122
PRODUCT ORIENTED COORDINATION BETWEEN DESIGN AND CONSTRUCTION SONG HONGBIN NATIONAL UNIVERSITY OF SINGAPORE 2004

PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

  • Upload
    others

  • View
    19

  • Download
    0

Embed Size (px)

Citation preview

Page 1: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

PRODUCT ORIENTED COORDINATION

BETWEEN DESIGN AND CONSTRUCTION

SONG HONGBIN

NATIONAL UNIVERSITY OF SINGAPORE

2004

Page 2: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

PRODUCT ORIENTED COORDINATION

BETWEEN DESIGN AND CONSTRUCTION

SONG HONGBIN

(M. Eng.)

A THESIS SUBMITTED

FOR THE DEGREE OF MASTER OF ENGINEERING

DEPARTMENT OF CIVIL ENGINEERING

NATIONAL UNIVERSITY OF SINGAPORE

2004

Page 3: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

ACKNOWLEDGEMENT

I would like to express my gratitude to many people who have supported me in

my study and my life at NUS.

First of all, I am deeply indebted to my supervisor, Associate Professor Chua

Kim Huat, David for his thoughtful guidance and instructive advices during the course

of study.

Appreciation is also given to the persons in the company I visited, who offered

time and data to help me understand real AEC projects.

I also wish to thank my colleagues. They have consistently provided valuable

suggestions for my research and have created a comfortable environment for work.

Finally, I appreciate the efforts of my parents and friends, who always

encourage me to work hard.

i

Page 4: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

TABLE OF CONTENTS

ACKNOWLEDGEMENT…………………………………………………..… i

TABLE OF CONTENTS………………………………………………...……. ii

SUMMARY………………………………………………………………..…... v

LIST OF FIGURES……………………………………………………..…….. vii

LIST OF TABLES………………………………………………………..…… x

CHAPTER 1 INTRODUCTION……………………………………………... 1

1.1 BACKGROUND………………………………………………………… 1

1.2 RESEARCH OBJECTIVES……………………………………………... 3

1.3 RESEARCH METHODOLOGY………………………………………… 4

1.4 RESEARCH CONTRIBUTIONS………………………………………... 4

1.5 DISSERTATION OUTLINE…………………………………………….. 5

CHAPTER 2 LITERATURE REVIEW........................................................... 6

2.1 COORDINATION……………………………………………..………… 6

2.2 PRODUCT AND PROCESS INTEGRATION………………………..… 9

2.3 PRODUCT MODEL…………………………..…………………………. 14

2.3.1 Introduction…………………………..…………................................ 14

2.3.2 Product Models………………………………..…………………….. 16

2.4 DESIGN MANAGEMENT……………………………..……………….. 20

2.4.1 Characteristics of Design……………………………..……………... 22

2.4.2 Design Process Management…………………..……………………. 26

2.4.3 Design Change Management………………..………………………. 30

2.5 CONSTRUCTION MANAGEMENT………………………..………….. 33

ii

Page 5: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

2.6 CONCLUSION………………………………………..…………………. 34

CHAPTER 3 MODEL DEVELOPMENT…………………………..……….. 36

3.1 WHY USE PRODUCT AS INTERFACE?................................................ 36

3.2 HOW TO REALIZE THE PRODUCT-ORIENTED COORDINATION? 37

3.3 MODEL FRAMEWORK……………………………..…………………. 41

3.3.1 Product and Parameter………………………………..……………... 42

3.3.2 Design Process and Parameter………………………………..……... 47

3.3.3 Construction Process and Parameter………………………...………. 55

3.4 COORDINATION ANALYSIS…………………..……………………... 60

3.4.1 Form Original Network…………………………………...…………. 60

3.4.2 Analyze and Manage the Network……………………………..……. 62

3.5 CONCLUSION…………………………..………………………………. 67

CHAPTER 4 CASE STUDY………………………………….......................... 69

4.1 INTRODUCTION……………………………..………………………… 69

4.2 INFORMATION FLOW ANALYSIS………………………………..….. 72

4.2.1 Internal Information Flow…………………………………..……….. 72

4.2.2 External Information Flow………………………………..…………. 74

4.3 MODEL FRAMEWORK………………………..………………………. 79

4.3.1 Identification of Key Parameters……………………..……………... 79

4.3.2 Analysis of Design Process………………………………..………… 81

4.3.3 Analysis of Construction Process……………………………..…….. 85

4.4 COORDINATION ANALYSIS………………..………………………... 86

4.4.1 Form Original Network………………………..…………………….. 86

4.4.2 Analyze and Manage the Network………………………..…………. 89

4.5 CONCLUSION………………………..…………………………………. 97

iii

Page 6: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

CHAPTER 5 CONCLUSIONS AND RECOMMENDATIONS...………..... 99

5.1 CONCLUSIONS..……………………..…………………………………. 99

5.2 RECOMMENDATIONS FOR FUTURE WORK…………………...….. 101

REFERENCES…………………..…………………………………………….. 103

iv

Page 7: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

SUMMARY

Design and construction are two of the most important stages in the lifecycle of

an AEC project. Traditionally, the AEC industry has separated these two stages,

resulting in numerous problems since the constraints that each stage puts on the other

cannot be fully taken into account. In recent years, design-build has been proposed as

an optimal project delivery approach aiming to integrate design and construction. The

success for design-build requires careful consideration of the interdependent

relationships between design and construction. Problems often occur due to

inappropriate management of these relationships. Thus, it is imperative to improve the

coordination between design and construction.

This thesis proposes a model to coordinate design and construction activities.

The model aims to manage the interdependence between design and construction. The

coordination model employs product as the interface since it is the common link

between design and construction. The framework of the model is composed of four

main parts, namely, parameter, product, design and construction. Parameters play an

important role in the coordination, connecting product with design and construction.

Any product component can be described by a set of parameters corresponding to

different properties of the component. At the same time, parameters are also important

to depict design and construction processes since the design activities are concerned

with the determination of these parameters while the construction activities realize

these parameters based on their values determined in the design stage. For a parameter,

it can be in different states during design and construction. Thus a state chain pictures

the evolution of the parameter. The state transformations correspond with different

process activities in design and construction. A process activity is characterized by its

information inputs and outputs which can be described using parameter states.

v

Page 8: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

Furthermore, much related information about parameter states can be grouped to form

deliverables (drawing, as-built measurement, etc.).

The whole dependency network is formed by connecting the process activity—

parameter state relationships. The network is inherently a network of information

dependencies which represents the links between process activities and their

information constraints. The fundamental purpose of coordination is to ameliorate the

relationship between required information flows and corresponding process sequence.

This thesis suggests several practical means to deal with information coordination

problems.

This thesis also presents a case study to illustrate the working principles of the

coordination model. The coordination model should be effective in dealing with

design-construction coordination issues. This model may be of great benefit to project

managers who are always frustrated by coordination problems between design and

construction. Thus, the application of the model may improve the efficiency of AEC

projects.

vi

Page 9: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

LIST OF FIGURES

Figure 2.1 Information Flow and Coordination of Production Processes…….....

Figure 2.2 Functional Tree of the Conceptual IA Framework…………………..

Figure 2.3 Overall Structure of the RATAS Model……………………...……...

Figure 2.4 Class Diagram of Building Entity………………………...…………

Figure 2.5 IDPM Node Tree……………………………...……………………..

Figure 2.6 Design Information Flow Model within a Level of Abstraction….....

Figure 2.7 Parameter Dependency Network………………………………...…..

Figure 2.8 Three Typical Relationships for Two Design Tasks…………...……

Figure 2.9 Design Loop…………………………………………………...…….

Figure 3.1 Relationship between Design/Construction and Product………...….

Figure 3.2 Activity and Parameter………………………………………...…….

Figure 3.3 Basic Structure of the Model…………………………...……………

Figure 3.4 Hierarchical Decomposition of Building Product………………...…

Figure 3.5 Parameter Classification………………………………...…………...

Figure 3.6 Basic Parameter and Derived Parameter………………………….....

Figure 3.7 State Chain of a Basic Parameter………………………………...….

Figure 3.8 State of a Derived Parameter………………………………...………

Figure 3.9 Typical Design Process………………………………………...……

Figure 3.10 State Transformations of a Basic Parameter in Design Stage...……

Figure 3.11 Preliminary and Check………………………………………...…...

Figure 3.12 Review and Refine………………………………………………….

Figure 3.13 Application of As-proposed State…………………………………..

Figure 3.14 Design Process……………………………………...………………

Figure 3.15 State Transformations of a Basic Parameter in Construction Stage..

8

10

17

18

21

23

24

26

27

37

39

41

42

43

44

45

46

48

49

50

51

54

56

58

vii

Page 10: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

Figure 3.16 Construction Activity and Input/Output………………...………….

Figure 3.17 Construction Process……………………………………...………..

Figure 3.18 Original Network…………………………………………...………

Figure 3.19 Original Plan…………………………………………...…………...

Figure 3.20 Result after Re-ordering……………………………………...…….

Figure 3.21 Original Activities………………………………………...………..

Figure 3.22 Parameter Dependencies in Activity 1…………………………......

Figure 3.23 Divide an Activity into Two Sub-activities…………………...……

Figure 3.24 Use an Earlier State……………………………………...…………

Figure 4.1 Perspective Views of a Glass Wall…………………………………..

Figure 4.2 Glass Wall Project…………………………………………...………

Figure 4.3 Glass Wall Design……………………………………...……………

Figure 4.4 Information Flows in the Glass Wall Project………………………..

Figure 4.5 External Information Constraints……………………………...…….

Figure 4.6 Inter-participant Information Dependency……………...…………...

Figure 4.7 Procedure for External Shop Drawing Design…………………...….

Figure 4.8 State Chain of D(S)…………………………………………...……...

Figure 4.9 State Chain of D(G)…………………………………………...……..

Figure 4.10 Glass Wall Shop Drawing Design……………………………...…..

Figure 4.11 Glass Wall Fabrication Drawing Design………………………...…

Figure 4.12 Glass Wall Construction Activities……………………………...…

Figure 4.13 Steel Beam Construction Activities………………………...………

Figure 4.14 Original Network……………………………………………...……

Figure 4.15 General Representation of the Network………………………...….

Figure 4.16 Traditional Plan and Information Dependencies…………...………

58

60

61

63

63

64

65

66

67

70

70

71

73

75

77

78

80

81

83

84

86

86

87

89

90

viii

Page 11: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

Figure 4.17 Solutions for the Coordination Problems………………...………...

Figure 4.18 Parameter Dependency Network after Adjustments………………..

93

96

ix

Page 12: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

LIST OF TABLES

Table 3.1 State Description…………………………………………………………

Table 4.1 External Information Constraints…………………………………….…..

Table 4.2 Parameter Identification………………………………………………….

Table 4.3 Design Activities…………………………………………………………

Table 4.4 Construction Activities…………………………………………………..

45

76

79

82

85

x

Page 13: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

CHAPTER 1

INTRODUCTION

1.1 BACKGROUND

The architecture, engineering, and construction (AEC) industry has a long

history. It contributed and is contributing to the development of world economy.

Meanwhile, theories and technologies in AEC have been developing and maturing. A

lot of research work has been done in managing AEC projects so as to improve the

effectiveness and efficiency.

An AEC project is very complex in that it is composed of many interconnected

stages and there are a lot of interdependent participants (Olsson, 1998; Rivard et al.,

1995; Sanvido, 1992). These stages include design, procurement, construction,

maintenance and so on, each of which contributes to the intended project based on the

predefined role. Among the participants involved in a project are client, architect,

structural engineer, service engineer, contractor, sub-contractor, supplier, facility

operator, to name a few. An essential ingredient of a successful project is good

communication and collaboration between the project participants. Due to the

fragmentation of these stages and the large number of participants required by the

increasingly complex and dynamic nature of today’s projects, the need for well-

structured collaboration and coordination has become more important than ever.

In the stages to realize a project, design and construction are of great

importance and have been the areas of much research (Luiten et al., 1998). Design

stage transforms client requirements into drawings and specifications, which are then

turned into reality through construction stage. Traditionally, design and construction

are treated as two relatively isolated processes (Anumba and Evbuomwan, 1996), each

1

Page 14: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

of which is completed by its own team members, namely designers or contractors. This

renders many problems (Anumba and Evbuomwan, 1996) since the constraints that

each stage puts on the other are not fully considered (Austin et al., 2000a). Thus, the

integration of design and construction has been proposed to be the optimal approach to

successfully eliminate some of the major problems in the AEC industry. In recent

years, the AEC industry has witnessed a growing interest in the area of integration of

design and construction (Anumba and Evbuomwan, 1996). Furthermore, AEC clients

are looking for companies that can provide complete products to them rather than

separate ones (Luiten et al., 1998). All these promote the design/build project delivery

approach aiming to integrate these two stages. Because of its obvious advantages

compared with traditional approach, design/build has become more and more popular

in practice.

However, the success for design/build is not always as easy to reach as

expected. Design/build only aligns the interests of designers and constructors. When it

comes to production level, many efforts need to be taken to coordinate design and

construction. At the production level, a variety of constraints must be fully taken into

account in order for design and construction work to be carried out successfully. These

constraints include engineering, resources, prerequisite work and so on which come

from diverse sources such as clients, designers, contractors, and external regulating

authorities. For the coordination of design and construction, the most important

constraints are the inter-stage constraints. In other words, design provides information

as prerequisite to construction and construction may affect design by as-built

measurement information feedback. Since these constraints involve both designers and

contractors, the management of them is a formidable task. In addition, it is now

common that AEC clients are demanding that projects be delivered in greatly reduced

2

Page 15: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

time frames (Bogus et al., 2000). This exacerbates the coordination problem. Thus, it is

imperative to deal with coordination between design and construction.

1.2 RESEARCH OBJECTIVES

The main objective of the dissertation is to develop a model to coordinate the

design work and construction work in an AEC project. The model aims to deal with

the interdependent relationships between design and construction. Since the

interactions between design and construction cannot be separated from design process

and construction process, relevant design knowledge and construction knowledge

should be included in the research to deal with the interactions. For design, the analysis

is biased toward the later stages which tend to be relatively structured and concentrates

less on the conceptual, creative or otherwise unstructured aspects. For construction, the

original network is deemed to be available. Then the main work focuses on the

management of relationships between design and construction and within design stage

while the construction stage is less discussed. However, this doesn’t mean that

construction knowledge will not be addressed. The traditional construction network

needs some changes to cater for the need of coordination. The relationships are formed

in terms of information requirement/production. However, the information involved in

AEC projects is highly complex. This study mainly deals with information produced

during design and construction while paying less attention to the various requirements

and constraints which come from clients, regulating authorities, codes and so on.

Below are the specific objectives:

1. Propose an appropriate coordination mechanism. A proper mechanism is very

important to the success of coordination between design and construction. This

mechanism should be able to effectively deal with the relationship between

design and construction.

3

Page 16: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

2. Establish information requirement/production for design and construction. The

relationship between design and construction is formed based on information

dependencies.

3. Derive dependency network. Through information dependencies, a network

will be established which includes both design and construction. It is the whole

network that is of concern. This network is the basis for coordination.

4. Analyze and manage the dependency network. The dependence network

provides information dependences for process. Some typical approaches will be

suggested to manage the dependence relationships so as to improve the

coordination.

1.3 RESEARCH METHODOLOGY

The research was conducted as follows:

(1) Find out coordination problems existing in AEC projects;

(2) Determine the basic research direction;

(3) Detailed literature review to have an understanding of the research direction;

(4) Determine specific research scope;

(5) Propose models to solve the problems;

(6) Collect data in case study;

(7) Use the case data to testify and optimize the model.

1.4 RESEARCH CONTRIBUTIONS

Through the coordination model, the two relatively independent networks --

design network and construction network, can be connected. This insures that as much

relevant information as possible is made available to the involved party that requires it

4

Page 17: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

in design and construction. Thus, continuous information flow is achieved so as to

improve the coordination.

This model may be of great benefit to project managers who are always

frustrated by coordination problems. In AEC projects, coordination-related problems

often occur between design and construction. Using this model, these problems may be

settled with ease. Thus, the application of the model may improve the effectiveness

and efficiency of AEC projects.

1.5 DISSERTATION OUTLINE

This chapter briefly introduces the scope of the research. Chapters 2 to 5 will

present the dissertation clearly. To enable readers to fully understand the research

concept, chapter 2 gives a detailed review of the relevant work that has been carried

out in the research area. As the main part of the dissertation, chapter 3 describes the

proposed model. After that, chapter 4 presents a case study to illustrate the working

principles of the model. Finally, chapter 5 provides conclusive remarks for the

dissertation.

5

Page 18: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

CHAPER 2

LITERATURE REVIEW

Extensive literature review has been conducted to gain a better understanding

of the research topic. The materials reviewed cover five key research areas, namely,

coordination, product and process integration, product model, design management and

construction management, which are all related to the intended research topic.

2.1 COORDINATION

Coordination problems arise naturally in a variety of disciplines such as

engineering design, computer science, organization theory, sociology, political science,

management science, systems theory, economics, linguistics, and psychology. In

recent years, there has been a growing interest in coordination-related problems. Since

coordination is a crucial problem in almost all these disciplines, it has been an area of

much research and continues to be a focus of considerable attention.

Coordination has a variety of definitions (Malone and Crowston, 1990, 1994).

Malone and Crowston (1994) suggested that “Coordination is managing dependencies

between activities.” In an AEC project, the different tasks are interdependent in one

way or another since they are related to the same project (Olsson, 1998). This suggests

that Malone and Crowston’s definition is applicable to the AEC industry. The need for

coordination is closely related to the degree of interdependence between different

activities (Kadefors, 1995). Different kinds of dependencies need different

coordination processes to manage them (Malone and Crowston, 1994). Furthermore,

Malone and Crowston (1990) concluded that interdependence between activities can

be analyzed in terms of common objects that are involved in some way in these

6

Page 19: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

activities. This idea is very important since it suggests a coordination mechanism

which is adopted in this research.

In addition, Albino et al. (2002) showed that the coordination of a process

mainly consists of the processing of the information necessary for the management of

interdependent activities. They proposed a methodology to describe and analyze the

information flows involved in the coordination of production processes. In their

methodology, a production process is considered as an information processing and

communication system where actors (resources) perform tasks, send and receive

messages, and process information. Information flows consist of exchanged messages

and information processing activities which are necessary for the process coordination

and deal with such issues as the agreement among decision-makers. Figure 2.1 shows

the framework of their methodology. The key factors affecting the information flow

within a production process are identified including the production process, the

coordination form, and the context. Based on these factors, the methodology can derive

a quantitative index that measures the information flows, i.e. the effort required to

properly coordinate the production process. By simulating different coordination

mechanisms of the process, the associated quantitative index can be used to select the

best options.

While the idea is accepted that the coordination of a production process is

closely related to the information flows, and indeed it is used as a fundamental basis

for the proposed model in this research, it is questionable that the methodology can be

applied to the intended research topic. The main objective of this methodology is to

measure information flows on the premise that production process network is available.

In other words, only after the task dependencies are identified, can the information

flows be derived. However, what the intended research concerns is the coordination of

7

Page 20: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

the process based on information flows rather than the measurement of information

flows in the coordination process.

Production Form of Context coordination process

Information flow

Figure 2.1 Information Flow and Coordination of Production Processes

This research intends to deal with coordination problems between design and

construction in AEC projects. The basic ideas in coordination theory can be adopted in

this research. Thus, analysis of interdependencies between design and construction is

fundamental to coordination. Since AEC area is information-intensive, information

flow exists between design and construction. Coordination will focus on information

related dependence relationships. A proper mechanism is essential to the success of

Satisfactory?

Coordination technology taxonomy

no

yes

Coordination technology

choice

8

Page 21: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

coordination. In an AEC project, design and construction are all related to the product

information. Thus, coordination between design and construction can use the common

object -- product as interface.

2.2 PRODUCT AND PROCESS INTEGRATION

The AEC area is information-intensive (Shahid and Froese, 1998). Over these

years, the industry has always been bedeviled with great difficulties in managing

information flow among its participants (Ndekugri and McCaffer, 1988). With the

increasing complexity of AEC projects, effective management of information has

become more and more critical throughout the life of AEC projects. The industry has

always been looking for approaches and tools to streamline the job of information

management (Rezgui, 2001).

To address information management in AEC industry, it is necessary to

develop an understanding of the information within an AEC project. Sanvido (1992)

presented an Information Architecture (IA) to picture the information contents in an

AEC project. Figure 2.2 shows an overview of all the IA elements. The Information

Architecture consists of five separate but related classes of information, namely,

product, process, process control, feedback, and constraints. Another effort in

modeling the information contents is the various project models. Project modeling

primarily deals with the overall information in a project (Luiten et al., 1993; Luiten et

al., 1998; Stumpf et al., 1996). The most important project models developed include

Unified Approach Model (Bjork, 1992a), GenCOM (Froese, 1992), BPM (Luiten and

Bakkeren, 1992; cited in a review by Luiten et al., 1993), IRMA (Luiten et al., 1993)

and ICIM (Stumpf et al., 1996).

These models provide frameworks for the overall information classes in an

AEC project. It can be seen that product and process are two of the most important

9

Page 22: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

10

Page 23: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

elements, which deal with different kinds of information (Platt, 1996). They are

regarded as different views about the project, while each provides a valuable

contribution. Product mainly deals with static project information. It contains

information regarding what the product looks like. Product status changes with the

progress of the process. Although a product undergoes changes as process advances, it

provides little information on how these changes can be achieved. Consequently,

product information is inadequate for dealing with the dynamics of a project. By

contrast, process is rich in information on how a product is transformed from one state

to another. It is the dynamics that are of concern. However, process itself provides

little insight into the structure and requirements of data within the product.

Traditionally, product and process have been developed independently since

the focus on them is quite different (Froese, 1996). This eases the development and

makes the model development more flexible (Dubois and Cutting-Decelle, 1996).

There is, however, a growing awareness that if these two kinds of models could be

successfully integrated with each other, there would be cumulative benefits to be

achieved throughout the design and construction process (Platt, 1996). In reality,

product and process are interrelated in that process is responsible for product change

and product provides information constraints to process, which provides the

opportunity for integration.

To make the integration possible, Dias and Blockley (1994) identified a close

structural correspondence between product and process models for design through the

definition of the role as a generic unit. A process model role has been defined as a

collection of responsibilities while a product model role is simply a collection of

functions. The organizational relationships of roles have been identified including

aggregation/decomposition and generalization/specialization. Such correspondence

11

Page 24: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

makes the design process efficient and synergistic. However, this effort only tries to

provide structural correspondence between product and process, while

interrelationships between product and process have been given less attention.

Furthermore, Lee et al. (1996) developed an entity-based integrated design product and

process model which used product and process entities to describe design information

and design activities, respectively. In this model, the relationships among the entities

were identified including organizational, interaction, and sequence relationships.

Organizational relationships provide a logical arrangement of product and process

entities by organizing entities into hierarchies. Interaction relationships refer to the

interdependent nature among product information while sequence relationships

identify the sequences in which process entities are initiated during the design process.

In this model, the researchers present formal representation for entities and

relationships so as to provide a clear understanding of and a theoretical basis for the

computer-integrated design system. However, this model focuses on structural design,

providing a procedure for building structures design. This model cannot deal with the

design of other systems, which are also important for a building. It should be noted that

these efforts focus on product and process integration for design stage, while the

construction stage is not addressed.

As a major effort to model information classes, the various project models also

provide information to product and process integration (Froese, 1996). These models

show the relationships between the information elements including product and

process. Generally, they treat product as design results and focus on the construction

stage when it comes to process analysis. Thus they only provide mechanisms for the

integration of design results (product information) with construction process (process

12

Page 25: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

information). The design evolution information is rarely discussed in detail in these

frameworks.

As another effort, Sanvido (1992) explored an approach to linking the different

levels of abstraction of a building design to both a product and a process model. In this

approach, design and construction are all included in the process model. Thus, design,

construction and product can be connected in this approach. For design and

construction, however, this approach only considers one-way information flow -- from

design to construction. The as-built information feedback is not taken into account

which flows from construction to design.

The integration of product and process establishes the connection between

product and process, which is considered as one necessary step for the product-

oriented coordination. As described, researchers have done much work in this area and

they employ different mechanisms to integrate product and process. While these

researches are beneficial, they all have some limitations in terms of coordination

between design and construction. Generally, process objects are at the very kernel of

these models. The linking between design and construction is performed from a

process viewpoint in that process and product are connected through process output,

which is defined as group of documents. Thus the linking only provides high-level

relationships between product and process. Detailed information links between design

and construction cannot be tracked in these models. The proposed model in this

dissertation also involves product and process integration. However, it deals with this

problem from a different viewpoint—parameter viewpoint. It is a more efficient tool

with the capability to deal with the coordination between design and construction

based on the evolution of parameters.

13

Page 26: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

2.3 PRODUCT MODEL

In recent years, computers have been used in numerous disciplines. Because of

their apparent advantages, computers have also become prevalent in the AEC area. The

use of computers considerably improves the capacities of handling the huge amount of

information that characterizes an AEC project, which is deemed almost unbelievable

for manual, paper-based work. However, most of the applications are isolated, which

makes the information sharing and exchange impractical. Thus, computer integrated

construction (CIC) emerges with the aim to integrate the different applications.

Research and development in the area of CIC has been looking into various aspects of

fragments in the construction industry (Turk et al., 2000), exploring the sharing and

exchange of project information among all project participants and all project life-

cycle stages.

A cornerstone of CIC is the development of data standards, i.e., common

information models (Froese, 1996). Among them is the development of standards for

the description of buildings in computerized form, so called product models. The

introduction of product models represents a revolution to information handling in that

the use of product models ease information exchange and information sharing.

2.3.1 Introduction

A product model is a conceptual description of a product which includes the

necessary information for that product. Product models contain large amount of

information regarding products. Generally, a product model is developed as a common

language for a particular type of product rather than as a representation for a single

product (Bjork, 1992b).

Several scholars (Bjork, 1989; Bjork and Penttila, 1989; Rivard and Fenves,

2000) addressed the requirements for product models. Two of the most important

14

Page 27: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

requirements are multi-view representation and dynamic extension, which are essential

characteristics for a practical product model. Multi-view representation is necessary for

a product to accommodate different disciplines (Dias, 1996; Howard et al., 1992;

Rivard et al., 1999; van Nederveen and Tolman, 1992). It is the foundation of

collaborative design (Rosenman and Wang, 1999). Functions are considered as the

basis for multi-view representation since different disciplines are interested in different

functions of a product (Rosenman and Gero, 1996). Furthermore, a product model

should be extensible since it is very difficult to develop an all-inclusive product model

(Eastman, 1992; Eastman and Fereshetian, 1994; Ekholm and Fridqvist, 1998; Rivard

and Fenves, 2000). Thus, a product model acts as a basis for application so that a user

can create new information when necessary.

The basic concepts used in almost all product models are objects, attributes and

relationships (Bjork, 1992b; Eastman and Fereshetian, 1994; Shimodaira, 1992). They

play fundamental roles in product modeling. An object may correspond to a physical

or abstract entity meaningful to the product. Objects use attributes to represent their

different aspects of properties. Relationship is used for connecting objects. The two

basic types of relationships are decomposition/aggregation and

specialization/generalization. Decomposition/aggregation is used for relating different

level objects. Generally, the low level objects have “part of” relation with high level

object in the decomposition/aggregation relationship. A given global product can have

a number of aggregation/decomposition hierarchies where objects can also display

cross-hierarchical interactions. Specialization/generalization is used to connect a class

of individual objects of similar types with a single named object. The basic idea is to

specify all general information on a class level and then to define additional

distinguishing parameters on the subclass level. Generally, “type of” relations exist in

15

Page 28: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

the specialization/generalization abstraction. In this abstraction hierarchy, data can be

managed efficiently by using common attributes which descendent objects inherit from

a generic object. These two kinds of relationships form two kinds of orthogonal

hierarchies where generalization/specialization hierarchies are defined at each

hierarchical level in the aggregation/decomposition hierarchy (Dias and Blockley,

1994). Generally, the generation/specialization hierarchies can be treated as libraries,

members of which are instantiated to form members of various

aggregation/decomposition hierarchies, which together constitute the model of the

global product.

2.3.2 Product Models

In the AEC area, a variety of product models have been developed by both

industry and academia. All these efforts aim to provide a foundation for product

representation. However, the application scope for these models is different. Some of

them are more generic and describe the information structure for a whole branch of

industry while others are more specific and describe the information structure for a

restricted type or family of products.

RATAS (Developed by the RATAS committee in Finland) is one of the best

known product models (Bjork, 1989, 1994; Bjork and Penttila, 1989). RATAS

provides an approach to describe building products. Figure 2.3 gives an illustration of

RATAS representation. Five abstraction levels, namely, building, system, subsystem,

part and detail, are used to describe a building functionally. Objects from the higher

levels are especially useful in early design stages for defining functional requirements

and for making high-level design choices while objects from the lower levels are more

tangible so that they correspond with detail design process. Each of the objects belongs

to at least one class. Classes can be arranged in meaningful hierarchies. Two types of

16

Page 29: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

relationships are used: part-of and connected-to. Generally, the part-of relationship

connects objects from different abstraction levels while connected-to relationships

connect objects from the same level (usually lower abstraction levels).

OBJECTS CLASSES

Building level

--------------------System level

--------------------

Subsystem level

--------------------

Part level

--------------------

Detail level

Figure 2.3 Overall Structure of the RATAS Model

Another important product model has been developed in SEED-Config, which

is one of the modules of SEED (Software Environment to support the Early phases in

building Design) (Fenves et al., 2000; Rivard and Fenves, 2000; Rivard et al., 1996).

This building representation consists of two levels of abstraction models defined on

top of the object-oriented data model. The first level is an information model, called

the BENT (Building ENtity and Technology) model, which defines a set of basic

constructs that can represent any building design domain. Figure 2.4 shows the class

17

Page 30: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

18

Page 31: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

diagram of the building entity and the other constructs. The second level is a

conceptual model that defines the types of objects, relationships, and data needed to

represent the information in a particular design domain. It refines the first level

representation by specifying the categories of information used in a particular domain.

SEED models provide representation for conceptual design of buildings. They store

design data as they are generated during conceptual design. The aim of these models is

to support early design exploration -- the fast generation of alternative design concepts

and their rapid evaluation against a broad spectrum of relevant and possibly conflicting

criteria. However, they are not applicable to later stages of design.

Other product models include EDM (Eastman, 1992), ICON (Ford et al., 1994),

GOOD_B (Biedermann and Grierson, 1995), CIMSTEEL (Crowley and Watson,

1997), and so on.

Most of these models are design-centric (Harfman and Chen, 1993) in that they

are closely related to the design process. They have been developed to support design

evolution and exploration (Rivard and Fenves, 2000). Since the end user’s concern is

space, spatial properties have been addressed by some authors to support the design

process (Bjork, 1992b; Eastman and Siabiris, 1995; Ekholm and Fridqvist, 1996, 2000;

Maher et al., 1997).

Although there are common objects for these different product models, each of

them has its own characteristics and application scope. The logical extension of these

models is standardization. Standard models are developed to guarantee some degree of

uniformity within different applications by using the same standards (Fischer and

Froese, 1996).

There are two most important international standardization efforts that address

the product models, namely, ISO-STEP (Burkett and Yang, 1995) and more recently

19

Page 32: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

IAI-IFC (Kiviniemi, 1999). Standard models also include LexiCon, which has been

developed by STABU (the Dutch national building specification organization)

(Woestenenk, 2002). LexiCon can be seen as an extension to STEP and IFC. All these

provide standards libraries from which a user can select necessary entities to model a

product. Although standardization has been accepted in the industry, there are still

some limitations for standard models (Rezgui, 2001; Tolman, 1999).

This research intends to deal with product-oriented coordination which uses

product information as the interface for coordination between design and construction.

Thus, product model is closely related to this research. However, this research focuses

on the application rather than the development of product models. The various efforts

in product modeling contribute much to this research by providing an understanding of

the basic ideas and concepts for product models. In the proposed coordination model, a

product is composed of different level components with relationships among them.

The components are described by parameters which correspond to different

characteristics of components.

2.4 DESIGN MANAGEMENT

Design is a problem solving stage. In this stage, the client’s requirements are

conceptualized into solutions which are generally represented using procedures,

drawings and technical specifications. Design is extremely important for the success of

a project since the quality of design has an extensive impact on all subsequent stages of

a project’s life cycle. IDPM (Integrated Design Process Model) provides a

comprehensive view of the entire design stage (Sanvido and Norton, 1994). It

represents the major functions and activities necessary for a successful design. Figure

2.5 shows the general break-down of the IDPM through its first three levels of detail.

20

Page 33: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

21

Page 34: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

2.4.1 Characteristics of Design

1. Evolution

Design is generally composed of several evolutionary phases including

feasibility study, conceptual design, preliminary design and final design. In each phase,

the design problem is partially solved at a level of abstraction (Wilson and Shi, 1996).

Along the stages of design, abstract concepts are incrementally refined so that design

solutions are determined in more and more details. Throughout the evolution of the

design process, information continues to flow and accumulate. The work to capture,

store, and retrieve design information is one of the major challenges in design

management.

Shooter et al. (2000) proposed a design information flow model which

concentrates on the information that flows among individual design activities

regardless of the activities’ particular sequence. It aims to support a semantics-based

approach for developing information exchange standards. The model organizes design

information into levels of abstraction, each of which is a view of a design problem that

includes only the issue designers are considering relevant at a given time in the design

process. Then it identifies the various transformations within a level of abstraction and

between levels of abstraction. Figure 2.6 shows the design information flow model

within a level of abstraction.

As another effort, de la Garza and Alcantara Jr. (1997) suggested the

representation of design evolution information using parameter dependency network

(PDN). PDN shows how other object-parameter pairs affect a certain object-parameter

pair. Designers solve decision problems by determining required functions and

transforming these requirements into specific performance parameters. These

performance parameters then form the basis for the generation and evaluation of

22

Page 35: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

23

Customer Needs

Family of Solutions Unbound Behavior Intended Description Model Behavior

Proposed Artifact

Bound Description

Specifications

Engineering Requirements

Observed Behavior

Evaluated Behavior

Evaluated Requirements

Refine/Revise

Refine/Revise

QFD, etc.

Refine/Revise

Brainstorming Synectics, etc.

(Re)select

(Re)bind

Simulation

Figure 2.6 Design Information Flow Model within a Level of Abstraction

Page 36: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

design alternatives. This approach is based on a representation of object design

rationale as performance criteria. Figure 2.7 shows an example of the PDN. In Figure

2.7, the object-parameter pair Mechanical Room--Function affects the object-

parameter pair Mechanical Room--Fire Resistance Rating, which, in turn, affects the

object-parameter pairs Door--Fire Resistance Rating, Wall--Fire Resistance Rating,

and HVAC Equipment--Fire Resistance Rating. Then these performance parameters

are used to select door, wall and HVAC equipment materials.

Figure 2.7 Parameter Dependency Network

All these efforts focus on the knowledge representation. They provide

understanding for the design process evolution.

2. Multidiscipline

Design is multidisciplinary in nature in that it involves clients, architects,

designers, contractors and so on, each of which has its own area of concern. Experts

from these disciplines, loosely organized as a design team, work together to finish the

Mechanical Room Function

House HVAC Equipment

Mechanical Room Fire Resistance Rating

2 hours

Door Fire Resistance Rating

2 hours

HVAC Equipment Material Brand Z

Wall Fire Resistance Rating

2 hours

HVAC Equipment Fire Resistance Rating

2 hours

Door Material Brand X

Affected By Affects

Legend

Wall Material Brand Y

Object Parameter

Value or Constraint

24

Page 37: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

design of a project. Communications among these participants are frequently impeded

(Rivard et al., 1999). A quality design is highly dependent upon effective collaboration

and coordination among the diverse disciplines to produce a coherent set of final

design documents. Generally, these participants are geographically distributed so that

much research work has been done related to distributed design coordination and

collaboration (Anumba et al., 2002; Brazier et al., 2001; Rosenman and Wang, 2001;

Tiwari and Gupta, 1995; Wang et al., 2002; Whitfield et al., 2002). During these years,

a variety of coordination approaches and systems have been developed in the field of

engineering design (Coates et al., 2000; Whitfield et al., 2000). More recently, lean

thinking principles have been adopted to coordinate different design disciplines

(Andery et al., 2000). Furthermore, as a step towards effective design coordination,

Hegazy et al. (1998) conducted a questionnaire survey related to design coordination at

the inter-team level and the interdisciplinary level as well. This questionnaire reveals

the coordination problems encountered and solutions to resolve them. In addition, Law

and Krishnamurthy (1996) developed a three layered data management model for

multidisciplinary collaboration design. All these efforts suggest the importance of

design coordination and collaboration.

3. Iteration

Design is distinct from other processes in that iteration and rework are

commonplace. Usually, the design work is performed in a process of iterative step-

wise refinement. Iterations represent conflicts in the flow of information within the

design process (Yassine et al., 1999). The presence of iterations leads to difficulty in

finding appropriate sequence of the design process activities (Smith and Morrow,

1999). As one of the principal causes for inefficient design, iterations drive up both

25

Page 38: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

development time and cost. Some mathematical models have been suggested to

minimize the number of iterations between design activities (Ahmadi et al., 2001).

These inherent characteristics contribute much to the complexity of design

projects. Due to the complexity of design, research has been conducted in diverse areas

related to design improvement (Hegazy et al., 1998).

2.4.2 Design Process Management

Generally, design is based on decomposition principles in that the design

process is decomposed into many tasks (Boujut and Laureillard, 2002). Each task

involves certain problem analysis which is necessary for achieving the goal of the

design. Information is treated as connector between tasks in that each task is driven by

certain input information and produces output information. The output information of

one task may affect the input information of another task (Lee et al., 1996). Thus,

relationships exist between these tasks. However, the information relationships

between tasks are highly complex in design projects. Figure 2.8 shows three possible

relationships for two design tasks based on input/output (Eppinger et al., 1994).

A A

A B

B B

Interdependent Tasks Dependent Tasks Independent Tasks (Coupled) (Series) (Parallel)

Figure 2.8 Three Typical Relationships for Two Design Tasks

It is common that tasks are mutually dependent on each other’s information output

(Ahmadi et al., 2001). The interdependent tasks comprise a loop, which may include

many tasks (Figure 2.9).

26

Page 39: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

Figure 2.9 Design Loop

Generally, it is easy to manage series and parallel relationships. However, the

management of coupled relationship is a formidable task. The success of a design

project requires the coordination of design tasks with complex information

dependencies between them (Ahmadi et al., 2001).

1. Tools

Streamlining design processes has always been regarded as an important step to

the success of design products. Many tools have been employed to structure processes

(Park and Cutkosky, 1999; Rogers, 1999). Traditional tools such as CPM and PERT

can be used in processes with sequential relationships. However, they are not

applicable to design process analysis since they cannot handle iterations and feedback

loops (Kusiak et al., 1995; Park and Cutkosky, 1999; Rogers, 1999; Smith and Morrow,

1999; Yassine et al., 1999). Thus, new tools have been developed to address design

process such as Incidence Matrix (Kusiak and Wang, 1993; Kusiak et al., 1995) and

DR (Design Roadmap) (Park and Cutkosky, 1999). However, IDEF0 and DSM may be

two of the most widely used tools.

As an influential tool, IDEF0 is frequently used in process modeling

(Malmstrom et al., 1999). In IDEF0 representation, the information modeling is

performed in four aspects, namely, input, output, control and mechanism. Furthermore,

IDEF0 can use top-down decomposition to break up a complex process into small sub-

processes. IDEF0 representation provides a good overview for a process, however, it

……..A (1) A (2) A (i) A (n) ……..

27

Page 40: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

suffers from practical size limitations in that IDEF0 models tend to grow fast in

complexity for a large number of tasks. Although IDEF0 can represent a process, it

does not offer any capability to optimize it. In addition, the IDEF0 methodology gives

weak support for the modeling of iterations and feedback loops, because of its strong

feed-forward focus. Since one of the challenges in design management is to deal with

iterations, a modeling technique for design should be able to handle them. The IDEF0

technique is weak in this area, which makes it less efficient for dealing with design

problems.

Another powerful tool is DSM, which provides a simple, compact, and visual

representation of a complex system by using a matrix. DSM is a very robust technique

that can be used in many different problems (Browning, 2001). A DSM helps identify

problem areas within a process and can support restructuring of it in order to make it

more efficient. DSM representation overcomes the size and visual complexity of all

graph-based techniques. It provides a better overview than IDEF0, since the

complexity of DSMs does not grow as fast as that of IDEF0 diagrams (Malmstrom et

al., 1999). Thus it can be applied to large problems, while maintaining a relatively

good overview of the problems. The primary advantage of the DSM format is the

capability to deal with iterations commonly found in a design project. The DSM

handles iterations well and is relatively easy to understand. Due to these advantages, it

can be used in the current research proposed model to deal with network analysis.

2. Models

Many models have been developed to manage design processes. However, they

address the problem from different viewpoints and apply to different conditions.

ADePT (Analytical Design Planning Technique) is a model with the capability

to schedule the building design process (Austin et al., 1999a, 1999b, 2000a, 2000b,

28

Page 41: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

2000c). The ADePT methodology is composed of three stages, namely, design process

modeling, DSM-based analyzing and design schedule generation. The first stage is the

creating of design process model (DPM). The model is represented using a modified

version of the IDEF0 methodology, which shows design activities and their

information flows. The data in the DPM are then linked to a DSM (Dependency

Structure Matrix) analysis tool in the second stage. DSM is used in this stage to

identify iteration within the design process and optimize the sequence of the activities

based on their information flows. This is the central part of ADePT methodology. In

order for DSM to be used as a means of controlling the design process, the analysis

result needs to be represented against a timescale. Thus the third stage produces a

design programme – a schedule for the design activities based on the optimised process

sequence determined in the second stage. DePlan is another model which combines

ADePT and Last Planner (Hammond et al., 2000). In this model, ADePT is used to

provide an improved design sequence while the Last Planner methodology will then be

used to schedule and control the design process. In addition, Clarkson and Hamilton

(2000) proposed “signposting”--a parameter-based model of design. The distinct

feature for this model is to use design parameters as a basis for identifying the next

task so as to form design process network.

These models aim to structure the design process from a process viewpoint in

that the design process is represented as a number of tasks which, when ordered

appropriately, enable successful design development. They employ different

mechanisms to order the process activities.

More recently, Chua et al. (2003) presented PPI (Process-Parameter-Interface)

model. This model is different from those activity-based models in that it is parameter-

centered. It focuses on the parameter relationships. This model can deal with the

29

Page 42: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

iterations and improve design knowledge sharing. Furthermore, it supports the

regrouping of parameters to form new tasks and networks. This model provides a

flexible representation of design process and can improve design process management.

It can be seen that two viewpoints are available for design management --

process viewpoint and parameter viewpoint. They are complementary to each other.

Process viewpoint focuses on the inter-task information transfers, however, they ignore

many important technical interactions among the engineering parameters, which can be

explicitly described from parameter viewpoint. The proposed model in this research

provides a better management of design by combining these two viewpoints.

Furthermore, parameter evolution will be taken into account. By employing these

approaches, the design process can be improved.

2.4.3 Design Change Management

Throughout the design process, changes are frequently introduced for many

reasons. The changes inevitably and continuously affect the quality of design

documents. Thus, the effective management of design changes becomes crucial to the

success of a project.

Design changes are in fact modifications to some design data. As the design

data are interdependent, the modifications normally impact other data. Until all the

related data are adjusted accordingly, the designs remain incompatible (Mokhtar et al.,

1998). In some cases, the designer who initiated the change may forget to inform other

affected designers. Therefore, the difficulty in design change management is how to

make designers of any discipline aware of all changes which affect their own design

(Mokhtar et al., 1998). This requires full understanding of the rationale behind the

original design.

30

Page 43: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

In recent years, a novel parametric approach was suggested to address the issue

of design changes (Soh and Wang, 2000; Wang and Soh, 2001). This approach can

facilitate the coordination of design information through managing design changes. A

parametric coordinator was proposed which provides each building component with

the linking knowledge. Then the design consistency between building components can

be achieved through the proposed linking knowledge as well as a group pattern module.

Furthermore, this study extended the technique of knowledge-based approach from

single-view 2D model to manage the relationships of entities between different views

by incorporating the projection knowledge and graphic inference. A corresponding

multiview constraint solver was developed. This knowledge-based constraint solver

can be combined with the linking knowledge between building components to

facilitate the coordination of design information for multiview models. This approach

essentially limits design changes to geometry-related information. Thus it aims at

resolving dimension-change problems.

In addition, some researchers presented information models to provide

improved design coordination through managing design changes (Hegazy et al., 2001;

Mokhtar et al., 1998; Zaneldin et al., 2001). The core idea of the model proposed by

Mokhtar et al. (1998) is to assign the task of design change propagation to the building

components themselves. Each component is equipped with the necessary linking

knowledge to identify the disciplines that are affected by a specific design change and

how they are affected. The model uses a central database to carry the building

components data and capture the linking knowledge in the form of rules. When design

change occurs to a building component attribute, the component checks all the rules

that are stored in the database. If any of these rules applies to the change, messages are

automatically sent to the relevant designers. In addition to its ability to propagate

31

Page 44: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

design changes, the model is capable of tracking past changes and helping in the

planning and scheduling of future ones. The model uses textual data rather than

drawings as the main media for storing and communicating design information and it

does not address the issue of automation of the design change process. Furthermore, it

does not capture design rationale, which is an essential requirement for properly

managing design changes. The design rationale information is incorporated into the

information model proposed by Hegazy et al. (2001) and Zaneldin et al. (2001). This

model is built around a central library of generalized building components that can be

used to describe a complete building project hierarchy. Each component allows the

designer to store desired performance criteria and related design rationale. Each

component is also sensitive to its own changes and automatically communicates such

changes to affected parties through preset communication paths. The rationale,

however, only identifies the components related to a component attribute. The

relationships between attributes of these components cannot be tracked directly.

All these models, as such, provide improved design coordination and control

over changes, thus helping to increase the consistency and productivity of the overall

design process. A common characteristic for them is the attaching of linking

knowledge to components, which serves as the basis of change propagation. Although

design change management will not be addressed in this research, the model in this

research provides potential to deal with design changes by employing product as the

interface for coordination. Design change is product-oriented in that it is generally the

modification of product component properties. Once product information is changed,

the related process information will be affected accordingly based on the product-

process connection. Thus, the proposed coordination model can also be used to

manage design changes if necessary.

32

Page 45: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

2.5 CONSTRUCTION MANAGEMENT

Managing construction is a highly practical profession. Demands for efficient

management and control in construction are growing due to the increasingly

complexity of construction projects. Areas in this scope include planning and

scheduling, estimating, cost control, accounting and so on. Planning and scheduling are

among the most important functions and much work has been conducted related to

these areas. The process of Planning and scheduling is typically done in a top-down

fashion. Generally, master, lookahead and commitment plan/schedule are three levels

of abstraction used by construction project managers. They are used in different

conditions and serve different functions.

Many tools have been developed to plan and schedule the construction work.

CPM and PERT are two of the most widely used tools. Other early planning systems

include OARPLAN (Darwiche et al., 1988) and MDA Planner (Jagbeck, 1994). More

recently, Fischer and Aalami (1996) suggested computer-interpretable construction

method models which support the automated generation of realistic construction

schedules. To take advantage of the increasingly accepted lean ideas, Choo et al. (1999)

suggested WorkPlan to systematically develop weekly work plans according to the

Last Planner method. Work packages are used as scheduling unit in WorkPlan.

Furthermore, Choo and Tommelein (2000) developed WorkMovePlan to address

distributed planning and coordination. WorkMovePlan can be employed to develop

lookahead plans and weekly work plans. In addition, as an effort to overcome the

limitations of traditional scheduling methods, Chua et al. (2003) proposed IPS

(Integrated Production Scheduler) as a new scheduling tool to help produce quality-

assured lookahead schedules. IPS enhances the reliability of planning by modeling two

additional types of hidden constraints on activities. In recent years, lean production has

33

Page 46: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

been applied in the area of construction management. By adopting lean ideas, Chen et

al. (2003) presented Information Flow Integrated Process Modeling (IFIPM) technique

to incorporate information flows into CPM planning. The technique can improve

construction productivity through balancing conversion processes and information

flows. All these planning and scheduling tools are process-oriented in that they all

schedule the construction work from process viewpoint. Starting from a different

viewpoint, Chua and Song (2003) and Song and Chua (2002) suggested POST

(Product Oriented Scheduling Technique) as an alternative intelligent scheduling tool

for programming construction work from the product point of view. The POST model

can reduce errors and improve constructability analysis.

Since construction management is not the focus of this research, these efforts

can be treated as the basis of construction network in the proposed model. However,

traditional construction network is weak in dealing with as-built measurement

information, which is very important to the coordination between design and

construction. The as-built measurement information is generally considered as side-

product of construction activities in the traditional construction network. In the

proposed model, a new kind of activities is added which produces as-built

measurement information. Thus, the proposed model can improve the coordination by

explicitly representing the as-built measurement information.

2.6 CONCLUSION

The work related to the proposed research topic spans across various areas

including coordination, product and process integration, product model, design

management and construction management. From the forgoing discussion of the

literature, researchers have mainly focused on process viewpoint, with limited

consideration on parameter viewpoint when it comes to design and construction

34

Page 47: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

analysis. Also, most of the research efforts related to parameter viewpoint dealt mainly

with design stage and treated a parameter as a whole. Although these features are

beneficial, they are not sufficient alone to meet the expectations of a coordination

model. The evolution of parameters should be taken into account from design to

construction. Another problem is the as-built measurement information feedback. Most

of the research efforts related to design-construction coordination only considered the

information flow from design to construction, while the as-built measurement

information feedback from construction to design was rarely discussed. The

shortcomings of these efforts lead to inefficient coordination. There is a clear need,

therefore, for an effective approach to address this crucial problem. The next chapter

will describe the proposed coordination model.

35

Page 48: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

CHAPTER 3

MODEL DEVELOPMENT

3.1 WHY USE PRODUCT AS INTERFACE?

This research intends to coordinate design and construction. A proper

mechanism is very important to the success of coordination. Based on the coordination

theory which deals with the interdisciplinary study of coordination, the

interdependence between activities can be analyzed in terms of common objects

(Malone and Crowston, 1990). In reality, product is the common link between design

and construction.

Product contains static project information. The basic objects in a product are

components, which can be in different abstraction levels such as system level,

subsystem level or individual entity level. In practice, design work and construction

work are all related to these components. Designers typically break down complex

design work into many parts, each of which is concerned with a set of specific and

meaningful product components. Detailed design tasks are based on these product

components. On the other hand, the construction work is also closely related to the

product components since the completion of a component or system of components

can be considered as the result of many relevant construction activities. It can be seen

that product is the common object for design and construction. The product, thus,

serves as the interface for coordinating design and construction. Figure 3.1 shows the

relationship between design/construction and the related product information. Since

product is used to describe static project information, design and construction results

can be recorded in product as product-design and product-construction information,

respectively. Design tasks treat product-design information as input/output, which is

36

Page 49: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

the basis to form design network. Similarly, construction network can be formed by

using product-construction information as input/output of construction tasks. In

addition, relationships also exist between design and construction in that construction

tasks need design result information as prerequisite and design tasks may require

construction result information as feedback.

produce Construction

Process

Product-Construction Information

Figure 3.1 Relationship between Design/Construction and Product

3.2 HOW TO REALIZE THE PRODUCT-ORIENTED COORDINATION?

As described, product can serve as the interface for the coordination between

design and construction. The realization of product-oriented coordination is through

parameters in that any product component can be described by a set of parameters

corresponding to different properties of the component. During the project, the design

activities are concerned with the identification, estimation and iterative refinement of

these parameters, until a sufficient level of confidence in these parameters is achieved

Product-Design Information

contain affect

produce Design Process

Product

37

Page 50: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

while construction activities realize these parameters based on their values determined

in the design stage.

Parameters play an important role in the coordination. They are not only

closely related to product, but also important to depict design and construction. To

representing design and construction, activity-based description and parameter-based

description are introduced in this study. Both types of descriptions are very useful and

insightful in different ways.

Activity-based representation provides an overview of a process. It makes

people have a clear understanding of what should be done to achieve the goal.

However, activity-based description has some limitations such as the lack of flexibility.

In activity-based representation, all the activities are predefined. It is well known that a

design process is flexible in that a variety of design activities can be defined to achieve

the design goal. Furthermore, activity-based representation aims to form design

activities network, while the relationships among the parameters cannot be represented

clearly. In activity-based representation, a design activity is characterized by a group

of parameters as input and another group of parameters as output. For one activity, it

seems as if the group of output parameters depends on the group of input parameters.

In reality, the relationships between the individual parameters are missed. In addition,

activity-based representation may provide a “false” sense for inter-activity information

transfer. In activity-based representation, if the output parameters of some former

activities are connected to a latter activity, it means that the latter activity depends on

those output parameters of the former activities. Sometimes this may not be true. The

real parameter that the latter activity depends on may be the derived parameter of those

dependent parameters. Generally, the derivation relationship is embedded in the latter

activity.

38

Page 51: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

P3

P1

Figure 3.2 Activity and Parameter

ACTIVITY 1 P2

P1 P3

P4

P2

P4

ACTIVITY 1

ACTIVITY 3

ACTIVITY 2

P1

P2

P5

P3

P4

P1

P2

P3

P4

P5 P

(a)

-------------------------------------------------------------------------------------------------

(b)

-------------------------------------------------------------------------------------------------

39

Page 52: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

Figure 3.2 shows activity-based representation and the real parameter

relationships. In this figure, (a) is the representation of individual activity and intra-

activity parameter relationships. From activity-based representation, it can only be

known that (P3, P4) depends on (P1, P2), while the real dependency is missed. (b) is

the representation of several related activities and inter-activity parameter relationships.

In the activity-based representation, “P5” depends on “P3” and “P4”. In reality, “P5”

depends on “P” which is derived from “P3” and “P4”. In this case, “P” is an implicit

parameter embedded in “ACTIVITY 3”.

With regard to a construction process, the general activity-based representation

is also inadequate for design/construction coordination. In the traditional construction

network, the as-built measurement information cannot be described clearly. In reality,

the as-built measurement information can also be represented from parameter

viewpoint.

Thus, to improve coordination, parameter relationships need to be explicitly

represented in sufficient level of detail. This would depend on the interface between

the different disciplines or teams. Parameter-based description documents the

relationships between individual parameters. Parameter-based description is very

important for coordination analysis since the information transfers between design and

construction (design information or as-built measurement information) are generally

parameter-based interactions. Furthermore, parameter-based representation supports

reorganizing of parameters based on the dependencies to form new activities, which

makes it more flexible.

It can be seen that activity-based description and parameter-based description

are complementary to each other. The former is strong in providing overall view but

inflexible and ignores too many important technical details, while the latter documents

40

Page 53: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

the detail relationships for parameters and supports flexible formation of process

elements but lacks the overall context. The combination of these two viewpoints can

enhance the coordination efficiency.

3.3 MODEL FRAMEWORK

Based on the previous analysis, the model is established which is composed of

four main parts, namely, parameter, product, design and construction. Product is

described by parameters while design determines the values of these parameters, which

will then be realized by construction. Figure 3.3 shows the basic structure of the model.

Product

describe

Parameter

realize

Design

determine

Construction

Figure 3.3 Basic Structure of the Model

A building product is composed of many inter-related components. A product

component can be a system, a subsystem, a structural frame, an individual entity such

as a column, a beam. Figure 3.4 shows the hierarchical structure of a building product.

It should be pointed out that this structure is only one option for building product

decomposition. It is possible for a building product to have other kinds of hierarchical

structures.

41

Page 54: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

--------------

Figure 3.4 Hierarchical Decomposition of Building Product

A component can be described by a set of parameters corresponding to its different

properties. For a parameter, it goes through evolution during design and construction.

That means it can be in different conditions with the progress of a project. The concept

of ‘state’ is used to represent various status of a parameter. The state transformations

correspond with different process activities in design and construction. The state

description is useful for process analysis since a process activity is characterized by its

information inputs and outputs which can be represented using parameter states.

Furthermore, parameter states can group to form deliverables such as drawings, as-

built measurement information units and so on.

3.3.1 Product and Parameter

Parameters are used to describe product components. “Parameter” is a broad

term given to the key variables that define the product components, which provide a

Building

Structural system

Electrical system

Architectural system

……….

Foundation subsystem

Frame subsystem

Column Beam ……….

--------------

---------------

……….

Basic element

--------------Building

--------------

--------------System

--------------

--------------

Subsystem

42

Page 55: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

better insight to the product. They cover various aspects of the product components

including physical properties (dimension, material), evaluation-related attributes (cost,

stress distributions), and so on. These key parameters are critical for the coordination

between design and construction.

Figure 3.5 Parameter Classification

Figure 3.5 shows the relationship between product components and parameters.

The parameters belonging to a component are called intra-component parameters since

they describe the properties of this component. The intra-component parameters are

classified into two types, namely, basic parameters and derived parameters. Basic

Derived Parameter

Basic Parameter

Component 1 Component 2

Derived Parameter

Intra-component Parameter Basic

Inter-component Parameter

Parameter

Derived Parameter

Derived Parameter

Basic Parameter

Basic Parameter

Component 3 Component 4

Derived Parameter

Intra-component Parameter

43

Page 56: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

parameters are those defining the component’s basic characteristics, such as its

dimension, material properties. Derived parameters are derived from the basic

parameters. Generally, a derived parameter is the combination result of several basic

parameters. For example, weight of a component is a derived parameter. It can be

derived from dimension and material properties of the component which are basic

parameters. However, a parameter may involve several components. In that case, it is

termed inter-component parameter. Inter-component parameters are generally derived

parameters which are related to the basic parameters of different components (such as

the gap between a mechanical duct and an electrical duct). In this figure, four groups

of intra-component parameters are presented, which belong to four different

components. At the same time, interactions exist between these components in that

some inter-component parameters are produced by the parameters of these components.

A “derivation” relation is used to represent the relationship between basic parameters

and the derived parameter (Figure 3.6).

P1

Figure 3.6 Basic Parameter and Derived Parameter

All parameters undergo evolution during product design and construction,

which can be pictured by state chains. Generally, typical state chain for a basic

parameter can be described as (Initial As-proposed As-confirmed As-

designed As-built As-built measured) (Figure 3.7).

[Derivation] P3

P2 P1, P2 – Basic parameters P3 – Derived parameter

44

Page 57: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

Initial (0) Undefined

As-proposed (1)

Figure 3.7 State Chain of a Basic Parameter

Initial represents the undefined state of the parameter, which is the starting point of

design analysis. (As-proposed; As-confirmed; As-designed) are the states in design

stage while (as-built; as-built measured) are the states in construction stage. The state

transformations correspond with different process activities in design and construction.

Table 3.1 State Description State No.

Name Description

0 Initial Starting point of design analysis Undefined

1 As-proposed Preliminary determination of parameter value

2 As-confirmed Parameter value is checked and confirmed by involved designers

3 As-designed Parameter value is ready for construction use

Design stage

4 As-built The related component is constructed

5 As-built measured Measurement value of parameter

Construction stage

As-built measured (5)

As-confirmed (2)

As-designed (3)

As-built (4)

Design Activity Design

Stage

Construction Activity

Construction Stage

45

Page 58: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

Table 3.1 provides description for these states. For a derived parameter, its states are

defined to match those of the basic parameters that derive it. As shown in Figure 3.8,

P3 is derived from basic parameters P1 and P2. If P1 and P2 are in state n, then P3 is

also in state n. This is generally the case since it ensures a coincidence between these

two kinds of parameters.

P1

n

Figure 3.8 State of a Derived Parameter

Parameter state chain provides clear evolution information for a parameter. At

the same time, it is also important for process analysis. In the traditional process

analysis, activity input and output are parameters rather than the states of parameters.

In reality, although several different activities need the same parameter, it is possible

for them to require a different status of the parameter.

Note that only the states in design and construction are shown since this

research aims to manage the interdependence between design and construction. A

parameter may have states in other stages of the project. Furthermore, the proposed

state chain for design and construction is only one option. It does not mean that all

parameters must undergo these states in any condition. For example, as-built measured

state only exists in such parameters whose as-built measurement information is useful

in coordination analysis. The intent of this research is to develop the basic concepts

P2

[Derivation] P3 “n” -- state n of the parameter

n

n

46

Page 59: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

rather than all the possible states. The state chain proposed can be changed based on

real conditions.

3.3.2 Design Process and Parameter

Design is flexible in that design processes vary widely from one organization to

another reflecting the cultures of design teams. Individual design teams can follow a

multitude of design process models for a same design project. As a result, it is almost

impossible to use one process representation to support a wide range of design projects.

Thus, the design process description in this research is only one choice. It allows

customization to any firm. Since process evolution is closed related to state

transformations, different process representation may require different state chain.

Designers solve a design problem through a continuous refinement where the

designers expand the problem’s description by incorporating additional detail. Figure

3.9 shows the typical design process.

Generally, the design process is composed of three stages, namely, preliminary

determination, check and confirm, and drawing review. After check and confirm,

drawings will be produced. The drawings will then undergo review activity which

intends to generate approved drawing. The review task is generally conducted by

external parties including the main contractor, architects, engineers and design

consultants. This process is represented in case 1.

However, for those components requiring shop fabrication, the design process

is slightly different. In that case, the shop drawing review will be followed by an extra

stage -- fabrication design, which produces fabrication drawings. The fabrication

drawing design is controlled by the shop drawing design. Generally, the fabrication

drawings do not need to be reviewed. The design process including fabrication design

is shown in case 2.

47

Page 60: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

Preliminary determination

Check and confirm

Approved drawing

Drawing Drawing Drawing review

Waiting for approval

Construction

Figure 3.9 Typical Design Process

Check and confirm

Shop drawing review

Approved drawing

Waiting for approval

Preliminary determination

Shop drawing

Construction

Fabrication design

Shop drawing Fabrication drawing

(a) Case 1

(b) Case 2

48

Page 61: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

Based on this process, a design activity itself may take the form of a

“Preliminary”, a “Check”, a “Review” or a “Refine”, which correspond to preliminary

determination, check and confirm, drawing review and fabrication design, respectively.

These activities are responsible for the state transformations of a basic parameter in

design stage (Figure 3.10).

Initial (0) Initial (0)

Figure 3.10 State Transformations of a Basic Parameter in Design Stage

A “Preliminary” transforms a parameter from initial state (state 0) to as-proposed state

(state 1), which will be turned into as-confirmed state (state 2) by a “Check”. For the

transformation from state 2 to state 3, two conditions exist which correspond with the

two design processes described previously. In case 1, the as-confirmed state (state 2)

information of parameters can be grouped into drawings. These drawings will undergo

“Review” activities, which can be performed by designers or external parties.

“Review” updates the information in drawings so as to produce approved drawings

which contain the as-designed state (state 3) information of parameters. In case 2, the

As-proposed (1)

As-confirmed (2)

As-designed (3a)

Preliminary

Check

Review

As-designed (3b)

Refine

As-proposed (1)

As-confirmed (2)

As-designed (3)

Preliminary

Check

Review

(a) Case 1 (b) Case 2

49

Page 62: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

as-designed state (state 3) is divided into two parts, namely states 3a and 3b. State 3a is

directly related to the reviewed shop drawings while state 3b is closely related to

fabrication drawings. From state 2 to state 3a, the procedure is similar to that of case 1.

However, there is a transformation from state 3a to state 3b in case 2, which is

completed by “Refine” activities. Thus, there are two typical state chains for design

stage, namely, (0 1 2 3) (case 1) and (0 1 2 (3a 3b)) (case 2).

As described, design activities are responsible for the state transformations in

design stage. However, a design activity may require external information to fulfill the

transformation function. The external information constraints may be produced by

other design activities, construction activities (as-built information feedback), or

external influences (loads). A design activity is characterized by its information inputs

and outputs. Different types of design activities have different types of information

inputs/outputs. Figure 3.11 and Figure 3.12 show the four kinds of design activities.

Background information

Figure 3.11 Preliminary and Check

P1

P2

P3 P4

External influence

1

1

0

Preliminary

n

1

2 2

Check

50

Page 63: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

unreviewed unreviewed

Drawing 1 Drawing 2

Figure 3.12 Review and Refine

Shop drawing

P5 P7

Shop drawing

unreviewed

reviewed

2

3a

3b

Fabrication drawing 1

5

P1 P2 P3 P4

Drawing 1 Drawing 2

reviewed reviewed

2

3

222

33 3

(a) Case 1

(b) Case 2

P6

2

3a

Review

Review

3b

Refine 1 Refine 2

Fabrication drawing 2

51

Page 64: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

For “Preliminary”, it transforms a parameter (such as P1) from the initial state (state 0)

to the as-proposed state (state 1). Generally, it needs “Background information” such

as general project information. In this respect, there seems to be a reliance on the

experience of designers. A “Check” is concerned with the evaluation of the as-

proposed state (state 1) based on component performance such as stress, deflection,

crack and so on. Other parameter states (such as P2 at state n) and “External influence”

(such as loads) may be involved in the “Check” activity. After “Check”, the as-

proposed state (state 1) is turned into as-confirmed state (state 2). For review, its input

and output are drawings — different states of drawings, namely “unreviewed” state

and “reviewed” state. Since drawings are connected with the states of parameters,

“Review” is related to parameter states (state 2 and 3 (3a)) indirectly. For the design

process involving fabrication design, “Refine” is responsible for parameter

transformation from state 3a to state 3b. As-built measurement information may be a

constraint for “Refine”. For example, “Refine 1” transforms P5 from state 3a to state

3b, which requires as-built measurement information, namely state 5 of P7.

It can be seen that other parameters may be involved in the state

transformations of a parameter. These external parameters may come from other

project participants. The source activities and participants of these parameters should

be found so that information responsibility can be clearly determined. These

interactions mostly happen in “Check” and “Refine” activities. For “Check”, the

involved state of other parameters may be the as-proposed state, the as-confirmed state,

the as-designed state or the as-built measured state depending on the project conditions.

Generally, later states give greater confidence for the parameter value. However, it

may take a longer time to obtain the parameter value of later states so that the related

activity is delayed. For “Refine”, it may involve as-built measured state (state 5) of

52

Page 65: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

other parameters since refine represents the fabrication design which generally requires

exact pre-design information.

Generally, as-proposed state (state 1) is not allowed to be used to produce other

parameters, since it is only the estimated value of a parameter. However, sometimes it

is necessary to use the as-proposed state of a parameter to save time. Although it

sacrifices the exactness of the parameter and is in danger of rework, it saves much time

which is considered more important in some projects. In this situation, the designed

component based on estimation will have extra capacity to buffer downstream design

parameters, although this may not be economical. An obvious case in view is

foundation design. For foundation design, the weight of aboveground structure is a

parameter. Theoretically, only after the design of the aboveground structure is

completed can its weight be obtained. However, since the construction of the

foundation precedes that of the aboveground structure, the design of foundation should

be completed as early as possible to save time. Then the weight of the aboveground

structure can be estimated so that it can be used in foundation design.

Figure 3.13 shows an example for the application of as-proposed state. This

example is about the design of a column and its foundation. D, M and W represent the

dimension, material and weight of the column, respectively. Foundation design needs

the weight of the column, which is derived from its dimension and material. In the

figure, (a) shows the relationship between column parameters and foundation design.

This is the general representation for information dependence. (b) shows the

relationship based on column parameter states. In this case, foundation design needs

the as-confirmed state (state 2) of W, which is derived from the as-confirmed state

(state 2) of D and M. In contrast, (c) shows the use of state 1 in foundation design.

Under this situation, foundation design can start with an estimation of the column

53

Page 66: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

D

[Derivation]

54

D

M

W

D – Dimension M – Material 1 – As-proposed state W – Weight 2 – As-confirmed state

Check Foundation

Design [Derivation]

M

W Foundation Design

(a)

(b)

(c)

1

1

2

2

D

M

W Check Foundation

Design [Derivation]

2

1

1

2

2

1

2

Figure 3.13 Application of As-proposed State

Page 67: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

weight (state 1 of W). The use of state 1 makes design flexible, which is important to

the information coordination.

The preceding section has identified the different kinds of design activities and

explained the relationships between design activities and parameter states. To better

understand design, Figure 3.14 provides an overview for design. This figure includes

four kinds of design activities and two kinds of drawings described previously. It also

shows the formation of the different kinds of design drawings. “Preliminary” is

responsible for P1 and P2’s transformation from state 0 to state 1, which requires

“Background information” to fulfill the transformation function. The state 1 of P1 and

P2 is then turned into state 2 by “Check”. “External influence” and state 2 of P3 are

external constraints for “Check”. After “Check”, state 2 of P1 and P2 will form shop

drawing which is in “unreviewed” state. The “unreviewed” shop drawing undergoes

“Review” intending to produce “reviewed” shop drawing, which is related to state 3a

of P1 and P2. Two “Refine” activities exist in this figure. “Refine 1” transforms P1

from state 3a to state 3b. As-built measurement information is involved in “Refine 1”,

which is represented by state 5 of P4. State 3b of P1 forms fabrication drawing 1.

Similarly, “Refine 2” is responsible for P2’s transformation from state 3a to state 3b,

which is related to fabrication drawing 2.

3.3.3 Construction Process and Parameter

Construction management is not the focus of this research. The construction

activity network is deemed to be available. However, the traditional network is not

enough to be used in the coordination analysis. To cater for coordination use, the

design information and as-built measurement information need to be attached to the

construction network. Design information can be treated as input to construction

55

Page 68: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

Background information

56

Shop drawing

P1

P4 Preliminary

Shop drawing

unreviewed

reviewed

2

3a3b

Fabrication drawing 1

5

External influence

Refine 1 Refine 2 P3

20 0

P2 3a 3b 1 1

2

Check

Review

Fabrication drawing 2

Figure 3.14 Design Process

Page 69: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

network while as-built measurement information is the output of the construction

network serving as the input for design shop and fabrication drawings.

The as-built measurement information feedback plays an important role in the

coordination. Construction is the stage of parameter realization. The realized parameter

value may be different from what has been designed. Generally, a little deviation is

acceptable since all component parameters have allowable tolerance for their values.

However, it may be very serious for work requiring exact pre-design information such

as glass fabrication design in glass wall projects. This kind of design work needs actual

as-built information of the related components. In this case, the related components

must be constructed and the parameters are measured before the detailed design can

begin. This kind of dependency increases the complexity of the network since it means

that the design of a component depends on the construction finish of other components.

As-built measurement feedback is very important for components with long

procurement and fabrication times. For these components, they need to be designed as

early as possible. However, the required as-built information may not be available

when design is to start.

To manage the as-built measurement information feedback, a new kind of

activities is added to the traditional network. Since traditional construction activities

transform the product into reality, they are called “Conversion” activities in this model.

The new activities are called “Measurement”. Thus, design information can be

attached to conversion activities which are followed by measurement activities to

produce as-built measurement information. In this case, “Conversion” turns as-

designed state into as-built state while “Measurement” is responsible for the

transformation from as-built state of a parameter to as-built measured state (Figure

3.15).

57

Page 70: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

As-designed

Figure 3.15 State Transformations of a Basic Parameter in Construction Stage

Certainly, the as-designed state can be state 3 or the combination of states 3a and 3b.

A construction activity is characterized by its information inputs and outputs

(see Figure 3.16).

Figure 3.16 Construction Activity and Input/Output

For a “Conversion” activity, its information constraints may include design

information, precedence constraints, resources and so on. Only design information is

Conversion P2 P1

Measurement

P4

P5

P6

P7

Measurement

[Derivation]

3 3

44

4 5

4

4

4 5

Conversion P3

4

3a

3b

As-built measured (5)

As-built (4)

Conversion

Measurement

58

Page 71: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

modeled while other inputs are deemed to be available. The design information refers

to the as-designed state of parameters, which can be state 3 or the combination of state

3a and 3b. The output of a “Conversion” activity is the as-built state of parameters. In

this figure, state 3 of P1 and P2 is transformed into state 4 by “Conversion”. This

applies to projects which do not involve fabrication design. If fabrication design exists,

the as-designed state of the parameter (such as P3) is represented by states 3a and 3b.

Under this situation, “Conversion” transforms P3 from states 3a and 3b to state 4. For a

“Measurement” activity, its input is the as-built state of the parameter and output is the

as-built measured state of the parameter. Generally, as-built measurement is geometry-

related problems which may involve one component or several components. In other

words, the measured parameter may be an intra-component parameter or inter-

component parameter. For inter-component parameter, a “Derivation” relation exists.

In this figure, P4 and P7 are involved in measurement. P4 is an intra-component

parameter while P7 is an inter-component parameter which is derived from P5 and P6

(in state 4).

The as-built measured states of parameters are grouped into many units to be

released for design use. Figure 3.17 shows the formation of one as-built measurement

information unit. This figure includes two kinds of construction activities

(“Conversion” and “Measurement”) and a “Derivation” relation. “Conversion 1”

transforms P1 and P2 from state 3 to state 4 while “Conversion 2” is responsible for

P3’s transformation from states 3a and 3b to state 4. The state 4 of P1 is turned into

state 5 by “Measurement 1”. In addition, the state 4 of P4 is derived from the state 4 of

P2 and P3. P4 is an inter-component parameter. “Measurement 2” is responsible for

P4’s transformation from state 4 to state 5. The state 5 of P1 and P4 forms one “As-

built measurement information unit” which is used by design.

59

Page 72: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

Figure 3.17 Construction Process

3.4 COORDINATION ANALYSIS

3.4.1 Form Original Network

The original network is formed by connecting the basic process activity--

parameter state relationships, which involves both design and construction. Figure 3.18

gives an example of the network. The network is parameter state centered while

activities are embedded in the state-state relationships. Since this network intends to

show activity—parameter state relationships, other items such as drawings and

external influences are excluded. Eight parameters are included in this figure. To

simplify the representation, only some states are displayed for these parameters. P1, P2,

P3 and P4 are involved in the design state analysis while the construction states of P6,

P7 and P8 are shown. P5 is included in both design and construction analysis. These

Conversion 1 P2 P1

Measurement 1

P4 Measurement 2

[Derivation]

3 3

44

5

4

5

Conversion 2 P3

4

3b

3a

As-built measurement information unit

controlDESIGN

60

Page 73: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

[DC1]

61

P1

0

1

2

P2

2

1

P3 2

P5 2

1

P4

3a

1

2

P8 5

3

4 4P6 4

3

P7 5

4

0

0 0

[D1][DC1]

[DC1]

[DP1]

[DP2]

[DC1]

[DP3] [DP4] [DC3]

[DC3]

[DR1]

[DC2]

DESIGNSTAGE

[CC2][CC1][CC1]

[CC1][CC1]

[CM1]

[CM2]

[CC2]

[DF1]

[D2]

--------------

[DP1], [DP2], [DP3], [DP4] – Preliminary activities in design

[DC1], [DC2], [DC3] – Check activities in design

[DR1] – Review activity in design

[DF1], [DF2] – Refine activities in design

[CC1], [CC2] – Conversion activities in construction

[CM1], [CM2] – Measurement activities in construction

[D1], [D2] – Derivation relations

[DR1]

[DR1] [DR1]

3b

3a

3b

3b

3a

[DF2] [DF1]

P5

CONSTRUCTIONSTAGE

Figure 3.18 Original Network

Page 74: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

parameters undergo state transformations with the action of relevant activities. At the

same time, interactions occur between the states of different parameters such as P4 and

P5, which are reviewed together. Relationships are also shown between design and

construction. For example, design information (states 3a and 3b) of P5 controls its

construction. As-built measurement information feedback is also displayed between P4

and P8. The state 5 of P8 is used to produce state 3b of P4.

3.4.2 Analyze and Manage the Network

The original network is inherently a network of information dependencies,

which presents the links between process activities and their information constraints. It

enables modeling of the information flow between process activities. In this way, the

information flow can be better coordinated and managed.

The coordination should insure that the required information for process

activities can be obtained on time. Because of the complexity of the dependence

relationships, it is not so easy to solve the information constraints for these activities.

The most frequently occurred coordination problems are information delays and loops

(iterations). Thus it is necessary to adjust the activities such that the availability of

information required is maximized and the number and size of iterative loops is

minimized. Generally, several approaches can be used to solve these coordination

problems:

1. Adjust time attributes of activities (start/finish time, duration)

This approach is effective in dealing with information delays. For example, the

start and finish time of the activities in the non-critical paths can be adjusted so that

these activities can release production information earlier.

2. Re-order activities

62

Page 75: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

Some information coordination problems are caused because of inappropriate

work sequence. By re-ordering the activities, these problems can be solved.

Figure 3.19 shows the original plan and the dependency relationships for six

activities, namely A1, A2, A3, A4, A5 and A6. It can be seen that a big loop exists in

the original plan (A1 A2 A3 A4 A5 A6). This loop is due to the

interdependence between A2 and A5. In reality, the loop can be reduced by re-ordering

these activities.

Figure 3.19 Original Plan

Figure 3.20 shows the result after re-ordering. The loop is reduced through the re-

ordering of these activities.

Figure 3.20 Result after Re-ordering

In a project, there are many activities with complex relationships. The re-

ordering can be achieved with the help of the method of Design Structure Matrix

(DSM) (Yassine et al., 1999).

A3 A4

A5A2A1 A6

A3 A4 A5 A2 A6A1

63

Page 76: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

3. Divide an activity into several sub-activities

In practice, one activity may involve several components, each of which has its

own parameters. Thus the output of this activity includes a group of parameters.

Generally, the output parameters are released together at the end of the activity. Before

its completion, some parameters are generated which may be required by another

design activity. This provides the opportunity to divide an activity into several sub-

activities, which produce the output parameters separately to cater for different needs.

This approach is generally used to solve information delays. But before this can be

exploited, a mapping of the parameter dependencies is required to adequately design

the sub-activities.

As shown in Figure 3.21, there are two activities, namely “Activity 1” and

“Activity 2”. P1, P2 and P3 are inputs of “Activity 1” while P4 and P5 are its outputs.

“Activity 2” depends on “Activity 1” in that “Activity 2” requires P4, which is one of

the output parameters of “Activity 1”.

Figure 3.21 Original Activities

From the activity perspective, the implied parameter dependencies for “Activity 1” are

as shown in Figure 3.22 (a). This means that delay in any of the parameters P1, P2 and

P3 will affect both P4 and P5 so that “Activity 2” is also delayed. However, the real

parameter dependencies may not be the same as those in Figure 3.22 (a). For example,

Activity 1

Activity P4 2

P2

P5 P3

P1

64

Page 77: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

the real dependencies may be as shown in Figure 3.22 (b). In this case, P6 and P7 are

embedded in “Activity 1”. Actually, the real dependency network can be divided into

two sub-networks (see Figure 3.22(c)).

P1 P1

Figure 3.22 Parameter Dependencies in Activity 1

Based on the two sub-networks, the original “Activity 1” can be divided into two sub-

activities, namely, “Activity 11” and “Activity 12” (see Figure 3.23). For “Activity 11”,

its dependent parameters are P1 and P2 while its production is P4. For “Activity 12”,

its dependent parameters are P1, P2 and P3 while its production is P5. Now “Activity

2” depends on “Activity 11”. After the division, the delays for “Activity 2” can be

resolved. For example, the receipt of P3 is delayed for some reason. In the original

plan, this will retard the production of P4 so that “Activity 2” is also delayed. However,

P6

P7 P5

P4

P2

P3

P4

P6 P4

P2

P1 P6

P7

P5 P2

P1

P3

(a)

(c)

P5

P2

P3

(b)

65

Page 78: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

with the new configuration based on the underlying parameter dependencies, P4 will

not be affected by P3. Thus, “Activity 11” can be performed earlier so that “Activity

2” will not be delayed.

Figure 3.23 Divide an Activity into Two Sub-activities

4. Use an earlier state

For a parameter, different states represent different values of the parameter

during design and construction. Although later states provide more exact information

for the parameter value, it may take a longer time to obtain them. Thus, using later

states may cause information delays. To solve these problems, earlier states can be

used. The earlier the state is, the sooner the related value can be obtained. Although it

sacrifices the exactness of the parameter, using an earlier state can produce the

required information sooner so as to solve information delays which is considered

more serious in some projects.

As shown in Figure 3.24, the as-design state (state 3) of parameter P1 provides

more exact information than the as-confirmed state (state 2) of parameter P1 since state

3 represents the parameter value after drawing review. However, review may take a

long time in some projects. Then the activity (“Check 2”) requiring the information

Activity 11

Activity 12

Activity P4 2

P2

P5

P3

P1

66

Page 79: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

(state 3 of parameter P1) needs to put on hold to wait for the information. In reality, the

as-confirmed state (state 2) of parameter P1 can be used in “Check 2”, which is

produced in an earlier time. Under this situation, there should be a verification process

after the state 3 of P1 is obtained. If the difference between state 3 and state 2 of P1 is

not acceptable, then there will be rework for “Check 2”.

Figure 3.24 Use an Earlier State

3.5 CONCLUSION

This chapter introduces the proposed coordination model. This is the main part

of the dissertation. The model aims to improve the coordination between design and

construction. It has been developed using product information as the interface.

Parameters play an important role in the product-oriented coordination in that they are

employed to describe the properties of the product components. Furthermore, activity-

Check 1

P1 1 2

Review 1

P1 2 3

Check 2

P2 1 2

Check 1

P1 1 2

Review 1

P1 2 3

Check 2

P2 1 2

67

Page 80: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

based representation and parameter-based representation are combined together to

depict design and construction processes. In addition, a new kind of activities is added

to the construction network to deal with as-built measurement information.

One of the most important characteristics of the model is that states are used to

represent the different status of parameters. Through the parameter states, relationships

can be established between design and construction activities. The whole dependence

network is formed by connecting these dependence relationships. By forming the

network, the model is capable of making information flows more explicit. Based on the

network, action can be taken to deal with information coordination problems. It should

be noted that the proposed approaches are not isolated. Effective coordination will be

achieved by fully considering all these approaches.

To illustrate the working principles of this model, the next chapter will present

one case study.

68

Page 81: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

CHAPTER 4

CASE STUDY

A case is presented in this chapter to illustrate the working principles of the

proposed coordination model. This case is about the design and construction of a glass

wall, which is one part of a building. The original data for this case was taken from

Chen (2002).

The glass wall was completed by a glass wall specialist subcontractor. As a

small-sized specialist subcontractor, its information coordination problems are

comparatively simpler than those of the other bigger companies. However, it still

encountered many difficulties with regard to the coordination between design and

construction. The glass wall is selected for the case study because it is compact enough

to show the relationships between design and construction, thus providing a good

context for the application of the model.

4.1 INTRODUCTION

The glass wall is composed of two main parts — primary steel frame and

surface glass panel. Normally, the glass panels are supported by frames. Some

auxiliary components are necessary to fix glass panels such as bolts, spider clamps and

so on. Figure 4.1 exhibits the perspective views of the glass wall from both outside and

inside.

A typical glass wall project includes three main stages, namely, design,

fabrication and installation, which are related to each other (Figure 4.2). Since glass

wall system is a high-tech, complex, and high quality item, the design-build delivery

system was adopted by the specialist subcontractor to better maintain quality and

constructability. However, the fabrication work was subcontracted to a fabrication

69

Page 82: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

company so that the glass wall specialist subcontractor can concentrate on the design

and installation work.

Figure 4.1 Perspective Views of a Glass Wall

Design

Fabrication

Installation

Figure 4.2 Glass Wall Project

70

Page 83: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

The design stage is information-intensive, which needs a variety of technical

information as well as financial and controlling information coming from many kinds

of internal and external sources. The designer is responsible to provide qualified

drawings for fabrication and installation use. Generally, the glass wall design is

composed of shop drawing design and fabrication drawing design, which generate the

shop and fabrication drawings, respectively (see Figure 4.3).

Preliminary determination

Check and confirm

Approved drawing

Figure 4.3 Glass Wall Design

The fabrication drawing design is controlled by the shop drawing design. The shop

drawing design includes three processes, namely, “preliminary determination”, “check

and confirm”, and “shop drawing review”. After “check and confirm”, shop drawing

will be produced. Shop drawing will then undergo a review before it is approved. The

review task is generally conducted by external parties including the main contractor,

architects, engineers and design consultants.

The main fabrication tasks include glass and steel fabrication. Generally, the

fabrication work is conducted in the factory. Since fabrication is not the focus of the

case analysis, detailed information for fabrication will not be discussed.

Shop drawing review

Waiting for approval

Shop drawing

Fabrication design

Fabrication drawing

Shop drawing

Shop drawing design

Fabrication drawing design

71

Page 84: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

Installation follows fabrication. Glass wall installation comprises two main

tasks -- steel installation and glass installation. Installation process can be executed

successfully only with a combination of needed resources and information, such as

design information, fabrication products, technical workers, and appropriate tools and

equipment under well-prepared site conditions. It should be noted that the installation

may affect the design by providing as-built measurement information.

4.2 INFORMATION FLOW ANALYSIS

In the glass wall project, design and installation are two crucial stages which

experienced a lot of information flow problems. Figure 4.4 presents the information

flows involved in this project. This figure provides an overview of the information

flows among project processes. Two kinds of information flows can be identified,

namely, internal information flow and external information flow.

4.2.1 Internal Information Flow

Internal information flow is related to the information relationships between

different processes within the glass wall project.

For the two sub-stages of glass wall design, shop drawing design provides

“approved drawing” to control fabrication drawing design including glass fabrication

design and steel fabrication design. At the same time, “approved drawing” is also used

to direct construction activities -- glass installation and steel installation. The

fabrication design is followed by fabrication and shipment before installation work.

Thus, both “approved drawing” and “steel fabrication drawing” influence the steel

installation. Similarly, the glass installation is affected by “approved drawing” and

“glass fabrication drawing”. The conventional viewpoint suggests that construction

72

Page 85: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

External information constraints (1)

Glass wall shop drawing design

73

Steel installation

Steel fabrication

design

Glass installation

Glass fabrication

design

Glass fabrication & check

Glass shipment

to site

Steel shipment

to site

Steel fabrication & check

Approved drawing

External information

constraints (2)

Steel fabrication

drawing

Steel installation measurement

Glass fabrication drawing

Figure 4.4 Information Flows in the Glass Wall Project

Page 86: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

should not start until the relevant drawings are ready. In this way, the design process

becomes the key constraint to the installation process.

However, the installation process also affects the design process by providing

as-built measurement information. In this project, the as-built measurement

information of steel frame is of great importance for the glass fabrication design. In

glass fabrication, any error in the fabrication drawings leads to failure and re-

fabrication. Thus, accurate fabrication drawing information is very essential to the

glass fabrication. Since the glass panels are to be installed in steel frame, the

information of steel frame is definitely necessary to determine accurate dimension

details for glass panels. Since steel frame installation is difficult to control due to site

complexity, the steel frame information can only be verified after the installation of

steel frame. The availability of “steel installation measurement” information is crucial

to produce accurate glass fabrication design that will not pose problems on site later.

One of the difficulties for this project lies in the glass fabrication design since it has

two critical internal constraints including “approved drawing” and “steel installation

measurement”.

4.2.2 External Information Flow

External information flow refers to the information constraints coming from

other project participants. Generally, a single project involves many participants

working together to complete the project successfully. Inter-participant information

interference is inevitable. It is impossible for a participant to finish his part of the work

without relying on information of other participants.

Since the glass wall is only one part of a building, it has close relationship with

the work of some other participants. The external information constraints of Figure 4.4

are shown in Figure 4.5.

74

Page 87: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

1. Relevant background drawings and specifications

2. Wind tunnel test report

3. Review comments

Figure 4.5 External Information Constraints

There are seven external information items. These information items are classified into

two groups, which control glass wall shop drawing design and glass wall fabrication

design, respectively. The glass wall shop drawing design is very complex in that it is

dependent on six external information items, namely, “relevant background drawings

and specifications”, “wind tunnel test report”, “review comments”, “stone fixing detail

for involved columns”, “size and location of air-con ducts”, and “size and location of

sunshade motor and housing”. The fabrication design also requires one external

information constraint -- “site measurement of steel beam installation”.

These information items come from many other participants. If the

relationships among the different participants are not well linked, effective information

coordination is difficult to achieve. Table 4.1 provides the source activities and

responsible participants for these external information items.

4. Stone fixing detail for involved columns

5. Size and location of air-con ducts

6. Size and location of sunshade motor and housing

7. Site measurement of steel beam installation

External information constraints (1) ==

==External information constraints (2)

75

Page 88: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

Table 4.1 External Information Constraints No. Description Source activity Responsible participant

1 Relevant background drawings and specifications

Subcontract award

Main contractor

2 Wind tunnel test report Wind tunnel test RWDI consultant

3 Review comments Shop drawing review

Architect, engineer and consultant

4 Stone fixing detail for involved columns Shop drawing

design Stone work contractor

5 Size and location of air-con ducts Shop drawing design

HVAC contractor

6 Size and location of sunshade motor and housing Shop drawing deign

Facility supplier

7 Site measurement of steel beam installation Steel beam installation

Steel work contractor

It can be seen that these items are produced by seven different external activities

including “subcontract award” (main contractor), “wind tunnel test”(RWDI

consultant), “shop drawing review”(architect, engineer and consultant), “shop drawing

design”(stone work contractor), “shop drawing design”(HVAC contractor), “shop

drawing design”(facility supplier), and “steel beam installation”(steel work contractor).

Through these information links, the activities in the glass wall can be

connected with the relevant external activities. Figure 4.6 presents the task links for

inter-participant information dependencies. Since these external constraints affect the

design stage of the glass wall, only design activities are shown for the glass wall. Since

glass wall shop drawing design includes three processes, its six external information

constraints are linked to the corresponding processes. The “relevant background

drawings and specifications” provides background information to “preliminary

determination” while “review comments” is incorporated into “drawing review”. The

remaining four items are connected with “check and confirm” including “wind tunnel

test report”, “stone fixing detail for involved columns”, “size and location of air-con

76

Page 89: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

77

Page 90: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

ducts”, and “size and location of sunshade motor and housing”. In fabrication design

stage, the information item “site measurement of steel beam installation” affects both

“glass fabrication design” and “steel fabrication design”. Among the glass wall

processes, “check and confirm” has the most external constraints with 4 external

information items, three of which are related to the shop drawing designs of other

participants. It should be noted that the procedure of these external shop drawing

designs is similar to that of the glass wall shop drawing design stage (see Figure 4.7).

Preliminary determination

Check and confirm

Approved drawing

Shop drawing Shop

Figure 4.7 Procedure for External Shop Drawing Design

Although all the seven information items are important for the project, the

analysis will focus on “stone fixing detail for involved columns”, “size and location of

air-con ducts”, “size and location of sunshade motor and housing” and “site

measurement of steel beam installation” since problems that often occur are related to

these items.

Efficient information flows are difficult to achieve due to the complexity of the

information dependencies. Problems occurred in this project because of inappropriate

management of internal and external information flows. Thus, information

coordination is very important and necessary for the glass wall subcontractor to resolve

these problems.

review

Waiting for approval

drawingShop

drawing

Construction

78

Page 91: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

4.3 MODEL FRAMEWORK

4.3.1 Identification of Key Parameters

Many components are involved in this project. Parameters are identified based

on these components. For the glass wall, there are two main components, namely, steel

frame and glass panel, each having one parameter. The relevant external components

and parameters are also very important since they are related to the external

information flow. All the main components and parameters involved in the project are

provided below in Table 4.2.

Table 4.2 Parameter Identification Description Component Parameter 1 Steel

frame S

D(S)

(dimension detail of steel frame) 2

Glass wall Glass

panel G D(G)

(dimension detail of glass panels) 3 Stone

work C D(C)

(Stone fixing detail for involved columns) 4 Air-con

duct H D(H)

(Size and location of air-con ducts) 5 Facility

work F D(F)

(Size and location of sunshade motor and housing) 6

Relevant external

work

Steel beam

B D(B) (dimension detail of steel beam)

Six parameters are identified based on the corresponding components. The two

parameters D(S) and D(G) are used to describe the dimension properties of the glass

wall steel frame and glass panel, respectively. The other four parameters, namely D(C),

D(H), D(F) and D(B), are related to the external work. These parameters are not all the

parameters of the relevant components. Generally, other parameters such as material

properties, have been determined in previous stages. All the identified parameters are

intra-component parameters in that each of them only involves one component.

Furthermore, they are basic parameters since they describe the basic properties of the

relevant components.

79

Page 92: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

Initial (0)

Figure 4.8 State Chain of D(S)

These parameters undergo state transformations during design and construction.

As shown in Figure 4.8, state chain for parameter D(S) can be described as

Initial (0) As-proposed (1) As-confirmed (2) As-designed (3a-3b)

As-built (4) As-built measured (5)

As shown in Figure 4.9, state chain for parameter D(G) can be described as

Initial (0) As-proposed (1) As-confirmed (2) As-designed (3a-3b)

As-built (4)

D(S) has as-built measured state (state 5) while as-built measured state is not involved

in D(G).

As-proposed (1)

As-built measured (5)

As-confirmed (2)

As-designed (3a)

Undefined

Preliminary

Check Design Stage

Construction Stage

Review

As-designed (3b)

Conversion

Refine

As-built (4)

Measurement

80

Page 93: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

Initial (0)

Figure 4.9 State Chain of D(G)

The external parameters, namely, D(C), D(H), D(F) and D(B), provide external

information constraints for the glass wall design. They also have state chains. Since the

evolution of these parameters is not the focus of this case analysis, their state chains

will not be shown. The involved states for D(C), D(H), D(F) are as-confirmed state

(state 2) and as-designed state (state 3), which represent design information of these

parameters. However, the as-built measured state (state 5) of D(B) is included in the

case analysis, which provides as-built measurement information.

4.3.2 Analysis of Design Process

The glass wall design is composed of two stages – shop drawing design and

fabrication drawing design. Furthermore, the shop drawing design includes three

processes, namely, “preliminary determination”, “check and confirm”, and “shop

drawing review”. Thus, all the four kinds of design activities, namely “Preliminary”,

As-proposed (1)

As-confirmed (2)

As-designed (3a)

Undefined

Preliminary

CheckDesign Stage

Construction Stage

Review

As-designed (3b)

Conversion

Refine

As-built (4)

81

Page 94: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

“Check”, “Review” and “Refine”, are involved in the glass wall design. Table 4.3

shows all the design activities for glass wall. Since the design of steel frame and the

design of glass panels are tightly coupled in the shop drawing design stage, they are

combined together for “Preliminary”, “Check” and “Review”.

Table 4.3 Design Activities No. Name Type Description

1 DP Preliminary Preliminary determination of steel frame and glass panel dimension

2 DC Check Check and confirm for steel frame and glass panel dimension

3 DR Review Shop drawing review

4 DF1 Refine Steel frame fabrication design

5 DF2 Refine Glass panel fabrication design

Glass wall

These activities are characterized by their information inputs/outputs which can

be described using parameter states. Figure 4.10 shows the activities and their

relationships with parameter states in the glass wall shop drawing design. The

preliminary activity “DP” is responsible for D(S) and D(G)’s transformation from

initial state (state 0) to as-proposed state (state 1), which is then turned into as-

confirmed state (state 2) by the check activity “DC”. “DC” needs external information

which is represented by as-designed state (state 3) of D(C), D(H) and D(F). The state 2

information of D(S) and D(G) can be grouped into shop drawings. These drawings will

undergo review activity “DR”, which is performed by external parties. “DR” updates

the information in drawings so as to produce approved drawings which contain the as-

designed state (state 3a) information of D(S) and D(G). For review, its input and

output are different states of drawings, namely unreviewed state and reviewed state.

Since drawings are connected with the states of parameters, “DR” is related to state 2

and 3a of D(S) and D(G) indirectly.

82

Page 95: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

D(S)

0

DP

0

D(G)

1 1

DC

DR

Shop drawing

Shop drawing

unreviewed

reviewed

D(S)

2

D(G)

2

1 1

D(S)

3a

2

D(G)

3a

2

D(C)

3

D(H) D(F)

3 3

State: Activity: State 0: Initial DP: (Preliminary) Preliminary determination State 1: As-proposed state of steel frame and glass panel dimension State 2: As-confirmed state DC: (Check) Check and confirm for steel frame State 3a: As-designed state and glass panel dimension (for shop drawing) DR: (Review) Shop drawing review

Figure 4.10 Glass Wall Shop Drawing Design

83

Page 96: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

Figure 4.11 shows the activities and their relationships with parameter states in

the glass wall fabrication drawing design. Two refine activities exist in the glass wall

fabrication drawing design. Refine may involve as-built measured state (state 5) of

other parameters since it represents fabrication design which generally requires exact

pre-design information. The steel frame fabrication design “DF1” is responsible for

D(S)’s transformation from as-designed state (state 3a) to as-designed state (state 3b).

It needs as-built measurement information which is represented by as-built measured

state (state 5) of D(B). The steel fabrication drawing is related to the state 3b of D(S).

Similarly, glass panel fabrication design “DF2” transforms D(G) from state 3a to state

3b. The involved as-built measurement information for “DF2” is described using state

5 of D(B) and D(S). State 3b information of D(G) will form glass fabrication drawing.

Figure 4.11 Glass Wall Fabrication Drawing Design

D(G)

D(S)

3a

3b

DF2

Fabrication drawing 2

5D(S)

3a

3b

DF1

Fabrication drawing 1

D(B) D(B)

55

State: Activity: State 3a: As-designed state DF1: (Refine) Steel frame fabrication design (for shop drawing) DF2: (Refine) Glass panel fabrication design State 3b: As-designed state (for fabrication drawing) State 5: As-built measured state

84

Page 97: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

4.3.3 Analysis of Construction Process

struction activity may be a “Conversion” or

“Measu

No. Name Type Component

As described in Chapter 3, a con

rement” activity. These two kinds of activities exist in steel work since the site

measurement of the steel frame is necessary for the glass fabrication design. However,

only conversion activity is involved in glass work because the as-built measurement

information of glass panels is not very important for the case analysis. In addition, the

steel beam construction is also relevant to this case study. Since the steel beam

supports the steel frame for the glass panels, the measurement information after steel

beam installation is crucial to steel frame and glass fabrication design. Thus, the

construction activities for the steel beam include “Conversion” and “Measurement”.

Table 4.4 shows the construction activities for these components.

Table 4.4 Construction Activities Description

1 CC1 Co n Steel frame instanversio llation

2 CC2 Conversion Glass panels installation

3 CM1 Measurem frame installation

Glass wall

ent Site measurement of steel

4 CC Conversion Steel beam installation

5 CM Measurem beam installation Steel beam ent Site measurement of steel

A “Conversion” activity transforms parameters from as-designed state (state 3

or the c

state 4. “CC1” precedes “CC2” based on the construction precedence relationship.

ombination of 3a and 3b) to as-built state (state 4), which will be turned into as-

built measured state (state 5) by “Measurement” activity. Figure 4.12 shows the glass

wall construction activities and their relationships with state transformations. The steel

installation activity “CC1” is responsible for D(S)’s transformation from states 3a and

3b to state 4, which is changed to state 5 by the site measurement of steel installation

“CM1”. The glass installation activity “CC2” transforms D(G) from states 3a and 3b to

85

Page 98: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

Figure 4.12 Glass Wall Construction Activities

The parameter sta tivities of the steel

eam are provided in Figure 4.13. The steel beam installation “CC” is responsible for

D(B)’s

gu 3 teel Beam Construction Activities

4.4 COORDINATION ANALYSIS

.4.1 Form Original Network

Many activities are involved in this project. These activities are connected

through parameter states. A network is formed by connecting the relationships (Figure

4.14).

te transformations for the construction ac

b

transformation from as-designed state (state 3) to as-built state (state 4) while

the as-built measurement “CM” turns state 4 into as-built measured state (state 5) for

D(B).

Fi re 4.1 S

4

D(B) 43

CC

D(B)4 5

CM

D(S)43a 3b D(G)

43a3b

CC1 CC2

D(S)4 5

CM1

86

Page 99: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

87

D(S)

5

4

3a

2

1

0

D(G)

1

0

4

3a

2

[DP]

[DC]

[DR]

[DP]

[DC]

[DC]

[CONSTRUCTION PRECEDENCE]

[DR]3b 3b

[DF2]

(1)

(2)

External information constraints for glass wall shop drawing design

(1)

(2)

[DC]

[DF1] [DF2]

D(C)

3

D(H)

3

D(F)

3

D(B)

5

External information constraints for glass wall fabrication drawing design

==

==

==

==

Figure 4.14 Original Network

Page 100: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

The network is parameter state centered while activities are embedded in the state-state

relationships. D(S) and D(G) undergo state transformations with the action of relevant

activities. The state trans rmations within D(S) and D(G) are not own since they are

easy to understand. At the same time, i c occ between the states of these

two parameters showing the dependencies of their design and construction. D(S) and

D(G) are tight coupled in the s p d

are presented between the states of D(S) and D(G) and those of the external parameters.

It can be seen that the as ed state (state 2) of D(S) and D(G) depends on the as-

designed state (state 3) of D(C), D(H) and D(F) while the as-built measured state (state

5) of D(B) affects the as-designed state

transformations for these external parameters are not shown since they are not the

focus of the case analysis. It should be noted that a construction precedence

relationship exists between the as-built state (state 4) of D(S) and the as-built state

(state 4) of D(G).

The dependency network is very complex. To make it easier to understand,

Figure 4.15 provides an alternative representation of the network. The relationships are

classified into two ps, ly design related relationship and construction related

relationship, which are represented by solid lines and dashed lines, respectively.

Design related relationship includes design interdependence and design dependence

while const ion t

measurement feedback. In this case, the design interdependence refers to the coupled

relationships between D(S) and D(G) in the shop drawing design stage. For external

constraints, they can be design related constraints or construction related constraints. In

this case, the as-designed state (state 3) of D(C), D(H) and D(F) is design related

fo sh

ntera tions ur

ly ho rawing design stage. In addition, relationships

-confirm

(state 3b) of D(S) and D(G). The state

grou name

ruct related relationship includes construction precedence and as-buil

88

Page 101: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

constraint while the as-built measured state (state 5) of D(B) is construction related

constraint.

D(S)

D(B)

D(F) D(H) D(C)

D(G)

5 3b

4

3

2 2

3b

5

4

Design related relati

4.4.2 Analyze and Manage the Network

1. Coordination problems

In the beginning of project plan, information dependencies among the different

tasks cannot be fully taken into consideration because of the large number of tasks and

the complexity of the information relationships. Therefore, information problems may

occur due to unreasonable project plan. Figure 4.16 shows the traditional plan and

information dependencies between these activities.

Design interdependence Construction precedence

As-built measurement feedbackDesign dependence

onship: Construction related relationship:

4 4

5

Figure 4.15 General Representation of the Network

89

Page 102: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

90

Page 103: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

It should be noted that the information dependencies in this figure match those in

Figure 4.14. In this figure, only the design and installation activities are shown while

the fabrication activities are excluded since this figure aims to describe the information

flows between design and construction. From the activity perspective, the fabrication

will follow the fabrication design and precede installation.

(1) Problems related to internal information flow

A problem occurred in this case because of the as-built measurement

information feedback. In glass fabrication, any error in the fabrication drawings leads

to failure and re-fabrication. Thus, accurate fabrication drawing information is very

essential to the glass fabrication. Since the glass panels are to be installed in steel

frame, the information of steel frame is definitely necessary to determine accurate

dimension details for glass panels. Because steel frame installation is difficult to

control due to site complexity, its information can only be verified after the installation

of steel frame. The availability of steel installation measurement information is crucial

to produce accurate glass fabrication design.

Generally, glass fabrication design is followed by glass fabrication, which can

proceed only after the detailed fabrication drawing information is confirmed. Normally,

the fabrication of glass panels has a long lead time. Therefore, it is necessary to start

the fabrication design and fabrication of glass panels much earlier to avoid delay. In

addition, glass panels are fragile so that damages may occur in transportation, handling,

or installation. If the fabrication is performed earlier, the contractor will have time to

replace them in case of damage or mistake.

As shown in this figure, based on the information dependency, “CC1” and

“CM1” should be completed before “DF2” starts. This means that “DF2” has to be put

on hold to wait for the as-built measurement information. Under this situation, the

91

Page 104: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

project schedule will be affected because of the long lead time for glass fabrication.

Thus, the dilemma is that the glass fabrication design “DF2” should start early to avoid

delay, but it cannot start until the as-built measurement information of steel frame (D(S)

at state 5) is obtained. This requirement for as-built information has often led to

schedule overruns in specialist work such as the glass wall specialist subcontractor. A

.

(2) Pro

e generally generated and released at the

end of

tate (state 5) of beam dimension (D(B)),

affects

proper method is then needed to resolve this problem

blems related to external information constraints

Based on the traditional plan presented above, two groups of information

delays can be identified from external information constraints.

---- Information delays for glass wall shop drawing design

Check activity “DC” in the glass wall shop drawing design depends on the

availability of three external information items relating to the shop drawing design of

stone work contractor, HVAC contractor and facility supplier. In this project,

information delays are identified for “DC” due to the late receipt of these external

information items. These information items ar

the relevant shop drawing designs. Generally, shop drawing design includes

drawing review and revision. This means that “DC” is delayed because it cannot get

the information related to as-designed state (state 3) of D(C), D(H) and D(F) as early

as it should.

---- Information delay for glass wall fabrication design

Regarding the glass wall fabrication design, the site measurement of steel beam

installation, namely the as-built measured s

both steel fabrication design “DF1” and glass fabrication design “DF2” since

the steel beam supports the steel frame for the glass panels. In this case, both ‘DF1”

and “DF2” were often delayed because of the late receipt of state 5 of D(B).

92

Page 105: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

93

Page 106: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

2. Solutions for these coordination problems

The preceding section has identified and explained the existing information

coordination problems in the glass wall project. Proper measures should be taken to

improve the flows of required information. Since information flows and project

processes are closely interrelated, appropriate adjustments of processes can be an

effective approach to alleviate the information coordination problems. Figure 4.17

shows the solutions for these coordination problems.

The approaches 2 and 3 described in the last chapter, namely “Re-order

activities” and “Divide an activity into several activities”, can be combined together to

deal with the as-built information feedback in the internal information flow. In reality,

the glass wall includes many different types of glass panels. Not all the glass panels

require the as-built measurement information of the steel frame. Based on their

different conditions, the glass panels can be classified into two groups—typical glass

panels and special glass panels. This means that the glass component “G” is divided

into two components, “G1” and “G2”, which are described by “D(G1)” and “D(G2)”,

respectively. Accordingly, glass fabrication design “DF2” is divided into two tasks

“DF21” and “DF22”. For the typical glass panels “G1”, the related fabrication design

“DF21” can be performed earlier because the glass panels in “G1” are comparatively

regular and do not need the as-built measurement information. However, since the

special glass panels in “G2” are very irregular or their related steel work is difficult to

control due to site complexity, their fabrication design “DF22” should be postponed

until steel frame installation “CC1” is finished and as-built measurement “CM1” is

taken. Resulting from this adjustment, the number of glass panels requiring as-built

measurement information is decreased so that less time is needed for their fabrication

94

Page 107: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

design and subsequent fabrication. Thus, the project schedule could be better

accomm

g reviews took a long time and

were b

original network representation in Figure 4.15, D(G) is divided into D(G1) and D(G2).

odated.

To deal with the information delays for the check activity “DC” in the glass

wall shop drawing design, approach 4 suggested in the chapter 3, namely “Use an

earlier state” can be used. The delays are caused because of the late release of the as-

designed state (state 3) information of D(C), D(H) and D(F). Actually, the external

shop drawing designs were retarded because drawin

eyond the control of the glass wall specialist. Since the glass wall shop drawing

design is not so sensitive to the external parameters as the glass fabrication design, the

as-confirmed state (state 2) of D(C), D(H) and D(F) can be used which is produced

before drawing reviews. Although it sacrifices the exactness of these parameters and is

in danger of rework, it saves much time which is considered more important in this

project.

For the information delay related to steel fabrication design “DF1” and glass

fabrication design “DF2”, approach 1, namely “Adjust time attributes of activities”,

can be employed. This delay occurred because the as-built measured state (state 5) of

D(B) cannot provide timely information to “DF1” and “DF2”. Since the steel beam

installation and subsequent site measurement are not on the critical path, it is then

possible and practical to do some adjustments on them. Then the steel work

subcontractor can shift the steel beam installation and subsequent site measurement to

an earlier time so that they can be accomplished prior to the time as required. Thus the

information delay problem can be resolved.

Figure 4.18 shows the parameter dependency network after these adjustments.

This network focuses on the interactions among these parameters. Compared with the

95

Page 108: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

96

D(S)

D(F) D(H) D(C)

D(G2)

5

D(B)

3b

4

2 2

2

4

3b

5

Design interdependence Construction precedence

As-built measurement feedbackDesign dependence

Design related relationship: Construction related relationship:

4 4

5

D(G1)

4

2

3b

Figure 4.18 Parameter Dependency Network after Adjustments

Page 109: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

Since the steel frame and the glass panels are tightly coupled in the shop drawing

design stage, design interdep e exis een D G1) and D(G2). Because

the steel frame should be constructed before the installation of all the glass panels, the

as-built state (state 4) of D(S) provides cons aints to the as-built state (state 4) of

D(G1) and D(G2). For the two groups of glass panels, only the fabrication design of

the special panels (G2) requires the as-built measurement information of the steel

frame. Thus, the as-designed state (sta of D(G2) depends on the as-built

measured state (state 5) of D(S). For external information items, the as-confirmed state

(state 2) instead of the as-designed state (state 3) of D(C), D(H ) and D(F) provides

constraints to the as-confirmed state (state 2) of D(S), D(G1) and D(G2) while the as-

built measured state (sta fects the as-desig e (state 3b) of D(S),

D(G1) and D(G2).

By applying the proposed approaches, all the existing information coordination

problems have been successfully eliminated. Although these amendments look simple,

they are very useful in reality. Successf prove the information

coordination to a great extent. The proposed model for representing parameter

dependencies in design and construction enables the information related flows between

design and construction activities to be better understood and represented so that the

p be exploited. approaches did

change the involved participants’ original plans and schedules to some degree.

Although this kind of changes may lead to ome delays or ex if

the damage cause on-related issues is mo

4.5 CONCLUSION

A case is presented in this chapter to show the coordination between design and

construction of a glass wall. The case study he

endenc ts betw (S), D(

tr

te 3b)

te 5) of D(B) af ned stat

ul application will im

roposed approaches can It is also evident that these

s tra costs, it is necessary

d by the informati re serious.

provides a clear understanding of how t

97

Page 110: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

coordination model works. The suggested model makes the relationships between glass

wall design and construction explicit by using parameter states. Through parameter

dependency network, the information flows are clearly displayed for the glass wall.

Thus, the information coordination problems can be identified easily. The suggested

coordination approaches are employed to solve these problems successfully. The case

indicates that the coordination model is effective in dealing with design-construction

coordination issues so as to enhance the project efficiency.

However, this case is only about a small project. Not all the concepts are shown

for the coordination model. In reality, AEC projects may be much more complex than

the glass wall. There will be more parameters involved in the projects. Accordingly,

the parameter dependency network will become more and more complicated with the

increase in the number of parameters and states. Although the coordination model

applies

to them, more attention should be paid in the application.

Up to now, the main work for the proposed model has been described. The next

chapter will conclude the dissertation with an overview of the model.

98

Page 111: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

CHAPTER 5

CONCLUSIONS AND RECOMMENDATIONS

5.1 CONCLUSIONS

Design and construction are two of the most important stages in the lifecycle of

an AEC project. Traditionally, the AEC industry has separated these two stages. In

recent years, design-build has been proposed as an optimal project delivery approach,

which tries to integ

and construction. The coordination model

eters play an important role in the product-oriented coordination in that any

roduct component can be described by a set of parameters corresponding to different

roperties of the component. At the same time, parameters are also important to depict

esign process and construction process. Four types of design activities are identified

r design process, which are concerned with the determination of the parameters of

roduct components. In construction, these parameters are realized into reality by

onstruction activities. To deal with the as-built measurement information, a new kind

f activities is added to the traditional construction network.

One of the most important characteristics of the model is that states are used to

eters. The state transformations correspond with

rate design and construction. The success for design-build requires

careful consideration of the constraints that each stage puts on the other. Problems

often occur due to inappropriate management of these constraints. Thus, it is

imperative to improve the coordination between design and construction.

This research attempted to develop a model to coordinate design and

construction work. The model aims to manage the interdependence between design

has been developed employing product as

the interface since product is the common link between design and construction.

Param

p

p

d

fo

p

c

o

represent the different status of param

99

Page 112: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

different process activities in des ion. The state representation is

useful fo rmation

puts and outputs which can be described using parameter states. Through the

ndency relationships can be established between design and

construction activities. Furtherm

ameliorate the relationship between requi

construction stage. Design is very com

ign and construct

r process analysis since a process activity is characterized by its info

in

parameter states, depe

ore, parameter states can group to form deliverables

(drawing, as-built measurement, etc.).

The whole dependency network is formed by connecting the basic process

activity--parameter state relationships. The network is inherently a network of

information dependencies which represents the links between process activities and

their information constraints. By forming the network, the model is capable of making

information flows more explicit. The fundamental purpose of coordination is to

red information flows and corresponding

process sequence. Several practical means have been suggested to deal with

information coordination problems. It should be noted that these approaches are not

isolated. Effective coordination will be achieved by fully considering all these

approaches. Although these approaches may lead to some changes to the original

project plan, it is worth doing if the coordination problems are more serious.

After the model was established, it was tested with one case. The case study

provided a clear understanding of how the coordination model works. Results

indicated that the coordination model is effective in dealing with design-construction

coordination issues so as to enhance the project efficiency.

The proposed model eases coordination analysis between design and

construction through the application of “state” to parameters for both design stage and

plex in that it is composed of many interrelated

sub-stages. By recording different design states of a parameter, the changes of the

100

Page 113: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

parameter in design stage can be traced so that a better understanding of design

evolution is achieved. This is beneficial to design improvement. Furthermore, two

more states in construction stage are added to complete the evolution chain of a

parameter and support the construction and the as-built feedback. The as-built

information feedback is critical for the coordination analysis. Thus, by using parameter

states, the evolution of design and construction and the information flows between

design

5.2 RECOMMENDATIONS FOR FUTURE WORK

This model may be of great benefit to project managers who are always

frustrated by coordination problems. In AEC projects, coordination-related problems

often occur. Using this model, these problems may be settled with ease. Thus, the

application of the model may improve the effectiveness and efficiency of AEC projects.

However, it is very difficult to develop an all-inclusive model because of the wide-

ranging aspects of the AEC industry. Since the research and case study have been done

in Singapore, this model is most applicable to the AEC projects in Singapore.

Although the basic theories are common, the model may need some modifications to

cater for different conditions when applied in other countries because of the difference

in work flow.

Parameters play an important role in the proposed model. This model focused

on the parameter dependency relationship. However, the attributes of parameters have

not been addressed, which include the range of the parameter value, the degree of ease

for estimation, and so on. These attributes provide a better understanding for

parameters and direct the parameter state utilization. Actually, the attributes of

parameters were discussed in the Process-Parameter-Interface (PPI) model (Chua et al.,

and construction are represented clearly so that the coordination between these

two stages can be achieved easily.

101

Page 114: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

2003). The proposed model in this study can be further developed to incorporate

parameter attributes so as to improve the coordination efficiency.

It is also noted that the proposed parameter dependency network can be quite

cumbersome with the increasing number of parameters and states. Although the

conventional terms in network models can be used to define the problem, it is very

difficult to represent a dependency network clearly with so many parameters and states

using conventional network model. Consequently, an alternative more compact

representation was employed in the case study without losing information on the

parameter state dependencies from design and construction perspectives. Further work

should be done in this alternative representation so that the interdependencies of design

can be better encapsulated in the proposed model.

This research proposed the model aiming at improving the coordination

between design and construction by managing the information flows. The research

work focused on developing the ideas. However, this research did not develop

applicable software to facilitate the process of coordination. In order to realize an

extensive implementation of the proposed model, an intelligent software prototype

should be developed in further research so that the information transformations can be

achieved automatically. If the proposed framework can be further integrated with a

feature-based CAD design platform, the changes in the parameters can be

automatically captured and shared.

102

Page 115: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

REFERENCES Ahmad

Austin,

in Proceedings of the ICE: Civil Engineering, Vol. 138(4), pp.177-182, 2000a

Austin, S., Baldwin, A., Li, B. and Waskett, P. Analytical design planning technique

process, Construction Management and Economics, Vol. 18 (2), pp.173-182,

Waskett, P. Application of the analytical design planning technique to construction project management, Project Management Journal, Vol. 31(2), pp.48-59, 2000c

iedermann, J.D. and Grierson, D.E. A generic model for building design, Engineering with Computers, Vol.11, pp.173-184, 1995

jork, B.-C. Basic structure of a proposed building product model, Computer-Aided Design, Vol.21(2), pp.71-78, 1989

Bjork, B.-C. A unified approach for modelling construction information, Building and

Environment, Vol.27(2), pp.173-194, 1992a

i, R., Roemer, T.A. and Wang, R.H. Structuring product development processes, European Journal of Operational Research, Vol. 130, pp.539-558, 2001

Albino, V., Pontrandolfo, P. and Scozzi, B. Analysis of information flows to enhance

the coordination of production processes, International Journal of Production Economics, Vol. 75, pp.7-19, 2002

Andery, P., Vanni, C. and Borges, G. Failure analysis applied to design optimisation,

in Proceedings of IGLC-8, Brighton, United Kingdom, 2000 Anumba, C.J. and Evbuomwan, N.F.O. A concurrent engineering process model for

computer-integrated design and construction, in Proceedings of the International Conference on Information Technology, Glasgow, UK, 1996

Anumba, C.J., Ugwu, O.O., Newnham, L. and Thorpe, A. Collaborative design of

structures using intelligent agents, Automation in Construction, Vol. 11, pp.89-103, 2002

S., Baldwin, A., Li, B. and Waskett, P. Analytical design planning technique for programming building design, in Proceedings of the ICE: Structures & Buildings, Vol.134, pp.111-118, 1999a

Austin, S., Baldwin, A., Li, B. and Waskett, P. Analytical Design Planning Technique:

a model of the detailed building design process, Design Studies, Vol. 20 (3), pp.279-296. 1999b

Austin, S., Baldwin, A., Li, B. and Waskett, P. Integrating design in the project process,

(AdePT): a dependency structure matrix tool to schedule the building design

2000b

Austin, S., Baldwin, A., Li, B. and

B

B

103

Page 116: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

Bjork, B.-C. A conceptual mode aries and enclosing structures, Automation in Construction

, 1989

Chen, ordination within and among Specialty Subcontractors,

Master’s thesis, National University of Singapore, 2002

Chen, Q Proceedings of IGLC-11, Virginia Tech, Blacksburg, Virginia, USA, 2003

Choo,

hoo, H.J., Tommelein, I.D., Ballard, G. and Zabelle, T.R. WorkPlan: constraint-based

Chua, ournal of Construction Engineering and

hua, model for identifying

l of spaces, space bound, Vol. 1(3), pp.193-214, 1992b

Bjork, B.-C. RATAS project -- developing an infrastructure for computer-integrated

construction, Journal of Computing in Civil Engineering, Vol. 8(4), pp.401-419, 1994

Bjork, B.-C. and Penttila, H. A scenario for the development and implementation of a

building product model standard, Advances in Engineering Software and Workstations, Vol.11(4), pp.176-187

Bogus, S., Songer, A.D. and Diekmann, J. Design-led lean, in Proceedings of IGLC-8,

Brighton, United Kingdom, 2000 Boujut, J.-F. and Laureillard, P. A co-operation framework for product-process

integration in engineering design, Design Studies, Vol.23, pp.497-513, 2002 Brazier, F.M.T., Moshkina, L.V. and Wijngaards, N.J.E. Knowledge level model of an

individual designer as an agent in collaborative distributed design, Artificial Intelligence in Engineering, Vol.15, pp.137-152, 2001

Browning, T.R. Applying the Design Structure Matrix to system decomposition and

integration problems: a review and new directions, Ieee Transactions on Engineering Management, Vol. 48(3), pp.292-306, 2001

Burkett, W.C. and Yang, Y. The STEP integration information architecture,

Engineering with Computers, Vol. 11(3), pp.136-144, 1995

Q. Information Co

., Chua, D.K.H. and Song Y. Information flow integrated process modeling, in

H.J. and Tommelein, I.D. WorkMovePlan: database for distributed planning and coordination, in Proceedings of IGLC-8, Brighton, United Kingdom, 2000

Cdatabase for work package scheduling, Journal of Construction Engineering and Management, Vol. 125(3), pp.151-160, 1999 D.K.H., Shen, L.J. and Bok, S.H. Constraint-based planning with integrated production scheduler over Internet, JManagement, Vol. 129(3), pp. 293-301, 2003

D.K.H. and Song Y. Application of component-state Cconstructability conflicts in a merged construction schedule, Advances in Engineering Software, Vol. 34 (11-12), pp. 671-681, 2003

104

Page 117: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

Chua, D.K.H., Tyagi, A., Ling, S. and Bok, S.H. Process-parameter-interface model for design management, Journal of Construction Engineering and Management, Vol. 129(6), pp. 653-663, 2003

Clarksodesign process, Research in Engineering Design, Vol.12, pp.18-38, 2000

omputers in Civil Engineering, Vol.12(1), pp.69-81, 1997

Darwic by reasoning about objects, actions and resources, Artificial Intelligence for

de la G dependency network to

represent design rationale, Journal of Computing in Civil Engineering,

Dias, W

in Civil Engineering, Vol.10 (1), pp.78-86, 1996

Dias, W rocess models for design, Design Studies, Vol15 No 4, pp.417-432, 1994

Dubois namic and life cycle aspects of the construction process: available formalisms and on-going work, in

78, Bled, Slovenia, 1996

n, P.J. and Hamilton, J.P. 'Signposting', a parameter-driven task-based model of the

Coates, G., Whitfield, R.I., Duffy, A.H.B. and Hills, B. Coordination approaches and

systems--part II: An operational perspective, Research in Engineering Design, Vol.12, pp.73-89, 2000

Crowley, A.J. and Watson, A.S. Representing engineering information for

constructional steelwork, Microc

he, A., Levitt, R.E. and Hayes-Roth, B. OARPLAN: Generating project plans

Engineering Design, Analysis and Manufacturing, Vol.2(3), pp.169-181, 1988

arza, J.M. and Alcantara Jr., P.T. Using parameter

Vol.11(2), pp.102-112, 1997

.P.S. Multidisciplinary product modeling of buildings, Journal of Computing

.P.S. and Blockley, D.I. The integration of product and p

, A.-M. and Cutting-Decelle, A.-F. Modelling the dy

Proceedings of the International Conference on Information Technology, Glasgow, UK, 1996

Eastman, C.M. A data model analysis of modularity and extensibility in building

databases, Building and Environment, Vol. 27(2), pp.135-148, 1992 Eastman, C.M. and Fereshetian, N. Information models for use in product design: a

comparison, Computer-Aided Design, Vol. 26 Number 7, pp.551-572, 1994

Eastman, C.M. and Siabiris, A. A generic building product model incorporating building type information, Automation in Construction, Vol. 3(4), pp.283-304, 1995

Ekholm, A. and Fridqvist, S. Modelling of user organizations, buildings and spaces for

the design process, in Proceedings of CIB W78/TG10 Workshop: Construction on the Information Highway, Publication 198, pp. 165-1

105

Page 118: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

Ekholm, A. and Fridqvist, S. A dynamic information system for design applied to the construction context, in Proceedings of CIB W78 Workshop: The Life-Cycle of Construction IT Innovations, Stockholm, Sweden, 1998

2000

Eppingroduct development, Research in Engineering Design,

Vol. 6, pp.1-13, 1994

Fenvesborative building design environment, Artificial Intelligence in

Engineering, Vol.14, pp.233-247, 2000

Fischer

122(4), pp.337-347, 1996

Fischer Engineering, Vol.10(3), pp.174-182, 1996

formation, Microcomputers in Civil Engineering, Vol. 9(6), pp.413-423, 1994

Froese, rough Standard Object-Oriented Models, Ph.D. thesis, Stanford University, 1992

Froese,

ammond, J., Choo, H.J., Austin, S., Tommelein, I.D. and Ballard, G. Integrating

998

Ekholm, A. and Fridqvist, S. A concept of space for building classification, product

modelling, and design, Automation in Construction, Vol.9(3), pp.315-328,

er, S.D., Whitney, D.E., Smith, R.P. and Gebala, D.A. A model-based method for organizing tasks in p

, S.J., Rivard, H. and Gomez, N. SEED-Config: a tool for conceptual structural design in a colla

, M. and Aalami, F. Scheduling with computer-interpretable construction method models, Journal of Construction Engineering and Management, Vol.

, M. and Froese, T. Examples and characteristics of shared project models, Journal of Computing in Civil

Ford, S., Aouad, G.F., Kirkham, J.A., Cooper, G.S., Brandon, P.S. and Child, T. An

object-oriented approach to integrating design in

T. Integrated Computer-Aided Project Management th

T. Models of construction process information, Journal of Computing in Civil Engineering, Vol.10(3), pp.183-193, 1996

Hdesign planning, scheduling, and control with DePlan, in Proceedings of IGLC-8, Brighton, United Kingdom, 2000

Harfman, A.C. and Chen, S.S. Component-based building representation for design

and construction, Automation in Construction, Vol.1, pp.339-350, 1993 Hegazy, T., Khalifa, J. and Zaneldin, E. Towards effective design coordination: a

questionnaire survey, Canadian Journal of Civil Engineering, Vol.25, pp.595-603, 1

Hegazy, T., Zaneldin, E. and Grierson, D. Improving design coordination for building

projects. I: Information model, Journal of Construction Engineering and Management, Vol.127(4), pp.322-329, 2001

106

Page 119: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

Howard, H.C., Abdalla, J.A. and Phan, D.H.D. Primitive-composite approach for structural data modeling, Journal of Computing in Civil Engineering, Vol. 6(1), pp.19-40, 1992

Jagbeck, A. MDA planner: interactive planning tool using product models and

construction methods, Journal of Computing in Civil Engineering, Vol. 8(4), pp.536-554, 1994

iviniemi, A. IAI and IFC—State of the art, in Proceedings of the 8th International

usiak, A. and Wang, J. Decomposition of the design process, Journal of Mechanical

Kusiak D.W. and Feng, C.-X. A structured approach for

analysis of design processes, Ieee Transactions on Components, Packing, and

aw, K.H. and Krishnamurthy, K. A configuration and version management model for

ee, C.-H., Sause, R. and Hong, N.K. Overview of entity-based integrated design

cture, engineering, and construction, in Proceedings of the First International Conference on the Management of

Luiten, .A. Project-modeling in AEC to integrate

design and construction, Computers in Industry, Vol. 35, pp.13-29, 1998

Maher, sing an activity/space model, Automation in Construction, Vol.6(2), pp.77-95, 1997

Malmsodeling of information management processes, Concurrent

Engineering: Research and Applications, Vol.7(2), pp.95-103, 1999

Maloneings of the 1990 ACM conference

on Computer-supported cooperative work, pp.357-370, Los Angeles, California, United States, 1990

Kadefors, A. Institutions in building projects: Implications for flexibility and change.

Scandinavian Journal of Management, Vol.11 (4), pp.395-408, 1995

KConference on Durability of Building Materials and Components, Vancouver, Canada, 1999

KDesign, Vol.115, pp.687-695, 1993

, A., Wang, J. (R.), He,

Manufacturing Technology, Vol. 18(3), pp.664-673, 1995

Lcollaborative design, in Proceedings of the International Conference on Information Technology, Glasgow, UK, 1996

Lproduct and process models, in Proceedings of the International Conference on Information Technology, Glasgow, UK, 1996

Luiten, G., Froese, T., Bjork, B.-C., Cooper, G., Junge, R., Karstila, K. and Oxman, R.

An information reference model for archite

Information Technology for Construction, Singapore, 1993

G.T., Tolman, F.P. and Fischer, M

M.L., Simoff, S.J. and Mitchell, J. Formalising building requirements u

trom, J., Pikosz, P. and Malmqvist, J. Complementary roles of IDEF0 and DSM for the m

, T.W. and Crowston, K. What is coordination theory and how can it help design cooperative work systems?, in Proceed

107

Page 120: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

Malone, T.W. and Crowston, K. The interdisciplinary study of coordination, ACM Computing Surveys, Vol.26(1), pp.87-119, 1994

okhtar, A., Bedard, C. and Fazio, P. Information model for managing design changes

dekugri, I.E. and McCaffer, R. Management information flow in construction

ark, H. and Cutkosky, M.R. Framework for modeling dependencies in collaborative

ezgui, Y. Review of information and the state of the art of knowledge management

ivard, H., Bedard, C., Fazio, P. and Ha, K.H. Functional analysis of the preliminary

ivard, H., Bedard, C., Ha, K.H. and Fazio, P. Shared conceptual model for the

Rivard esign of buildings,

Journal of Computing in Civil Engineering, Vol. 14(3), pp. 151-159, 2000

Rivard inary design of buildings, in Proceedings of CIB W78/TG10 Workshop: Construction

ogers, J.L. Tools and techniques for decomposing and managing complex design

Rosenm jects in a

collaborative CAD environment, Computer-Aided Design, Vol. 28(3), pp.193-

Rosenm

Research in Engineering Design, Vol. 11, pp. 193-205, 1999

Min a collaborative environment, Journal of Computing in Civil Engineering, Vol.12(2), pp.82-92, 1998

Ncompanies, Construction Management and Economics, Vol. 6, pp. 273-294, 1988

Olsson, R. Subcontract coordination in construction, International Journal of

Production Economics, Vol. 56-57, pp.503-509, 1998

Pengineering processes, Research in Engineering Design, Vol.11, pp. 84-102, 1999

Platt, D.G. Building process models for design management, Journal of Computing in

Civil Engineering, Vol. 10(3), pp. 194-203, 1996

Rpractices in the construction industry, The Knowledge Engineering Review, Vol. 16(3), pp. 241-254, 2001

Rbuilding envelope design process, Building and Environment, Vol. 30(3), pp. 391-401, 1995

Rbuilding envelope design process, Building and Environment, Vol. 34, pp.175-187, 1999

, H. and Fenves, S.J. A representation for conceptual d

, H., Gomez, N. and Fenves, S.J. An information model for the prelim

on the Information Highway, Publication 198, pp. 435-448, 1996

Rprojects, Journal of Aircraft, Vol. 36(1), pp. 266-274, 1999

an, M.A. and Gero, J.S. Modelling multiple views of design ob

205, 1996

an, M. and Wang, F. CADOM: A component agent-based design-oriented model for collaborative design,

108

Page 121: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

Rosenman, M. and Wang, F. A component agent based open CAD system for collaborative design, Automation in Construction, Vol. 10, pp. 383-397, 2001

anvido, V.E. and Norton, K.J. Integrated design-process model, Journal of

Shahid, S. and Froese, T. Project management information control systems, Canadian

Journal of Civil Engineering, Vol. 25(4), pp. 735-754, 1998

Shimod representing and using knowledge of buildings in CAAD systems, Artificial Intelligence in Design’92,

Shooter, S.B., Keirouz, W.T., Szykman, S. and Fenves, S.J. A model for the flow of

design information in product development, Engineering with Computers, Vol.

mith, R.P. and Morrow, J.A. Product development process modeling, Design Studies,

Soh, C etric coordinator for engineering design, Journal of

Computing in Civil Engineering, Vol. 14(4), pp. 233-240, 2000

Song, analysis, in Proceedings of the International Workshop on

Information Technology in Civil Engineering, pp.124-135, Washington, D.C.,

Stumpf, A.L., Ganeshan, R., Chin, S. and Liu, L.Y. Object-oriented model for

integrating construction product and process information, Journal of

iwari, S. and Gupta, A. Constraint management on distributed design configurations,

Tolman tion industry:

past, present and future, Automation in Construction, Vol.8, pp.227-235, 1999

Turk, Z ling for concurrent engineering, International Journal of Computer-Integrated Design and

Van Nederveen, G.A. and Tolman, F.P. Modelling multiple views on buildings,

Automation in Construction, Vol. 1(3), pp. 215-224, 1992

Sanvido, V.E. Linking levels of abstraction of a building design, Building and

Environment, Vol. 27 (2), pp.195-208, 1992

SManagement in Engineering, Vol. 10(5), pp. 55-62, 1994

aira, H. Basic structure of a building model for

pp. 241-263, 1992

16, pp.178-194, 2000

SVol.20, pp.237-261.1999

.-K. and Wang, Z. Param

Y. and Chua, D.K.H. POST: Product oriented scheduling technique for constructability

2002

Computing in Civil Engineering, Vol.10(3), pp. 204-212, 1996

TEngineering with Computers, Vol. 11, pp.199-212, 1995

, F.P. Product modeling standards for the building and construc

., Wasserfuhr, R. and Katranuschkov, P. Environment mode

Construction, Vol. 2(1), pp. 28-36, 2000

109

Page 122: PRODUCT ORIENTED COORDINATION · product oriented coordination between design and construction song hongbin (m. eng.) a thesis submitted for the degree of master of engineering department

Wang, L., Shen, W., Xie, H., Neelamkavil, J. and Pardasani, A. Collaborative conceptual design-state of the art and future trends, Computer-Aided Design, Vol. 34, pp. 981-996, 2002

Wang, for multiview models, Journal of Computing in Civil Engineering, Vol.15(2), pp.102-111, 2001

Whitfie ation approaches and systems -- part I: A Strategic Perspective, Research in Engineering Design,

hitfield, R.I., Duffy, A.H.B., Coates, G. and Hills, W. Distributed design

Wilson, J.L. and Shi, C. Coordination mechanisms for cooperative design, Engineering

Applications of Artificial Intelligence, Vol.9 (4), pp.453-461, 1996

Woesteributing Knowledge in Building, Denmark, 2002

oach, International Journal of Production Research, Vol. 37(13), pp. 2957-2975, 1999

Zaneld on for building projects. II: A collaborative system, Journal of Construction Engineering and

Z. and Soh, C.K. Managing design changes

ld, R.I., Coates, G., Duffy, A.H.B. and Hills, B. Coordin

Vol.12, pp.48-60, 2000

Wcoordination, Research in Engineering Design, Vol.13, pp.243-252, 2002

nenk, K. The LexiCon: structuring semantics, in Proceedings of CIB W78 Conference 2002: Dist

Yassine, A., Falkenburg, D. and Chelst, K. Engineering design management: an

information structure appr

in, E., Hegazy, T. and Grierson, D. Improving design coordinati

Management, Vol.127(4), pp. 330-336, 2001

110