Procurement Plan of Hydro Electric Power Plant Project MKI’s International Seminar Optimization of Hydro Power Plant Project Development August 31, 2012

Procurement Plan of Hydro Electric Power Plant Project 2012

Embed Size (px)

DESCRIPTION

Procurement Plan of Hydro Electric Power Plant Project 2012

Citation preview

Page 1: Procurement Plan of Hydro Electric Power Plant Project 2012

Procurement Plan of Hydro Electric Power Plant Project

MKI’s International Seminar Optimization of Hydro Power Plant Project Development

August 31, 2012

Page 2: Procurement Plan of Hydro Electric Power Plant Project 2012

Hydro Electric Power Plant Development Plan Java-Bali 3.296 MW

Project Owner Location Capacity (MW) COD Role Type of

Packaging Status/ Tender will

start on

Karangkates #4-5 PLN Central Java 100 MW 2018 Peak Load Multi package Funding/2014

Kesamben PLN East Java 37 MW 2017 Peak Load Multi package Funding/2014

Kalikonto-2 PLN East Java 62 MW 2016 Peak Load Multi package Funding/2013

Jatigede PLN West Java 2x55 MW 2015 Peak Load EPC One package

Funding (export credit) /2012

Upper Cisokan PS (FTP-2)

PLN West Java 4x260 MW 2016/17 Peak Load Multi package AMDAL finished. Land acquisition/ 2013

Matenggeng PS PLN Central-West Java

4x225 MW 2019/20 Peak Load Multi package Update FS, Bid Doc and EIA/2015

Grindulu PS PLN East Java 4x250 MW 2020/21 Peak Load Multi package FS Update/2016

Rajamandala (FTP-2) IPP West Java 47 MW 2016 Peak Load Not defined

Page 3: Procurement Plan of Hydro Electric Power Plant Project 2012

Projects Owner Location Capacity (MW) COD Role Type of

Packaging

Status/ Tender will

start on

Peusangan 1-2 PLN Aceh 88 2016 Peak Load Multi package Tender process

Asahan III PLN North Sumatera 174 2016 Base Load Multi package Tender process

Nanga Pinoh PLN West Kalimantan 98 2017/18 Peak Load Multi package FS/2014

Masang-2 (FTP-2) PLN West Sumatera 55 2017 Base Load Multi package FS/2014

Simonggo-2 PLN North Sumatera 86 2017 Base Load Multi package FS/2014

Merangin - PPP IPP Jambi 350 2017 Peak Load Not Defined FS-PLN/2014

Batang Toru - PPP IPP North Sumatera 510 2018 Peak Load Not Defined Plan/2015

Peusangan-4 (FTP-2) IPP Aceh 83 2018 Base Load Not Defined FS/2015

Simpang Aur (FTP-2) IPP Bengkulu 23.4 2015 Base Load Not Defined PPA

Semangka (FTP-2) IPP Lampung 56 2016 Base Load Not Defined PPA

Wampu (FTP-2) IPP North Sumatera 45 2014 Base Load Not Defined PPA Signed JKU Signed

Hasang (FTP-2) IPP North Sumatera 38 2017 Base Load Not Defined PPA

Hydro Electric Power Plant Development Plan Western Indonesia 1.606,4 MW

Page 4: Procurement Plan of Hydro Electric Power Plant Project 2012

Projects Owner Location Capacity (MW) COD Role Type of Packaging Status/ Tender

will start on

Kusan PLN South Kalimantan 65 2017 Peak load Multi Package FS/ 2014

Kelai PLN East Kalimantan 2x75 2019/20 To be advice Multi Package Plan/2015

Poso 2 PLN Central Sulawesi 2x65 2018/19 To be advice Multi Package Plan/2015

Bakaru II PLN South Sulawesi 2x63 2019 Peak load Multi Package Plan/2015

Konawe PLN South East Sulawesi 2x25 2016/17 Peak load Multi Package FS/2013

Watunohu PLN South East Sulawesi 2x28 2018/19 Base load Multi Package FS/2014

Poko PLN West Sulawesi 117 2020 Peak load Multi Package Plan/2016

Wai Tala PLN Maluku 54 2017/18 To be advice Multi Package Plan/2014

Baliem PLN Papua 50 2016-18 Base/peak Multi Package Tender process

Warsamson PLN West Papua 3x15.5 2015-17 Peak load Multi Package FS/2013

Poso IPP Central Sulawesi 195 2012 Base load Not Defined Construction

Bonto Batu (FTP-2)

IPP South Sulawesi 2x50 2017 Peak load Not Defined Tender process

Malea (FTP-2) IPP South Sulawesi 2x45 2016 Peak load Not Defined Tender process

Karama - PPP IPP South Sulawesi 450 2017 Peak load Not Defined FS-IPP/ 2012

Hydro Electric Power Plant Development Plan Eastern Indonesia 1.679,5 MW

Page 5: Procurement Plan of Hydro Electric Power Plant Project 2012

Procurement of Hydro Electric Power Plant Project PPP IPP

Page 6: Procurement Plan of Hydro Electric Power Plant Project 2012

HEPP - Private Project Partnership 3 Projects Planned as Peakers

No PPP – IPP Projects Status

1

PLTA Karama 450 MW COD 2019-2020

• Bappenas telah menetapkan PLN sebagai Penanggung Jawab Proyek Kerjasama (PJPK).

• Masuk PPP Book tahun 2012 sebagai Priority Project dengan kategori Government guarantee is required 2)

• Proyek ini belum masuk dalam RUPTL 2011-2020.

2

PLTA Batang Toru 510 MW COD 2019

• Unsolicited PPP, Bappenas 26 April 2012. • Masuk PPP Book 2012 sebagai Potential Project dengan kategori: Not

eligible for direct government support; Government guarantee maybe available 3)

• Proyek ini belum masuk dalam RUPTL 2011-2020.

3

PLTA Merangin - Kerinci 350 MW COD 2016-2017

• Merupakan proyek PLN yang akan diusulkan menjadi IPP dengan skema PPP – Solicited.

• Masuk PPP Book 2012 sebagai Potential Project dengan kategori: Not eligible for direct government support; Government guarantee maybe available 3)

Note: 1) Ready to Offer 2) Priority Project 3) Potensial Project

Page 7: Procurement Plan of Hydro Electric Power Plant Project 2012

PPP Project Business Model

PLN

PT PII (IIGF)

Investors

Minister of Finance Risk Management Unit

Recourse Agreement

Power Purchase Agreement

Guarantee Agreement

Guarantee Policy

Lender

Guarantee Fund Contracting Agency Regulates: PLN’s obligation to pay “regres”

Regulates: Guarantee scope, period

Page 8: Procurement Plan of Hydro Electric Power Plant Project 2012

PPP Project Unsolited Project Scheme (Perpres No 67 Tahun 2005 & Amendments)

Business Entity (Initiator)

Evaluation

Stop

No

Yes

Project Proposal KPS to PJPK

Tender by PJPK Initiator Receive Compensation Article 13

Establishment of Procurement Commmitee

Tender process

Winning Bidder Determination by PJPK

Article 18-22

Contract Agreement Signing

Article 23

(1) The provision of additional point, maximum in 10% (ten percent) of the Initiator’s tender value and announced publicly before procurement process.

(2) The purchase of project initiation, as replacement cost by PJPK or by the winning Bidder in the expense of Initiator’s Business Entity.

(3) The point addition and replacement cost, determined by PJPK based on consideration of independent assessor, before procurement process.

PJPK (PLN)

a. Feasibility study; b.The form of cooperation; c. Project funding plan and the source of fund;

and d.Cooperation proposal plan, include schedule,

process and assessment.

Article 11

a. provision of additional point ; or b.provision of ‘right to match’; or c. Purchase of project initiation by PJPK or by the

tender’s winning bidder

Article 12

Article 14

Funding Acquisition Pasal 24

a. Exclude of the sector master plan; b.Integrated technically to the sector

master plan; c. Feasible economically and financially; d.Government support in the form of

financial fiscal contribution

Article 10 Consider of:

Page 9: Procurement Plan of Hydro Electric Power Plant Project 2012

PPP Project Procurement Process

Construction Operation Financing

PPA IIGF • Guarantee Preparation

Transaction Advisory • Business Scheme • RFP Proposal • Bid Evaluation

Transaction Advisory

Procurement

Preparation Bidding

Compensation scheme

Page 10: Procurement Plan of Hydro Electric Power Plant Project 2012

PPP Project Unsolicited Project Implementation Procedure

Page 11: Procurement Plan of Hydro Electric Power Plant Project 2012

PLN’s Packaging Policy for Hydro Electric Power Plant (HEPP) Project

Procurement

Page 12: Procurement Plan of Hydro Electric Power Plant Project 2012

Packaging Policy Multi or One Package

• I : Civil Works (Unit Price Contract) • II : Metal Works (Lump Sum Contract) • III: Electro-mechanical Works (Lump Sum Contract) • IV: Transmission Line Works (Unit Price Contract) • V : Other One Package Contract for all: Civil, Metal Works, Electro-Mechanical Works, Transmission Line and other (if any)

Multi-package Contract

One-package/Turnkey Contract

1)

2)

Page 13: Procurement Plan of Hydro Electric Power Plant Project 2012

Multi Package Contract Advantages & Disadvantages

Detail Design by Employer (assist by Consultant/ Engineer)

ADVANTAGES DISADVANTAGES

• Employer’s intention is reflected well. • Higher Design Cost

• Easy to supervise the construction works. • Responsibility for design and procurement schedule by Employer

• Interfacing between Engineer and Contractors may be easy, better control of the interfaces

• More human and time resources are required to prepare, multiple tender documents, manage tender processes and coordinate and administer contracts

• Easy to design change in construction stage • Employer bears the responsibility and risk sin coordinating the Work

• The Contractor is specialist for each Work, better control of the quality

• More control of cash flow, through staging of the work packages

• The potential impacts of changing the design brief after construction commences are reduced

Page 14: Procurement Plan of Hydro Electric Power Plant Project 2012

Single package (Turnkey Contract) Advantages & Disadvantages

Detail Design by Contractor

ADVANTAGES DISADVANTAGES

• Early procurement possible • The Contractor is not always specialist for all works

• The contractor responsible for all design and procurement schedule

• Higher Construction phase Design costs

• The Contractor responsible for all design co-ordination/interfacing among works.

• Design work can be made after the contract sign and possibly delay. Approval of submittals may take time

• Cost for Design Delays may included in Penalty/LD Clauses in Supply Contract

• Interfacing between PLN’s Engineer and Contractors may be difficult

• Earliest commencement of the Project construction is possible

• All design risks taken over by Employer after approval

• Construction stage design changes difficult

• Contractor controls cash flow, once the contract is effective

• If the Employer’s requirements are not clearly and comprehensively described when the contract is awarded, the required outcomes may not be achieved or variations may required, with associated delay and cost.

Page 15: Procurement Plan of Hydro Electric Power Plant Project 2012

• Multi Package contract has more benefits on the Employer compared to Single Package contract, especially for projects with high complexity and high project cost.

• PLN, as the Employer utilizes Multi Package type of contract on Hydro Electric Power Plant Project, due to: – complexity of the project requires specialist Contractor on each type

of work i.e., Civil work contractor, Electro-mechanical work contractor, and Metal work contractor.

– HEPP projects has high investment cost and needs a Bidder with a high financial capability (in case of Single Package applied), therefore Multi Package type of contract allows many Bidders to join the tender

• For Jatigede HEPP, the Single Package Contract is applied due to: – Most scopes of Civil Works has been done by PU Ministry as the

Owner of Jatigede Dam (less scopes of civil work by PLN) – Acceleration of the project, so the COD target on 2015 can be

achieved

Procurement of HEPP Project Conclusion