-(-305)20Progress Summary

KEY ISSUES FOR COMING WEEKSl.NoAREAS OF CONCERN / CRITICAL ISSUESAction ByProgress in the last weekAction needed moving forward1Extended reviews/approvals process.AH/DPFPriority lists updated and workshops held with AH.Backlog of submittal to be reviewed and commented at the earliest. Priority items and Long lead materials requested to be cleared as a matter of utmost urgency. Code 3 responses to be minimized.

2Finalisation of Access control systemANC/TGRejected on 21Aug2014 by AH.ANC / TG to resubmit the drawings.3Approval of MEP light Fixtures- FOH, External , LabsAH/DPF-Approval is required to place the order for long lead items & Lab lights affect media ceiling panels.4RCP approvalsAH/DPF/ANC-3F Part c drawings to be reviewed and approved. ANC to incorporate comments & resubmit 2F Part c and 3F Part a drawings.5IronmongeryAH/DPF- Samples require urgent approval and hardware layout drawings and schedules.6Tiling LayoutsAH/DPF-Approval of shop drawings & decision regarding mosaic border above mirror.7External WorksAH/DPF-RC drawings for boundary walls and water features pending approval.8Acoustical wall & ceiling panelsAH/DPF-Sample requires urgent approval.9Main building staircase flooring (ASP Staircase flooring)AH/DPF/ANC-Shop drawings require urgent approval. ANC to submit samples. 10Penthouse BlockworkAH/DPF-Shop drawings require urgent approval.11Balustrades - Stair and Atrium (Technical Glass)AH/DPF-Shop drawings require urgent approval.INDICATION OF TOTAL SUBMISSIONS SINCE NOVEMBER-2013 AND RESPONSES FROM THE CONSULTANT24INDICATION OF APPROVALS PER WEEK SHOPDRAWINGS SHOP DRAWING REVIEW STATUS SUMMARY

FORECAST SHOP DRAWING APPROVALHISTORY OF RESPONSES-NosFORECAST RESPONSES REQUIRED

Drawings pending response- 229 NosAVERAGE-56REQ. AVERAGE-126AVERAGE RESPONSE TIME FOR SUBMITTALSSCAR- AVG RESPONSE TIMEMATERIAL SUBMISSION (Civil)- AVG RESPONSE TIMESHOP DRAWINGS APPROVAL architectural- AVG RESPONSE TIME