Upload
archana-krishnan
View
21
Download
2
Embed Size (px)
DESCRIPTION
Profiling and Settlement Review Group. Presentation to DCMF. Purpose of Profiling and Settlement Review. Report to SVG (a BSC Panel Committee) on whether current arrangements for profiling and settlement remain appropriate, given rollout of HH-capable metering to all customers: - PowerPoint PPT Presentation
Citation preview
Presentation to DCMFProfiling and Settlement Review Group
• John Lucas • 3 August 2010
» Report to SVG (a BSC Panel Committee) on whether current arrangements for profiling and settlement remain appropriate, given rollout of HH-capable metering to all customers:• Profile Classes 5-8 by 2014• Then Profile Classes 1-4 [rollout targets
to be defined]
» ELEXON, Supplier, DNO and Ofgem participants
Purpose of Profiling and Settlement Review
» 4 meetings so far
» Discussions have homed in on question of why ‘elective’ Half Hourly settlement is so little used• Are there artificial barriers to HH
settlement that ought to be removed?• Would mandatory HH settlement be
more accurate and equitable?
» Consultation (May 2010) on factors driving choice of HH or NHH settlement
Process Followed
» Choice of HH or NHH settlement is customer driven in most cases• HH settlement currently means a more
complex supply contract
» HH settlement means higher cost to serve• Supplier Agent costs, BSC Charges
» Concern about network charges• DUoS charges higher?• TNUoS charges less predictable?
(Triads)
Views from May Consultation
» PSRG intends to continue exploring:• Options for removing barriers to
elective HH• Cost-benefit of mandatory HH
settlement
» Late August – will be issuing impact assessment requests for:• Mandatory HH settlement in PC5-8
(from April 2014 onwards)• Impact of applying some GSP Group
Correction to HH market
Next Steps
» 1 October - Impact assessment responses received back
» 1 November – report drafted
» 30 November – report to SVG
Next steps (cont.)
» We tried to quantify this as part of our May consultation:• Calculated HH and NHH charges (in
each DNO area) for typical customer in PC5 to PC8
• Used average load research data for demand shape (and assumed NHH night rate from 00:00-07:00 GMT)
• Capacity based on peak demand and appropriate Load Factor
• Assumed no reactive power charges
DUoS Charges a Potential Barrier to Elective HH?
» Our rough calculation gave some support to Supplier concerns that HH DUoS charges are higher:• 14% higher for PC5• 8% higher for PC6• 3% higher for PC7• 1% lower for PC8
» Not huge differences, but consultation responses suggest Suppliers see it as a concern
DUoS Findings
» Do DUoS charges create an artificial incentive to choose NHH over HH settlement (for below-100kW customers, where the choice exists)?
» Would a different approach to DUoS for the HH elective market better facilitate the Charging Objectives?
» For example – apply NHH charges to everyone below 100kW?
Request for DCMF Help