    Frito-Lay Chips Away at Asset Care Goals

    Life may be, according to Forrest Gump, like a box of chocolates, but reliability is more akin to abag of Doritos. Or, is it Cheetos? Ruffles, perhaps. Tostitos? Either way, once you get started, it's

    hard to put it down.

    That's the tale of Frito-Lay and its snack food facility in Fayetteville, Tenn.

    After decades of decent yet suboptimized plant maintenance performance, Frito-Lay madeconcerted efforts to address asset care - including preventive maintenance activities andmachinery lubrication - beginning in 2002. With corporate guidance and plant-level leadership,the push to improve reliability has unleashed capacity, productivity and innovation in this high-demand, cost-cognizant industry.

    "When plants run really well in terms of downtime, it rains money on the production side," states

    Mike McKenzie, the company's national reliability manager.

    Crunchy, cheesy, salty money.

    Are you ready to tear open a bag? Read this case study and savor the flavor of what proactivemaintenance policies - including effective lubrication - can do for you.

    It Ain't Easy Being CheesyAs stated in the opening, the snack food business is rough on machinery. Potato chips, corn chipsand the like are not seasonal products. In good times and in bad, people like their snacks. Highproduct demand only increases during the summer, around Christmas and New Year, for Fourth

    of July - most any time families and friends come together to eat. When machines need to churnout the chips, it's hard to find time to perform strategic maintenance work. Add to that anenvironment where dust from flavorings continually wafts and lands on machinery and rotatingcomponents. Plus, it's an industry where all costs are under the microscope (plants produce 99-cent and $3 bags of chips, not million-dollar jet engines). These and other factors have long beenchallenges for Frito-Lay facilities. The difference between pre-2002 and today is the actions thatresult from the challenges.

  • 8/9/2019 Production of Lays Final

    2/13

    In the past, maintenance was resigned to its fate as a firefighting, Band-Aid brigade.

    Why put the time and effort into writing effective preventive maintenance (PM) tasks orscheduling PM tasks if production isn't going to give you the time to perform them and if theworkday is going to be consumed by a never-ending supply of emergency/help calls? "Honestly,

    maintenance in many of our plants was done after the equipment had failed," says McKenzie.

    Champion ChipCompany: Frito-Lay North America is the $11 billion convenient foods businessunit of PepsiCo. In addition to Frito-Lay, PepsiCo business units include Pepsi-Cola, Quaker Foods, Gatorade and Tropicana. Frito-Lay products include well-known brands such as Lays, Ruffles, Doritos, Tostitos, Cheetos, SunChips, Fritos,Funyons, Munchos, Rold Gold and Cracker Jack. The company has 36 productionsites in the U.S. and Canada.

    Focus site: Frito-Lay plant in Fayetteville, Tenn. The 330,000-square-foot siteemploys 500 people, including 35 in maintenance. The plant is non-union and runs15 shifts per week. It annually produces 100 million pounds of snacks, includingDoritos, Lays, Ruffles, Tostitos, Fritos, Baked Cheetos and Munchos. The plant wasbuilt by Eagle Snacks (Anheuser-Busch) in 1986 to produce pretzels. Frito-Laypurchased the facility in 1996 and began production in early 1997. It currentlyhouses more than 2,600 assets.

    FYI: Frito-Lay brands account for 59% of the U.S. snack chip industry. ... EightFrito-Lay plants are members of the EPAs National Environmental PerformanceTrack Program and 24 hold OSHA Voluntary Protection Program status.

    Why put the time and effort into understanding and executing effective greasing and lubricatingroutines if you only have time (or are only given the time) for a "fill-and-go"? Fallout fromoverlubrication and grease oozing from zerks become comfy landing pads for the airborneseasonings as well as dust from cardboard containers.

    You get these results:

    y Production sees maintenance - with its overtime and its air-freighting of replacementparts - as a cost drag.

    yMaintenance sees its mechanics as heroes, not for their ability to prevent failure but fortheir ability to fix the most recent one.

    y Plant leaders see downtime not as a key performance indicator but as something thatcomes with the business.

    y The plant sees a never-ending cycle of unreliability: PMs not completed lead toequipment failures, which lead to emergencies, which lead to PMs not completed, and onand on.

  • 8/9/2019 Production of Lays Final

    3/13

    "We had to move from a reactive situation to one that is proactive and predictive, but we weren'tsure how to do that at the time," says McKenzie.

    Terry Haycraft, a corporate reliability manager, adds that "we didn't understand the impact ofreliability or what it could do to change our business."

    Plant engineer Richard Cole (left) and business unit leaders Jason Gower and Jennifer Crabtree

    monitor maintenance performance at the Frito-Lay plant in Fayetteville, Tenn.

    No Small Potatoes

    When the chips are down, that forces some to break the cycle and say "enough is enough." Suchwas the case with Frito-Lay.

    Change started in 2002 with the establishment of a corporate reliability group led by McKenziethat would alter the way that plants and the company viewed maintenance and maintenancetasks.

    Group members asserted that best practices were out there, hidden in Frito-Lay's 36 plants in theUnited States and Canada and throughout industry at large.

    Group members asserted that downtime and underperforming equipment were not "part of doing

    business" but instead the result of misunderstanding, skewed priorities and a lack of processes.

    Group members asserted that this would be a difference-maker, if done right and done now.

    "We are working on a gazillion things. There is always something to do at Frito-Lay. We're allbusy trying to meet goals and targets," says McKenzie. "But, what touches all of those? If thereis one thing you could work on to impact all of those performance metrics - quality, safety,service, cost, output - what would it be? The only thing that does that is reliability. It touches

  • 8/9/2019 Production of Lays Final

    4/13

    everything that we do in some form or fashion. We started talking about reliability as 'the greatenabler.'"

    The group's advice to maintenance and production workers, salary and hourly, was simple anddirect.

    "Take action now. Fix it forever. Leave no stone unturned," says McKenzie.

    The Seven Laws of A.R.M.

    Frito-Lay defines the Seven Laws of its Asset Reliability Model (A.R.M.) as:

    1. One hundred percent of the work completed by a mechanic or operator torepair equipment failure or maintain equipment is documented via the workorder process.

    2. A skilled maintenance planner develops a detailed plan to ensure all theright parts are pre-kitted, and skilled mechanics are identified to completethe work.

    3. A master preventive maintenance schedule, built using national PM routinesand cycle count/run hours, is documented and followed for every piece ofequipment in the facility.

    4. Preventive maintenance is an integral part of the master productionschedule, and mechanics are scheduled 100 percent of the time to ensure 90percent static PM execution.

    5. All parts are logged out of the parts room out to specific pieces ofequipment, and all identified spares are at 99 percent accuracy for required

    stock levels.6. Mechanics are properly trained and certified in the critical skills needed tomaintain, troubleshoot and fix plant equipment. Operators are trained ontheir role to support A.R.M. processes.

    7. The site has a flight plan to address the top five equipment issues and andthe top five structural downtime issues for every processing line in the plant

    Crunch TimeDisplaying the cross-functional nature of the maintenance issue and the maintenance solution,

    the reliability team brought Frito-Lay associates from all levels and backgrounds to a Texas hotelin January 2003. They spent two weeks of long days and long nights hammering out a plantmaintenance business process which would serve as the path forward and allow a cycle ofincreasing benefits: Effective planning leads to PMs that are completed, which lead to reliableequipment, which leads to effective planning, and on and on. They created the Asset ReliabilityModel.

  • 8/9/2019 Production of Lays Final

    5/13

    Based on an assemblage of best practices and a new vision that proactive maintenance had atangible, bottom-line impact, A.R.M. evolved into a nearly 300-page manual, which detailedchapters on: work order management, maintenance planning, maintenance scheduling,preventive and predictive maintenance, parts management, project management, training, andperformance measurements. Chapters outlined definitions of terminology; specific activities

    required; workflow charts; potential obstacles and solutions; roles, responsibilities andaccountabilities; and scorecard metrics.

    Frito-Lay rolled out A.R.M. in 2004. Every employee at every site received extensive training.Maintenance employees (40 hours) received the most. Members of the corporate reliability grouphit the road, spending an additional 20 hours at each plant customizing the program to fit the site.It took three teams two years to cover all of the facilities throughout North America.

    After a while, the program was distilled from a 300-page master document down to the SevenLaws of A.R.M. (see sidebar), making it manageable, memorable and usable for individuals on adaily basis.

    The remainder of this article will focus on three laws - around scheduling (Law 3), preventivemaintenance (Law 4) and training (Law 6) - that tie in nicely with effective machinerylubrication and, specifically, with Frito-Lay's implementation of autonomous maintenance atplants such as Fayetteville, which annually produces more than 100 million pounds of Doritos,Cheetos, Tostitos, Fritos, Munchos, and Lays and Ruffles potato chips.

  • 8/9/2019 Production of Lays Final

    6/13

    The Fayetteville plant converts potatoes and corn into some of America's best-known snackfoods.

    Chips Off the BlockAs described earlier, maintenance had difficulties following its schedules because production

    dominated the relationship, product orders trumped maintenance windows, emergencies wereprevalent, and operators sought quick service for machine adjustments and other less-criticalissues.

    A.R.M. Law 3 rectifies that to a great extent through the creation of a master PM schedule(developed with extensive maintenance and production input) that is documented and followedfor every piece of equipment in a facility.

    Fulfilling today's product orders remains tantamount, but the value of maintenance to ensurefulfillment of tomorrow's orders (and the next day's, etc.) is much clearer.

    "We work with production to prioritize all that needs to get done," says Mike Thomas, a processmaintenance resource at the Fayetteville site.

    "We have to maintain a balance," adds packaging maintenance resource Julie Murdock. "If wehaven't had the downtime windows that we need, we may have to explain why the PM takespriority."

    Preventive maintenance is an integral part of the master production schedule (Law 4).

    Terry Haycraft is a reliability manager based out of Frito-Lay's corporate offices in Plano,Texas.

  • 8/9/2019 Production of Lays Final

    7/13

    Nacho Old Way of LubingDone well, PMs maximize the performance, output and life of equipment. Done poorly, thebenefits are not as apparent; the results can even be quite detrimental.

    Richard Cole, plant engineer at Fayetteville, admits that "our PMs were not world class." In fact,

    many were too basic to be of use, such as "Go PM a bagmaker." "Good" PM documents weretwo pages long. That's what happens when PMs are seen as the last priority. Those factors led to"pencil-whipped" PMs where necessary work may or may not have been completed.

    Jason Gower, a mechanic who now holds the role of business unit leader for facilities, warehouseand capital projects at Fayetteville, spent several weeks with McKenzie putting together PMtemplates covering virtually every piece of packing equipment. Input came from sessions withmechanics, operators and vendors. Since Frito-Lay plants utilize similar machines, the templateswere applicable throughout the company. Two-page "check the box" PM documents becamehighly detailed 70-page documents.

    "Do they take the 70-page document now every time that they do that PM? No. But they did thefirst several times and gained a better understanding of what needed to be done, the best way todo it, and why," says Gower. "The learnings that were gained were unbelievable."

    The packing machine sessions and additional ones at the corporate and plant level reviewedtopics such as PM-related lubrication. Standardization and greater clarity of correct lubricationpractices directly affects the performance and life of components such as bearings andgearboxes.

    At plants such as Fayetteville, mechanics handle the vast majority of lubrication tasks; operatorsaddress some tasks on specific processing machines.

    "The maintenance folks had always been taught that you stick the fitting in and grease it until itoozes out - 'that's how dad taught me, and that's how I do it.' We harmed or ruined more than ourshare of bearings from overlubrication," says Tyler Griffin, who manages compliance,autonomous maintenance and Continuous Improvement at the plant. "We also weren't consistenton our lubrication tools. For the same application, one mechanic would use a hand-pump greasegun, another would use an air-actuated model and another would use a fully automated model."

    Training and information resources provided a better understanding of proper and improperlubrication procedures. Lubrication PMs were shifted from calendar based (another big source ofoverlubrication) to cycle count based. Also, plants better understood what was needed and notneeded.

    "We plugged 60 percent of the lube points on some equipment because we didn't need it," saysMcKenzie. "We don't have the high-speed rotation in many cases, and the bearings don't rotate afull 360 degrees. We had previously been filling those things full of lubricant every shift."

  • 8/9/2019 Production of Lays Final

    8/13

    Adds Griffin, "After we performed a battery of tests, we removed 70 out of the 150 lube pointson a high-speed case packing unit. In those areas, the seal is going to bust or the bearing is goingto go bad way before there is going to be a lubrication problem."

    An additional benefit to lubrication PMs came through the creation and posting of phenolic

    labels. These two-tone, color-coded plastic squares, etched with an alphanumeric code, adhere tomachines and denote lube points. Cross-reference the code to the PM document to verifylocation and work instructions (the right grease in the right quantity at the right interval).

    Mechanic Joe Wolfe examines a schematic before performing maintenance activities on apackaging machine.

    Dip Into TrainingLaw 4 as well as Law 6 (training) came into play with the implementation of autonomousmaintenance (AM).

    Is AM about operators performing lubrication and maintenance tasks? Yes and no.

    Is AM similar to Total Productive Maintenance? Yes and no.

    Frito-Lay categorizes it as a four-step, team-based approach to return like-new appearance andperformance to machinery. It takes the Continuous Improvement mentality that Frito-Lay hasfostered for 15 years and injects it with technical training and cross-functional asset care. For agiven machine or line, an AM team is assembled, consisting of a team leader, operators, amechanic and a sanitation crew member. Step 1 is an initial cleaning. Step 2 is eliminatingcontamination and hard-to-reach areas. Step 3 is instituting the principles of Cleaning, Inspecting

  • 8/9/2019 Production of Lays Final

    9/13

  • 8/9/2019 Production of Lays Final

    10/13

    Training isn't confined to operators. Teams take the lessons they have learned and share thosewith others, including maintenance leaders and mechanics. One AM team came to a consensuson proper greasing tasks, cycles, quantities and methods of application for a high-speedpackaging automation line. The team helped to rewrite the PMs and trained maintenancemembers on how to perform the tasks.

    An example of phenolic labeling.

    Training will eventually come full circle. While mechanics do just about all lubrication tasks inthe packaging area, the eventual goal is to shift most of those to operators. Handoff will occurafter all packaging equipment and personnel have completed the AM process.

    "When you talk about gearbox lubrication, that's a mechanic's world," says Haycraft. "Bearinglubrication and similar tasks ... operators can do that."

    The ultimate goal is to free up mechanics to do more proactive work.

    "If the operators understand what lubrication points need to be taken care of, and we've taken thetime to educate and train them, you hand it over," says McKenzie. "You really want yourmechanics working on equipment upgrades, getting more out of what you have, equipmenthardening, examining the higher-level elements of machinery lubrication and asset care. Youwant them doing bigger things than manning a grease gun."

  • 8/9/2019 Production of Lays Final

    11/13

    Mechanics Wayne Harris (left) and Bruce Moorehead read over some PM instructions in theproduction area.

    Proactive methods decrease downtime, failures and emergencies. Frito-Lay has noted a 58percent decline in equipment downtime and a 44 percent drop in overall downtime company-wide since 2002. Equipment-related downtime at the Fayetteville plant is a minuscule 0.7percent. As a result, maintenance can push professional development and innovation.

    Mechanics now have the ability to attend one- and two-week classes at training sites in Plano,

    Texas, and Charlotte, N.C.

    And, they can compete in the company's annual innovation contest. Over the past few years,mechanics have submitted projects that have increased productivity, reduced energyconsumption and environmental impact, and saved the company millions of dollars.

    Take a Bite Out of Downtime

    Frito-Lay maintenance leaders offer the following advice on improving reliabilityand eliminating downtime:

    1. If you want to eliminate equipment failure, the first thing you must changeis your expectations about it. Equipment failure is not a "given". It could andshould be zero.

    2. Reset your equipment downtime goal, communicate it broadly within theorganization and then hold yourself personally accountable to achieve it.

    3. The downtime number must be readily available to every person in the site.

  • 8/9/2019 Production of Lays Final

    12/13

    4. Every person on every shift must understand the role that he or she plays ineliminating downtime.

    Big CheeseDowntime figures and innovation projects are just a few of the notable achievements since Frito-Lay and its plants halted the cycle of unreliability and installed a more proactive model. Thiscycle runs smoother, with a dose of proper lubrication and a path that has been cleared ofroadblocks.

    "With greater understanding and cooperation, we are making better decisions as a team," saysJennifer Crabtree, a maintenance business unit leader for computerized maintenancemanagement systems and parts room management at the Fayetteville site. "Those decisions arehaving a huge impact on reliability and on the business."

    It is raining money ... and corn and potato treats.

    "From a capacity standpoint, we have unleashed a facility the size of Fayetteville in the last fiveyears," says McKenzie. "We've unleashed 100 million pounds of capacity. The numbers arehuge. We are making more pounds that we ever have."

    Tyler Griffin is the compliance manager at the Fayetteville site, as well as its manager ofautonomous maintenance and Continuous Improvement.

    By unlocking the potential of existing facilities, the company has not had to purchase capacity inthe form of new plants or new lines. In many cases, it has eliminated the need for overflowequipment to create buffer inventory and for overflow labor to staff that equipment.

  • 8/9/2019 Production of Lays Final

    13/13

    "I think the majority of our plants, and the majority of our leaders in our plants - and certainly atthe regional vice president and division vice president level - really see everything that we havedone and continue to do as a means to maximize productivity and growth," says Cole.

    Reliability may just be like a bag of Frito-Lay snacks. Rip it open. Get a taste of what's inside.

    Once you get started, you'll find it's hard to put back down.