ROADWAY PRODUCTION RATES COMMENTS 5/16/2011 UNIT LOW AVE HIGH GENERAL MOBILIZATION DAYS 15 MOT MOBILIZE / MOT / EROSION CONTROL WKS 1 2 3 ADVANCED WARNING PANELS EA 15 BARRICADES EA 500 REMOVABLE PAV'T MARKINGS LF 18500 TEMP IMPACT ATTENUATORS EA 20 TEMPORARY BARRIER WALLS LF 450 3,000 TEMPORARY CURB LF 900 TEMPORARY PAV'T SY 440 750 TEMPORARY RPM'S EA 500 TEMPORARY STRIPING MI 4 VARIABLE MESSAGE SIGNS EA 10 WORK ZONE SIGNS EA 30 EROSION CONTROL FILTER FABRIC SY 2,500 FLOATING TUBIDITY BARRIER LF 500 HAY BALES TON 3 ROCKBAGS/SAND BAGS EA 400 SILT FENCE LF 750 1,500 3,000 SOIL TRACKING DEVICE EA 5 TURBIDITY BARRIER LF 600 CLEARING & GRUBBING MAILBOXES EA 25 REMOVE EXISTING CONCRETE PAV'T SY 600 REMOVE SIDEWALK SY 1,500 2,500 3,500 REWORK SHOULDERS SY ### SHOULDER Mi 1 C & G Ac 1 10 or large trees. Maximum 20 day EARTHWORK BACKFILL AROUND STRUCT. CY 50 100 200 EXCAVATION - TRUCK HAUL < 100,000 CY 900 100,000 - 300,000 CY 3,800 > 300,000 CY 7,500 EXCAVATION - BORROW EXCAVATION - REGULAR SEE CHART EXCAVATION - SUBSOIL EMBANKMENT SHOULDER GRADING MI 0.5 1 2 DRAINAGE ADJUST MANHOLE EA 6 CONCRETE BOX CULVERTS CY 20 50 80 CONCRETE BOX CULVERTS (PRECAST) LF 50 100 150 CONCRETE CLASS I (Culvert) CY 5 10 CONCRETE CLASS I (Endwalls) CY 5 10 CONCRETE ENDWALLS CY 15 DESILT PIPE LF 1,000 DESILT, CLEAN & SEAL JNT LF 30 DITCH PAVING SY 200 DRAINCRETE LF 1,500 GUNITE CF 65 130 INLET EA 6 JACK & BORE LF 20 24" Diameter JUNCTION BOX EA 6 MANHOLES EA 4 MISC. CONCRETE CY 15 MITERED END SECTIONS EA 8 13 PARTIAL MANHOLE EA 6 PIPE INSTALLATION < 5' deep LF 200 400 PIPE INSTALLATION > 5' deep LF 100 200 RIPRAP TN 50 STORM SEWERS, (Manholes & Inlet) LF 100 300 400 TEMPORARY PIPE(Slope Drain) LF 400 utilities {

Production Rates

Embed Size (px)

DESCRIPTION

productin rates in contruction

Citation preview

Page 1: Production Rates

ROADWAY PRODUCTION RATES COMMENTS

5/16/2011 UNIT LOW AVE HIGHGENERAL

MOBILIZATION DAYS 15

MOTMOBILIZE / MOT / EROSION CONTROL WKS 1 2 3ADVANCED WARNING PANELS EA 15BARRICADES EA 500REMOVABLE PAV'T MARKINGS LF 18500TEMP IMPACT ATTENUATORS EA 20TEMPORARY BARRIER WALLS LF 450 3,000TEMPORARY CURB LF 900TEMPORARY PAV'T SY 440 750TEMPORARY RPM'S EA 500TEMPORARY STRIPING MI 4VARIABLE MESSAGE SIGNS EA 10WORK ZONE SIGNS EA 30

EROSION CONTROLFILTER FABRIC SY 2,500 FLOATING TUBIDITY BARRIER LF 500 HAY BALES TON 3 ROCKBAGS/SAND BAGS EA 400 SILT FENCE LF 750 1,500 3,000 SOIL TRACKING DEVICE EA 5 TURBIDITY BARRIER LF 600

CLEARING & GRUBBINGMAILBOXES EA 25 REMOVE EXISTING CONCRETE PAV'T SY 600 REMOVE SIDEWALK SY 1,500 2,500 3,500 REWORK SHOULDERS SY 20,000 SHOULDER Mi 1 C & G Ac 1 10 Use low if there are a lot of utilities

or large trees. Maximum 20 days.

EARTHWORKBACKFILL AROUND STRUCT. CY 50 100 200 EXCAVATION - TRUCK HAUL < 100,000 CY 900 100,000 - 300,000 CY 3,800 > 300,000 CY 7,500

EXCAVATION - BORROWEXCAVATION - REGULAR SEE CHARTEXCAVATION - SUBSOILEMBANKMENTSHOULDER GRADING MI 0.5 1 2

DRAINAGEADJUST MANHOLE EA 6 CONCRETE BOX CULVERTS CY 20 50 80 CONCRETE BOX CULVERTS (PRECAST) LF 50 100 150 CONCRETE CLASS I (Culvert) CY 5 10 CONCRETE CLASS I (Endwalls) CY 5 10 CONCRETE ENDWALLS CY 15 DESILT PIPE LF 1,000 DESILT, CLEAN & SEAL JNT LF 30 DITCH PAVING SY 200 DRAINCRETE LF 1,500 GUNITE CF 65 130 INLET EA 6 JACK & BORE LF 20 24" DiameterJUNCTION BOX EA 6 MANHOLES EA 4 MISC. CONCRETE CY 15 MITERED END SECTIONS EA 8 13 PARTIAL MANHOLE EA 6 PIPE INSTALLATION < 5' deep LF 200 400 PIPE INSTALLATION > 5' deep LF 100 200 RIPRAP TN 50 STORM SEWERS, (Manholes & Inlet) LF 100 300 400 TEMPORARY PIPE(Slope Drain) LF 400

{

E7
cn982rm: District 2 0.065 days
F12
District 1: 2,000 LF
F13
District 1: 2,000 LF
F23
District 3: (PBS & J) 600 EA
G25
District 3: (PBS & J) 4,000 LF
F57
District 7: Range: 250 - 600
E67
District 7: Range: 3 - 7 Ea.
Page 2: Production Rates

TRENCH DRAIN (Special) LF 100 400 VALVE BOX, ADJUST EA 8 WINGWALLS SF 100 150 200

ROADWORKBASE SEE CHARTCONCRETE BARRIER WALL LF 200 300 400 CONCRETE CURB & GUTTER LF 400 600 800 CONCRETE PAVING SY 5,000 DIAMOND GRINDING CONC SY 2,000 MILLING SY 8,000 MILLING ASPHALT SY 8,000 MISC ASPHALT PAVEMENT TN 60 RUBBLIZATION SY 7,000 RUMBLE STRIP GRINDING MI 5 STABILIZE ROADBED SY 1,400 1,500 STABLIZATION SY 1,400 1,600 1,800 TEMPORARY PAV'T SY 60 TEXTURED PAVEMENT SY 150 TRAFFIC SEPERATOR LF 800 TURNOUT CONSTRUCTION SY 200

GUARDRAIL District 7REMOVE EXISTING LF 2,000 FURNISH & INSTALL LF 200 1,000 1,500 END ANCHORS EA 8

RAILINGHANDRAIL & BICYCLE RAILING LF 100 400

FENCE< 10,000 LF 500 > 10,000 LF 1,200 3,500 GATES EA 10

PAVEMENT MARKINGDELINEATOR TUBULAR (Flexible) EA 500 750 1,000 DIRECTIONAL ARROWS EA 25 50 GUIDE LINES (Thermo)(White) LF 2,000 ISLAND NOSE PAINT SY 55 MESSAGES EA 30 MISC. STRIPE LF 3,000 PAINTED PAV'T MARKINGS (Final Surface) NM 7 REFLECTIVE PAINT (Island Nose) SY 30 55 REMOVE EXIST THERMO (White/Black)(Other) SF 2,000 2,400 4,800 REMOVE EXIST THERMO (White/Black)(Solid) LF 2,000 4,800 9,600 REMOVE EXIST THERMO (White/Black/Blue)(Skip) GM 7 REMOVE EXIST THERMO (White/Black/Blue)(Solid)(6") NM 7 REMOVE EXIST THERMO (Yellow)(Other) SF 2,000 4,800 9,600 REMOVE EXIST THERMO (Yellow)(Skip) LF 2,000 2,400 4,800 REMOVE EXIST THERMO (Yellow)(Solid) LF 2,000 2,400 4,800 REMOVE EXISTING THERMO SY 350 RPM's (0 - 5,000) EA 500 750 1,000 STRIPING SKIP GM 7 STRIPING SOLID NM 7 THERMOPLASTIC STRIPING MI 6.7 TRAFFIC STRIPE MI 7 TRAFFIC STRIPE SKIP (Thermo)(White/Black/Blue) LF 2,000 TRAFFIC STRIPE SKIP (Yellow) LF 2,000 TRAFFIC STRIPE SOLID (Paint)(White)(24") LF 2,000 TRAFFIC STRIPE SOLID (Paint)(White/Black) LF 2,000 TRAFFIC STRIPE SOLID (Two Component)(Yellow)(18") LF 2,000 TRAFFIC STRIPE SOLID (Yellow)(18") LF 2,000 TRAFFIC STRIPE SOLID (Yellow)(6") NM 7 TRAFFIC STRIPE SKIP (Standard)(White)(6") GM 7 TRAFFIC STRIPE SKIP (White)(6") LF 2,000

SIGNALIZATIONDIRECTIONAL BORE < 6" LF 400 800

LF 400 800 DIRECTIONAL BORE 6" to < 12" (4- 1 ¼ Innerduct) LF 400 800 JACK & BORE CASING DIAMETER (<6") LF 50 400 JACK & BORE CASING DIAMETER (6" to <12") LF 50 400 CONDUIT ABOVE GROUND < 3" LF 500 1,000

DIRECTIONAL BORE 6" to < 12" (3- 1 ¼ Innerduct)

F85
District 1: 7,000 SY
F89
District 1: 1,800 SY
G110
cn982rm: District 7: Uses 1,000 Ea.
D125
District 7: Uses SF
F125
District 7: Uses: 4,500 Ranges: 2,000-4,800 SF
G126
District 7: Uses 1,000 Ea.
F145
District 7: Uses 100 LF
F146
District 7: Uses 200 LF
F147
District 7: Uses 500 LF
Page 3: Production Rates

CONDUIT F & I ABOVE GROUND 3" LF 500 1,000 LF 500 1,000 LF 500 1,000 LF 500 1,000

CONDUIT UNDERGROUND 2" LF 500 1,000 CONDUIT (F & I UNDERGROUND)(PVC SCH 40)(2") LF 500 1,000 CONDUIT UNDERGROUND 3" LF 500 1,000 CONDUIT UNDERGROUND 4" LF 500 1,000 CONDUIT UNDERGROUND 4" RGS LF 500 1,000 CONDUIT UNDER PAV'T 2" HDPE LF 500 1,000

LF 500 1,000 LF 500 1,000

CONDUCTORS (F&I)(Insulated)(No. 6) LF 500 2,500 CABLE SIGNAL PI 5 SPAN WIRE ASSEMBLY PI 5 CABLE INTERCONNECT (1-25 PR) LF 1,000 2,000 2,500 PULL BOXES 10 20 PULL & JUNCTION BOXES EA 8 PULL & JUNCTION BOXES (Fiber Optic-Pull Box) EA 10 15 20 PULL BOXES (Special) EA 5 10 PULL BOXES (Roadside) EA 10 20 SURGE PROTECTOR (Pole Base) EA 10 20 LIGHTNING PROTECTION SYSTEM (F&I)(Surge Suppresion) EA 10 20 LIGHTNING PROTECTION SYSTEM (F&I)(Point Discharge) EA 1 4

AS 2 ELECTRICAL POWER SERVICE WIRE (F&I) LF 500 1,000 2,500 ELECT PWR SRV WIRE DISCONNECT (POLE)(Cabinet) EA 2 PRESTRESSED CONC. POLES (Type N-11)(Dir. Burial) EA 2 STEEL STRAIN POLE (F&I)(NS-IX)(36') EA 0.5 0.7 STEEL STRAIN POLE (F&I)(NS-IX)(38') EA 0.5 0.7 MAST ARM (F&I/HL)(Single w/Luminare)(1st Arm Bx EA 0.5

EA 0.5 Add 7 Days for Conc. CureEA 0.5

MAST ARM (F&I/Reduced Loading) EA 0.5 MAST ARM (F&I)(Double Arm) EA 0.5 SIGNAL TRAFFIC AS 10 20 SIGNAL, POLE & DET (Pedestrian)(Complete) AS 2 3 5 DETECTOR CABINET EA 3 5 DETECTOR CABINET(Type II) (Pay Item 668-32) EA 3 6 DETECTOR CABINET(Type III) (Pay Item 668-33) EA 1 4 DETECTOR CABINET(Type V) (Pay Item 668-35) EA 1 4 DETECTOR CABINET(Type VI) (Pay Item 668-36) EA 0.2 0.5 SYSTEM COMM. (Multi-pair Cable) LF 1,000 5,000 SYSTEM COMM. (Fiber Optic Cable SM) LF 1,000 10,000 SYSTEM COMM. (FOC, 6-Count SM) LF 1,000 10,000 SYSTEM COMM. (FOC, 24-Count SM) LF 1,000 10,000 SYSTEM COMM. (FOC, 48-Count SM) LF 1,000 10,000 SYSTEM COMM. (FOC, 72-Count SM) LF 1,000 10,000 CCTV Equipt. (Install)(Camera Assembly) EA 2 5 CONTROLLER ASSEMBLY ACTUATED SS F&I Nema Pre(None) AS 2 5 CONTROLLER ASSEMBLY ACTUATED SS Modify Nema Preempt AS 1 3 CONTROLLER ASSEMBLY (Cabinet Assembly, Less Foundation) AS 2 5 SIGN (Internal Illuminated) EA 4 8 LUMINARE (F&I)(Roadway)(Special) EA 0.5 2 TMS Vehicle Sensor (Class II)(Type I) EA 4 12 TMS Vehicle Sensor (Class II)(Type I)(1/2 Ln) EA 4 12 TMS Inductive Loop Assembly (2 Loops per Lane) AS 4 12 TMS Cabinet (F&I)(Type III)(Pedestal)(2 Backplane) EA 3 6 SIGNALS PER INTERSECTION DAYS 15 ELECTRICAL POWER SERVICE AS 3 SIGNAL HEADS EA 10 POLES EA 10 LIGHTING POLE (Complete) EA 0.5 REMOVE EXISTING SPAN WIRE EA 20 REMOVE EXISTING SIGNAL EQUIPT. EA 8 REMOVE EXISTING SIGNAL INTERCONNECT (Cable) LF 1,000 1,500 MAST ARM (SINGLE) EA 4 MASTARM (DOUBLE) EA 3 TRAFFIC SIGNALS AS 8 PEDESTRIAN SIGNALS AS 10 CUT LOOP DETECTORS AS 6 LOOP ASSEMBLIES AS 4 6 8 PEDESTRIAN DETECTORS EA 8 SIGN PANELS EA 6

CONDUIT UNDERGROUND 1 ¼ RGS"CONDUIT UNDERGROUND 4" 3- 1¼" Innerduct)

CONDUIT UNDERGROUND 4- 1 ¼ "

CONDUIT UNDER PAV'T (3- 1¼ Innerduct)

CONDUIT UNDER PAV'T (4- 1¼ Innerduct)

ELCTRICAL POWER SERVICE (Underground-Purchased by Contractor from Pwr. Co.)

MAST ARM (F&I/Reduced Loading)(Single Arm w/o Luminare)(1st Arm C5)MAST ARM (F&I/Reduced Loading)(Single Arm w/o Luminare)(1st Arm C6)

F148
District 7: Uses 750 LF
F149
District 7: Uses 500 LF District 3 (PBS&J) Uses 750 LF for general underground conduit.
F150
District 7: Uses 500 LF
F151
District 7: Uses 500 LF
F152
District 7: Uses 500 LF
F153
District 7: Uses 500 LF
F154
District 7: Uses 500 LF
F155
District 7: Uses 500 LF
F156
District 7: Uses 500 LF
F157
District 7: Uses 500 LF
F158
District 7: Uses 500 LF
F159
District 7: Uses 500 LF
F160
District 7: Uses 1,000
F206
District 2: 0.065 per Intersection
F208
District 7: Uses 10-20 per day range
G219
District 7: Uses range 4 to 12 AS.
Page 4: Production Rates

LIGHTINGCONDUCTORS LF 750 MISC. CONCRETE CY 15 UNDERGROUND CONDUIT LF 750 PULL & JUNCTION BOXES EA 8 POLES EA 10 HIGHWAY STANDARD EA 5

SIGNINGDELINEATORS EA 10 DIRECTIONAL BORE LF 600 Less than 12"MILTIPOST REMOVAL AS 15.0 MULITPOST (F & I) AS 10.0 OBJECT MARKER EA 10.0 OVERHEAD SIGNS SF 0.2 0.7 RELOCATE SIGN PANELS EA 10 REMOVE SIGN PANELS EA 12 SIGN PANELS EA 15.0 SIGN INSTALL (Existing Breakaway Supports)(Single Post) AS 4 12.0 SINGLE POST SIGN AS 15 SINGLE POST SIGN RELOCATE AS 10 SINGLE POST SIGN REMOVAL AS 30 LARGE SIGNS EA 0.2 0.7 SMALL SIGNS EA 10 20 30 DRILLSHAFT BASE EA 0.5

ASPHALT SEE CHART2" SIDEWALK SY 800 Hot-In Place 1.5 " SY 6,000 ARMI Layer SY 7,040 Micro-Surfacing SY 20,000 25,000 20-25 Lbs/S.Y.SUPERPAVE ASPH CONC (Structural) SEE CHARTFRICTION COURSE SEE CHART

CONCRETEADA RAMPS EA 0.5

BARRIER WALL LF 200 BLOCK SOUND WALLS SF 400 BOX CULVERT CY 20 80 BREAK, COMPACT PAVEM'T SY 5,000 CURB & GUTTER LF 400 600 800 DITCH PAVEMENT SY 200 PAVING SY 5,000 SIDEWALK SY 300 SLAB REPLACEMENT SY 130 1,192

LANDSCAPINGPLANTS (Small) EA 30 PLANTS (Large) EA 15 SEEDLINGS (Trees & Shrubs) EA 800 1,000 1 GAL EA 400 3 GAL EA 200 500 7 GAL EA 100 SCRUB - 30 GAL EA 30 DIRECTIONAL BORE LF 600 Less than 12"FINISH SOIL LAYER (LANDSCAPING OPERATIONS) CY 1,500 5,000 FENCING (Type B(5.1 -6.0) (With Vinyl Coating) LF 500 FENCING GATE (Type B (Double 6.1 -12.0') Opening EA 2 3 5 ARTIFICIAL COVERING SY 1,500 5,000 SODDING SY 1,500 5,000 SEEDING SY 23,500 PERFORMANCE TURF SY 1,500 23,500 PERFORMANCE SOD SY 1,500 5,000 PLASTIC EROSION MAT,(TURF REINFORCED, TYPE 3) SY 1,500 5,000 PATTERNED/TEXTURED PAVEMENT (Asphalt) SY 150 250 PAVERS, Architectural (Roadway) SY 150 200

GRASSINGSEED & MULCH SY 23,500 SOD SY 1,500 2,200

3 components are footing, stem & barrierExamples: variable height median barrier, rigid shoulder barrier,rigid C&G barrier and rigid retaining barrier

Examples: variable height median barrier, rigid shoulder barrier,rigid C&G barrier and rigid retaining barrier

F238
District 7: Uses range 4-12 EA
F242
District 7: Uses range 4-8 AS
F244
District 7: Uses range 4-12 AS
F253
Approximately 3 lane miles/day
F259
Tpk: Calculates for 1,000 LF: 100 LF/day- footing 200 LF/day-stem 350 LF/day-barrier =18 work days/1,000 days = 55 LF/day
E267
District 1: 20 CY
F267
District 1: 30 CY
G267
District 1: 40 CY
Page 5: Production Rates

FINISH SOIL LAYER (TOPSOIL) SY 15,000

MISC CONSTRUCTION

Page 6: Production Rates

BRIDGE PRODUCTION RATEUNIT LOW AVE HIGH Comments

MOBILIZE MARINE - BARGE & CRANEDAYS 60

COFFERDAMSSY 100 200 300

CATHODIC PROTECT (Jackets)EA 1.5

DREDGEINGDRAG LINE CY 250 PUMP CY 500

DEMOLITIONBRIDGE SF 270 375 600 FENDER SYSTEM LF 50 SAW CUT DECK - 1" DEEP LF 550 BRIDGE RAIL LF 50 DECK & HANDRAIL SY 30 35 40 PARAPET LF 60 115 180 TIMBER BRIDGE SY 40 50 60

GRINDINGRiver Gravel Agg. SY 2,600 Limestone Agg. SY 4,000

HYDRO BLAST BRIDGE DECK2.5" DEEP SF 600 3.5" DEEP SF 215

ACROW BRIDGE

AVERAGE ACRO BRIDGE LF 30 Allow approx. 7 days for initial setup of substructure

PILESTEST PILES 24" - 30" EA 0.8 PRODUCTION PILES LF 200 300 400 PILE JACKETS 18" - 24" LF 7

SHEET PILINGCONCRETE PILE - 5 ft x 20 ft EA 15 SHEET STEEL PILING SF 640 2,000 4,000 SHEET STEEL PILING SHTS/day 32 40 48 STEEL PILE LENGTH - 40 ft LF 200

DRILLED SHAFT? WHAT SIZE ? LF 200 300 400 60" x 130 ft' EA 0.2 74" x 40 ft EA 0.5

BOX CULVERTCY 10 11 30

SUBSTRUCTURECOLUMNS / CAPS / BENTS CY 4 8 12 FOOTINGS CY 10 20 30 STEEL BEAMS LF 150 PRECAST BEAMS LF 250 425 600

SUPERSTRUCTUREBRIDGE DECK CY 6 11 14 BARRIER WALL LF 80 120 160

BRIDGE FLOOR GROOVINGSY 3,000

APPROACH SLABSCY 15

EXPANSION JOINTSCLEANING & RESEALING LF 3,000 3,500 MECHANICAL LF 35 SAW CUT/EPOXY/ANCHOR LANE 1

COMPRESSION SEAL REPLACEMENTCompression Seal Replacement LF 50 100 150

G23
District 7: Uses 50 - 180 LF
F39
District 2: 1-2 ea. District 3: (PBS & J) 2 ea.
F45
District 2 & 7: 1,000 SF
F46
TPK: uses 4 to 6 sheets per hour.
H46
TPK: When driving into compacted fill, especially limerock, use the lower number. When driving into swales, etc. without rock, use the higher production rate. I measure the length of the sheet pile wall along the top and divide that length by 1.5 LF (18”) per sheet to determine the number of sheets to drive. For installation of the tie backs/soil anchors, I use 6 each per work day for installation & grouting. The stressing & testing will lag behind a few days, but it is a separate crew and they can usually keep up the pace with the installation.
F59
District 2: 20-40
G64
District 3: (PBS & J) & District 7: Uses 7-20 CY
F68
District 2: 2,000 SY District 3: (PBS&J) 1,200 SY
Page 7: Production Rates

CLEAN & SEAL CONCRETE DECKSF 7,000

Cleaning & Resealing Joints LF 0 5,280 10,560

Cleaning & Resealing Joints MI 0 1 2

Cleaning & Sealing Random Cracks LF 0 1,478 1,478

Cleaning & Sealing Random Cracks MI 0 0.14 0.28

Grinding Concrete Pavement SY 555 1,500 2,700

Concrete Pav't Slab Replacement CY 24 60 94

Concrete Paving Plain (9") SY 0 500

Bridge Approach Expansion Joint LF 30 50 80

ERECT STRUCTURAL STEELTON 3 9 10.5

BEAM ERECTIONSTEEL LF 150 200 250

PRECAST LF 250 600

TRAFFIC RAIL BARRIERLF 80 160 200

HANDRAILS - BRIDGELF 150 225 300

WALLSRETAINING SF 100 150 200 BARRIER WALL LF 200

BARRIER WALL w/3 components LF 55 MSE WALL LF 750 NOISE BARRIER WALL SF 2,000 WINGWALLS SF 100 150 200

ERECT TIMBER FENDER SYSTEM SF 350 PER BENT DAYS 5

PAINTINGANTI-GRAFFITI COAT SF 2,500

STEEL TN 20

BRIDGE PAINTING SF 2,000

CLASS 5 APPLICATION SF 2,000

SMALL BASCULE per Leaf 20 w/Containment System(Bascule Open)

STEEL GIRDERS SF 2,000 w/Containment System

STEEL GIRDERS TN 9 w/Containment System

PAINT REMOVALDRY BLASTING SF 60

POWER TOOLED SF 28

WATER BLASTING SF 235 No-Containment, System Prep.for paint

SANDBLASTING SF 1,500

STEEL GIRDER-SANDBLASTING SF 1,500 w/Containment System

RIP RAPDUMPED TON 750 PLACED TON 185 PLACED CY 75 SAND BAG SY 120 Gabion mats & baskets SY 40 850 1,300 Gabion mats & baskets CY 20 45 80

SIGNSHIGHWAY EA 10 30 OVERHEAD EA 0.2 0.7

TOLL PLAZASRAMP MTH 4 8 MID SIZE MTH 12 MAINLINE MTH 18

3 components are footing, stem & barrierExamples: variable height median barrier, rigid shoulder barrier, rigid C&G barrier and rigid retaining barrier

F108
Tpk: Calculates for 1,000 LF: 100 LF/day- footing 200 LF/day-stem 350 LF/day-barrier =18 work days/1,000 days = 55 LF/day
F128
District 6: 1,000 SF/Day
H128
This note goes with District 6 rates.
F135
District 3: (PBS & J) 50 Tons
H138
CN982RM: Gabion Mats & Baskets: These rates come from Federal Lands & Highway Department
Page 8: Production Rates

PROCUREMENT UNIT AMOUNT

ALUMINUM HANDRAIL WKS 2-6

BUILDING PERMIT DAYS 45

RESURFACING - SUPERPAVE< 20,000 TONS DAYS 3020,000 - 60,000 TONS DAYS 60> 60,000 TONS DAYS 90

HIGHWAY LIGHTING DAYS 120-150CONVERT MERCURY TO Na DAYS 90

PILES WKS 3 - 5

FIBERGLASS PILE JACKETS DAYS 45

PUMP STATION WKS 12

SIGNALSCONCRETE STRAIN POLES DAYS 90STEEL MAST ARMS DAYS 150

SIGN TRUSS DAYS 150

SIGNS DAYS 60

STEEL BEAMS MTHS 4

IMPACT ATTENUATOR (G.R.E.A.TDAYS 30

UTILITY STEEL POLES - MAJOR MTHS 9

E29
Could be a short as 8 wks and as long as 20 wks. (Information based on fabricators).
Page 9: Production Rates

UTILITIES PRODUCTION RATEUNIT LOW AVE HIGH

ADJUST MANHOLE COVERS EA 4

WATERMAIN LF 75 100 150

RAILROAD X-ing 5 Lanes LF 3

Page 10: Production Rates

EARTHWORK

DAYS CUBIC YARDS

0 0 10 5,000 15 10,000 19 15,000 23 20,000 30 30,000 37 40,000 43 50,000 47 60,000 50 70,000 52 80,000

54.5 90,000 57 100,000

63.5 150,000 68 200,000 70 240,000 72 300,000 76 400,000 80 500,000 84 600,000 88 700,000 91 800,000 95 900,000 98 1,000,000

102 1,100,000 106 1,200,000 110 1,300,000

0 100,000 200,000 300,000 400,000 500,000 600,000 700,000 800,000 900,000 1,000,000 1,100,000 1,200,000 1,300,000

0

10

20

30

40

50

60

70

80

90

100

110

EARTHWORK

CUBIC YARDS

DA

YS

Page 11: Production Rates

BASE

WORK DAYS SQUARE YARDS

0.0 0 8.0 8,000 9.4 10,000 11.0 13,000 11.3 14,000 12.0 15,000 14.0 20,000 16.0 26,000 20.0 42,000 22.0 50,000 26.0 64,000 80.0 260,000

0 50,000 100,000 150,000 200,000 250,000 300,000

0.0

10.0

20.0

30.0

40.0

50.0

60.0

70.0

80.0

BASE

SQUARE YARDS

WO

RK

DA

YS

Page 12: Production Rates

SUPERPAVE

WORK DAYS TONS

0.0 0 3.0 500 4.5 1,000 5.7 1,500 6.3 2,000 7.0 2,500

73.5 65,000

ASPHALT TONNAGE CONVERSION CHART

1/2" = 0.0250 x SY 3" = 0.1500 x SY5/8" = 0.0313 x SY 3 1/2" = 0.1750 x SY3/4" = 0.0375 x SY 4" = 0.2000 x SY1" = 0.0500 x SY 4 1/2" = 0.2250 x SY

1 1/4" = 0.0625 x SY 5" = 0.2500 x SY1 1/2" = 0.0750 x SY 6" = 0.3000 x SY1 3/4" = 0.0875 x SY 7" = 0.3500 x SY

2" = 0.1000 x SY 8" = 0.4000 x SY2 1/4" = 0.1125 x SY 9" = 0.4500 x SY

0 5,000 10,000 15,000 20,000 25,000 30,000 35,000 40,000 45,000 50,000 55,000 60,000 65,000

0.0

10.0

20.0

30.0

40.0

50.0

60.0

70.0

80.0

SUPERPAVE

TONS

WO

RK

DA

YS

Page 13: Production Rates

2 1/2" = 0.1250 x SY 9 1/2" = 0.4750 x SY2 3/4" = 0.1375 x SY