Process Costing -Summer 2012

  • Upload
    ishas

  • View
    217

  • Download
    0

Embed Size (px)

Citation preview

  • 8/10/2019 Process Costing -Summer 2012

    1/51

    Working: Equivalent Production Units:

    Material Conversion

    1 Units in process (at start) - Work this period 4,000 2,500

    2 Units completed from current production 134,000 134,000

    3 Units in process (at end) - Work this period 4,800 4,200

    Equivalent Production units 142,800 140,700

    1 QUANTITY SCHEDULE:

    Units in process (at start) 10,000 (60% Material and 75% Conv

    Units received from previous dept 140,000

    TOTAL 150,000

    Units completed and transferred out 144,000

    Units in process (at end) 6,000 (80% Material and 70% Conv

    TOTAL 150,000

    2 Cost Charged to the department:

    Cost Units Rate

    a. Cost of WIP (at start) 98,000 - -

    b. Cost incurred in previous dept 770,000 140,000 5.50

    c. Cost added by the dept 3: EPU

    Direct material 571,200 142,800 4.00

    Direct labor 1,125,600 140,700 8.00

    FOH 914,550 140,700 6.50

    3,479,350 24.00

    3. Cost Accounted for1 COST OF FINISHED GOODS

    Total Finished goods = 144,000

    a. 10,000 - Finished goods - WIP at start:

    Cost incured till start (60% Material and 75% Conversion)

    Add: Further cost incurred to complete 100%:

    Direct material (10,000 units x 40% x Rs 4.00)

    COST OF PRODUCTION REPORT:

  • 8/10/2019 Process Costing -Summer 2012

    2/51

    Direct labor (10,000 units x 25% x Rs 8.00)

    Factory overhead (10,000 units x 25% x Rs 6.50)

    Total cost incurred on 10,000 units

    b. 134,000 - Finished goods - Current

    (134,000 units x 100% x Rs 24.00)

    Total Cost of Finished Goods

    2 COST OF WORK IN PROCESS (AT END)

    Total Work in process - at end 6,000

    Inventory cost (6,000 units x Rs 5.50) 33,000

    Direct material (6,000 units x 80% x Rs 4.0) 19,200

    Direct labor (6,000 units x 70% x Rs 8.0) 33,600

    Fatory overhead (6,000 units x 70% x Rs 6.50) 27,300

    Total Cost of Work in process -at end

    Previous dept (132,000 units x Rs 8.50) 1,122,000

    Direct material (132,000 x 100% X Rs 5) 660,000

    Direct labor (132,000 x 100% X Rs 4.5) 594,000

    FOH (132,000 x 100% X Rs 8.5) 1,122,000 3,498,000

  • 8/10/2019 Process Costing -Summer 2012

    3/51

    rsion)

    rsion)

    98,000

    16,000

  • 8/10/2019 Process Costing -Summer 2012

    4/51

    20,000

    16,250

    52,250

    150,250

    3,216,000

    3,366,250

    113,100

    3,479,350

  • 8/10/2019 Process Costing -Summer 2012

    5/51

    Working: Equivalent Production Units:

    Material Conversion

    1 Units in process (at start) - Work this period 200 1,600

    2 Units completed from current production 43,000 43,000

    3 Units in process (at end) - Work this period 3,000 2,100

    Equivalent Production units 46,200 46,700

    1 QUANTITY SCHEDULE:

    Units in process (at start) 2,000 (90% Material and 20% Conv

    Units received from previous dept 46,000

    TOTAL 48,000

    Units completed and transferred out 45,000

    Units in process (at end) 3,000 (100% Material and 70% Con

    TOTAL 48,000

    2 Cost Charged to the department:

    Cost Units Rate

    a. Cost of WIP (at start) 112,000 - -

    b. Cost incurred in previous dept 552,000 46,000 12.00

    c. Cost added by the dept 2: EPU

    Direct material 242,550 46,200 5.25

    Direct labor 116,750 46,700 2.50FOH 186,800 46,700 4.00

    1,210,100 23.75

    3. Cost Accounted for

    1 COST OF FINISHED GOODS

    Total Finished goods = 45,000

    a. 2,000 - Finished goods - WIP at start:

    Cost incured till start (90% Material and 20% Conversion)

    Add: Further cost incurred to complete 100%:Direct material (2,000 units x 10% x Rs 5.25)

    Direct labor (2,000 units x 80% x Rs 2.5)

    Factory overhead (2,000 units x 80% x Rs 4.0)

    Total cost incurred on 2,000 units

    b. 43,000 - Finished goods - Current

    (43,000 units x 100% x Rs 23.75)

    COST OF PRODUCTION REPORT:

  • 8/10/2019 Process Costing -Summer 2012

    6/51

  • 8/10/2019 Process Costing -Summer 2012

    7/51

    rsion)

    ersion)

    112,000

    1,050

    4,000

    6,400

    11,450

    123,450

    1,021,250

  • 8/10/2019 Process Costing -Summer 2012

    8/51

    1,144,700

    65,400

    1,210,100

  • 8/10/2019 Process Costing -Summer 2012

    9/51

    Working: Equivalent Production Units:

    Material Conversion

    1 Units in process (at start) - Work this period - 1,800

    2 Units completed from current production 144,000 144,000

    3 Units in process (at end) - Work this period 10,000 8,000

    Equivalent Production units 154,000 153,800

    1 QUANTITY SCHEDULE:

    Units in process (at start) 6,000 (100% Material, 70% Conver

    Units received from previous dept 154,000

    TOTAL 160,000

    Units completed and transferred out 150,000

    Units in process (at end) 10,000 (100% Material, 80% Conver

    TOTAL 160,000

    2 Cost Charged to the department:

    Cost Units Rate

    a. Cost of WIP (at start) 88,000 - -

    b. Cost incurred in previous dept 1,848,000 154,000 12.00

    c. Cost added by the dept 2: EPU

    Direct material 924,000 154,000 6.00

    Direct labor 1,230,400 153,800 8.00

    FOH 1,845,600 153,800 12.00

    5,936,000 38.00

    COST OF PRODUCTION REPORT:

  • 8/10/2019 Process Costing -Summer 2012

    10/51

    3. Cost Accounted for as follows

    1 COST OF FINISHED GOODS

    Total units in Finished Goods 142,000

    a) 10,000 units - From Units in process - at start:Cost incurred till start - 40% Material and 70% conversion

    Add: Further cost incurred to complete 100%:

    Direct material (10,000 units x 60% x Rs 5.00) 30,000

    Direct labor (10,000 units x 30% x Rs 4.50) 13,500

    Factory overrhead (10,000 units x 30% x Rs 8.50) 25,500

    Total cost incurred on 10,000 units

    b) 132,000 units - From Current production

    (132,000 units x 100% x Rs 26.50)

    Total cost of Finished goods

    2 COST OF WORK IN PROCESS (AT END)

    Total units in process - at end 8,000

    1. Previous dept (8,000 units x Rs 8.50) 68,000

    b. Direct material (8,000 units x 90% x Rs 5) 36,000

    c. Direct Labor (8,000 units x 40% x Rs 4.5) 14,400

    d. FOH (8,000 units x 40% x Rs 8.5) 27,200

    Cost of work in process - at end

  • 8/10/2019 Process Costing -Summer 2012

    11/51

    Previous dept (132,000 units x Rs 8.50) 1,122,000Direct material (132,000 x 100% X Rs 5) 660,000

    Direct labor (132,000 x 100% X Rs 4.5) 594,000

    FOH (132,000 x 100% X Rs 8.5) 1,122,000 3,498,000

  • 8/10/2019 Process Costing -Summer 2012

    12/51

    ion)

    ion)

  • 8/10/2019 Process Costing -Summer 2012

    13/51

    96,000

    69,000

    165,000

    3,498,000

    3,663,000

    145,600

    3,808,600

  • 8/10/2019 Process Costing -Summer 2012

    14/51

    Working: Equivalent Production Units:

    Material Conversion

    1 Units in process (at start) - Work this period - 2,000

    2 Units completed from current production 169,000 169,000

    3 Units in process (at end) - Work this period 26,000 19,500

    Equivalent Production units 195,000 190,500

    1 QUANTITY SCHEDULE:

    Units in process (at start) 5,000 (100% Material, 60% Conver

    Units placed in production 195,000

    TOTAL 200,000

    Units completed and transferred out 174,000

    Units in process (at end) 26,000 (100% Material, 75% Conver

    TOTAL 200,000

    2 Cost Charged to the department:

    Cost Units Rate

    a. Cost of WIP (at start) 57,000 - -

    b. Cost added by the dept 1: EPU

    Direct material 1,755,000 195,000 9.00

    Direct labor 857,250 190,500 4.50

    FOH 1,905,000 190,500 10.004,574,250 23.50

    3. Cost Accounted for as follows

    1 COST OF FINISHED GOODS

    Total units in Finished Goods 174,000

    a) 5,000 units - From Units in process - at start:

    Cost incurred till start - 100% Material and 60% conversion

    Add: Further cost incurred to complete 100%:Direct material (5,000 units x 0% x Rs 9.00) -

    Direct labor (5,000 units x 40% x Rs 4.50) 9,000

    Factory overrhead (5,000 units x 40% x Rs 10) 20,000

    Total cost incurred on 5,000 units

    b) 169,000 units - From Current production

    (169,000 units x 100% x Rs23.50)

    COST OF PRODUCTION REPORT:

  • 8/10/2019 Process Costing -Summer 2012

    15/51

    Total cost of Finished goods

    2 COST OF WORK IN PROCESS (AT END)

    Total units in process - at end 26,000

    a. Direct material (26,000 units x 100% x 9.00) 234,000

    b. Direct Labor (26,000 units x 75% x 4.5) 87,750

    c. FOH (26,000 units x 75% x 10.00) 195,000

    Cost of work in process - at end

    Previous dept (132,000 units x Rs 8.50) 1,122,000

    Direct material (132,000 x 100% X Rs 5) 660,000

    Direct labor (132,000 x 100% X Rs 4.5) 594,000

    FOH (132,000 x 100% X Rs 8.5) 1,122,000 3,498,000

  • 8/10/2019 Process Costing -Summer 2012

    16/51

    ion)

    ion)

    57,000

    29,000

    86,000

    3,971,500

  • 8/10/2019 Process Costing -Summer 2012

    17/51

    4,057,500

    516,750

    4,574,250

  • 8/10/2019 Process Costing -Summer 2012

    18/51

    Working: Equivalent Production Units:

    Material Conversion

    2 Units completed from current production 54,000 54,000

    3 Units in process (at end) - Work this period 6,000 5,400

    Equivalent Production units 60,000 59,400

    1 QUANTITY SCHEDULE:

    Units received from previous dept 60,000

    TOTAL 60,000

    Units completed and transferred out 54,000

    Units in process (at end) 6,000 (100% Material, 90% Conver

    TOTAL 60,000

    2 Cost Charged to the department:

    Cost Units Ratea. Cost incurred in previous dept 1,320,000 60,000 22.00

    b. Cost added by the dept 2: EPU

    Direct material 360,000 60,000 6.00

    Direct labor 386,100 59,400 6.50

    FOH 445,500 59,400 7.50

    2,511,600 42.00

    COST OF PRODUCTION REPORT:

  • 8/10/2019 Process Costing -Summer 2012

    19/51

    3. Cost Accounted for as follows

    1 COST OF FINISHED GOODS

    Total units in Finished Goods 54,000

    a) 54,000 units - From Current production(54,000 units x 100% x Rs 42

    Total cost of Finished goods

    2 COST OF WORK IN PROCESS (AT END)

    Total units in process - at end 6,000

    1. Previous dept (6,000 units x Rs 22) 132,000

    b. Direct material (6,000 units x 100% x 6) 36,000

    c. Direct Labor (6,000 units x 90% x 6.5) 35,100

    d. FOH (6,000 units x 90% x 7.5) 40,500

    Cost of work in process - at end

    Previous dept (132,000 units x Rs 8.50) 1,122,000

    Direct material (132,000 x 100% X Rs 5) 660,000

  • 8/10/2019 Process Costing -Summer 2012

    20/51

    Direct labor (132,000 x 100% X Rs 4.5) 594,000

    FOH (132,000 x 100% X Rs 8.5) 1,122,000 3,498,000

  • 8/10/2019 Process Costing -Summer 2012

    21/51

    ion)

  • 8/10/2019 Process Costing -Summer 2012

    22/51

    2,268,000

    2,268,000

    243,600

    2,511,600

  • 8/10/2019 Process Costing -Summer 2012

    23/51

    Working: Equivalent Production Units:

    Material Conversion

    1 Units in process (at start) - Work this period 4,000 4,000

    2 Units completed from current production 29,000 29,000

    Equivalent Production units 33,000 33,000

    1 QUANTITY SCHEDULE:

    Units in process (at start) 10,000 (60% Material and conversio

    Units placed in production 29,000

    TOTAL 39,000

    Units completed and transferred out 39,000

    Units in process (at end) -

    TOTAL 39,000

    2 Cost Charged to the department:

    Cost Units Rate

    a. Cost of WIP (at start) 48,000 - -

    b. Cost added by the dept 2: EPU

    Direct material 155,000 33,000 4.6970

    COST OF PRODUCTION REPORT:

  • 8/10/2019 Process Costing -Summer 2012

    24/51

    Direct labor 76,000 33,000 2.3030

    FOH 60,800 33,000 1.8424

    339,800 8.8424

    3. Cost Accounted for as follows

    1 COST OF FINISHED GOODS

    Total units in Finished Goods 39,000

    a) 10,000 units - From Units in process - at start:

    Cost incurred till start - 60% Material and conversion

    Add: Further cost incurred to complete 100%:

    Direct material (10,000 units x 40% x Rs 4.6970) 18,788

    Direct labor (10,000 units x 40% x Rs 2.3030) 9,212

    Factory overrhead (10,000 units x 40% x Rs 1.8424) 7,370

    Total cost incurred on 10,000 units

    b) 29,000 units - From Current production

    (29,000 units x 100% x Rs 8.8424)

    Total cost of Finished goods

  • 8/10/2019 Process Costing -Summer 2012

    25/51

    Previous dept (132,000 units x Rs 8.50) 1,122,000

    Direct material (132,000 x 100% X Rs 5) 660,000

    Direct labor (132,000 x 100% X Rs 4.5) 594,000

    FOH (132,000 x 100% X Rs 8.5) 1,122,000 3,498,000

  • 8/10/2019 Process Costing -Summer 2012

    26/51

    )

  • 8/10/2019 Process Costing -Summer 2012

    27/51

    48,000

    35,370

    83,370

    256,430

    339,799

    339,799

  • 8/10/2019 Process Costing -Summer 2012

    28/51

    COST OF PRODUCTION REPORT:

    1 QUANTITY SCHEDULE:

    Units in process (at start) 5,000 (100% Mat, 70% Conv)

    Units received from dept 1 95,000

    TOTAL 100,000

    Units completed and transferred out 98,000

    Units in process (at end) 2,000 (100% Mat, 30% Conv)

    100,000

    2 Cost Charged to the department:

    Cost Units Rate

    3. Cost Accounted for as follows

    1 COST OF FINISHED GOODS

    Total units completed during the period = 98,000

    a) From beginning work in process (5,000 units):

    Cost incurred till start 10,000

    Add: Further cost incurred to complete 100%

    Direct material (5,000 x 0% x 5) -

    Direct labor (5,000 x 30% x 4) 6,000

    FOH (5,000 x 30% x 4.50) 6,750

    Total cost incurred to complete 5,000 units 22,750

    b) From current production (93,000 units)

    (93,000 units x 100% x 24) 2,232,000

    Total cost of Finished goods 2,254,750

    2 COST OF WORK IN PROCESS (AT END)

    Inventory cost (2,000 units x 12) 24,000

    Direct material (2,000 units x 100% x 3.50) 7,000

    Direct labor (2,000 units x 30% x 4) 2,400

    FOH (2,000 units x 30% x 4.50) 2,700

  • 8/10/2019 Process Costing -Summer 2012

    29/51

    Total cost of WIP (at end) 36,100

    2,290,850

  • 8/10/2019 Process Costing -Summer 2012

    30/51

    Working: Equivalent Production Units:

    Material

    1. Units completed and transferred out 98,000

    2. Less: WIP (Start) - all units (5,000)

    Units started and completed 93,000

    3. Add: WIP (Start) - work this period -

    4. Add: WIP (End) - work this period 2,000

    Equivalent Production Units 95,000

  • 8/10/2019 Process Costing -Summer 2012

    31/51

  • 8/10/2019 Process Costing -Summer 2012

    32/51

    Conversion

    98,000

    (5,000)

    93,000

    1,500

    600

    95,100

  • 8/10/2019 Process Costing -Summer 2012

    33/51

    COST OF PRODUCTION REPORT:

    1 QUANTITY SCHEDULE:

    Units received from previous dept 100,000

    TOTAL 100,000

    Units completed and transferred out 82,000

    Units in process (at end) 18,000 (100% Mat, 80% Conv)

    100,000

    2 Cost Charged to the department:

    Cost Units Rate

    a. Per unit received from Previous dept 600,000 100,000 6.00

    b. Cost added by the dept:

    Direct materail 250,000 100,000 2.50

    Direct labor 289,200 96,400 3.00

    FOH 385,600 96,400 4.00

    1,524,800 15.5

    3. Cost Accounted for as follows

    1 COST OF FINISHED GOODS

    Total units completed during the period = 82,000

    From current production (82,000 units)

    (82,000 units x 100% x 15.50) 1,271,000

    Total cost of Finished goods 1,271,000

    2 COST OF WORK IN PROCESS (AT END)

    Inventory cost (18,000 units x 6) 108,000

    Direct material (18,000 x 100% x 2.50) 45,000

    Direct labor (18,000 x 80% x 3) 43,200

    FOH (18,000 x 80% x 4) 57,600

    Total cost of WIP (at end) 253,800

    1,524,800

  • 8/10/2019 Process Costing -Summer 2012

    34/51

    Working: Equivalent Production Units:

    Material

    1. Units completed and transferred out 82,000

    Units started and completed 82,000

    2. Add: WIP (End) - work this period 18,000

    Equivalent Production Units 100,000

  • 8/10/2019 Process Costing -Summer 2012

    35/51

    Conversion

    82,000

    82,000

    14,400

    96,400

  • 8/10/2019 Process Costing -Summer 2012

    36/51

  • 8/10/2019 Process Costing -Summer 2012

    37/51

    FOH (6,000 x 30% x 4) 7,200

    Total cost incurred to complete 6,000 units 68,800

    b) From current production (84,000 units)

    (84,000 x 100% x 9) 756,000

    Total cost of Finished goods 824,800

    2 COST OF WORK IN PROCESS (AT END)

    Direct material (10,000 units x 75% x 2) 15,000

    Direct labor (10,000 units x 40% x 3) 12,000

    FOH (10,000 units x 40% x 4) 16,000

    Total cost of WIP (at end) 43,000

    867,800

  • 8/10/2019 Process Costing -Summer 2012

    38/51

    COST OF PRODUCTION REPORT - Dept A

    1 QUANTITY SCHEDULE:

    Units put into proc ess 30,000

    TOTAL 30,000

    Units completed and transferred out 25,000

    Units in process (at end) 5,000 (60% Material % 60% Conv)

    30,000

    2 Cost Charged to the department:

    Cost Units Rate

    a. Cost added by the dept A: EPU

    Direct material 22,400 28,000 0.80

    Direct labor 19,600 28,000 0.70

    FOH 14,000 28,000 0.50

    56,000 2.0

    3. Cost Accounted for as follows

    1 COST OF FINISHED GOODS

    Total units completed during the period = 25,000

    From current production (25,000 units)

    (25,000 units x 100% x 2) 50,000

    Total cost of Finished goods 50,000

    2 COST OF WORK IN PROCESS (AT END)Direct material (5,000 units x 60% x 0.80) 2,400

    Direct labor (5,000 units x 60% x 0.70) 2,100

    FOH (5,000 units x 60% x 0.50) 1,500

    8 Total cost of WIP (at end) 6,000

    56,000

    COST OF PRODUCTION REPORT - Dept B

    1 QUANTITY SCHEDULE:

    Units received from previous dept 25,000

    TOTAL 25,000

    Units completed and transferred out 21,000

  • 8/10/2019 Process Costing -Summer 2012

    39/51

    Units in process (at end) 4,000 (60% Material % 60% Conv)

    25,000

    2 Cost Charged to the department:

    Cost Units Rate

    a. Per Unit cost of previous dept. 50,000 25,000 2

    b. Cost added by the dept B: EPU

    Direct material 9,360 23,400 0.40

    Direct labor 14,040 23,400 0.60

    FOH 28,080 23,400 1.20

    101,480 4.2

    3. Cost Accounted for as follows

    COST OF FINISHED GOODS

    Total units completed during the period = 21,000

    From current produ

    (21,000 units x 100% x 4.2) 88,200

    Total cost of Finished goods 88,200

    2 COST OF WORK IN PROCESS (AT END)

    Inventory cost (4,000 units x 2) 8,000

    Direct material (4,000 units x 60% x 0.40) 960

    Direct labor (4,000 units x 60% x 0.60) 1,440

    FOH (4,000 units x 60% x 1.20) 2,880

    8 Total cost of WIP (at end) 13,280

    101,480

    Entries in Process Costing:

    1. Transfer of units from one process to another process:

    Work in Process (Dept B) 50,000

    Work in Process (Dept A) 50,000

    (To record: the transfer of 25,000 units

    from Dept A to Dept B)

    2 Transfer Finished goods to Ware house:

    Finished Goods 88,200

    Work in Process (Dept B) 88,200

  • 8/10/2019 Process Costing -Summer 2012

    40/51

    (To record: the transfer of 21,000 units

    from Dept B to Ware house)

  • 8/10/2019 Process Costing -Summer 2012

    41/51

    Working: Equivalent Production Units:

    Material Conversion

    1. Units completed and transferred out (FG) 25,000 25,000

    2. Add: WIP (End) - work this period 3,000 3,000

    Equivalent Production Units 28,000 28,000

    Working: Equivalent Production Units:

    Material Conversion

    1. Units completed and transferred out (FG) 21,000 21,000

    2. Add: WIP (End) - work this period 2,400 2,400

    Equivalent Production Units 23,400 23,400

  • 8/10/2019 Process Costing -Summer 2012

    42/51

    Dept 1 Dept 2

    1 Units in process - at start 2,000 5,000

    2 Cost of WIP - at start 22,000 48,000

    3 Units placed in production 58,000 -

    4 Units in process - at end 5,000 10,000

    5 Cost added by the department:

    Direct material 155,000 210,000Direct labor 250,000 187,000

    FOH 145,000 195,000

    Stage of Completion:

    Work in process - at start 25% Mat 45% Mat

    95% Conv 55% Conv

    Work in process - at end 100% Mat 85% Mat

    45% Conv 25% Conv

    Working: Equivalent Production Units:

    Material Conversion

    1 Units in process (at start) - Work this period 1,500 100

    2 Units completed from current production 53,000 53,000

    3 Units in process (at end) - Work this period 5,000 2,250

    Equivalent Production units 59,500 55,350

    1 QUANTITY SCHEDULE:

    Units in process (at start) 2,000 (25% Material and 95% Co

    Units placed in production 58,000

    TOTAL 60,000

    Units completed and transferred out 55,000

    Units in process (at end) 5,000 (100% Material and 45% C

    TOTAL 60,000

    2 Cost Charged to the department:

    Cost Units Rate

    a. Cost of WIP (at start) 22,000

    b. Cost added by the dept 1: EPU

    Direct material 155,000 59,500 2.6050

    Direct labor 250,000 55,350 4.5167

    FOH 145,000 55,350 2.6197

    572,000 9.7414

    COST OF PRODUCTION REPORT:

  • 8/10/2019 Process Costing -Summer 2012

    43/51

    3. Cost Accounted for as follows

    1 COST OF FINISHED GOODSTotal numbers of units completed = 55,000

    a. 2,000 completed from Beginning Inventory

    Cost incurred till start (25% Material, 95% Conversion) 22,000

    Add: Further cost incurred to complete 100%:

    Direct material (2,000 units x 75% x Rs. 2.6050) 3,908

    Direct labor (2,000 units x 5% x Rs.4.5167) 452

    Factory overhead (2,000 units x 5% x Rs. 2.6197) 262

    Total cost incurred on 2,000 units

    b. 53,000 completed from current production

    (53,000 units x 100% x Rs. 9.7414)

    Total cost of Finished goods - 55,000 units

    2 COST OF WORK IN PROCESS (AT END)

    Direct material (5,000 units x 100% x Rs 2.6050 13,025

    Direct labor (5,000 units x 45% x Rs 4.5167 10,163

    Factory overhead (5,000 units x 45% x Rs 2.6197 5,894

    Total cost of Work in process -at end

  • 8/10/2019 Process Costing -Summer 2012

    44/51

    nversion)

    onversion)

  • 8/10/2019 Process Costing -Summer 2012

    45/51

    26,621

    516,294

    542,915

    29,082

    571,997

  • 8/10/2019 Process Costing -Summer 2012

    46/51

    Working: Equivalent Production Units:

    Material Conversion

    1 Units in process (at start) - Work this period 1,500 2,000

    2 Units completed from current production 35,000 35,000

    3 Units in process (at end) - Work this period 7,000 6,000

    Equivalent Production units 43,500 43,000

    1 QUANTITY SCHEDULE:

    Units in process (at start) 5,000 (70% Material and 60% Conv

    Units placed in production 45,000

    TOTAL 50,000

    Units completed and transferred out 40,000

    Units in process (at end) 10,000 (70% Material and 60% Conv

    TOTAL 50,000

    2 Cost Charged to the department:

    Cost Units Rate

    a. Cost of WIP (at start) 26,000

    b. Cost added by the dept 1: EPU

    Direct material 152,250 43,500 3.50

    Direct labor 172,000 43,000 4.00

    FOH 193,500 43,000 4.50

    543,750 12.00

    3. Cost Accounted for as follows

    1 COST OF FINISHED GOODS

    Total numbers of units completed = 40,000

    a. 5,000 completed from Beginning Inventory

    Cost incurred till start (70% Material, 60% Conversion) 26,000

    Add: Further cost incurred to complete 100%:

    Direct material (5,000 units x 30% x Rs 3.50) 5,250

    Direct labor (5,000 units x 40% x Rs 4.00) 8,000Factory overhead (5,000 units x 40% x Rs 4.50) 9,000

    Total cost incurred on 5,000 units

    b. 35,000 completed from current production

    (35,000 units x 100% x Rs 12)

    Total cost of Finished goods - 40,000 units

    COST OF PRODUCTION REPORT:

  • 8/10/2019 Process Costing -Summer 2012

    47/51

    2 COST OF WORK IN PROCESS (AT END)

    Direct material (10,000 units x 70% x Rs 3.50) 24,500

    Direct labor (10,000 units x 60% x Rs 4.00) 24,000

    Factory overhead (10,000 units x 60% x Rs 4.50) 27,000

    Total cost of Work in process -at end

    Working: Equivalent Production Units:

    Material Conversion

    1 Units in process (at start) - Work this period - -

    2 Units completed from current production 38,000 38,000

    3 Units in process (at end) - Work this period 1,200 800

    Equivalent Production units 39,200 38,800

    1 QUANTITY SCHEDULE:

    Units in process (at start) -

    Units received from Dept 1 40,000

    TOTAL 40,000

    Units completed and transferred out 38,000

    Units in process (at end) 2,000 (60% Material and 40% ConvTOTAL 40,000

    2 Cost Charged to the department:

    Cost Units Rate

    a. Per unit cost received from dept 1 468,250 40,000 11.7063

    b. Cost added by the dept 1: EPU

    Direct material 200,000 39,200 5.1020

    Direct labor 250,000 38,800 6.4433

    FOH 350,000 38,800 9.02061,268,250 32.2722

    3. Cost Accounted for as follows

    1 COST OF FINISHED GOODS

    Total numbers of units completed = 38,000

    38,000 completed from current production

    COST OF PRODUCTION REPORT:

  • 8/10/2019 Process Costing -Summer 2012

    48/51

    (38,000 units x 100% x Rs 32.2722)

    Total cost of Finished goods - 38,000 units

    2 COST OF WORK IN PROCESS (AT END)

    Inventory Cost (2,000 units x Rs 11.7063) 23,413

    Direct material (2,000 units x 60% x Rs 5.1020) 6,122

    Direct labor (2,000 units x 40% x Rs 6.4433) 5,155Factory overhead (2,000 units x 40% x Rs 9.0206) 7,216

    Total cost of Work in process -at end

  • 8/10/2019 Process Costing -Summer 2012

    49/51

    rsion)

    rsion)

    48,250

    420,000

    468,250

  • 8/10/2019 Process Costing -Summer 2012

    50/51

    75,500

    543,750

    rsion)

  • 8/10/2019 Process Costing -Summer 2012

    51/51

    1,226,344

    1,226,344

    41,906

    1,268,250