Progress PhotosMarch 2007
Construction Progress
Park Station
Portal Shaft Excavation16 March 2007
View towards South16 March 2007
General views of construction activities
Construction Progress
Rosebank
General views of construction site,
road diversion and pedestrian footbridge
spanning Oxford Road and station site
View towards South16 March 2007
View towards North16 March 2007
View towards South16 March 2007
Construction Progress
Rosebank
Batch Plant16 March 2007
Wheel Wash Pit16 March 2007
Site establishment is ongoing
Construction Progress
Shaft E5
Looking upfrom Platform20 March 2007
Looking down from Platform20 March 2007
Shaft depth 24 metres at 20 March 2007
Construction Progress
Sandton Station
Demolition of Old Taxi Rank20 March 2007
New Taxi Rank20 March 2007
Taxis were relocated to new rank on 9 March 2007
Official opening took place on 15 March 2007
Demolition of old taxi rank commenced on 12 March
2007
Construction Progress
Sandton Station
Diaphragm wall construction4 D-Wall panels concreted on 16 March 2007
Completed Panels20 March 2007
Cutter Excavationat North Shaft20 March 2007
Construction Progress
Mushroom Farm Park
Blast Preparation19 March 2007
Mucking Out20 March 2007Blast Protection Grids
19 March 2007
Shaft depth 15 metres at 20 March 2007
Construction Progress
Marlboro PortalThird set of canopy
tubes installed
Arch ribs visible in preceding sections
29 metres of tunnel excavated by 23 March
2007
View from Portal20 March 2007
Santa Barbara20 March 2007
Construction Progress
Marlboro ViaductsView towards South showing Marlboro Station
site in foreground, Viaducts 1a and 11 in centre and clearing of alignment towards Marlboro
Portal behind
Piling (4 piles as at 23 March 2007) and foundations in progress
View towards South22 March 2007
Piling at Viaduct 1122 March 2007
Foundations V11 and V1a22 March 2007
Construction Progress
Area 2Marlboro to Depot Section
View towards Depot19 March 2007
View towards East(behind Linbro)
19 March 2007
View from Landfill19 March 2007
Clearing and grubbing, topsoil stripped, and earthworks in progress
from Linbro Junction to Depot
Construction Progress
Depot
Train Depot Earthworks Platform
20 March 2007
Bus Depot Admin Building
20 March 2007
Bulk earthworks to both Train and Bus Depot areas is complete
Construction Progress
DepotPrecast Yard
Construction of M-Beam casting beds
M-Beam Pits20 March 2007
M-Beam Soffits20 March 2007
M-Beam Pit Walls20 March 2007
Construction Progress
Viaduct 13
First lift of Pier 8 being backfilled
Shutter erected for first lift of Pier 7 on the
opposite side of Centenary Way
Construction Progress
OR Tambo Station
The station concourse shell is
being constructed by ACSA above the
new elevated drop-off road
CJV site establishment at
ORT will commence at the end of March
Station Concourse Shell22 March 2007