Upload
others
View
2
Download
0
Embed Size (px)
Citation preview
PROCEDURES AND REGULATIONS FOR
PERMITTED ACTIVITIES
Ottawa County Road Commission
P.O. Box 739
14110 Lakeshore Drive
Grand Haven, Michigan 49417
(616) 842-5400
www.ottawacorc.com
March 1, 2018
TABLE OF CONTENTS
I. INTRODUCTION……………………………………………………………………………..1
II. DEFINITIONS………………………………………………………………………………...2
III. GENERAL PROVISIONS……………………………………………………………….……8
A. Activities that Require Permits……………………………………………………………8
B. Authority…………………………………………………………………………………..8
C. Standards, Guidelines, & Specifications for Design and Construction…………………...9
D. Preservation of Survey Monuments……………………………………………………...10
E. Amendment………………………………………………………………………………10
IV. PERMITTING PROCESS…………………………………………………………………...11
A. Permit Application……………………………………………………………………….11
B. Application Review & Permit Issuance………………………………………………….13
C. Permit Conditions & Limitations………………………………………………………...13
V. ADMINISTRATIVE COMPLETENESS……………………………………………………16
VI. DRIVEWAY STANDARDS & REQUIREMENTS………………………………………...17
A. General Driveway Standards & Requirement……………………………………………17
B. Commercial Driveway Requirements……………………………………………………21
C. Residential Driveway Requirements……………………………………………………..27
D. Field Driveway Requirements…………………………………………………………...30
E. Temporary Driveway Requirements……………………………………………………..30
VII. UTILITY STANDARDS & REQUIREMENTS…………………………………………….32
A. General Utility Standards & Requirements……………………………………………...32
B. Utility Construction Requirements………………………………………………………36
C. Utility Removal, Relocation, and Adjustments………………………………………….41
D. Utility Abandonment…………………………………………………………………….41
E. Annual Utility Permit Activities…………………………………………………………42
F. As-Built Plans for Public Utilities……………………………………………………….43
VIII. SIDEWALK AND PATH STANDARDS & REQUIREMENTS…………..…………….…44
A. General Sidewalk and Path Standards & Requirements………………………...……….44
B. Sidewalk and Non-Motorized Path Construction Requirements……………...…………44
C. As-Built Plans……………………………………………………………………………48
IX. DITCH ENCLOSURES AND DRAINAGE STANDARDS & REQUIREMENTS………..49
A. General Requirements……………………………………………………………………49
B. Ditch Enclosure and Drainage Facility Construction Requirements…………………….50
C. As-Built Plans……………………………………………………………………………50
X. RESTORATION AND INSPECTION STANDARDS & REQUIREMENTS……………...51
A. General Requirements……………………………………………………………………51
XI. TRANSPORTATION PERMIT REQUIREMENTS…………………………………….…..56
A. General Provisions……………………………………………………………………….56
B. Annual Transportation Permit……………………………………………………………56
C. Annual Mobile Home Transportation Permit……………………………………………57
D. Single Move Transportation Permit……………………………………………………...57
E. Super Move Transportation Permit………………………………………………………58
F. Single Mobile Home Transportation Permit……………………………………………..59
G. Seasonal Milk Haul Route Permit………………………………………………………..60
H. Seasonal Agricultural Permit…………………………………………………………….60
I. Seasonal Utility Non-Emergency Exemption Permit……………………………………61
XII. ENGINEERING AND SURVEYING PERMIT REQUIREMENTS………………………..62
XIII. BANNER AND PARADE REQUIREMENTS……………………………………...………62
A. Banners…………………………………………………………………………...……...62
B. Parades…………………………………………………………………………………...63
XIV. SEVERABILITY CLAUSE………………………………………………………………….65
XV. VARIANCES………………………………………………………………………...………65
APPENDIX A Administrative Completeness Checklists
APPENDIX B Detail PA-1 to Detail PA-16
ADDENDA
I. INTRODUCTION
This document has been prepared to consolidate all of the Procedures and Regulations for the issuance of
permits to conduct certain activities within the road right-of-ways under jurisdiction of the Ottawa County
Road Commission (OCRC). These Procedures and Regulations are made part of any permit issued by the
OCRC for such activities.
The County Engineer employed by the OCRC, or any OCRC employee designated to act for him or her,
is responsible for administering these Procedures and Regulations for Permitted Activities, through the
permit process, for certain uses of the road right-of-way in conformance with applicable provisions of
federal and state law. Specific standards, regulations, permit conditions, and procedures are necessary to
determine whether any proposed work within the right-of-way is acceptable. To assist with the
administration of the permit process, the Special Services Department of the OCRC was created to
provide timely, professional, and equitable service to all permit Applicants.
This document, adopted by the Board of County Road Commissioners at its meeting held on March 1,
2018, replaces and supersedes the previous publications, Rules Governing the Granting of Permits for
Driveways, Banners & Parades, dated April 4, 2002, and Rules Governing the Granting of Permits for
Utilities, Sidewalks, & Non-Motorized Facilities, dated January 9, 2003.
Should any part of these Procedures and Regulations be found by public act of law or a court of
competent jurisdiction to be invalid, void or illegal, such findings shall in no way affect, impair or
invalidate any other provisions contained in these Procedures and Regulations and such other provisions
shall remain in full force and effect. To this end, these Procedures and Regulations are declared to be
severable.
Questions regarding these Procedures and Regulations for Permitted Activities may be directed to the
Special Services Department of the OCRC:
(616) 842-5400
www.ottawacorc.com
1
II. DEFINITIONS
The following definitions shall be applicable to these Procedures and Regulations.
433 AGREEMENT - An agreement made with the Ottawa County Water Resources Commissioner for
the establishment of a county drain and county drain district pursuant to the Chapters 3 and 4 of the
Michigan Drain Act, Act No. 40 of 1956, as amended.
AASHTO - American Association of State Highway and Transportation Officials.
ACCESS - A way or means of providing entrance to or exit from a public road from property adjoining
the road by use of an approach.
ACCESS MANAGEMENT- A process of developing, providing, and managing reasonable access while
preserving the flow of traffic and maintaining safety, capacity, and proper speed on the roadway system.
ACCELERATION LANE - A lane, including a taper, constructed for the purpose of enabling a vehicle
entering the roadway to increase its speed to a rate at which it can safely merge with through traffic.
ADT - The average two-way daily traffic volume. Where daily data is not available, data from a shorter
period may sometimes be used.
APPLICANT (Driveway Permit) - A property owner or the property owner's authorized legal agent
desiring to construct, reconstruct, relocate, resurface, use, or maintain a driveway that connects to a
county road.
APPLICANT (Right-of-way Work) - A public or private entity or a person making application for a
permit to construct, operate, use and/or maintain a facility within the road right-of-way for the purpose
outlined within the application.
APPLICANT'S ENGINEER - Professional Engineer licensed in the State of Michigan employed by the
Applicant to prepare plans and supervise construction.
APPROACH - Portion of the driveway between the road pavement edge and the ROW Line.
AASHTO - The American Association of State Highway and Transportation Officials.
ALL-SEASON ROAD - A local or primary road constructed to a standard that will not require seasonal
weight restrictions.
AS-BUILT - Drawings/plans submitted by a Contractor upon completion of a project showing the exact
dimensions, geometry, elevations, and location of all elements of the completed work.
ASTM - American Society for Testing and Materials.
BACKFILL – Suitable material used to replace material removed from a trench..
BANNER - Any arrangement of words, lettering, symbols, or decoration, including a holiday decoration,
suspended over any portion of a road or adjacent to a travelled lane.
2
BENCH MARK - A surveyor’s mark on a permanent feature of known elevation and position used as a
reference point in surveying.
BOARD - The Board of County Road Commissioners of the County of Ottawa, State of Michigan.
BORING - A procedure of making a horizontal tunnel below the ground surface by the use of a machine.
CAD – Computer Aided Design.
CARRIER PIPE - A pipe directly enclosing a transmitted liquid, gas or solid.
CASING PIPE - A larger pipe enclosing a carrier pipe.
CATCH BASIN - A drainage structure intended to convey storm water runoff into a storm sewer system.
CERTIFIED OPERATOR - The Water Resources Division of the DEQ certifies Storm Water Operators
for construction sites and for industrial facilities.
CLEAR VISION ZONE - Refers to land acquired or used by the agency having jurisdiction over a
highway for the purpose of maintaining unobstructed view.
COLOCATION (UTILITY) - The use of pole lines, or other facilities, by two or more utilities.
COMMERCIAL DRIVEWAY - A driveway serving a commercial establishment, industry, governmental
or educational institution, hospital, church, apartment building, manufactured housing community, or any
other facility not included within the definitions of residential or field driveways.
CONSTRUCTION INSPECTOR – A qualified on-site independent inspector that verifies all road and
drainage construction, restoration, or improvements are completed in accordance with the approved
construction plans in accordance with the Procedures and Regulations for Permitted Activities.
CONTRACTOR – An individual, firm, association, partnership, corporation, company, or any
combination thereof that furnishes, constructs, or installs any improvement within the right-of-way.
COVER - Depth between the grade of roadway, ditch or other surface and a buried utility pipe, culvert,
communication cable, or electrical conductor.
COUNTY DRAIN - A County Drain is established drain under the jurisdiction of the Water Resources
Commissioner that may be an open ditch, stream or underground pipe, retention pond or swale that
conveys storm water.
COUNTY ENGINEER - The OCRC Engineering Director or any OCRC employee designated to act for
him or her in implementing these Procedures and Regulations of the Board.
CROSS-SECTION – A profile view that is normal to the centerline of a highway, road, or street that plots
existing and proposed roadway features that can include items such as road section layers, shoulders,
ditches, culverts, storm sewer, curbs, utilities, sidewalks, paths, etc.
CULVERT - A structure providing surface water conveyance under the crossing of a road or driveway.
3
DECELERATION LANE - A lane, including a taper, constructed for the purpose of enabling a vehicle to
leave the through traffic lane at a speed equal to or slightly less than the speed of traffic, and then
decelerate to a stop or execute a low-speed turn.
DIRECTIONAL DRILLING - Drilling a rod horizontally through the soil, and then pulling a reamer and
casing (or carrier pipe) back through the drilled soil.
DRIVEWAY- A way or means of providing entrance to or exit from a public road from property
adjoining the road by use of an approach.
DRIVEWAY FLARE - A triangular pavement surface at the intersection of a driveway and a public road
that facilitates turning movements and is used in lieu of a turning radius areas.
DRIVEWAY CONSTRUCTION - Shall be defined as construction of new driveway approaches, any
change or reconstruction of existing driveway grades or surface, installation of drainage facilities, or any
other modification of an existing driveway within the right-of-way or influence of right-of-way.
DRIVEWAY OFFSET - The distance between the centerlines of driveways on opposite sides of an
undivided roadway.
DRIVEWAY SPACING - The distance between the inside edges of driveways on the same side of the
road.
DRIVEWAY WIDTH - The narrowest width of a driveway, measured perpendicular to the centerline of
the driveway.
EASEMENT - A right-of-way granted, but not dedicated, for specific and limited use of private land.
EGRESS: - The exit of vehicular traffic from property abutting a roadway.
EROSION - The process by which the ground surface is worn away by action of wind, water, gravity, or a
combination thereof.
EXCAVATION or CUT - Any act by which soil or rock is cut into, dug, quarried, uncovered, removed,
displaced or relocated.
FIELD DRIVEWAY - Any driveway serving a farm yard, cultivated or uncultivated field, timberland or
undeveloped land not used for industrial, commercial, or residential purposes.
FRANCHISE UTILITY – Gas, electric, and telecommunication facilities that are approved by the
Governing Body.
FRONTAGE - Portion of property that abuts a public highway right-of-way that is not a limited access
highway.
GOVERNING BODY - Local unit of government in which the development is situated.
GPS - Global Positioning System, composing of the set of longitude and latitude coordinates describing a
specific geographic location.
4
GRADE (GRADIENT) - The rate or percentage change in slope, measured along the centerline of a
roadway or access point, either ascending or descending from or along the roadway.
GRADING - Any stripping, excavating, filling, stockpiling, or any combination thereof.
HARD SURFACED - A surface paved with asphalt, seal coat or concrete.
HIGHWAY, ROAD, or STREET - A general term denoting a public way for purposes associated with
travel, including the entire area within the right-of-way.
HMA - Hot Mix Asphalt.
INGRESS - The entry of vehicular traffic to property abutting a roadway.
INSURANCE REQUIREMENTS – A policy that establishes the minimum insurance requirements to
work within the road ROW as adopted by the Board. The current insurance requirement policy can be
obtained from the OCRC offices.
JACKED-IN-PLACE - A construction method that pushes a pipe through the soil while a boring auger
rotates within the pipe to remove soil.
LABORATORY – A certified laboratory that has been approved by the County Engineer.
LEFT TURN LANE - A lane that is added between opposite directional lanes to accommodate storage of
left-turning vehicles.
LOCAL ROAD - Local roads are lower volume highways, roads, or streets that provide limited mobility
and provide access to residential areas, businesses, and farms and are certified as part of the local county
road system.
MDEQ - Michigan Department of Environmental Quality.
MDOT – Michigan Department of Transportation.
MDOT SPECIFICATION - Michigan Department of Transportation’s 2012 Standard Specifications for
Construction or current edition will be used except where noted.
MIOSHA - Michigan Occupational Safety and Health Administration.
MISS DIG - Michigan’s utility safety notification system.
MMUTCD - Michigan Manual of Uniform Traffic Control Devices.
OCRC – Ottawa County Road Commission.
OCWRC – Ottawa County Water Resources Commissioner.
OPEN-CUT - An excavation in the pavement that is open to the sky at its surface, such as a trench.
OSHA - Occupational Safety and Health Administration.
5
PA - Public Act of the State of Michigan.
PASSING LANE - A paved area within the right-of-way which will allow vehicles to pass to the right of
a left-turning vehicle.
PERMIT HOLDER: - The Applicant or a person, partnership, corporation or entity under sufficient
authority and control of the Applicant to perform the work requested by the Applicant in accordance with
the requirements set forth in these rules and the terms and conditions of a permit once it has been issued
by the OCRC.
PLOWING - The placing of cable, conductors or flexible pipe underground by a plow designed to cut the
ground so as to permit the cable, conductor, or pipe to be fed through the plow blade to a minimum
specified depth with minimal displacement of soil.
PRIMARY ROAD - Primary Roads are higher traffic volume highways, roads, or streets that balance
mobility and land access and are certified as a part of the primary county road system.
PRIVATE ROAD - A road which is not under the jurisdiction of the OCRC and which serves more than 5
living units. A private road is considered a commercial driveway.
PROPERTY OWNER - A person, firm, association, partnership, corporation, or combination therof, or
any other party having an ownership interest in land.
PUBLIC UTILITY – Water and sanitary sewer facilities that are owned and maintained by a Governing
Body.
RESIDENTIAL DRIVEWAY - A driveway serving four or less single-family units.
ROADBED – The complete cross-section of a road that can include a subgrade, subbase, base, and
surface.
ROW - Right-of-way; the official area of land dedicated to the public for road, drainage, pedestrian, and
utility use. The Road Commission manages and regulates the use of the right-of-way.
ROW LINE - Right-of-way line; the boundary between property and public land under legal control of
the agency having jurisdiction over the highway, road, or street.
ROAD CLOSURE – A road closure is designed to eliminate the exposure of motorists to work zones and
workers to traffic by temporarily closing a road for construction, rehabilitation, or maintenance.
ROADSIDE - A general term denoting the area adjacent to and outside of the travelled way.
SCHEDULE OF FEES – A policy adopted by the Board to establish a fee schedule for items related to
developing public roads, permitted activities, and other miscellaneous needs. The current fee schedule
policy can be obtained from the OCRC offices.
SIGHT DISTANCE - The distance drivers can see an approaching vehicle from their right or left.
SESC - Soil Erosion and Sedimentation Control, Part 91 of the Michigan Natural Resources and
Environmental Protection Act, Act No. 451 of 1994.
6
STORM SEWER - An underground pipe that carries storm surface runoff from a public road to an outlet.
SUPER-ELEVATED - The outside edge of a road curve is raised, or super-elevated, to help vehicles
around the curve.
TAPER - Widening of pavement to allow the redirection and transition of vehicles around or into an
auxiliary lane.
TEMPORARY TURNAROUND - A temporary turnaround is placed at the end of short public road
segments or roads that are to be extended in the future and facilitates plowing and routine maintenance of
the road system.
THROAT LENGTH - A distance running parallel to the centerline of a driveway from the access point to
the first onsite location at which a driver can make a right or left turn; measured from the face of the curb
on roadways with curb and gutter and from the outside edge line on roadways without a curb and gutter.
THROAT WIDTH - The narrowest width of a driveway, measured perpendicular to the centerline of the
driveway.
TRAFFIC CONTROL PLAN - A plan identifying all required traffic control devices, including, but not
limited to, signs, barriers, barricades, plastic drums, lights, and pavement markings in accordance with the
current MMUTCD.
TRAFFIC COUNT - A tabulation of the number of vehicles or pedestrians passing a certain point during
a specified period of time.
TRAFFIC IMPACT STUDY - Analysis of the potential traffic impacts generated by a proposed project
on intersection level-of-service and the safety and operation of the public road system. The type of study
and level of analysis will vary depending upon the type and size of development.
TRAVELLED WAY - The portion of the road for the movement of vehicles.
TREE PLANTING POLICY – A policy adopted by the Board to identify requirements regarding tree size
and species, location, and general conditions for trees planted in the ROW. The current tree planting
policy can be obtained from the OCRC offices.
TRENCH - A narrow open excavation.
USGS: United States Geological Survey (NAVD88 datum or as directed by County Engineer).
UTILITY SERVICE CONNECTIONS - Facilities supplying utility service to individual consumers from
a main line.
VARIANCE/DEVIATION - A formal request to deviate from the stated standards.
7
III. GENERAL PROVISIONS
This document has been prepared to consolidate all of the Procedures and Regulations for the issuance of
permits to conduct certain activities within the ROW of roads under the jurisdiction of the OCRC. These
Procedures and Regulations are made part of any permit issued by the OCRC for such activities.
A. Activities that Require Permits
It is the responsibility of any person, business, corporation, utility, Governing Body, or organization who
desires to construct, operate, maintain, work, use and/or remove in the public ROW to secure a permit
from the OCRC that authorizes the activity. The types of activities that require a permit include, but not
limited to:
1. Construct, reconstruct, relocate, surface, or resurface a driveway or road approach adjoining a
road under the jurisdiction of the OCRC.
2. Engage in a use of the land served by a driveway or road approach which is changed or expanded
from that previously existing.
3. Operate, use or maintain a driveway or road connecting to a public road or ROW under the
jurisdiction of the OCRC.
4. Install, maintain, or connect any surface-level, underground, or overhead public, franchise, or
private utility, pipeline, wire, conduit, sewer, or associated appurtenance.
5. Conduct surveying or geophysical operations.
6. Erect or suspend a banner, decoration, or similar object.
7. Close a road or section thereof to normal traffic for the purpose of construction, staging a parade,
celebration, festival, race/walk, or similar activity.
8. Install, repair or maintain a sidewalk or non-motorized path.
9. Conduct grading, landscaping, tree trimming or tree removal.
10. Move vehicles or loads which exceed the size and weight limitations specified by law.
11. Any other activity which requires excavation in the ROW, working from the ROW to reach
abutting property, or disruption of normal traffic operations or patterns.
B. Authority
1. The OCRC is the jurisdictional authority over all public roads lying outside the incorporated
cities and villages within Ottawa County, exclusive of any state trunk-line highways. This was
first established by Act No. 283 of 1909, as amended, being MCL §220.1 et seq, commonly
known as the County Road Law.
2. Michigan law further provides: "Each governmental agency having jurisdiction over any highway
shall maintain the highway in reasonable repair so it is reasonably safe and convenient for public
8
travel. Any person sustaining bodily injury or damage to his property by reason of failure of any
governmental agency to keep any highway under its jurisdiction in reasonable repair and in
condition reasonably safe and fit for travel may recover the damages suffered by him from such
governmental agency." This section provides a specific and narrowly limited exception to
governmental immunity. MCL §691.1402.
3. Operations within the county ROW other than normal vehicular or pedestrian travel require a
permit when conducted by anyone other than OCRC personnel, agents, or Contractors. The
statutory authority of the OCRC to require compliance with permit requirements is predicated
upon its jurisdictional authority and is set forth in various statutes. These include, without
limitation and in no particular order, the following:
a. MCL §247.321 et seq, known as the Driveways, Banners. Events, and Parades Act, sets forth
parameters regarding the regulation of driveways, banners, events, and parades upon and over
highways. The term "driveways" is broadly defined to include all points of access to public
roads. The statute places responsibility for the regulation of such activities upon the highway
authority. With respect to Ottawa County roads, the authority is the Board.
b. MCL §224.19b, states that "a person, partnership, association, corporation, or
governmental entity shall not construct, operate, maintain or remove a facility or perform any
other work within the ROW of a county road except sidewalk installation and repair without
first obtaining a permit from the county road commission having jurisdiction over the road.”
c. MCL §560.101 et seq, known as the Land Division Act, regulates the subdivision of land. It
requires certain approvals by the OCRC, including the development of any public roads. The
details of the OCRC’s role with respect to the Land Division Act are covered in the OCRC
publication Procedures and Regulations for Developing Public Roads.
d. MCL §247.171 et seq. prohibits obstructions and encroachments on public highways and
provides for the removal thereof, and further prescribes the conditions under which public
utility companies, cable television companies, and municipalities may enter upon public
roads, bridges, and streets for the construction of their utility facilities.
e. MCL §257.l et seq, known as the Michigan Vehicle Code, governs the operation of vehicles
on county roads.
C. Standards, Guidelines, & Specifications for Design and Construction
The following non-exhaustive list of engineering publications will provide guidance to Applicants and the
County Engineer. These publications do not supersede the need for sound engineering judgment in
conformity with accepted engineering principles.
The OCRC hereby adopts by reference and incorporates in these Procedures and Regulations as if fully
stated herein the most current editions of the following list of publications:
• AASHTO A Policy On Geometric Design of Highways and Streets
• AASHTO Roadside Design Guide
• ITE Trip Generation Handbook
• ITE Trip Generation Manual
• MDOT Design Manual
9
• MDOT Drainage Manual
• MDOT Geometric Design Guide
• MDOT Maintaining Traffic Typical Details
• MDOT Road and Bridge Standard Plans and Special Details
• MDOT Standard Specifications for Construction
• Michigan Manual on Uniform Traffic Control Devices
• TRB, Highway Capacity Manual
D. Preservation of Survey Monuments
To ensure compliance with the provisions of MCL §54.201 et seq. regarding the preservation of survey
monuments and witnesses, the following procedures shall apply to all permit Applicants, their engineers
and surveyors, and Permit Holders performing work within OCRC ROW.
1. Public land survey corners and property controlling corners located within a construction area
shall be witnessed prior to the commencement of construction, and their locations shall be noted
on plans submitted as part of a permit application. All corners shall be re-established in
accordance with MCL §54.201 et seq. The Permit Holder and Contractor shall coordinate the
work with a professional Surveyor licensed in the State of Michigan during construction activities
for the purpose of replacing survey monuments and monument boxes in new pavement, etc.
2. If a survey corner or property controlling monument is located in a public roadway that is hard
surfaced, a monument box shall be used and placed flush with the finished pavement elevation on
all sides.
3. If a survey corner or a property controlling monument is located in a public roadway that is not
hard-surfaced, the monument shall be at least 12 inches below the surface of the finished road.
4. Upon completion of the requirements of MCL §54.201 et seq., the Professional Surveyor shall
submit two (2) copies of the recorded Land Corner Record Certificate (with Liber and Page): one
(1) shall be sent to the project engineer and one (1) shall be sent to the County Engineer.
E. Amendment
From time to time and as may be required, the Board may amend all or any part of these Procedures and
Regulations as provided by law.
10
IV. PERMITTING PROCESS
Permit requirements, supplemental specifications, and a schedule of permit and inspection fees are
adopted as necessary by the Board. Fees charged are to cover the necessary and actual costs applied in a
reasonable manner for the issuance of the permit and for review of the proposed activity, inspection and
related expenses.
A. Permit Application
Applications for permits shall be submitted in the manner prescribed by these Procedures and Regulations
and on the appropriate forms supplied by the OCRC (See Detail PA-1).
All permit applications shall meet the following basic requirements before they are accepted for
processing:
1. Application
Each permit application shall be completely filled out and signed by the Permit Holder and
Contractor. If the Contractor is not known at the time a permit is issued, the OCRC shall be
notified, in writing, of the Contractor's name, address and telephone number before work may
start. A separate permit may be required for each Contractor, clearly delineating the area of work
responsibility.
2. Construction and/or Site Plans
Certain permit applications, primarily those involving construction activities, shall be
accompanied by two (2) paper copies and an electronic PDF file of construction and/or site plans
prepared in accordance with these Procedures and Regulations. Typically, an application for a
residential driveway permit will be exempt from the aforementioned plan requirements.
3. Permit Fees
All permit fees shall be submitted prior to a review of a permit application. Fees shall be paid in
amounts per the current Schedule of Fees, as adopted by the Board.
4. Indemnity and Certificates of Insurance
The Applicant or its Contractor shall furnish proof of general liability insurance in amounts not
less than $1,000,000 each occurrence; and general aggregate, proof of automobile liability in
amounts not less than $1,000,000 combined single limit for each accident, bodily injury per
accident, and property damage per accident; and in an amount not less than $300,000 for bodily
injury per person. The Permit Holder shall name OCRC as an additional insured party on the
policy. An Applicant for a single residential or field driveway permit, who is the property owner,
may furnish proof of general liability insurance for the property in lieu of the insurance
requirements noted above.
Such insurance shall cover a period not less than the term of the permit and shall provide that it
cannot be cancelled without 30 days advance written notice to OCRC by certified mail, first-
class, return receipt requested.
11
a. The Permit Holder shall defend and hold harmless the OCRC against any claim for damages
or related costs and expenses arising from any activities or operations covered by the permit,
provided, however, that in the case of construction activities, the Permit Holder shall not be
obligated to indemnify the OCRC against its own sole neglect.
b. The Applicant shall name the OCRC as additional insured, by name, on the policy of
insurance worded as follows: “The Board of County Road Commissioners of the County of
Ottawa, the Ottawa County Road Commission, and its officers, agents and employees”.
c. The certificate of insurance must be provided by a person, a corporation, or by an authorized
representative who signed personally either the application or permit. Insurance shall remain
in force until the permitted activity is completed, inspected and approved.
d. Should insurance coverage be cancelled or reduced below acceptable limits, authorization to
continue work under the permit shall be suspended or revoked. OCRC may in such case take
appropriate action to restore or protect the road and appurtenances, utilizing any security
deposits or applicable bonds to defray expenses.
5. Bonds
Bonds shall be required for all construction activity within the public ROW to protect
OCRC against the cost of completing construction or repairing deficiencies. Acceptable
types of bonds are cash, certified or cashier's checks, and money orders payable to the
Ottawa County Road Commission. Table 1 indicates the minimum permit bonding amounts
for the various types of work in the ROW. The County Engineer may require a higher
bonding amount based on the proposed work and impact to the ROW.
Table 1. Minimum Bonding Requirements for Permits
Permit Type Bond Amount
Commercial Driveway $5,000
Residential Driveway $200*
Field or Temporary Driveway $200
Utility $5,000
Sidewalk and Path $5,000
Road Open-Cut/Reconstruction $10,000
Other As determined by County Engineer
*A $5,000 Annual Performance Bond may be posted in lieu of bonding individual
residential driveway permits. No bond is required to resurface an existing residential
driveway.
When an Annual Performance Bond is furnished, a permit is still required for each
individual project within the ROW requiring a permit. Annual Performance Bond funds
may be retained by the OCRC to recoup any costs and expenses incurred in relationship
to any non-permitted work performed during the year by the Principal of the Annual
Performance Bond.
After receipt of a written request by the Permit Holder and satisfactory completion of the
permitted activity as verified by the County Engineer, any unused bond amount (driveway bonds
only) will be returned to the Applicant or Permit Holder within fifteen (15) business days.
12
In any action by the OCRC against a Permit Holder to enforce the latter’s permit related obligations
(or to collect on a bond deposited in connection with the same), the Permit Holder shall be required to
reimburse the OCRC for all of its associated costs and attorney fees that are in excess of the bond or
are not collectable from the bonding agent.
6. Administrative Completeness Checklist
It is required that applicable administrative completeness checklists in accordance with Section V
of these Procedures and Regulations be submitted in order to assess if the permit application
materials are administratively complete.
B. Application Review & Permit Issuance
1. Within 30 days of receipt of a verified administratively complete permit application, review
comments will be provided by the County Engineer.
2. The OCRC will work cooperatively with the Applicant to resolve all issues prior to taking action
on the permit application.
3. If the OCRC denies an application, the OCRC shall provide the Applicant a copy of the
application marked "denied" along with any attachments and a written explanation for the
decision.
4. If the OCRC approves a permit application, the permit shall be prepared for issuance to the
Applicant and its Contractor, and shall include any additional terms and conditions established by
the review. The Applicant and Contractor noted on the permit will become the Permit Holder. If
the Permit Holder does not agree to all terms and conditions of the permit, the permit shall be
deemed denied.
5. The permit is fully executed and in force after the application and any attached plans are
approved, and the permit is signed and issued by an authorized representative of OCRC.
C. Permit Conditions & Limitations
1. The Permit Holder shall abide by the conditions and limitations contained on the permit. The
application and any work undertaken under the permit shall constitute the Permit Holder's agreement
to this provision.
2. Any activity described in Section III.A of these Procedures and Regulations shall be allowed only
after an approved permit has been issued from the County Engineer. The activity shall be as described
in an approved permit and any construction or site plans accompanying the permit. The OCRC must
approve in writing any significant changes in approved plans.
3. The Permit Holder shall provide the County Engineer at least two (2) days (excluding Saturdays,
Sundays and Holidays) written notice prior to the commencement of any activity covered by the
permit. In certain instances, OCRC may require more notice.
4. In the event of failure to comply with the terms and conditions of any permit issued in accordance
with these Procedures and Regulations, or failure to obtain an appropriate permit, the County Engineer
shall have the right to issue a Stop Work Order. At that time, the Permit Holder shall immediately cause all activity covered by the Stop Work Order to cease and desist until adequate corrections have
been made or deficiencies corrected.
13
5. The OCRC reserves the right of inspection by its authorized representatives of all activity within the
ROW.
6. Any Permit Holder who conducts operations in a manner detrimental to OCRC's ability to maintain
roads reasonably safe and convenient for public travel will be required to cease all such operations.
7. The Permit Holder shall restore the ROW and roadway to a condition determined acceptable to the
OCRC at it sole discretion. All restoration and construction inspection requirements shall conform to
these Procedures and Regulations. The OCRC will take all reasonable actions necessary to provide
reasonably safe and convenient public travel, preservation of the roadway and drainage, prevention of
soil erosion and sedimentation, and elimination of nuisances to abutting property owners caused by
the permitted activity. The cost of any such action will be charged to the Permit Holder, who shall
reimburse the OCRC. In the event that a suspension of work will be protracted or that the work will
not be completed by the Permit Holder, the Permit Holder shall restore the ROW to a condition
similar to the condition that existed prior to issuance of the permit. Such restoration shall be subject to
OCRC review and acceptance.
8. All expenses incurred by the OCRC due to obtaining or enforcing compliance with conditions and
requirements of the permit, failure to obtain a permit, or defective workmanship or materials shall be
borne by the Permit Holder or other responsible party, as the case may be.
9. The Permit Holder shall keep a paper or electronic copy of the permit and any associated approved
plans available at the site during permitted activities.
10. The Permit Holder shall take, provide and maintain all necessary precautions to prevent injury or
damage to persons and property from operations covered by the permit, and shall use warning signs
and safety devices which are in accordance with the current MMUTCD. The Permit Holder shall
conduct all activities and maintain all facilities as set forth in the permit in a manner so as not to
damage, impair, interfere with, or obstruct a public road or create a foreseeable risk of harm to the
travelling public. The Permit Holder shall comply with all applicable OSHA and MIOSHA
requirements.
11. The Permit Holder shall comply with all requirements of the Miss Dig Statute, MCL §460.701 et seq.,
as amended. The Permit Holder shall call "MISS DIG" at (800) 482-7171 at least three (3) full
working days (excluding Saturdays and Sundays), but not more than twenty-one (21) calendar days,
before starting any underground work. The Permit Holder assumes all responsibility for damage to or
interruption of underground utilities.
12. The Permit Holder shall surrender the permit, cease operation, and surrender all rights thereunder,
whenever notified to do so by the OCRC because of a public need to use the area covered by the
permit, or because of a default of any condition or requirement of the permit.
13. Drainage shall not be altered to flow into the road ROW or road drainage system unless approved by
the OCRC.
14. OCRC makes no warranty, either express or implied, as to the condition or suitability of subsurface
conditions or any existing facility which may be encountered during an excavation. The Permit Holder
is responsible for proper disposal, in accordance with current regulations, with any material excavated
from within the ROW. Such materials include, without limitation, soils or groundwater contaminated
by petroleum products or other pollutants associated with sites identified by the MDEQ or reported on
appropriate release forms for underground storage tanks.
14
15. The Permit Holder shall remove all surplus materials to an area outside the ROW unless the permit
otherwise provides. Excavated material and raw materials or equipment shall not be stockpiled or
stored so as to adversely affect the safety of the traveling public, nor shall such material be disposed in
such a manner that wetlands, floodplains, streams, rivers, drains, or other defined watercourses or
water sources are impacted. Work within wetlands or wetland fringes is not authorized by the permit
unless accompanied by State or local wetland permit.
16. All work authorized by the permit shall be completed to the satisfaction of the County Engineer on or
before the completion date specified in the permit. Any request for an extension of time for
completion shall be in writing and shall demonstrate good cause for granting the request. Approval of
an extension of time shall be based on extenuating circumstances indicating no neglect on the part of
the Permit Holder. Additional requirements may be imposed as a condition of an extension of time
due to seasonal limitations or other considerations. These additional requirements may include,
without limitation, changes to materials or construction methods, re-establishment of fees, bonds, and
insurance requirements.
17. The Permit Holder shall notify the County Engineer in writing of completion of the work and shall
request a final inspection. All work authorized by permit shall be completed prior to final inspection,
and all items identified by the final inspection shall be resolved prior to release of the permit bond.
18. The Applicant and the Permit Holder are responsible for obtaining any permits and complying with
State, Federal and Local laws, rules, regulations and ordinances. These include, without limitation,
those pertaining to inland lakes and streams, wetlands, woodlands, flood plains, filling, noise
regulation, and hours of operation. Issuance of an OCRC permit does not authorize activities
otherwise regulated by State, Federal or Local agencies.
19. The Permit Holder is solely responsible for the correctness and completeness of plans submitted as
part of a permit application. Any errors in the plans which become evident after the issuance of a
permit, and which change the scope of permitted work, are subject to these Procedures and
Regulations and the review of the County Engineer, and may be grounds for revocation of the permit.
20. Where roads or road drainage cannot be contained within the existing ROW due to the Applicant's
proposed work, the OCRC may require that additional ROW be dedicated. Prior to permit issuance,
required ROW and easements shall be reviewed and approved by the County Engineer, and submitted
in a format that is recordable by the Ottawa County Register of Deeds.
21. The Permit Holder shall at all times possible maintain a minimum of one acceptable access to all
abutting occupied properties, driveways, and side streets unless otherwise allowed on the approved
plans. The Permit Holder shall notify any owners or occupants of properties whose access may be
temporarily disrupted during the permitted work. The local police, fire, or emergency service
agencies shall define acceptable access. The Permit Holder shall provide traffic control signing and
other improvements necessary to ensure adequate access until the roadway, driveway, or street is
restored. The Permit Holder shall conduct all operations so as to minimize inconvenience to abutting
property owners. The OCRC reserves the right to reasonably limit the progress of work by the Permit
Holder based on the rate of roadway and ROW restoration, including permanent or temporary
pavement. The OCRC may require that work be suspended until satisfactory backfilling of open
trenches or excavations has been completed, and driveways, streets, and drainage are restored.
22. All pumping or dewatering operations shall be conducted in compliance with NPDES permits. Outlet
filters or sediment basins shall be used before discharged water reaches roadside ditches, storm sewer
inlets, or surface waters. Placement of discharge lines on or across the surface of the travelled portion
of any road will not be allowed without advance written permission from the OCRC. The Permit
Holder shall perform all necessary restoration of the road drainage system. If the OCRC deems it
15
necessary for the Permit Holder to either alter dewatering operations or to cease dewatering operations
altogether for reasons of public safety, the Permit Holder shall immediately comply. The Permit
Holder shall locate all dewatering facilities as far from the road surface as possible. If, due to
extenuating circumstances, these facilities are located closer to the road than the back slope of the
ditch, a Type B high intensity flashing light mounted on a plastic drum shall be required at each
location.
23. Normal weight restrictions will be in effect at all times, except during the period when reduced
seasonal load limitations are in effect. If, due to the high volume of trucking, damage to the roads is
threatened, the Permit Holder shall reduce loads carried on the roads as necessary to avoid damage, as
directed by OCRC. The use of tracked or crawler mounted equipment on road pavements shall not be
permitted unless specifically authorized in advance in writing by the OCRC. Written authorization for
such use will usually require complete replacement or resurfacing of the entire pavement width so
used.
24. All subsurface construction within the ROW during the winter season is discouraged. It is extremely
difficult to properly and safely maintain traffic when construction is carried out within the ROW
during the winter months. In addition, adequate restoration of the travelled surface and immediately
adjacent areas to meet traffic needs cannot be satisfactorily achieved during the winter months.
Additionally, disruption of highway structure and substructure is magnified when construction is
carried out within portions of the ROW during the winter months. The winter season shall be
generally defined as the portion of the year beginning on the first day of November and extending to
the date that restricted load-limit/seasonal weight restriction enforcement on the public road system is
removed. This shall not apply to emergency repair of existing utilities or to construction that is
essential to the provision of direct customer service, and which could not have been scheduled other
than during the season of prohibition. Any proposed construction that will be carried out during the
winter season shall be approved, based on a permit obtained from the OCRC in advance of actual
construction or as soon as possible in the case of an emergency repair. Such permits will be issued
with restrictions adequate to protect the interests of the motoring public, roadway facilities, and the
ROW.
25. The Permit Holder shall maintain all work areas in the ROW in a safe, dust and debris free condition
until all work in a given area is completed, including the hauling of materials. Dust control at a
frequency determined by the OCRC shall be provided on any unpaved detour, by-pass, or shoulder
which is to be used by traffic. Dust control shall be provided in compliance with current MDOT
Standards.
26. If the area disturbed by the work is one (l) acre or greater, and requires a NPDES Permit, the Permit
Holder shall notify the OCRC and provide the name and address of the Certified Operator.
V. ADMINISTRATIVE COMPLETENESS
To aid in submitting the necessary materials for all Commercial Driveway, Residential Driveway, Utility
Construction, and Sidewalk and Path Construction Permit applications, as outlined in the Procedures and
Regulations for Permitted Activities, administrative completeness review checklists are provided in
Appendix A.
It is required that these administrative completeness checklists be submitted in order to assess if the
materials are administratively complete. Technical review of the permit application will not begin until
the County Engineer determines the review checklist and associated permit application materials are
administratively complete.
16
VI. DRIVEWAY STANDARDS & REQUIREMENTS
A. General Driveway Standards & Requirements
1. Access Management
The purpose of access management is to provide vehicular access to land development in a manner
that preserves the safety and efficiency of the transportation system. Access management can extend
the operational life of roadways, increase public safety, reduce traffic congestion, and improve the
appearance along the ROW. This, in turn, benefits property owners abutting county roads by
preserving property values and enhancing development potential.
a. The OCRC recognizes that the right of reasonable access to public roads is incidental to
ownership of abutting land. The goal of the OCRC is to grant landowners access connections
for their needs consistent with OCRC access management and access control requirements in
the public’s interest. The OCRC driveway permit process provides guidance for the location
and design of driveways so as to provide freedom of traffic movement, safety for roadway
and ROW users, and preservation of roadway capacity. A successful access management
program reduces crash potential and preserves capacity by regulating parameters such as
driveway location, driveway spacing, driveway design, traffic signal progression, use of
channelization, and use of alternate access systems.
b. Construction or reconstruction of a new or existing driveway, shared driveway, or private
road connecting to a county road, shall be allowed only after an approved permit has been
obtained from the County Engineer. The construction or reconstruction of all driveways or
private roads shall be as described in an approved permit and construction plans.
c. Permits for access connections to public roads shall be issued when consistent with public
safety and based upon traffic volumes, drainage requirements, maintenance needs, the
character of the use of the land adjoining the roadway, and any other requirements in the
public’s interest.
d. When the use of the land served by the driveway is changed or expanded, and the change or
expansion may cause the existing driveway to be a potential safety hazard or to be
inconsistent with the criteria described herein, the driveway will be considered a new
driveway in accordance with MCL §247.327. Factors that may indicate a potential safety
hazard include, but are not limited to, the following:
1. Elevated crash rate
2. Increased traffic volume on the main road
3. Increased turning movements using the driveway or road approach
4. Improper drainage
5. Inadequate sight distance
6. Excessive grades of driveway
7. Improper driveway design for use
8. Change in functional classification of the road
e. The OCRC may revoke any driveway permit if at any time the permitted item, use, or activity
fails to meet the requirements of these Procedures and Regulations, MCL §247.321 et seq., or
the terms and conditions of the permit itself.
17
2. Sight Distance
a. To assure sufficient sight distance requirements, the centerline profile of an intersected public
road shall be shown for a minimum distance of 700 feet in both directions from the proposed
driveway centerline. Sight distance at proposed driveway locations shall comply with the
following diagram shown in Figure 1 and the chart shown in Table 2.
Figure 1. Recommended Minimum Sight Distance
Table 2. Recommended Minimum Driveway Sight Distance Existing Road
Speed Limit (mph)
Proposed Driveway
Safe Sight Distance, d (feet)
25 300
30 360
35 420
40 480
45 540
50 600
55 660
b. The County Engineer may request sight distance diagrams to verify safe sight distance for
any proposed driveways and private roads.
3. Drainage
a. The driveway, including any new lanes or tapers, shall be constructed so that the existing
drainage system and patterns are not adversely affected. The drainage and the stability of the
road subgrade shall also not be altered by driveway construction or roadside development.
18
b. No additional storm water runoff shall be directed or diverted onto the ROW, unless
specifically approved by the OCRC. Existing drainage structures including, but not limited to
culverts, catch basins, and impoundment areas, shall be protected from physical damage and
sedimentation.
c. No driveways shall be built on any existing drainage structures unless approved by the
County Engineer.
d. Driveway Culvert: The County Engineer shall determine whether or not a culvert is required
and, if required, the diameter of the culvert. Unless the driveway crosses a county drain, in
which case the OCWRC will make these determinations. The Permit Holder shall furnish,
install, and maintain unrestricted water flow through the culvert and ditch. Permit Holder
maintenance shall include routine debris removal from the culvert ends and adjacent ditches.
1. Culverts shall be installed in line with existing ditch, unless otherwise directed by the
County Engineer.
2. Unless specified larger, culverts shall be a minimum of 12 inches in diameter and a
minimum of 24 feet in length.
3. Culverts shall conform to MDOT Class A culverts as shown in Figure 2 below.
4. The use of headwalls on culvert ends is prohibited.
5. Culverts over 30 inches in diameter shall require approved slope end sections.
6. Sod, rip-rap, or other suitable material shall be placed at all culvert ends to prevent
erosion.
7. Side slopes of ditch shall be 1 vertical to 3 horizontal or flatter.
Figure 2. MDOT Pipe Alternatives for Culverts
19
4. Number of Driveways and Location
a. In general, one access point is adequate for most driveway applications. The County
Engineer will consider an additional access point if the Applicant can provide sufficient
information to show:
1. The property will generate significant traffic volumes to warrant two points of access or;
2. An additional access point is necessary for safe internal operations on the property.
If an additional access point is allowed by the County Engineer, the preferred location would
be a joint access point with an adjacent property owner.
b. Driveways shall be located to maintain free movement of road traffic, provide the required
site distance, and result in the most favorable driveway grade.
c. Driveways shall be avoided on primary roads where local road access is available, and
avoided on a local road where a residential or private road access is available.
d. Driveways shall not be constructed along the acceleration or deceleration lanes and tapers
connected to a public road unless no other reasonable access point is available.
e. A driveway, including the radii/flares but not including the right-turn lanes and tapers, shall
be located entirely within the area between the Permit Holders property line extended to the
centerline of the road. A driveway radius may extend outside of that area only if written
permission is obtained from the adjacent property owner allowing such an extension.
f. Subject to OCRC’s discretion, short public road segments and/or public roads ending with a
Temporary Turnaround shall not be used as a means of ingress and egress to adjoining
property.
5. Driveway Grades
To achieve appropriate driveway profiles, some of the significant factors to be considered are:
a. Abrupt grade changes, which cause vehicles entering and exiting driveways to move at
extremely slow speeds that can create:
1. The possibility of rear end collisions for vehicles entering the driveway.
2. The need for large traffic gaps that may be unavailable or infrequent, causing safety
issues for drivers.
b. The presence of sidewalks or paths where pedestrians may be expected in developing areas
now or in the future.
c. Grades that are compatible with the site requirements for sight distance and drainage, to
prevent excessive drainage runoff from entering the roadway or adjacent property.
Driveways should be constructed with a vertical sag curve a minimum of 8 feet from the back-of-curb
or road edge and the ROW Line (See Detail PA-2).
20
All driveway grades shall be limited between 2 to 4 percent from the back-of-curb or road edge in
accordance with Detail PA-2. Maximum overall driveway grades shall be limited to 10 percent for
residential driveways and to 8 percent for commercial driveways where grades and drainage influence
the ROW.
6. Traffic Control and Public Safety
The Permit Holder and/or Contractor shall provide and maintain all necessary precautions to
prevent injury or damage to persons and property from operations covered by the permit, and
shall use warning devices in accordance with the current edition of the MMUTCD.
7. Local Governing Body and OCWRC Review and Approval
The Applicant and/or Permit Holder shall contact the local Governing Body in which the
driveway construction will occur and the OCWRC to ensure compliance with requirements to the
improvement, expansion, development or redevelopment of private property, including any
access requirements, which may be applicable.
8. Permit Application
a. An application for a driveway permit, on forms supplied by the OCRC (See Detail PA-1),
shall specify the type of driveway requested, including the location, number and type of
driveways. The OCRC may approve the system as requested or may condition approval on
such changes as may be necessary to maintain safe conditions and proper spacing between
driveways. Application review will be based on anticipated traffic volumes on the driveways
and on the roadway, type of traffic to use the driveways, type of roadside development,
drainage, and other operational considerations in the public’s interest.
b. The proposed driveway location shall be clearly identified at the project site by staking and
flagging, or other method, so it can be easily located by the County Engineer making a field
review. Information on stakes shall include the Applicant’s name, property address number
and, where applicable, plat lot number. Failure to provide this information will delay the
review of the permit application.
c. A permit granting permission to construct, reconstruct, relocate, resurface, use and maintain a
driveway that connects to a county road may be issued by the OCRC after receipt of an
approved application and only to the property owner or the property owner's authorized
representative.
B. Commercial Driveway Requirements
An application for a commercial driveway permit shall be submitted in a manner prescribed in these
Procedures and Regulations. To aid in submitting this material, a Checklist for Submittal of Permit
Application for Commercial Driveway in accordance with Section V of these Procedures and Regulations
is required with all submissions in order to assess if the permit application is administratively complete.
1. Construction Plan Requirements
Applications shall be accompanied by two (2) sets of paper and an electronic PDF file of
construction plans signed and sealed by a Professional Engineer.
21
The plans shall be drawn on 24 inch x 36 inch sheets and to a standard scale of not less than 1
inch = 50 feet horizontal and 1 inch = 5 feet vertical.
The plans shall include a cover sheet indicating the name of the proposed development, index of
sheets, and location sketch of the proposed development within Ottawa County.
Plans shall clearly show the following features:
a. North directional arrow and scale of plan.
b. Location map and Township information.
c. Existing road pavement, shoulders and shoulder points, ditches, poles, hydrants, utility
service boxes, trees, shrubs, ROW and property lines, road appurtenances, medians (if
existing) and dimensions thereof, driveways on adjacent property and on property opposite
the frontage, and names of existing and proposed roads (public and private).
d. All buildings and appurtenances, both proposed and existing, with dimensions and a
notation as to present or proposed general use of the buildings.
e. All driveways, tapers, through lanes, right turn lanes, center left turn lanes, or passing lanes to
be constructed, reconstructed, relocated, surfaced, resurfaced, operated, used, or maintained
shall include the following dimensions and features:
1. Widths of all driveways and lanes
2. Radii of driveway returns and other points of curvature and deflection
3. Driveway grades and profile view of driveway
4. Road centerline and edge of pavement grades at 50-foot intervals or less, or as directed
by the County Engineer
5. Sight distance for the proposed driveway approach
f. Distance from existing driveway(s) and proposed driveway(s) to the nearest intersecting
street, and distance from edge of driveways to properly lines.
g. All roadside features to be constructed within the ROW, including without limitation curb,
sidewalks, paths, traffic control devices, manholes, poles, utilities, etc.
h. Existing and proposed drainage systems to include:
1. Size of drive culvert or storm sewer
2. Material type of culvert or storm sewer
3. Type of culvert end treatment
4. Grade of culvert or storm sewer with sufficient elevations upstream and downstream to
show the extent of flow across the proposed development and to the proposed outlet
5. Direction of surface water flow to and from adjacent property
6. Drainage structure size, type, and elevation of all applicable inlets, inverts, and sump
7. Drainage plan and outlet for all storm drainage on the site
22
2. Traffic Impact Study
A traffic impact study from a qualified traffic engineer is required for all developments, unless
waived by the County Engineer, and shall either be a traffic impact statement or traffic impact
assessment, depending on the type and size of the proposed development.
a. A traffic impact statement shall be required for any proposed development which would be
anticipated to generate over 100 or more peak-hour directional trips or over 750 daily trips
(over a 24 hour period). The volume of generated traffic shall be evaluated for its potential
impact on the adjacent street system including nearby intersections and access points of the
development under consideration.
b. A traffic impact assessment shall be required for a project generating less than 99 peak-hour
directional trips. This type of study is recommended for smaller scale projects that are not
anticipated to have a significant impact on the overall road system but may impact the site
access. The analysis for this type of study can typically be isolated to the turning movements
at all site access points.
c. After review of the traffic study, the County Engineer may require improvements to nearby
intersections and the access points to the development with any necessary auxiliary lanes
(deceleration lane, by-pass lane, right-turn lane and/or center left-turn lane) or road
modifications.
3. Driveway Location
The location and spacing of access for commercial driveways and road approaches is an
important element in the planning, design, and operation of roadways. Access points are the main
location of crashes and congestion. Their location and spacing directly affect the safety and
functional integrity of the roadway. Commercial driveway location and spacing shall comply
with the following diagram shown in Figure 3 and the chart shown in Table 3.
Figure 3. Commercial Driveway Spacing Requirements
23
Table 3. Recommended Minimum Commercial Driveway Spacing
Minimum Driveway Spacing (feet)
a b c d
Two Lane Road 100 100 150 130
Multi-Lane Road 150 250 250 75
a. Spacing Requirements for Adjacent Driveways (a)
Table 3 indicates the desirable access spacing as a function of road type for adjacent
commercial driveways. These distances are based on average vehicle acceleration and
deceleration considered adequate to maintain good traffic operations. Driveway spacing is
measured from edge of driveway to edge of driveway.
b. Spacing Requirements from Driveways on Opposite Side of Road (b) and (d)
To minimize turning conflicts, driveways should be either aligned with those directly across
the road or offset a sufficient distance from those across the road to achieve the minimum
spacing standards listed in Table 3. Driveway spacing is measured from centerline to
centerline.
c. Spacing Requirement from a Public Road Intersection (c)
In accordance with AASHTO guidelines, driveways shall not be situated within the
functional boundary of intersections. This boundary includes the longitudinal limits of all
full width auxiliary lanes. An access point may be allowed within the above boundary only if
the entire property frontage is located in this boundary.
A driveway shall not be constructed along acceleration or deceleration lanes and tapers,
unless no other reasonable access point is available. OCRC may require an extension of
these lanes by the Applicant.
Spacing between a road intersection and an access connection shall be sufficient to avoid
creating conflicts between driveway traffic movements and road traffic movements at the
intersection. Table 3 provides the minimum corner separation dimensions that are measured
from the edge of the proposed driveway to the near ROW Line of the intersecting road.
4. Sight Distance Requirements
Acceptance of site access onto an existing public road is subject to the field review and
recommendations of the County Engineer. Considerations include, but are not limited to, vehicle
speed, sight distance, and topography. An area of clear vision, free from obstructions and
encroachments, shall be provided. Fences, trees, shrubs, poles, signs, boulders, mailboxes, and
other obstacles shall be removed or modified in this area to afford an unobstructed view in both
directions of the approaching traffic.
A clear-vision area, as shown in Figure 1 and Table 2, shall be provided at all commercial
driveways entering onto a road under the jurisdiction of the OCRC. The County Engineer may
request a sight distance diagram to verify safe sight distance for any proposed driveway or private
road.
24
5. Driveway Geometrics
A typical standard commercial driveway approach consists of a two-way traffic design (See
Detail PA-3).
Optional commercial driveway approach designs may be either divided three lane with a median
or a typical three lane design. A divided commercial driveway shall have a curbed island
separating the entering and exiting movements with a dedicated exiting left turn lane (See Detail
PA-4). A typical three lane commercial driveway shall be designed with a dedicated exiting left
turn lane (See Detail PA-5).
A one-way commercial driveway is a special case and may be allowed depending on the site-
specific characteristics. A one-way driveway shall either be for entering or exiting and designed
to facilitate the desired turning movement and to discourage prohibited movements. The
installation and maintenance of directional signs shall be the responsibility of the Applicant
and shall be shown on the site plan.
a. Width
1. The typical two-lane commercial driveway design shall include one (1) entrance lane and
one (1) exit lane, with a maximum total throat width of thirty (30) feet from back-of-curb
to back-of-curb. (See Detail PA-3).
2. When larger driveway traffic volumes are expected, two (2) exit lanes will be allowed.
• The driveway shall be designed with a curbed median dividing the exit lanes from the
entrance lane (See Detail PA-4) or,
• The driveway shall be designed with permanent lane lines and arrows to be placed
and maintained by the Permit Holder (See Detail PA-5).
• Exit lane widths shall be 12 feet. Entrance lane widths will vary in design based on
vehicle usage and range from 12 feet to a maximum of 16 feet.
b. Radii
1. Driveways shall have a minimum twenty-five (25) foot entrance and exit radius.
2. When truck traffic is expected, a minimum thirty (30) foot radius shall be used.
• The County Engineer may request that commercial vehicle turning templates be
graphically placed on the proposed driveway design to verify the appropriate radius.
c. Concrete Curb & Gutter
Concrete curb and gutter is required for all commercial driveways. The County Engineer
may consider waiving this requirement if all three (3) of the following are met:
1. Traffic volume of the adjacent public road is less than 1,000 vehicles/day
2. Traffic volume of the driveway is anticipated to be low. The Applicant shall provide
calculations for the estimated number of peak hour trips for the driveway for review by
25
the County Engineer. These calculations shall be determined using the current edition of
the ITE Trip Generation Manual.
3. The area between the ROW Line and public roadway is ditched or constructed to prohibit
use on all areas other than approved driveway locations.
If concrete curb and gutter is waived by the County Engineer, the commercial driveway shall
only have a HMA surface, as a concrete surface would be prohibited.
d. Deceleration/Acceleration, Tapers, Turn Lanes, and Connection Lanes
1. Additional lanes and taper lengths may be required by the County Engineer based on
ADT of the adjoining road, location of existing and proposed driveways, and where high
driveway traffic volumes are anticipated (See Detail PA-6 and PA-7 for two examples).
e. Joint Driveways
1. When property owners of adjoining properties agree, a joint driveway may be
constructed. The driveway shall meet the same requirements regarding commercial
driveways.
6. Driveway Construction Standards
Commercial driveways shall meet the following minimum subbase, aggregate base, and
concrete curb and gutter requirements listed below:
a. Subbase - MDOT Spec. 301
Material - Granular Material Class II
Gradation - MDOT Spec. Table 902-3
Thickness - 18” Minimum
b. Aggregate Base Course - MDOT Spec. 302
Material - Dense-Graded Aggregate 22A or 21AA
Gradation - MDOT Spec. 902-1 Minimum 25% crushed
Thickness - 7” Minimum
c. Concrete Curb and Gutter - MDOT Spec. 802
- MDOT F4-Modified (without reinforcement)
or as directed by the County Engineer
Material - MDOT Grade S2
Commercial driveways shall be hard surfaced with either HMA or concrete materials, and meet
the following minimum requirements as listed below:
26
d. HMA Surface - MDOT Spec. 501
Material - HMA Mixture LVSP Leveling
- HMA Mixture LVSP Surface
Thickness - 3 ¼” (360#/syd) Minimum
Asphalt Cement - Performance Grade 58-28
e. Concrete Surface - MDOT Spec. 601
The pavement structure, materials, thickness, and concrete mix and joint spacing/layout
shall be evaluated by a qualified Pavement Design Engineer.
C. Residential Driveway Requirements
A driveway for the purposes of serving a single or two-family dwelling shall be deemed a residential
driveway. A residential driveway or private street serving more than five (5) single family homes, units,
dwellings, or properties will be considered a commercial driveway and will be subject to all commercial
driveway requirements thereto.
An application for a residential driveway permit shall be submitted in a manner prescribed in these
Procedures and Regulations. To aid in submitting this material, a Checklist for Submittal of Permit
Application for Residential Driveway in accordance with Section V of these Procedures and Regulations
is required with all submissions in order to assess if the permit application is administratively complete.
1. Site Plan Requirements
Residential driveway permit applications require the submittal of a site plan, unless waived by the
County Engineer. The following information should be provided on the site plan:
a. Plans drawn to a scale not less than 1 inch = 30 feet horizontal.
b. North directional arrow with Township information.
c. All existing roads and driveways
d. The proposed driveway and home orientation on the property.
2. Driveway Location
The location and spacing of access for residential driveways is an important element in the
planning, design, and operation of roadways. Access points are the main location of crashes and
congestion. Their location and spacing directly affect the safety and functional integrity of the
roadway. Residential driveway location and spacing shall comply with the following diagram
shown in Figure 4 and the chart shown in Table 4.
27
Figure 4. Residential Driveway Spacing Requirements
Table 4. Recommended Minimum Residential Driveway Spacing
Minimum Driveway Spacing (feet)
a b c d
Two Lane Road 50 50 100 50
Multi-Lane Road 50 50 150 50
a. Spacing Requirements for Adjacent Driveways (a)
Table 4 indicates the desirable access spacing as a function of road type for adjacent
driveways. These distances are based on average vehicle acceleration and deceleration
considered adequate to maintain good traffic operations. Driveway spacing is measured from
edge of driveway to edge of driveway.
b. Spacing Requirements from Driveways on Opposite Side of Road (b) and (d)
To minimize turning conflicts, driveways should be either aligned with those directly across
the road, or offset a sufficient distance from those across the road to achieve the minimum
spacing standards listed in Table 4. Driveway spacing is measured from centerline to
centerline.
c. Spacing Requirement from a Public Road Intersection (c)
In accordance with AASHTO guidelines, driveways shall not be situated within the
functional boundary of intersections. This boundary includes the longitudinal limits of all
full width auxiliary lanes. An access point may be allowed within the above boundary only if
the entire property frontage is located in this boundary.
28
A driveway shall not be constructed along acceleration or deceleration lanes and tapers,
unless no other reasonable access point is available.
Spacing between a road intersection and an access connection shall be sufficient to avoid
creating conflicts between driveway traffic movements and road movements at the
intersection. Table 4 provides the minimum corner separation dimensions that are measured
from the edge of the proposed driveway to the near ROW Line of the intersecting road.
3. Sight Distance Requirements
Acceptance of site access onto an existing public road is subject to the field review and
recommendations of the County Engineer. Considerations include, but are not limited to vehicle
speed, sight distance, and topography. An area of clear vision, free from obstructions and
encroachments, shall be provided. Fences, trees, shrubs, poles, signs, boulders, mailboxes, and
other obstacles shall be removed or modified in this area to afford an unobstructed view in both
directions of the approaching traffic.
A clear-vision area, as shown in Figure 1 and Table 2, shall be provided at all residential
driveways entering onto a road under the jurisdiction of the OCRC. The County Engineer may
request a sight distance diagram to verify safe sight distance for any proposed driveway.
4. Driveway Geometrics
A residential driveway approach shall conform to Detail PA-8.
a. Width
A residential driveway shall have a minimum width of ten (10) feet and maximum width of
thirty-two (32) feet within the road right-of-way.
b. Radii
A driveway may have a radius on both sides of the driveway. Each radius is included in the
maximum driveway width measurement of thirty-two (32) feet.
c. Flare
A driveway may have a flare on both sides of the driveway. Each flare is included in the
maximum driveway width measurement of thirty-two (32) feet.
d. Joint Driveways
When property owners of adjoining properties agree, a joint driveway may be constructed.
The driveway shall meet the same requirements regarding residential driveways.
5. Driveway Construction Standards
If the adjacent roadway has a bituminous valley curb or concrete curb and gutter, the residential
driveway approach shall be hard surfaced with either HMA or concrete materials. A gravel
surface will not be permitted. (See Detail PA-8).
29
If the adjacent roadway does NOT have a bituminous valley curb or concrete curb and gutter, the
residential driveway approach can be hard surfaced with HMA only or have a gravel surface. A
concrete surface will not be permitted within ten (10) feet of the road pavement edge nor ten (10) feet from the shoulder point of a gravel road. (See Detail PA-8).
Recommended Minimum Residential Driveway Construction
a. Subbase - MDOT Granular Material Class II, 12 inches minimum
b. Aggregate Base - MDOT Dense-Graded Aggregate 22A, 6 inches minimum
c. HMA Surface - MDOT HMA 36A, 3 inches (2 lifts) minimum
d. Concrete Surface - Minimum 5 inches*Concrete is not permitted on un-curbed roads within ten feet of the road
pavement edge nor within ten (10) feet of the shoulder point of a gravel road.
D. Field Driveway Requirements
A driveway serving a cultivated field, timberland, or undeveloped land not utilized for industrial,
commercial, or residential uses, shall be considered a field driveway.
An application for a field driveway permit shall be submitted in a manner prescribed in these Procedures
and Regulations.
1. Driveway Location
Low use driveways designed to access cultivated or undeveloped land, are allowed every 500 feet
of frontage or portion thereof.
A field driveway shall not be permitted within a residential development, plat, or subdivision.
2. Sight Distance Requirements
A clear-vision area, as shown in Figure 1 and Table 2, shall be provided at all field driveways
entering onto a road under the jurisdiction of the OCRC. The County Engineer may request a
sight distance diagram to verify safe sight distance for any proposed driveway.
3. Driveway Construction Standards
Grass, gravel, or HMA driveways may be accepted. A concrete driveway shall not be permitted.
Where soil erosion is a perceived problem or becomes a problem, hard-surfaced HMA driveway
shall be required.
E. Temporary Driveway Requirements
A temporary driveway may be allowed by the County Engineer for a maximum 12-month period if it is to
service a site for a specific function or project.
An application for a temporary driveway permit shall be submitted in a manner prescribed in these
Procedures and Regulations.
30
1. Driveway Location
The driveway location shall conform to Commercial Driveway standards unless otherwise
approved by the County Engineer.
2. Sight Distance Requirements
A clear-vision area, as shown in Figure 1 and Table 2, shall be provided at all temporary
driveways entering onto a road under the jurisdiction of the OCRC. The County Engineer may
request a sight distance diagram to verify safe sight distance for any proposed driveway.
3. Driveway Construction Standards
The type and thickness of driveway materials will be identified by the County Engineer based on
use of the driveway. Aggregate or HMA driveways will be allowed, depending on use, erosion
potential, maintenance, and other safety factors.
31
VII. UTILITY STANDARDS & REQUIREMENTS
A. General Utility Standards & Requirements
1. General Provision
The primary purpose of all public road ROW is the reasonably safe and convenient operation of
facilities for public transportation. All occupancies shall therefore be designed and constructed so
that roadway operations, facilities, and maintenance shall not be impeded, interrupted or
endangered. In addition, any permitted facility shall be located so as to minimize any
interference to the ROW and ensure that the OCRC shall have unrestricted use of the ROW for
current and future operations.
2. Authorized Applicant
Classification as a Franchise or Public Utility for purposes of using county ROW shall require
membership of MISS-DIG and conformance with one of the following criteria:
a. Franchise Utility
1. Telecommunication Company
The organization shall provide direct service to the general public and the service shall be
in the public’s interest.
The organization shall be recognized by the Michigan Public Service Commission
(MPSC) as a regulated telecommunication company licensed in Michigan to provide
basic local exchange service or a regulated telephone inter-exchange carrier and
competitive access provider operating in Michigan or must be a cable television company
authorized to operate in Michigan.
The organization shall be authorized by the Governing Body where the facility is located
to operate within its jurisdiction.
2. Power or Gas Company
The organization must be a power or gas company within the meaning of MCL §247.171
et seq. and must be authorized to operate in Michigan.
The organization shall provide direct service to the general public, and the service shall
be in the public’s interest.
Gas and petroleum distribution companies must be (a) certified by MPSC as a company
distributing natural gas or as a common purchaser or common carrier, or (b) certified by
the federal government as an interstate pipeline operator.
Electric companies must be recognized by MPSC as an investor-owned or cooperative
electric provider.
32
b. Public Utility
1. Sanitary Sewer
Facilities that are owned and maintained by a Governing Body and provide direct
sanitary sewer service to the general public, and the service shall be in the public’s
interest.
2. Water Main
Facilities that are owned and maintained by a Governing Body and provide direct water
supply service to the general public, and the service shall be in the public’s interest.
3. Utility Location and Alignment
Utility installations shall be located so as to: (l) minimize the need for adjustments to
accommodate future roadway improvements and (2) permit access to service the installations
with minimal interference to roadway traffic.
The alignment of utilities within the public ROW shall be in accordance with the established
corridor plan (See Detail PA-9 and PA-10), and shall be located and aligned to best conform to
the layout of existing facilities. In roads where no pattern has been established, locations shall be
as follows:
a. Sanitary Sewer - shall be located on the west or south side of the road.
• 8 feet from ROW centerline for a gravity sewer main. (On primary or section line roads,
the gravity sewer shall be placed at 11 feet from ROW centerline.)
• 18 feet from ROW centerline for a sanitary sewer force main.
b. Water Main – shall be located on the east or north side of the road.
• 29 feet from ROW centerline. (22 feet from ROW centerline for subdivision streets)
• Stop boxes shall be located at the ROW Line.
c. Gas Main – shall be located on the east or north side of the road.
• Roads with concrete curb or valley curb shall be 26 ½ feet from ROW centerline or as
directed by County Engineer.
• Roads without concrete curb or valley curb shall be 31 ½ feet from ROW centerline or
as directed by County Engineer.
d. Electric
• Buried: - 4 ½ to 7 feet from ROW Line or as directed by County Engineer.
- Buried electric shall be located on the south and west side of road.
• Poles: - 0 to 7 feet from ROW Line or as directed by County Engineer.
- Only one pole line shall be allowed in the ROW on either side of the
road.
- Wood poles shall maintain a minimum clearance of 10 feet from
travelled lane line or back-of-curb as determined by County Engineer.
- Fiberglass poles shall maintain a minimum clearance of 6 feet from
travelled lane line or back-of-curb as determined by County Engineer.
33
- Metal poles shall have a breakaway design in accordance with AASHTO
standards and must be approved by the County Engineer.
- Poles shall not be placed in the road shoulder or bottom of a ditch.
e. Telecommunications
• Buried Cable: - 2 ½ to 4 ½ feet from ROW Line or as directed by County Engineer.
- Buried cable shall be located on the west or south side of road.
• Buried Fiber: - 0 to 2 ½ feet from ROW Line or as directed by County Engineer.
- Buried fiber shall be located on the west or south side of road.
• Poles: - 0 to 7 feet from ROW Line or as directed by County Engineer.
- Only one pole line shall be allowed in the ROW on either side of the
road.
- Wood poles shall maintain a minimum clearance of 10 feet from
travelled lane line or back-of-curb as determined by County Engineer.
- Fiberglass poles shall maintain a minimum clearance of 6 feet from
travelled lane line or back-of-curb as determined by County Engineer.
- Metal poles shall have a breakaway design in accordance with AASHTO
standards and must be approved by the County Engineer.
- Poles shall not be placed in the road shoulder or bottom of a ditch.
f. Aerial Wire and Cables
Vertical clearance of overhead electric and telecommunications lines above the road shall
conform to the minimum distances provided in Table 5.
Table 5. Overhead Utilities Vertical Clearance Utility Type Minimum Vertical Clearance (feet)
Telecommunications 18
Electrical 0 - 750 volts 18
Electrical 71 – 22.000 volts 20
Electrical 22,001 to 50,000 volts 21
The minimum vertical clearance of a utility line crossing the road shall be measured from the
lowest portion of the utility line crossing the highest elevation of the road [i.e. centerline
(crown), high point of super-elevated curve, etc.]. An unloaded aerial utility line with no
wind at 60 degrees shall not be less than the minimum vertical clearances outlined in Table 5.
g. Utility Services and Road Crossings
• All utility road crossings and services shall be placed at right angles (90°) to road
centerline.
34
4. Depth of Utility Cover
Unless shown on approved plans, all new or replacement utilities shall be installed to provide a
minimum depth of cover of four (4) feet below and in reference to the road surface, cross culvert,
and ditch bottom whichever is the lowest. Where approved plans or the minimum depths outlined
in Table 6 require a greater depth of cover, the approved plan depth and/or minimum depths
outlined in Table 6 depth shall govern.
Table 6. Minimum Depth of Utility Cover Utility Type Minimum Depth of Utility Cover
Main Line (inches) Services (inches) *
Sanitary Sewer 60 60
Water Main 60 60
Gas Main 36 24
Electric 36 24 Telecommunications (Fiber, Cable, Phone) 36 24
*Utility services shall be placed at right angles (90°) to road centerline.
Where the roadway is super-elevated, the minimum depth of the cover shall be measured from the
lower side of the road surface.
5. Traffic Control and Public Safety
The Permit Holder and/or Contractor shall provide and maintain all necessary precautions to
prevent injury or damage to persons and property from operations covered by the permit and shall
use traffic control devices in accordance with the current edition of the MMUTCD.
6. Local Governing Body and OCWRC Review and Approval
The Applicant and/or Permit Holder shall contact the local Governing Body in which the utility
construction will occur and the OCWRC to ensure compliance with requirements that may be
applicable.
7. Permit Application
a. An application for utility construction within the public ROW, on forms provided by the
OCRC (See Detail PA-1), shall specify the utility installation requested, including the
location and alignment. Application review will be based on existing and future roadway
operations, facilities, maintenance, and other operational considerations in the public’s
interest.
b. The proposed utility location for all Franchise Utility (Except Telecommunication)
construction applications shall be clearly identified at the project site by staking and flagging,
or other method, so it can be easily located by the County Engineer making a field review.
1. Underground utility facilities shall be staked at a maximum of 200-foot intervals with a
beginning and ending stake. The County Engineer may request additional stakes based
on the topography. Stakes shall be placed at the ROW Line.
35
2. Utility poles and anchors shall be staked individually.
3. Road bores and utilities crossing under the existing road pavement shall be staked on
each side of the road.
Information on stakes shall include the Applicant’s name and proposed utility alignment.
Failure to provide this information will delay the review of the permit application.
c. A permit granting permission to construct, install, place, and maintain a utility that is within
the ROW may be issued by the OCRC after receipt of an approved application.
B. Utility Construction Requirements
An application for a utility permit shall be submitted in a manner prescribed in these Procedures and
Regulations. To aid in submitting this material, a Checklist for Submittal of Permit Application for Utility
Construction in ROW in accordance with Section V of these Procedures and Regulations is required with
all submissions in order to assess if the permit application is administratively complete.
1. Construction Plan Requirements
Applications shall be accompanied by two (2) sets of paper and an electronic PDF file of
construction plans signed by a Professional Engineer or Project Manager.
Public Utility plans and Franchise Utility (Telecommunication Only) plans shall be drawn on 24
inch x 36 inch sheets and to a standard scale of not less than 1 inch = 50 feet horizontal and 1
inch = 5 feet vertical or as approved by the County Engineer.
Franchise Utility (Except Telecommunication) plans shall be drawn on 11 inch x 17 inch
sheets and to a standard scale of not less than 1 inch = 50 feet horizontal and 1 inch = 5 feet
vertical or as approved by the County Engineer.
Plans shall clearly show the following features or as directed by the County Engineer:
a. North directional arrow and scale of plan.
b. Location map and Township information.
c. Existing road pavement, shoulders, ditches, drainage systems, poles, hydrants, utility service
boxes, trees, shrubs, ROW and property lines, driveways, buildings, sidewalks, paths, road
appurtenances, medians (if existing) and dimensions thereof and names of existing roads.
d. All existing and proposed utilities.
e. The location and elevation of the nearest USGS bench mark used in establishing elevations.
f. Offset dimensions.
36
2. Utility Road Crossings
All underground utility crossings of paved roads shall be done by an approved trenchless or
nondestructive method unless so indicated on the Approved Plans or approved in advance by the
County Engineer.
a. Directional Boring. If approved, the following requirements shall be followed:
1. Equipment:
• The equipment shall have a radio location boring head.
• Location equipment shall be used to track bore head location.
• Back reaming shall be done by MDOT Specifications only.
• Compactor back reaming is not allowed.
• Proper drilling lubricant shall be used.
• Only steerable type boring methods are allowed for main line utility road crossings.
2. Operations:
• The path of the proposed bore must be marked in advance of the boring to check for
conflicts with utilities and structures.
• The top bore hole shall be a minimum of 48” below the pavement subgrade, ditch
line, or culvert, whichever is lower in elevation.
• Bore pits shall be a minimum of 10 feet off the edge of the pavement or 10 feet
behind the curb.
• When boring is done near electrical supply cables, proper care shall be taken to
protect the operator, locator, and others from shock hazards.
• When back reaming pilot holes, and dragging product, the use of compaction type
cutter heads is prohibited. The Contractor shall use a cutting head suitable to cutting
a hole large enough to accommodate the product and lubricating fluid. Plain water
will not be used as a lubricating fluid on bores exceeding 2 inches in diameter.
• After boring operations and connections are completed, the Contractor shall restore
the bore pit areas to the same or better condition than the original condition.
• In the event of damage to the pavement or roadside due to drilling operations, the
Contractor shall repair the pavement or roadside in a manner specified by the OCRC
before further boring operations can continue.
b. Boring and Jacking. If approved, the following requirements shall be followed:
If a pipe is to be installed under the roadbed by boring and jacking, the leading edge of the
pipe shall precede the auger by ½ times the diameter of the pipe. If the auger cannot be
operated inside the utility pipe, a casing pipe is required. A casing pipe may also be required
at other times when deemed necessary by the County Engineer. The casing must be bulk-
headed with cementitious material to prevent material infiltration after installation.
All shafts or pits shall be located at least 10 feet off the edge of pavement. If the shaft or pit
must be closer to the road than the above dimensions due to the location of the utility to be
tapped, sheeting or shoring must be used on all sides of the excavation which are closer to the
road than the above requirements. Backfill and compaction methods shall meet OCRC
backfill requirements.
All voids shall be filled by pressure grouting or other OCRC approved method.
37
If any settlement or other change in grade of the roadway, curbs, or ditches occurs, the road
and/or drainage facilities shall be repaired or reconstructed to proper grade as directed by
County Engineer.
c. Open-Cutting. If Open-Cutting is allowed, the following requirements shall be followed:
If a utility crossing cannot be done by an approved trenchless or nondestructive method due
to extenuating circumstances, an Open-Cut crossing may be approved by the County
Engineer. Provisions for handling traffic shall be as directed by the County Engineer, and the
Permit Holder shall bear all the expenses thereof, including but not limited to signing,
pavement markings, and traffic control.
Lane closures, work operations, and related activities will not be authorized on the day
preceding major holiday weekends and during major holiday weekends, including Memorial
Day, Fourth of July, Labor Day, and Thanksgiving Day weekends and the day before
Christmas through the New Year holidays. All equipment and material necessary for
restoration, including but not limited to compaction equipment and granular backfill material,
shall be onsite prior to beginning excavation or pavement removal. Material which cannot be
stored, such as HMA, shall be immediately available. Open-Cuts will not be allowed to
begin if inclement weather is threatening which may impede the Contractor's ability to restore
the travelled way in a timely manner or provide for safe use of the travelled lanes.
No road shall be closed without prior approval of the County Engineer. Approval of Road
Closures requires that detours be installed in accordance with an approved traffic control plan
by the County Engineer. The Permit Holder shall request Road Closures from the County
Engineer in writing, at least two weeks in advance, and include in the written request the
location, length of time the road will be closed, approximate starting and completion dates,
reasons for the request, and a traffic control plan showing the detours and all detour signage.
If a Road Closure is not approved, through-traffic must be maintained at all times. If field
conditions warrant sheeting, the Permit Holder shall provide sheeting of the excavation to
protect the road. Depending on traffic volumes and other conditions, the County Engineer
may require the Permit Holder to provide bypass lanes (either paved or unpaved), may allow
properly controlled one-lane traffic, or may require some combination of the two.
1. Pavement Removal
Any crossing of a paved road by the Open-Cut method shall include the removal of the
full thickness of pavement to a minimum width of at least two (2) feet beyond the limits
of the trench or as determined by County Engineer.
The pavement cut shall be made by sawing prior to excavation unless otherwise indicated
on the approved plans. Cuts in driveways or road approaches may require a resurfacing
of the entire driveway or road approach as determined by the County Engineer.
All saw cuts shall be made in a straight line and shall be parallel to existing transverse
and longitudinal joints unless otherwise approved.
38
If Contractor operations remove or damage 20% or more of the road surface, or if it is
determined that any open-cut will result in substantial surface deterioration or pavement
integrity loss, the entire roadway shall be resurfaced, rehabilitated, or reconstructed as
required by the County Engineer. See Figure 5 for more details.
a:
b:
c:
Figure 5. Typical Open-Cut Restoration Limits
The pavement shall be saw cut and removed
perpendicular to the road lane line or centerline
a minimum of two (2) feet beyond the limits of
trench or as determined by the County
Engineer.
The pavement shall either be milled 1½ inches
deep or saw cut and removed to the road lane
line or centerline as determined by the County
Engineer.
Typical Single Open-Cut
Restoration Limits
Multiple and Longitudinal Open-Cut Restoration Limits
If the distance between two open-cuts is less than 100 feet, then the entire area between the
open-cuts shall be milled 1½ inches deep to the road lane line or centerline as determined by the
County Engineer.
If the total area of each single open-cut restoration limits exceeds 20% of the total area of b x
the entire paved road width, then entire road shall be milled 1½ inches deep from the first open-
cut to the last open-cut as determined by the County Engineer. If less than 20% as calculated
above, but the total area of each single open-cut restoration limits exceeds 20% of the total area
of b x the road lane width, then the entire lane shall be milled 1½ inches deep from the first
open-cut to the last open-cut as determined by the County Engineer.
If the distance for a longitudinal open-cut is greater than 200 feet, then the entire area of paved
road shall be milled 1½ inches deep to lane line, centerline, or full pavement width as
determined by the County Engineer.
39
2. Backfilling and Compaction of Backfill
Backfill materials shall conform to current MDOT specifications.
Compaction shall be accomplished by suitable mechanical compaction equipment and
methods pursuant to current MDOT specifications.
Granular compacted material shall be used within roadbed limits or under concrete or
asphalt sidewalks, driveways, or parking areas unless otherwise shown on approved plans
or approved in writing by the County Engineer.
If the Permit Holder proposes to use excavated material not shown on approved plans, the
OCRC requires that the Permit Holder agree to suitable provisions for material sampling,
testing, storage, and handling prior to the use of such materials. The backfill shall be
placed in layers of not more than twelve (12) inches in thickness.
The Permit Holder shall supply material sampling and testing reports conducted by an
approved independent testing company to assure that compaction requirements are being
accomplished. The Permit Holder shall notify the OCRC of the name, address and phone
number of the testing laboratory 72 hours prior to beginning backfill operations.
The following densities shall be obtained on road restoration by MDOT standard methods
of compaction:
Backfill 95% of Maximum Unit Weight
The minimum frequencies of tests for density control are as follows:
Trench Backfill – 1 test per 12 inch layer of backfill per run of pipe,
between structures. Minimum 1 test per lateral, unless
waived by the County Engineer.
Structure Backfill – 1 test per 12 inch layer of backfill at each structure,
unless waived by the County Engineer.
Field compaction test methods shall be employed which give immediate test results.
Written compaction test results are to be submitted to the County Engineer within one (1)
week of the test date.
All underdrain systems that are disturbed shall be rebuilt in a manner that completely
restores their function.
Any geotextile fabric or geogrid encountered in the excavation must be restored in a
manner that ensures the integrity of the material as it was originally intended. The OCRC
must approve the material and methods of repair prior to installation.
If approved by the County Engineer, flowable fill may be utilized as backfill. All
requirements for flowable fill and related work shall conform to MDOT specifications.
40
3. Utility Structures
The height of the top of any utility structure constructed or reconstructed within the ROW shall
be determined as follows.
a. If the structure falls within a paved road or other paved surface including driveways, side
streets, sidewalks, and non-motorized paths, the cover shall be flush with the finished
pavement elevation on all sides.
b. If the structure falls within the roadbed of a gravel road or the unpaved shoulder of a paved
road, the cover shall be six (6) inches below the finished gravel surface.
c. If the structure falls within a ditch, the cover elevation shall be set at the top the of ditch slope
elevation and the ditch shall be relocated around the structure and away from the road with a
stable earth berm around the structure. Where called for on the approved plans or as directed
by the OCRC, a culvert of adequate length and size shall be installed in order to carry storm
water around the structure.
d. Any structure on the back slope of a ditch shall not protrude more than six (6) inches above
the slope.
e. If a utility cover falls within a travelled lane, turn lane, or taper, and final pavement
restoration will take place more than 30 days after temporary pavement repair, then such
structure covers shall be set flush with the temporary surface or the first course of asphalt.
The structure cover shall be re-adjusted at the time of final surface restoration.
Structures within the ROW shall be able to withstand expected traffic volume and load.
4. Restoration and Inspection
All restoration and construction inspection requirements shall conform to these Procedures and
Regulations.
C. Utility Removal, Relocation, and Adjustments
Utility owners shall be responsible, at no expense to the OCRC, to repair, remove, and/or relocate any
existing facility within the ROW, if such repair, removal or relocation is required by the OCRC for any
purpose including but not limited to road or drainage improvements.
D. Utility Abandonment
Except for asbestos pipe, utility owners may abandon existing underground facilities or structures that do
not pose a hazard or impediment to the use and maintenance of the ROW. Abandonment may require that
the utility owner remove its facility or structure, at the discretion of the OCRC, and restore all areas to
conditions satisfactory to the OCRC. All abandoned pipe shall be pressure grout filled. In any such case,
the utility owner shall maintain ownership and responsibility for the facility or structure, including any
and all costs associated with accommodating future road and drainage improvements.
A utility owner proposing to cease operation of an asbestos pipe system shall remove the abandoned
system from the ROW, and shall properly dispose of the materials pursuant to all applicable regulations.
41
E. Annual Utility Permit Activities
1. Utility companies are allowed to undertake the following activities in OCRC ROW under an
Annual Utility Permit.
a. Maintenance tree trimming, with permission of abutting property owners (no tree removal
without OCRC and adjacent property owner's permission).
b. Repair of existing underground conduit, buried cable, buried wire, and pipe (except under
pavement). In such cases the Contractor shall backfill and restore in accordance with OCRC
specifications.
c. Replacement of defective or degraded buried cable sections within an existing conduit.
d. Installation of plastic pipe inserts or lining through existing mains (gas, water or sewer), in
connection with maintenance and renewal programs not requiring pavement cuts.
e. Installation, removal or replacement of load coil case on existing buried cable or wire,
including loop from main trench, at one location only.
f. Replacement of open wires, single pair rural wire and/or drop wire with multiple line wire or
small cable on same pole line, not extending beyond the present wire.
g. Repair and maintenance of open wire, multiple type wire, drop wire and/or aerial cable.
h. Replacement or addition of up to two (2) poles within or beyond an existing pole line,
provided that poles are not relocated laterally and that no tree work is required because of
increased pole height.
i. Repair and/or replacement of leaking, distressed, or otherwise damaged sections of up to
twenty (20) feet of existing gas main (except under pavement). In such cases the Contractor
shall backfill and restore in accordance with OCRC specifications.
j. Replacement of guys and anchors to poles when at the same location as existing.
k. Installation of aerial drops which do not require a new pole within road ROW outside of the
existing pole line, or installation of aerial drop along with intermediate pole in an existing
pole line to facilitate installing an aerial drop.
l. Inspection and maintenance of systems, valves, and meters and their associated manholes.
m. Installation of a gas service line not more than two (2) inches in diameter to one (1)
residential or commercial customer.
n. Installation of an electric or telecommunication service line to one (1) residential or
commercial customer.
2. Additional Conditions for Annual Utility Permit Activities
a. Emergency repairs may be made provided notification is given to the OCRC as soon as
possible, and no later than the next OCRC business day.
42
b. Immediate notification must be given for emergency operations (due to public safety, health
and welfare concerns) which involve cutting of pavement, and an individual permit shall be
obtained by the Permit Holder as soon as possible.
c. The County Engineer shall be notified of normal repairs in advance, and in writing. The
Permit Holder shall provide the approximate location and date of all work to be performed.
d. Traffic shall be maintained in accordance with the current MMUTCD and OCRC
specifications.
e. Miss Dig shall be notified prior to any work.
f. An Annual Utility Permit shall remain in force until such time as written notice has been
received of its cancellation by either party, subject to the payment of all annual fees and
monthly billings in accordance with the conditions specified upon invoices submitted by
the OCRC.
F. As-Built Plans for Public Utilities
1. After completion of the final inspection of the permitted activity by the County Engineer, a set of
as-built plans shall be furnished showing all changes, additions and deletions to the road and
public utilities constructed within the ROW.
a. All storm sewer and drainage structure information shall include GPS locations and
elevations.
b. Electronic files shall also be furnished in PDF and one of the following: DXF, DWG, or
DGN on an electronic format acceptable to the County Engineer.
43
VIII. SIDEWALK AND PATH STANDARDS & REQUIREMENTS
A. General Sidewalk and Path Standards & Requirements
1. General Provision
The primary purpose of all public road ROW is the reasonably safe and convenient operation of
facilities for public transportation. All permitted facilities in the ROW, including sidewalks and
non-motorized paths, shall therefore be designed and constructed to provide a safe environment
for all users of the road, sidewalk, and non-motorized paths.
2. Local Governing Body and OCWRC Review and Approval
The Applicant and/or Permit Holder shall contact the local Governing Body (in which the
sidewalk or path construction will occur) and the OCWRC to ensure compliance with
requirements that may be applicable.
3. Permit Application
a. An application for sidewalk or non-motorized path construction within the ROW, on forms
provided by the OCRC (See Detail PA-1), shall specify the location and alignment.
Application review will be based on existing and future roadway operations, facilities,
maintenance, drainage, and other operational considerations in the public’s interest.
b. The proposed sidewalk or non-motorized path location shall be clearly identified at the
project site by staking and flagging, or other method, so it can be easily located by the County
Engineer making a field review.
• Sidewalk and paths shall be staked at a maximum of 200-foot intervals with a beginning
and ending stake. The County Engineer may request additional stakes based on the
topography. Stakes shall be placed at the ROW Line.
Information on stakes shall include the Applicant’s name and proposed sidewalk or path
alignment or offset. Failure to provide this information will delay the review of the permit
application.
c. A permit granting permission to construct, install, place, and maintain a sidewalk or path that
is within the ROW may be issued by the OCRC after receipt of an approved application.
B. Sidewalk and Non-Motorized Path Construction Requirements
An application for a sidewalk or a non-motorized path permit shall be submitted in a manner prescribed in
these Procedures and Regulations. To aid in submitting this material, a Checklist for Submittal of Permit
Application for Sidewalk and Path Construction in ROW in accordance with Section V of these
Procedures and Regulations is required with all submissions in order to assess if the permit application is
administratively complete.
44
1. Construction Plan Requirements
Applications shall be accompanied by two (2) sets of paper and an electronic PDF file of
construction plans signed and sealed by a Professional Engineer.
The plans shall be drawn on 24 inch x 36 inch sheets and to a standard scale of not less than 1
inch = 50 feet horizontal and 1 inch = 5 feet vertical.
Plans shall clearly show the following features:
a. North directional arrow and scale of plan.
b. Location map and Township information.
c. Existing road pavement, shoulders, ditches, drainage systems, poles, hydrants, utility service
boxes, trees, shrubs, ROW and property lines, driveways, buildings, sidewalks, paths, road
appurtenances, medians (if existing) and dimensions thereof and names of existing roads.
d. All existing and proposed sidewalks and non-motorized paths.
e. Offset of all proposed culverts, and station/offset of all proposed drainage structures.
f. The plans shall include information on how the affected storm water runoff from the
proposed sidewalk or non-motorized path will be accommodated. The County Engineer may
require a positive outlet for the drainage system.
g. The plans shall include existing contour intervals no more than every two (2) foot change in
elevation. The location and elevation of the nearest USGS bench mark used in establishing
elevations.
h. Cross-sections with existing topographical data from the centerline of the roadway to a
distance of 10 feet beyond the ROW Line with the proposed sidewalk or non-motorized path
shown, shall be submitted for every 100 feet of centerline stationing. These cross-sections
will be utilized to verify drainage patterns, impacts to the ROW, and proposed elevations of
the sidewalk or non-motorized path. Cross-sections shall be drawn to a standard scale of not
less than 1 inch = 10 feet horizontal and 1 inch = 1 foot vertical.
2. Width, Location, and Grade
Sidewalk and non-motorized path width, location, and grading shall conform to the limits
provided in Table 7 (See Detail PA-11).
Table 7. Sidewalk & Path Width, Location, and Grade
Width Location Grade
from edge of road from ROW Line Transverse Longitudinal
Sidewalk 5 feet 10 feet min. 1 foot 2% 5% max.
Path 8 feet min. 10 feet min. 1 foot 2% 5% max.
45
a. Additional ROW or easements may be required by the County Engineer to accommodate
sidewalk or path width, drainage, and other ROW needs.
b. The sidewalk or non-motorized path transverse grade of 2% (1/4” per foot) shall drain toward
the road if the road has a roadside drainage system that can accommodate the additional
storm water runoff. Otherwise, the sidewalk or non-motorized path shall drain toward the
ROW Line (private property) with accommodations for the sidewalk and path drainage.
c. The maximum allowable longitudinal grade for sidewalk and non-motorized paths shall be
5%. This grade shall not be exceeded unless the road grade is of a steeper grade, in which
case the longitudinal sidewalk grade shall not exceed the road grade.
d. If possible, the sidewalk or non-motorized path should match existing driveway elevations.
The sidewalk or path elevations shall not exceed an elevation of higher than six (6) inches
above the centerline of the roadway, unless approved by the County Engineer.
3. Drainage
The sidewalk or non-motorized path shall be constructed so that the existing roadside drainage
system and patterns are not adversely affected. The drainage and the stability of the road
subgrade shall not be altered by sidewalk or path construction.
No additional storm water runoff shall be directed toward a roadside drainage system, unless it
can be demonstrated that the drainage system can accommodate the storm water run-off from the
sidewalk or non-motorized path. Drainage calculations may be requested by the County Engineer
to verify appropriate capacity of the roadside drainage system.
Storm water runoff from the sidewalk or non-motorized path shall be accommodated.
Storm sewer, drainage structures, and culverts placed as part of the permitted sidewalk or non-
motorized path construction shall become the local Governing Body’s responsibility to maintain
and replace as part of the permitted sidewalk or non-motorized facility.
4. Sidewalk and Path Construction Standards
The following sidewalk and non-motorized path standards are established as the minimum
necessary to meet the concerns of the OCRC. Meeting these requirements does not in any way
substitute for the necessity of obtaining any required permit from, and meeting all requirements
of, the local Governing Body who will own and maintain these facilities.
a. Sidewalks
Sidewalk construction shall be in accordance with MDOT Specification 803 and the
specifications of the local Governing Body.
Sidewalks should meet the following minimum base course requirements as listed below:
Granular Base Course - MDOT Spec. 301
Material - Class II
Thickness - 6” compacted in place
46
Sidewalks shall be hard surfaced with concrete with the following materials as listed below:
Concrete Surface - MDOT Spec. 802
Material - MDOT Grade S2
Thickness - 4” minimum
- 6” through residential driveways
- 8” through commercial driveways
b. Non-Motorized Paths
Non-motorized path construction shall be in accordance with MDOT Specification 806 and
the specifications of the local Governing Body.
Paths should meet the following minimum subbase and base course requirements as listed
below:
Granular Subbase (over cohesive soils) - MDOT Spec. 301
Material - Class II
Thickness - 6” compacted in place
Aggregate Base Course - MDOT Spec. 302
Material - 22A or 21AA
Thickness - 6” compacted in place
Paths shall be hard surfaced with HMA with the following materials as listed below:
HMA Surface - MDOT Spec. 501
Material - HMA Mixture LVSP or 36A
Thickness - 2 1/2” (275#/syd Effective Yield)
Asphalt Cement - Performance Grade 58-28
c. ADA Ramps
Sidewalks and non-motorized paths shall provide ramps in accordance with the American
with Disabilities Act (ADA) of 1990 and the Rehabilitation Act of 1973 (Section 503) as
amended. Ramps shall conform to the current MDOT Specifications, MDOT Standard
Plan/Special Detail R-28 for Sidewalk Ramps, and shall be required for all sidewalks and
paths crossing:
1. Commercial Driveways as required by the County Engineer
2. Private Roadways
3. Public Roadways
47
C. As-Built Plans
1. After completion of the final inspection of the permitted activity by the County Engineer, a set of
as-built plans shall be furnished showing the pedestrian facility and all changes, additions and
deletions to the road and public utilities constructed within the ROW.
a. All storm sewer and drainage structure information shall include GPS locations and
elevations.
b. Electronic files shall also be furnished in PDF and one of the following: DXF, DWG, or
DGN on an electronic format acceptable to the County Engineer.
48
IX. DITCH ENCLOSURE AND DRAINAGE STANDARDS & REQUIREMENTS
A. General Requirements
1. General Provision
Roadside ditches, swales, storm sewer, culverts, or other similar drainage features are
constructed/installed to convey storm water from the road surface and roadbed to an outlet such
as a pond, county drain, creek, infiltration area, or other waterway. These roadside drainage
systems are typically located in the ROW and maintained by the OCRC, or in some instances the
OCWRC. Importantly, the primary role of roadside drainage is to drain the road, not adjacent
private property, unless the roadside drainage system has been established as a County Drain.
All drainage facilities shall be designed and constructed so that roadway operations, facilities, and
maintenance shall not be impeded, interrupted or endangered. In addition, any permitted drainage
facility shall be located so as to minimize any interference to the ROW and ensure that the OCRC
shall have unrestricted use of the ROW for current and future operations.
Storm sewer, drainage structures, and culverts placed as part of the permitted drainage work shall
become the Permit Holder’s responsibility to maintain as part of the permitted drainage work.
2. Drainage Facility Location and Alignment
The alignment of drainage facilities including but not limited to culverts, ditches, and storm sewer
within the public ROW shall be determined by the County Engineer (See Detail PA-12). Storm
Sewer shall be located and aligned to best conform to the layout of existing facilities.
3. Depth of Storm Sewer and Culverts
Unless shown on approved plans or as approved by the County Engineer, all storm sewer and
culverts shall be installed to provide a minimum depth of cover of three (3) feet below the top of
the centerline of road elevation.
4. Traffic Control and Public Safety
The Permit Holder and/or Contractor shall provide and maintain all necessary precautions to
prevent injury or damage to persons and property from operations covered by the permit, and
shall use warning devices in accordance with the current edition of the MMUTCD.
5. OCWRC Review and Approval
The Applicant and/or Permit Holder shall contact the local Governing Body in which the drainage
construction will occur and the OCWRC to ensure compliance with requirements that may be
applicable.
6. Permit Application
a. An application for a ditch enclosure or drainage construction within the public ROW, on
forms provided by the OCRC (See Detail PA-1), shall specify the drainage work requested,
including the location and alignment. Application review will be based on existing and future
roadway operations, facilities, maintenance, and other operational considerations.
49
b. The proposed drainage facility location shall be clearly identified at the project site by staking
and flagging, or other method, so it can be easily located by the County Engineer making a
field review.
Ditch enclosures and drainage facilities shall be staked at a maximum of 200 foot intervals
with a beginning and ending stake. The County Engineer may request additional stakes based
on the topography. Stakes shall be placed at the ROW Line.
Information on stakes shall include the Applicant’s name and proposed utility alignment.
Failure to provide this information will delay the review of the permit application.
c. A permit granting permission to construct, install, place, and maintain a drainage facility that
is within the ROW may be issued by the OCRC after receipt of an approved application.
B. Ditch Enclosure and Drainage Facility Construction Requirements
An application for a ditch enclosure or drainage facility permit shall be submitted in a manner prescribed
in these Procedures and Regulations.
1. Construction Plan Requirements
Applications shall be accompanied by two (2) sets of paper and an electronic PDF file of
construction plans signed by a Professional Engineer unless waived by the County Engineer.
The plans shall be drawn on 24 inch x 36 inch sheets and to a standard scale of not less than 1
inch = 50 feet horizontal and 1 inch = 5 feet vertical or as approved by the County Engineer.
Plans shall clearly show the following features or as directed by the County Engineer:
a. North directional arrow, scale of plan, location map, and Township information.
b. Existing road pavement, shoulders, ditches, existing and proposed drainage systems, poles,
hydrants, utility service boxes, trees, shrubs, ROW and property lines, driveways, buildings,
sidewalks, paths, road appurtenances, and dimensions thereof, etc.
c. The location and elevation of the nearest USGS bench mark used in establishing elevations.
C. As-Built Plans
1. After completion of the final inspection of the permitted activity by the County Engineer, a set of
as-built plans shall be furnished showing the constructed drainage facility within the ROW.
a. All storm sewer and drainage structure information shall include GPS locations and
elevations.
b. Electronic files shall also be furnished in PDF and one of the following: DXF, DWG, or
DGN on an electronic format acceptable to the County Engineer.
50
X. RESTORATION AND INSPECTION STANDARDS & REQUIREMENTS
A. General Requirements
The Permit Holder shall restore, at its expense, all public and private property damaged as a result of acts
or omissions by the Permit Holder or its Contractor, to a condition similar and equal to that existing
before the damage was done. If the Permit Holder neglects to make restoration, the OCRC may, after 48
hours written notice to the Permit Holder, proceed to make the restoration. The cost of restoration shall
be paid by the Permit Holder.
1. Pavement Restoration
Before disturbing or removing any pavement, the Applicant or Permit Holder shall survey or
measure existing roadway conditions in sufficient detail to allow description of any road
restoration which may become necessary due to the project. This shall include depiction of lane
widths, shoulder widths, cross-slope, super-elevations, vertical or horizontal curves, ditch cross-
sections and grades, pavement section thicknesses, and subgrade type. Where vertical curves or
horizontal curves with super-elevation exist, cross-sections shall be provided at maximum
intervals of 50 feet. Should the Applicant or Permit Holder fail to provide this information on
approved plans or other documentation prior to disruption or removal, the current design
guidelines shall apply to any restoration.
If more than 20% of the width of a lane of a HMA surfaced road (or section thereof) is removed
or damaged by the Permit Holder’s operations, the OCRC will require a full overlay replacement
of the roadway width (or section thereof). The full overlay shall consist of a minimum HMA
thickness of two (2) inches of MDOT LVSP or as determined by the County Engineer, placed
over the entire road (or section thereof), after replacing or removing the damaged pavement in
accordance with these Procedures and Regulations. An appropriate OCRC approved bond coat
shall be applied prior to the placement of the HMA overlay. The County Engineer may require a
thicker HMA overlay in high traffic areas.
The County Engineer shall determine the final area of the pavement to be replaced and/or
overlaid. The final repaving shall be done by a Contractor in accordance with the MDOT
Standards. Before pavement replacement is started, the Permit Holder shall submit in writing to
the OCRC the name of the proposed Contractor and a list of equipment and source of materials
that will be used during pavement replacement. The OCRC must also approve in writing the
Contractor and the equipment and materials. The Contractor must notify the OCRC with at least
48 hours (two (2) business days) before pavement replacement is started. The OCRC reserves the
right, at its sole discretion, and at the Permit Holder’s cost, to test and inspect at the point of
origin and/or at the time of placement, all materials to be used. Permit Holder shall restore to the
satisfaction of the OCRC all pavements in the ROW damaged due to the Permit Holder’s
operations, including without limitation all travelled lanes including turn lanes, passing lanes,
tapers, paved shoulders, driveways, street approaches, and any other part of the ROW that may be
damaged directly or indirectly by the work operations or related activities of Permit Holder and
those working directly or indirectly for the Permit Holder, including damage due to material
handling, trucking, equipment, or temporary roads. Materials that do not meet design
specification, shall not be placed and shall be removed from the worksite. Materials placed and
workmanship found by the OCRC, at its sole discretion, to be out of specification shall be
removed and replaced at the OCRC’s direction and at the Permit Holder’s cost.
51
The final pavement replacement shall be structurally equivalent to, and of the same type as, the
pavement being replaced, and in accordance with the following minimum standards or as directed
by the County Engineer:
Subbase - MDOT Spec. 301
Material - Granular Material Class II
Gradation - MDOT Spec. Table 902-3
Thickness - 18 inches
Aggregate Base - MDOT Spec. 302
Material - Dense-Graded Aggregate 22A
• 21AA shall be utilized from October 1 to April 30
-In accordance with MDOT/MDEQ Specifications
Gradation - MDOT Spec. 902-1 Minimum 25% crushed
Thickness - 8 inches
HMA Surface - MDOT Spec. 501
Material - HMA Mixture *LVSP Base and Leveling
- HMA Mixture *LVSP Wearing
Thickness - *3 ¼” (360#/syd) Minimum
Bond Coat - Required between all lifts
*The County Engineer may require a different HMA mixture and thickness.
Final Pavement restoration shall include wedging as necessary with suitable asphalt to establish
or reasonably restore pavement cross-slope, super-elevation, or transitions, including adjustments
to driveways, side streets, and paved shoulders. The Permit Holder is responsible for adjustment
to shoulders, including the adding of material to achieve a smooth cross-slope. Special care shall
be taken to maintain positive drainage at all locations including driveway aprons.
Curb lines shall be milled or otherwise adjusted to accept the new roadway surface. Butt joints
shall be provided at intersections, driveways, at the end of an overlay, and other locations. Said
joints shall be clean, straight, and perpendicular or parallel to the roadway.
The Permit Holder shall repair any damaged pavement, including subgrade repair, prior to
placement of the wearing course of asphalt surfacing.
2. Gravel Road Restoration
All excavations within the limits of the roadbed shall be backfilled with material as shown on
approved plans. Alternate backfill materials must be approved in writing by the OCRC, at its sole
discretion, and are subject to these Procedures and Regulations.
Immediately after the trench is backfilled and compacted, the affected portion of the road and
ditches shall be rough graded to the appropriate gravel road cross-section indicated in these
specifications, and the affected portion of the road surface shall be stabilized with a minimum of
eight (8) inches of compacted processed road gravel (MDOT 22A or 21AA aggregate base).
52
If road surface areas outside of the excavation are used for storage of construction materials or
excavated materials, or are otherwise damaged or contaminated due to construction operations,
the contaminated material shall be removed and replaced with a minimum of two (2) inches of
compacted MDOT 23A road gravel immediately following construction.
All excess construction materials, excavated materials, and any contaminated materials shall be
removed prior to the placement of gravel, unless otherwise approved by the OCRC. The road
surface shall be maintained in good, smooth, dust free condition at all times, and MDOT 23A
road gravel shall be added if settlements occur. Before requesting final inspection, the Permit
Holder shall place over the entire road surface within the affected portion of the roadway 2 inches
of compacted MDOT 23A road gravel, suitably stabilized with liquid calcium chloride or other
material as approved by the County Engineer.
3. Road Restoration Compaction and Testing Requirements
The Permit Holder shall supply materials sampling and testing reports conducted by an
independent approved testing company to assure the OCRC that compaction requirements are
being accomplished. The Permit Holder shall notify the Road Commission of the name, address
and phone number of the testing laboratory 72 hours prior to beginning road restoration
operations.
The following densities shall be obtained on road restoration by MDOT standard methods of
compaction:
Embankment 95% of Maximum Unit Weight
Subbase 95% of Maximum Unit Weight
Aggregate Base 98% of Maximum Unit Weight
Gravel Road Surface 98% of Maximum Unit Weight
HMA 92%-96% of Theoretical Maximum Density
The minimum frequencies of tests for density control are as follows:
Subbase – 1 test per 400 linear feet of roadway.
Aggregate Base – 1 test per 400 linear feet of roadway.
Gravel Road Surface – 1 test per 400 linear feet of roadway.
HMA – 1 test per 400 linear foot of HMA course.
Field compaction test methods shall be employed which give immediate test results. Written
compaction test results are to be submitted to the County Engineer within one week of the test
date.
4. Shoulder Restoration
Shoulder restoration shall include MDOT 23A aggregate shoulder gravel to be placed at a
minimum depth of six (6) inches. Shoulder width shall be consistent with the current road with a
minimum width of four (4) feet or as determined by the County Engineer. The reuse of original
shoulder gravel will not be permitted.
If the shoulders were grass covered, the grass shall be removed and the shoulder shall be restored
and brought flush with the road surface with 23A gravel or as directed by the County Engineer.
Paved or gravel shoulders shall be restored to the same type.
53
5. Roadside Restoration
All areas within the road ROW beyond the shoulders, curbs, or edge of gravel of the road, which
are disturbed as the result of the Permit Holder's activities, shall be restored as soon as possible
during the first growing season. Temporary measures may be required prior to the growing
season where necessary to minimize erosion or hazards. Restoration shall not be delayed until
project completion. Failure to comply with this specification shall be cause for the OCRC to stop
the remaining construction work until the required restoration is completed. The ground cover
specified on approved plans shall be maintained until growth is established.
Sod may be required by the OCRC in areas where topsoil, seeding, and mulching cannot (or has
not) provided the effective ground cover required because of steep slopes or grades, velocity or
volume of water, or other conditions. Sod may be required in areas of established, maintained
lawns. All sod shall be placed on three (3) inches of topsoil following preparation of the surface
per the MDOT specifications. The Permit Holder is responsible for the establishment and growth
of vegetation. The permit bond will not be released until the OCRC is satisfied that vegetation
has been re-established.
Areas that are not to be sodded shall be topsoiled, seeded, fertilized, and mulched. The seed shall
be MDOT roadside seed mixture, unless otherwise specified on approved plans. Topsoil, seed,
fertilizer and mulch shall be applied pursuant to MDOT specifications.
6. Drainage Restoration
All road drainage shall be restored as soon as possible following construction. Ditches, ditch
slopes, and other areas within the ROW shall be restored to meet then current standards, unless
otherwise shown on approved plans.
All culverts and ditch enclosures removed in good condition, as determined by OCRC, shall be
re-placed in proper position and elevation. All culverts and ditch enclosures or sections thereof
which are not in good condition after removal shall be replaced with pipe meeting the current
OCRC standards. Culverts and other drainage facilities which are damaged but not removed
during the Permit Holder's operations must be fully repaired to the satisfaction of the OCRC or be
replaced in accordance with current OCRC standards. Grading or ditching may be required near
the inlet or outlet in order to re-establish drainage beyond that shown on approved plans.
The Permit Holder shall restore or re-establish any drainage patterns or systems disturbed by the
Permit Holder's activities, including cleaning of drainage structures and culverts. The Permit
Holder shall perform any survey necessary to establish elevations of culverts, ditches, inlets,
outlets, or any other structure required in order to restore function to the drainage system. The
Permit Holder shall re-ditch or establish new ditch elevations based on changes to culverts or
other structures in order to ensure that a stable, maintainable ditch is established. If the velocity of
water is great enough that erosion of the ditch bottom may occur, rip-rap or other structural
elements may be required in order to stabilize the roadside ditches or their outlets. The OCRC
will notify the Permit Holder if additional soil erosion and sedimentation control measures are
required.
Road drainage shall not be diverted onto private property without the dedication of a drainage
easement by the affected property owner(s).
54
If culverts or other drainage structures that are not shown on approved plans are encountered
during the course of the work, the Permit Holder shall notify the County Engineer and replace
and/or restore any such structures.
7. Construction Inspection
The Permit Holder shall retain an independent Construction Inspector as approved by the County
Engineer to verify that all road and drainage construction, restoration, and improvements are
constructed in accordance with the approved construction plans and these Procedures and
Regulations.
The Construction Inspector shall be on site during all construction operations that impact the
existing road or drainage system to inspect the Contractor’s work. An Inspector’s Daily Report
(IDR) (See Detail PA-13) will be completed by the Construction Inspector for each day of
inspection and submitted to the County Engineer within one week of the inspection date. The
IDR should include such items as:
a. Weather for the day
b. Contractor and sub-contractor on site
c. Type of work performed by Contractor
d. Location of work (from Station to Station)
e. Materials utilized and tested
f. Deviations from plan
g. Other pertinent notes or sketches
h. List of equipment
Periodic inspections from the County Engineer do not alleviate the Permit Holder of the
responsibility for all stages of construction of the development.
55
XI. TRANSPORTATION PERMIT REQUIREMENTS
A. General Provisions
1. Any generally accepted permit application requirements, guidelines, rules or standards, not
specifically provided for is hereby incorporated by this reference.
2. An application/permit issued under these regulations shall be in writing on a form issued by the
OCRC and properly executed by the owner of the vehicle for which the permit is being requested.
3. A permit will be issued to the company or individual actually transporting a vehicle and/or load
which exceeds the legal size and axle weight limitations provided the vehicle and/or load cannot;
be readily dismantled, reduced, or otherwise rearranged to come within the legal limits, as
provided for in Wheel and Axle Loads (Act No. 300 of 1949, as amended MCL §257.722).
4. An additional cash deposit fee may be required, prior to issuance of a permit to move a house,
building, or oversized load, to cover the expenses of the OCRC, including supervising the
building move.
5. During times of restricted load-limit/seasonal weight restriction, as set forth in Act No.300 of
1949, as amended, (MCL §257.722 and commonly referred to as Seasonal Road Restrictions),
and at any other time when conditions are unfavorable, a permit will not be issued for overweight
vehicles and/or overweight loads. A permit issued for overweight vehicles and/or overweight
loads on a seasonal basis will not be valid during periods of reduced loading restrictions.
6. A permit will not supersede posted load limitations on any bridge, culvert, or road.
7. The OCRC reserves the right to refuse to issue a transportation permit when the condition of the
road is such that above-legal load limitations would cause harm or injury to the bridge, culvert, or
public road.
8. A permit is void on Sunday and federally recognized holidays, or any time when weather, road or
traffic conditions create a potentially hazardous condition, unless specifically approved by the
OCRC.
9. A copy of the permit shall be in the transporting vehicle.
10. A vehicle shall be loaded in such a manner as to minimize the excess over-statutory size or axle
weight limitations. A load shall be arranged to affect the least dimensions for height, length, or
width.
B. Annual Transportation Permit
The OCRC Annual Transportation Permit application form shall be submitted for approval prior to
issuance of a permit. This permit applies to moves within the following parameters:
Width: 8 feet to 12-1/2 feet
Length: Length of any combination less than 75 feet
Height: Maximum 13-1/2 feet
56
Overweight: Up to 25% over legal axle load and not to exceed on any wheel 700 pounds per
inch width of tire
1. All permits will expire on December 31 of the year issued.
2. The permit applies to vehicles such as mobile cranes, lowboys, over length or over width trailers,
self-propelled construction machinery and pole trailers. The permit does not apply to
modular/manufactured homes or building moves.
3. A separate transportation permit will be issued for each power unit (truck, tractor, or self-
propelled equipment).
C. Annual Mobile Home Transportation Permit
The OCRC Annual Mobile Home Transportation Permit application shall be submitted for approval prior
to issuance of the permit. This permit applies to moves within the following parameters:
Width: Up to 14 feet maximum
Length: Up to 95 feet maximum
Height: Up to 14 feet maximum
1. All permits will expire on December 31 of the year issued.
2. Permit Holder is responsible for checking route for overhead clearance and any obstructions
along the route of movement.
3. Permit Holder is responsible for any damage to property or utilities along the route of movement.
4. Permit Holder will be responsible for any expenses associated with the permit approval.
5. Restriction of movement is as described on the reverse side of the permit.
6. A separate permit is required for each power unit.
7. The driver of the power unit shall have a valid copy of the permit in their possession while
operating on any OCRC road and shall present it upon request to any law enforcement officer or
agent of the OCRC.
8. The Permit Holder shall comply with all requirements of Mobile Home Transport Requirements
(Act No. 300 of 1949 MCL §257.719a) and Special Permits for Non-Conforming Vehicles (Act
No. 300 of 1949 MCL §257.725) of the Michigan Vehicle Code.
D. Single Move Transportation Permit
The OCRC Single Move Transportation Permit application form shall be submitted for approval prior to
issuance of the permit.
A Single Move Transportation Permit may be issued to move a vehicle and/or load exceeding the legal
allowable size and axle weight limitations on a per-move basis. Prior to issuance of such a permit, the
proposed route will be checked for interference with overhead facilities and other obstacles by the
Applicant with the results of the investigation submitted to the OCRC. In addition, before the permit is
57
issued, approval shall be obtained by the Applicant from all public agencies and private entities whose
facilities may be affected by the proposed move.
This permit applies to moves within the following parameters:
Width: 8 feet to 16 feet
Length: Less than 95 feet
Height: Over 14 feet
Overweight: Over legal axle loading
1. A single move permit may be issued to allow an excess-width vehicle, between 8 feet and less
than 16 feet, to travel on public roads with the route approved by an authorized representative of
the OCRC.
2. A permit may be issued to move a vehicle of excessive length, up to 95 feet, as long as the
movement of such a vehicle will not impede the safety of the public and will not cause
unreasonable interference with normal traffic on public roads.
3. Over legal axle loading.
4. The Permit Holder will be responsible for any costs associated with the permit approval.
5. The permit shall designate the route to be taken and will remain in effect only for as long as is
designated on the permit, as long as is necessary to complete the designated movement, or until
the permit is revoked.
E. Super Move Transportation Permit
The OCRC Super Move Transportation Permit application form shall be submitted for approval prior to
issuance of the permit.
A super move transportation permit may be issued to move a vehicle and/or load exceeding the single
move permit size parameters on a per-move basis. Prior to issuance of such a permit, the proposed route
will be checked for interference with overhead facilities and other obstacles by the Applicant with the
results of the investigation submitted to the OCRC. In addition, before the permit is issued, approval
shall be obtained by the Applicant from all public agencies and private entities whose facilities may be
affected by the proposed move.
This permit applies to moves within the following parameters:
Width: Over 16 feet
Length: Over 95 feet
Height: Over 14 feet
1. A permit may be issued to move machinery, equipment, and/or loads in excess of 16 feet in width
at the OCRC's sole discretion.
2. A permit may be issued to move a vehicle of excessive length, over 95 feet, as long as the
movement of such a vehicle will not impede the safety of the traveling public and will not cause
unreasonable interference with normal traffic over public roads.
58
3. Prior to issuance of such a permit, the proposed route shall be checked for interference with
overhead facilities and other obstacles, and approval shall be obtained from all public agencies
and private entities whose facilities may be affected by the proposed move.
4. The Permit Holder will be responsible for any expenses associated with the Permit approval.
5. A vehicle transporting a load exceeding 14-1/2 feet in width or 70 feet in overall length, except
utility poles, shall be protected by one or more pilot cars equipped with a roof-mounted amber
revolving light. The Permit Holder is responsible for OCRC expenses including supervision of
the building move. A local law enforcement escort is required for house moves.
6. The Permit Holder may be required to submit a letter of credit sufficient in amount to reimburse
the OCRC for any costs incurred or occasioned by the move and to guarantee the repair of any
damage to the road or road appurtenances and the complete and satisfactory restoration thereof.
7. No such movement will be allowed between sundown and sunrise, or on Sunday or federally
recognized holidays, or any time when weather, road or traffic conditions create a potentially
hazardous condition, unless specifically approved by the OCRC.
8. The permit shall designate the route to be taken and will remain in effect only for as long as is
designated on the permit, as long as is necessary to complete the designated movement, or until
the permit is revoked.
9. A permit will be issued as follows:
a. An application for each permit shall be submitted for approval at least five (5) days in
advance of the anticipated moving day, (excluding Saturday, Sunday and federally
recognized holidays).
10. All applicable state standards for signing and flags on oversized loads shall be complied with.
F. Single Move Mobile Home Transportation Permit
The OCRC Single Move Mobile Home Transportation Permit application form shall be submitted for
approval prior to issuance of the permit.
A permit may be issued to move mobile and/or modular homes exceeding the allowable width, length or
height limitations on a per-move basis. Single move for mobile and modular homes within the following
parameters:
Width: Over 14 feet but less than 16 feet
Length: Over 95 feet
Height: Over 14 feet
1. Permit Holder is responsible for checking proposed route for overhead obstructions and any other
obstacles and is responsible for damage caused to any property or utility by movement on the
proposed route.
2. A permit will be issued to move a mobile and/or modular home as long as the movement will not
jeopardize the safety of the traveling public and will not cause unreasonable interference with
normal traffic over public roads.
59
3. The Permit Holder will be responsible for any expenses associated with permit approval.
4. The permit shall designate the route to be taken and will remain in effect only for as long as is
designated on the permit, unless otherwise approved in writing by OCRC, or until the permit is
revoked.
5. Permit Holder shall comply with all requirements for movement of mobile and modular homes as
prescribed in Mobile Home Transport Requirements (Act No. 300 of 1949; MCL §257.719a) and
Special Permits for Non-Conforming Vehicles (Act No. 300 of 1949; MCL §257.725), found in
the Michigan Vehicle Code.
6. The driver shall have a valid copy of the permit in his or her possession during the move and shall
present it upon request to any law enforcement officer or agent of the OCRC.
G. Seasonal Milk Haul Route Permit
The OCRC Seasonal Milk Haul Route Permit application form shall be submitted for approval prior to
issuance of the permit.
1. Permit Holder shall show good cause as per section 722 of Act No. 300 of 1949, as amended;
MCL §257.722.
2. Permit Holder shall allow sufficient time for application processing so a proper inspection can be
made of the requested highway or highways.
3. A permit may be issued to carry legal axle loads on a specific section of road, or roads on a
seasonal or short-term basis, dependent upon the route to be followed and the condition of the
road thereon.
4. Speed limits for such vehicles will be 35 mph maximum.
5. Failure of the permittee to fulfill terms of the permit is just cause for revoking the permit.
6. Any expense the OCRC attributes to the permit and to maintaining and restoring the haul route
will be charged to the Permit Holder.
7. The permit shall designate the route to be taken and will remain in effect only for as long as is
designated on the permit, as long as is necessary to complete the designated move, or until the
permit is revoked.
H. Seasonal Agricultural Permit
The OCRC Seasonal Agricultural Permit application form shall be submitted for approval prior to
issuance of the permit. This permit may be issued during seasonal weight restrictions on a per-move
basis. Single moves for agricultural commodities within the following parameters:
Weight: Up to legal per-axle loads, or a maximum of 700 lb. /in. of tire width, whichever
is lesser of the two.
60
1. Permit Holder shall comply with all requirements prescribed in the Agricultural Commodities
Exclusion as provided for in Act No. 300 of 1949; MCL §257.722.
2. A permit shall be obtained not less than 48 hours before pickup or delivery.
3. Designated route of travel shall be approved by the OCRC.
4. The date and time of the movement shall be submitted and approved by the OCRC.
5. Speed limits for such vehicles will be 35 mph maximum.
6. Any other conditions agreed to between the parties.
I. Seasonal Utility Non-Emergency Exemption Permit
The OCRC Seasonal Utility Non-Emergency Exemption Permit form for each vehicle shall be submitted
for approval prior to issuance of the permit.
1. Permit Holder shall qualify as per Section 722 of Act No. 300 of 1949, as amended and be
performing work specifically as per MCL §257.722.
2. A permit shall be obtained before the initiation of seasonal weight restrictions on equipment or
combinations of equipment so designated by the utility.
3. A permit shall be carried in each vehicle covered under the permit.
4. Per Act No. 300 of 1949; MCL §257.722, use of restricted roads during weight restriction
periods shall be minimized and utilized only when necessary to perform work using the public
utility vehicle or vehicle configuration, and non-restricted roads shall be used for routine travel
when available.
5. Speed limits for such vehicles will be 35 mph maximum.
Notification requirements under the permit:
1. The OCRC requires notification, by fax form, of the use of restricted roads by vehicles covered
by this permit not later than 24 hours before the time of the intended travel.
2. Upon determination, the OCRC may deny access to all or any part of that road to the utility
within 24 hours after receiving notification of intended use. Any notification that is not
disapproved within 24 hours after the notice is received by the OCRC is considered approved.
Approval for selected routes will not be unreasonably denied.
3. The notification application requires:
a. Permit Holder utility name and address
b. Address or location of the non-emergency work
c. Date or dates of the non-emergency work
d. Route to and from the work site and the permitted vehicle(s) to be involved with the work
e. Restricted road or roads intended to be travelled upon to the non-emergency work site or sites
f. Vehicle number or Permit number
61
XII. ENGINEERING AND SURVEYING PERMIT REQUIREMENTS
An annual permit is required for all engineering or surveying field crews doing any work in the ROW.
The OCRC application permit shall be submitted for approval prior to issuance of the permit. A permit
will expire on December 31 of the year issued.
Field crews digging for survey monuments will be required to place a monument box and cover on all
section and quarter corners. Monument boxes and covers for monuments shall conform to Ottawa County
standards.
XIII. BANNER AND PARADE REQUIREMENTS
A. Banners
Pursuant to MCL §247.323, a permit for installation of any banner to be placed within or over
county road ROW may be issued only to the Governing Body of a city, incorporated village, or
township. Commercial signs shall not be permitted within the ROW of any road under the
jurisdiction of the OCRC.
1. Permit Application
Applications for permits for the erection of banners shall be in the manner prescribed by or on
the appropriate forms supplied by the OCRC (See Detail PA-13).
Any permit application shall be submitted by an authorized official of the Governing Body to
make the application for the city, village, or township. The Governing Body shall indemnify and
hold harmless the OCRC for all claims and expenses of any kind or nature arising as a result of
the permitted banner installation. The application shall be submitted approximately one (1)
month in advance of the proposed installation.
The application shall include the following Information:
a. The activity in connection with which the banner is to be placed.
b. The location of the proposed installation, including distance to overhead traffic control
devices.
c. A description of the banner, including any legend or symbol thereon.
d. The height of any overhead banner from the road surface to its lowest point.
e. The dates on which the banner will be erected and removed. This period shall not exceed
a time specified by the OCRC. A generally acceptable period of time for banners to be
in place is three (3) weeks, except for Holiday decorations, which may be in place for eight
(8) weeks.
f. Such other information as the OCRC may require.
2. Banner Design and Placement Requirements
Any banner shall be designed, installed, and located so as to avoid danger to those using the
road or undue interference with the free movement of traffic or maintenance operations.
Any banner shall be securely fastened, shall have a minimum bottom height of 18 feet above
the surface of the travelled way, shall be placed no closer than 100 feet in advance of flashing
62
beacons or traffic control signals, and shall be placed so as not to obstruct a clear view of
traffic lights or signals or other traffic control devices. Banners shall not be attached to trees.
No banner shall have displayed thereon any legend or symbol which may in any way be
construed to advertise or otherwise promote the sale of or publicize any merchandise or
commodity, or which may be construed to be political in nature.
No banner shall have displayed thereon any device that is or purports to be, is an imitation of,
resembles, or may be mistaken for a traffic control device, or which attempts to direct the
movement of traffic.
Decorations shall not include flashing lights, reflective materials, or other devices that may
distract motorists.
3. Additional Permit Conditions
Any permit for the erection or installation of a banner may be revoked by the OCRC if such
installation becomes dangerous to those using the road or unduly interferes with the free
movement of traffic or maintenance operations.
The city, village or township making application shall faithfully fulfill all permit requirements.
Any permit may be revoked by the OCRC upon failure to comply with any permit conditions.
B. Parades
A permit granting permission to temporarily close a county road for a reasonable length of
time for a parade, event, celebration, festival or similar activity or to use a county road as a
detour for traffic around such activity taking place on a non-county road, may be issued by the OCRC
only to the Governing Body of a city, incorporated village, or township.
1. Permit Application
Applications for permits to close or partially close or use as a detour on a county road for a
parade, event, celebration, festival or similar activity shall be made on a form supplied by the
OCRC (See Detail PA-14).
Any permit application shall be shall be submitted by an authorized official of the Governing
Body to make the application for the city, village, or township requesting permission for the road
closure or use as a detour.
The application shall include without limitation the following information:
a. The nature of the activity for which the permit is requested.
b. The dates and times it is proposed to close and reopen the county road to traffic.
c. The roads and/or portions of roads to be closed.
d. The proposed detour route or routes.
e. Such other information as the OCRC may require.
63
2. Road Closure Permit Conditions
All permits allowing the closure or partial closure of a road shall be issued subject to the
following conditions:
a. The closure or partial closure of the road and any detour route selected shall allow
alternative routes for the reasonably safe and convenient movement of traffic.
b. No suitable alternate location is available for the parade, event, celebration, or festival
which would allow greater traffic safety and/or impose less interruption of traffic.
c. Where a temporary nighttime closure is permitted for a parade, event, celebration,
festival or similar activity, all points of potential hazard and all barricades and warning
signs shall be lighted at the Permit Holder's expense.
d. All traffic control devices installed in conjunction with the road closure or partial closure
and any detour route shall conform to the provisions of the current MMUTCD.
e. The Applicant or Permit Holder shall at its sole expense, furnish, install, maintain, and
remove when no longer necessary, any required traffic control devices.
f. The city, village, or township making the application shall faithfully fulfill all permit
requirements and shall indemnify and hold harmless the OCRC from all claims and
expenses of any kind or nature arising as a result of the permitted activity.
g. The Permit Holder shall, at its sole expense, immediately following conclusion of the
permitted activity, clean up and remove any litter, debris, refuse, etc., placed or left in the
ROW as a result of the permitted activity. In the event that the Permit Holder fails to cleanup
as required, causing the OCRC to do the cleanup work, the Applicant shall reimburse the
OCRC for the cost thereof.
64
XIV. SEVERABILITY CLAUSE
If any part of these Procedures and Regulations for Permitted Activities are found to be invalid, such
invalidity shall not affect the validity of the remaining portions of these Procedures and Regulations for
Permitted Activities.
XV. VARIANCES
A. Variance Request Submittal
1. A variance from OCRC Procedures and Regulations for Permitted Activities may be requested in
writing on the Variance Request for Deviation form (See Detail PA-16) by the Applicant or
Applicant’s Engineer of a proposed permit request. A written request for a variance shall include
sufficient technical details to support a reasonable justification for the request.
2. A submittal requesting a variance must include the non-refundable variance request fee. The fee
amount shall be paid in accordance with the current schedule of fees, as adopted by the Board.
3. A request for a variance shall be submitted to the County Engineer for review prior to the
submittal of the permit application. Although instances may arise when a request for a variance
is submitted after submittal of the permit application, the application shall be resubmitted with the
approved revisions in these cases.
4. Within thirty (30) days of receipt of a variance request, fee, and supporting materials, the County
Engineer will notify the requestor for any additional information or materials and/or provide the
Board meeting date the request will be considered.
5. A variance will be considered by the Board only in cases involving practical difficulties or
unnecessary hardship and when the record on the appeal to the Board supports the following
affirmative findings:
a. The hardship or difficulties, or both, are exceptional or unique to a given site.
b. Allowing the variance will result in substantial justice being done, considering the benefit to
the public and the individual hardships that will be suffered by a failure of the Board to grant
the variance.
c. The conditions and circumstances, which are the basis of the variance request, shall not be
self-imposed.
B. Expiration of Granted Variance Request
If a variance has been granted and the construction authorized with the variance has not commenced
within one year from the date of its approval, the variance will be automatically rescinded. Any
submitted fees shall not be refunded and the variance request process shall start over if construction is still
desired to continue.
65
APPENDIX A
Administrative Completeness Assessment Checklists
Checklist for Submittal of Permit Application for Commercial Driveway
Checklist for Submittal of Permit Application for Residential Driveway
Checklist for Submittal of Permit Application for Utility Construction in
ROW
Checklist for Submittal of Permit Application for Sidewalk or Path
Construction in ROW
CHECKLIST FOR SUBMITTAL OF PERMIT APPLICATION FOR COMMERCIAL DRIVEWAY
Used for Administrative Completeness Assessment
Project Name ________________________________________________ Township _______________
Property Address _______________________________________________________________
_______________________________________________________________
I have read and understand the current OCRC Procedures and Regulations for Permitted Activities.
Signature_________________________________________________ Date: ___________________
Printed Name ____________________________________
Check
A. Permit Application
1. Application to Construct a Commercial Driveway within ROW (See Detail PA-1)
2. Two (2) paper copies on 24 inch x 36 inch sheets and an electronic PDF file of construction
plans signed and sealed by a Professional Engineer
3. Commercial Driveway Permit Fee submitted
4. It is understood that the County Engineer may require additional fees after review of the
application and construction plan
5. Certificate of Insurance in accordance with these Procedures and Regulations submitted
6. A Bond in accordance with these Procedures and Regulations submitted
7. The proposed driveway location is staked and identified on the site
B. Commercial Driveway Plan
1. Cover sheet for plans including:
• Name of development
• Index of sheets
• Location of proposed development and driveway in relationship to existing access
points
2. Plans drawn to scale not smaller than 1 inch = 50 feet horizontal and 1 inch = 5 feet vertical
Page 2
Commercial Driveway
Permit Application Checklist
3. North directional arrow and scale of plan
4. Location map and Township information
5. All existing physical features (e.g. road pavement, shoulders, ditches, poles, hydrants, utility
service boxes, trees, shrubs, etc.) are shown and dimensioned
6. All existing and proposed buildings and appurtenances are shown and dimensioned
7. Distance from existing driveway(s) and proposed driveway(s) to the nearest intersecting street,
and distance from driveways to property lines
8. All driveways, tapers, through lanes, right turn lanes, center left turn lanes, or passing lanes to be
constructed are shown and dimensioned and include the following features:
Widths of all driveways and lanes
Radii of driveway returns and other points of curvature
Driveway grades and profile view of driveway
Road centerline and edge of pavement grades
Angle of the driveway(s) relative to the roadway centerline
9. Existing and proposed drainage system to include:
Size of drive culvert or storm sewer
Material type of culvert or storm sewer
Type of culvert end treatment
Grade of culvert or storm sewer with sufficient elevations upstream and downstream to
show the extent of flow across the proposed development and to the proposed outlet
Direction of surface water flow to and from adjacent property
Drainage structures
Drainage plan and outlet for all storm drainage on the site
C. Traffic Impact Study
1. A traffic impact statement or assessment from a qualified traffic engineer is provided
2. It is understood that the County Engineer may require improvements to adjacent primary and/or
local roads and/or nearby intersections
D. Driveway Location
1. The proposed driveway location complies with the spacing requirements outlined in Figure 3 and
Table 3.
2. The proposed driveway, including the radii, but not including tapers and right-turn lanes, is
located entirely within the area between the Applicant’s property lines extended to the centerline
of the road.
Page 3
Commercial Driveway
Permit Application Checklist
E. Sight Distance
1. Minimum sight distances at all proposed driveway locations are met
2. It is understood that the County Engineer may request sight distance diagrams to verify safe
sight distance for any proposed driveways
F. Driveway Grade
1. It is understood that the driveway is to be constructed with a vertical sag curve between the back
of curb or shoulder point and the driveway approach in accordance with these Procedures and
Regulations.
2. It is understood that the driveway approach grade shall be limited between 2 to 4 percent from
the road edge.
G. Driveway Geometrics and Construction
1. The proposed driveway geometrics complies with these Procedures and Regulations.
2. The proposed driveway construction cross-section complies with these Procedures and
Regulations.
It is understood that this checklist is to aid in the submittal process, and that the County Engineer
may require revisions and/or additional requirements prior to the consideration of permit issuance.
CHECKLIST FOR SUBMITTAL OF PERMIT APPLICATION FOR RESIDENTIAL DRIVEWAY
Used for Administrative Completeness Assessment Township _______________________________ Property Address/Parcel No. ____________________________________________________ ____________________________________________________ I have read and understand the current OCRC Procedures and Regulations for Permitted Activities.
Signature ______________________________________________ Date: _________________
Printed Name ____________________________________
Check
H. Permit Application 1. Application to Construct a Residential Driveway within ROW (See Detail PA-1)
2. Residential Driveway Permit Fee submitted
3. Certificate of Insurance in accordance with these Procedures and Regulations submitted
4. A Bond in accordance with these Procedures and Regulations submitted
5. The proposed driveway location is staked and identified on the site
6. A site plan with the following information submitted:
a. Plans drawn to a scale not less than 1 inch = 30 feet horizontal. b. North arrow with Township information. c. All existing roads and driveways d. The proposed driveway and home orientation on the property.
I. Driveway Location
1. The proposed driveway location complies with the spacing requirements outlined in Figure 4 and Table 4.
2. The proposed driveway, including the radii or flares, is located entirely within the area between
the Applicant’s property lines extended to the centerline of the road.
Page 2
Residential Driveway
Permit Application Checklist
J. Sight Distance
1. Minimum sight distances at all proposed driveway locations are met
2. It is understood that the County Engineer may request sight distance diagrams to verify safe
sight distance for any proposed driveways
K. Driveway Grade
3. It is understood that the driveway is to be constructed with a vertical sag curve between the back
of curb or shoulder point and the driveway approach in accordance with these Procedures and
Regulations.
4. It is understood that the driveway approach grade shall be limited between 2 to 4 percent from
the road edge.
L. Driveway Geometrics
1. The proposed driveway will have a minimum width of ten (10) feet and maximum width of
twenty-four (24) feet as measured by the driveway throat width.
2. If the driveway has a radius, each radius will be a minimum of ten (10) feet and a maximum of
twenty (20) feet.
3. If the driveway has a flare, each flare will be straight for ten (10) feet in length and extend five
(5) feet from the driveway along the pavement edge.
M. Driveway Construction
1. It is understood that if the adjacent roadway has a bituminous valley curb or concrete curb and
gutter, the residential driveway will be hard surfaced with either HMA or concrete materials.
And that a gravel surface is not permitted.
2. It is understood that if the adjacent roadway does NOT have a bituminous valley curb or
concrete curb and gutter, the residential driveway will be a gravel surface or hard surfaced with
HMA only. And that a concrete surface is not permitted.
It is understood that this checklist is to aid in the submittal process and that the County Engineer may
require revisions and/or additional requirements prior to the consideration of permit issuance.
CHECKLIST FOR SUBMITTAL OF PERMIT APPLICATION FOR
UTILITY CONSTRUCTION IN ROW
Used for Administrative Completeness Assessment
Utility Name _________________________________________________ Township _______________
Project Location ________________________________________________________________
I have read and understand the current OCRC Procedures and Regulations for Permitted Activities.
Signature_________________________________________________ Date: ___________________
Printed Name ____________________________________
Check
A. Permit Application
1. Application for Utility Construction within ROW (See Detail PA-1)
2. Type of Utility
Sanitary Gravity Sewer Sanitary Forcemain Water Main Gas Main
Electric Telecommunications Other __________________
3. Two (2) paper copies and an electronic PDF file of construction plans signed by a Professional
Engineer or Project Manager
4. Utility Construction Permit Fee submitted
5. It is understood that the County Engineer may require additional fees after review of the
application and construction plan
6. Certificate of Insurance in accordance with these Procedures and Regulations submitted
7. A Bond in accordance with these Procedures and Regulations submitted
8. All proposed Franchise Utility (except Telecommunication) construction location(s) is staked
and identified in the ROW
Page 2
Utility Construction in ROW
Permit Application Checklist
B. Utility Construction Plan
1. Cover sheet for plans including:
• Name of Utility
• Index of sheets
• Location of proposed utility construction in relationship to existing public roads
2. Plans drawn to scale not smaller than 1 inch = 50 feet horizontal and 1 inch = 5 feet vertical or as
approved by the County Engineer
3. North directional arrow and scale of plan
4. Location map and Township information
5. All existing physical features (e.g. road pavement, shoulders, ditches, driveways, buildings,
sidewalks, poles, hydrants, utility service boxes, trees, etc.) are shown and dimensioned
6. All existing and proposed utilities are shown and dimensioned
7. ROW and property lines are shown and dimensioned
C. Utility Location and Alignment
1. The proposed utility location conforms to the OCRC corridor location plan
2. It is understood that the County Engineer may require the utility to be placed at a location to
accommodate future road improvements
D. Depth of Utility Cover
1. Minimum depth of utility cover at the proposed locations are met
E. Utility Road Crossing
1. Utility road crossing of paved roads will be done by an approved trenchless or nondestructive
method. Check the paved road utility crossing method
Directional Boring Boring and Jacking
If the utility road crossing of a paved road cannot be done by approved trenchless or
nondestructive method, a written request outlining the extenuating circumstances is attached
for the County Engineer to consider
Page 3
Utility Construction in ROW
Permit Application Checklist
F. Traffic Control Requirements
1. Traffic control plans and details are in accordance with the latest edition of the MMUTCD and
are attached
2. It is understood that the County Engineer may require revisions and/or additional traffic control
devices during construction
G. Restoration
1. All restoration work, including inspection and testing, will conform to these Procedures and
Regulations and will be done to match the existing conditions to equal or better prior to the start
of the utility work
H. As-Built Plans
1. A paper copy of the as-built plans with storm sewer and drainage structure GPS locations and
elevations and electronic file in PDF will be submitted to the County Engineer
It is understood that this checklist is to aid in the submittal process and that the County Engineer may
require revisions and/or additional requirements prior to the consideration of permit issuance
CHECKLIST FOR SUBMITTAL OF PERMIT APPLICATION FOR
SIDEWALK OR PATH CONSTRUCTION IN ROW
Used for Administrative Completeness Assessment
Township ___________________
Project Location ________________________________________________________________
I have read and understand the current OCRC Procedures and Regulations for Permitted Activities.
Signature_________________________________________________ Date: ___________________
Printed Name ____________________________________
Check
A. Permit Application
1. Application for Sidewalk or Path Construction within ROW (See Detail PA-1)
Project Type: Sidewalk Non-Motorized Path
2. Two (2) paper copies on 24 inch x 36 inch sheets and an electronic PDF file of construction
plans signed and sealed by a Professional Engineer
3. Sidewalk and Non-Motorized Path Construction Permit Fee submitted
4. It is understood that the County Engineer may require additional fees after review of the
application and construction plan
5. Certificate of Insurance in accordance with these Procedures and Regulations submitted
6. A Bond in accordance with these Procedures and Regulations submitted
7. The proposed sidewalk or path construction location(s) is staked and identified in the ROW
B. Sidewalk or Path Construction Plan
1. Cover sheet for plans including:
• Index of sheets
• Location of proposed sidewalk or path construction in relationship to existing
public road system
2. Plans drawn to scale not smaller than 1 inch = 50 feet horizontal and 1 inch = 5 feet vertical
3. North directional arrow and scale of plan
Page 2
Sidewalk or Path Construction in ROW
Permit Application Checklist
4. Location map and Township information
5. All existing physical features (e.g. road pavement, shoulders, ditches, drainage systems,
driveways, buildings, poles, hydrants, utility service boxes, trees, etc.) are shown and
dimensioned
6. All existing and proposed sidewalks and paths are shown and dimensioned
7. ROW and property lines are shown and dimensioned
8. Existing contour elevations and location and elevation of USGS bench mark are shown
9. Cross-sections with existing topographical data and the proposed sidewalk or non-motorized
path for every 50 feet of centerline stationing drawn to a standard scale of not less than 1 inch =
10 feet horizontal and 1 inch = 1 foot vertical are submitted
C. Sidewalk and Path Width, Location, and Grade
1. The proposed sidewalk or path location conforms to these Procedures and Guidelines
2. It is understood that the County Engineer may require an easement beyond ROW Line so a
portion or all of sidewalk or path can be placed to accommodate roadside drainage, other ROW
needs, or future road improvements
D. Sidewalk and Path Drainage
1. Roadside drainage systems and patterns are not impacted by the sidewalk or path
2. Sidewalk and path storm water runoff is accommodated
Sidewalk or path drains toward the roadside drainage system
Calculations are attached verifying that the existing roadside drainage system
can accommodate the additional storm water runoff
Sidewalk or Path drainage is accommodated along the ROW Line or private property
3. It is understood that any storm sewer or drainage structures placed as part of the sidewalk or
non-motorized construction shall become the local Governing Body’s responsibility to maintain
E. Sidewalk and Path Construction
2. Sidewalk or path construction conforms to the local Governing Body standards or OCRC
recommended cross-section
Page 3
Sidewalk or Path Construction in ROW
Permit Application Checklist
3. ADA ramps in accordance with MDOT and OCRC standards are provided for all required
commercial driveway, private road, and public road crossings
F. Traffic Control Requirements
1. Traffic control plans and details are in accordance with the latest edition of the MMUTCD and
are attached
2. It is understood that the County Engineer may require revisions and/or additional traffic control
devices during construction
G. As-Built Plans
1. A paper copy of the as-built plans with storm sewer and drainage structure GPS locations and
elevations and electronic file in PDF will be submitted to the County Engineer
It is understood that this checklist is to aid in the submittal process and that the County Engineer may
require revisions and/or additional requirements prior to the consideration permit of issuance
APPENDIX B
Permitted Activities Details
Detail PA-1 Permit Application Form
Detail PA-2 Typical Driveway Grade
Detail PA-3 Typical Commercial Driveway Approach
Detail PA-4 Optional Divided Commercial Driveway Approach
Detail PA-5 Typical Three-Lane Commercial Driveway
Approach
Detail PA-6 Center Left Turn Lane
Detail PA-7 Passing Lane
Detail PA-8 Residential Driveway Details
Detail PA-9 Typical Utility Locations within ROW – Curbed
Roads
Detail PA-10 Typical Utility Locations within ROW – Uncurbed
Roads
Detail PA-11 Sidewalk and Path Cross-Section
Detail PA-12 Ditch Enclosure
Detail PA-13 Inspector’s Daily Report Form
Detail PA-14 Application Request to Place a Banner
Detail PA-15 Application Request for a Parade, Celebration,
Festival, or other event
Detail PA-16 Variance Request for Deviation Form
since 1911
APPLICATION To Construct, Operate, Use, Maintain and/or
Remove Within a County Right-of-Way,
or to Close a County Road
Ottawa County Road Commission
14110 Lakeshore Drive
Grand Haven, Michigan 49417
(616) 842-5400
Applicant Job No.
An Applicant is defined as an owner of property adjacent to the right-of-way, the property owner's authorized representative; or an
authorized representative of a governing body or utility who applies for a permit to construct, operate, use, and/or maintain a facility
within the right-of-way for the purpose outlined within this application. A Contractor who makes application on behalf of a property
owner or utility must provide documentation of authority to apply for a permit. When an Applicant hires a Contractor to perform
the work, the Permit Holder is the Applicant and Contractor and BOTH assume responsibility for provisions of the Permit, and the
Ottawa County Road Commission’s Procedures and Regulations for Permitted Activities.
APPLICANT CONTRACTOR
Name Name
Company Company
Address Address
City City
Phone Phone
Email Email
By signing, applicant agrees to the General Conditions and Specifications, the Ottawa County Road Commission’s Procedures and
Regulations for Permitted Activities, and any additional permit terms and requirements.
Signature Date:
PLEASE CHECK THE APPROPRIATE BOX(ES) THAT APPLIES TO THE TYPE OF WORK REQUESTED BY THE APPLICATION
Driveway: Commercial Residential Drive Surface: Bituminous Concrete Gravel
Utility: Sanitary Sewer Water Storm Sewer Gas Electric Telecommunications
Sidewalk or Non-Motorized Path
Ditch Enclosure or Drainage Improvement
Other
Fiber Cable Phone
THE FOLLOWING MUST BE ATTACHED TO THE APPLICATION: 1. Permit Fee 2. Checklist 3. Plans 4. Bond 5. Cert. of Insurance
THE FOLLOWING ITEMS MUST BE STAKED PRIOR TO THIS APPLICATION SUBMITTAL: Commercial Driveways,
Residential Driveways, Franchise Utilities (except Telecommunications), Sidewalks, Non-Motorized Paths, Ditch Enclosures, and Drainage Improvements.
DETAIL PA-1 Pg. 1 of 2
Description and Location
Township Section No.
Permit to Construct, Operate, Use, Maintain and/or Remove Within a
County Right-of-Way, or to Close a County Road
GENERAL CONDITIONS & SPECIFICATIONS 1. FEES AND COSTS. Permit Holder shall be responsible for all fees and/or costs required by the Commission in connection with issuance of this
permit and shall deposit same as determined at the time the permit is issued.
2. SPECIFICATIONS. All work performed under this permit must be done in accordance with the plans, specifications, maps and statements filed with
the Commission and must comply with the Commission’s current requirements and specifications on file at its offices, including, but not limited to, the
Ottawa County Road Commission’s Procedures and Regulations for Permitted Activities and M.D.O.T. specifications.
3. PERMIT. This permit is subject to accompanying supplemental specifications or those on file with the Road Commission, including, but not limited to,
the Ottawa County Road Commission’s Procedures and Regulations for Permitted Activities, and Act 200 of Public Acts of 1969 and amendments. The
person in charge of the work shall have the permit, specifications, approved plans and sketches in his possession at the work site at all times.
4. BONDS. The Permit Holder shall furnish the County Road Commission with a minimum surety bond in the amount of $5,000 or such higher amount as
required by the County Road Commission guaranteeing performance in accordance with the Road Commission’s specifications and its Procedures and
Regulations for Permitted Activities. By furnishing such bond funds, the Permit Holder and contractor agree to comply with the Ottawa County Road
Commission’s Procedures and Regulations for Permitted Activities, including, but not limited to, those imposing liability upon the Permit Holder and
contractor for attorney fees and costs incurred by the Ottawa County Road Commission in any action to collect and/or permanently retain the bond
funds. The County Road Commission may retain any portion of a bond deposited herewith which in the opinion of the Road Commission shall be
necessary to cover any expense or damage incurred by it through the granting of this permit, and the bond or the balance thereof shall be returned to the
applicant upon completion of the work to the satisfaction of the County Road Commission.
5. INSURANCE. A Certificate of Insurance in the amount of $300,000 minimum property damage and $1,000,000 minimum public liability protecting
the Ottawa County Road Commission against any and all claims for damages arising from operations covered by the permit shall be provided by the
Permit Holder. Such insurance shall cover a period not less than the term of this permit and shall provide that it cannot be cancelled without ten (10)
days advance written notice by certified mail with return receipt required to the Road Commission. For additional information and details regarding
insurance requirements and exception, refer the Ottawa County Road Commission’s Procedures and Regulations for Permitted Activities, Section IV.
A. 4.
6. INDEMNIFICATION. Permit Holder shall hold harmless and indemnify and keep indemnified the Commission, its officers and employees from all
claims, suits and judgments to which the Commission, its officers, or employees may be subject and for all costs and actual attorney fees which may
be incurred on account of injury to persons or damage to property, including property of the Commission, whether due to the negligence of the Permit
Holder or the joint negligence of the Permit Holder and the Commission, arising out of the work under this permit, or in connection with work not
authorized by this permit, or resulting from failure to comply with the terms of this permit, or arising out of the continued existence of the work
product which is the subject of this permit.
7. MISS DIG. The Permit Holder must comply with the requirements of Act 53 of Public Acts of 1974, as amended. CALL MISS DIG AT (800)
482-7171 AT LEAST TWO (2) FULL WORKING DAYS, BUT NOT MORE THAN TWENTY ONE (21) CALENDER DAYS, BEFORE YOU
START WORK. Permit Holder assumes all responsibility for damage to or interruption of underground utilities.
8. NOTIFICATION OF START AND COMPLETION OF WORK. Permit Holder must notify the Commission at least 48 hours before starting
work and must notify the Commission when work is completed.
9. TIME RESTRICTIONS. All work shall be performed Mondays through Saturdays daylight hours, unless written approval is obtained from the
Commission, and work shall be performed only during the period set forth in this permit.
10. SAFETY. Permit Holder agrees to work under this permit in a safe manner and to keep the area affected by this permit in a safe condition until the
work is completed. All work site traffic controls shall comply with Michigan Manual of Uniform Traffic Control Devices. If highway is to be closed at
any time due to construction, the Contractor shall notify the Commission two (2) working days in advance of said closure to allow the Commission to
determine a detour route. The signing of said detour shall be the responsibility of the Contractor.
11. RESTORATION AND REPAIR OF ROAD. Permit Holder agrees to restore the road and right-of-way to a condition equal to or better than its
condition before the work began; and to repair any damage to the road right-of-way which is the result of the facility whenever it occurs or appears. In
any action by the Ottawa County Road Commission against the Permit Holder for installation of non-conforming or defective work in a Right-of-Way
under its jurisdiction, the Permit Holder is responsible for the Ottawa County Road Commission’s attorney fees and costs.
12. LIMITATION OF PERMIT. This permit does not relieve Permit Holder from meeting other applicable laws and regulations of other agencies.
Permit Holder is responsible for obtaining additional permits or releases which may be required in connection with this work from other
governmental agencies, public utilities, corporations and individuals, including property owners. Permission may be required from the adjoining
property owners.
13. REVOCATION OF PERMIT. The permit may be suspended or revoked at will, and the Permit Holder shall surrender this permit and alter, relocate
or remove its facilities, at its expense, at the request of the Commission.
14. VIOLATION OF PERMIT. This permit shall become immediately null and void if Permit Holder violates the terms of this permit and alter, relocate
or remove its facilities, at its expense, at the request of the Commission.
15. ASSIGNABILITY. This permit may not be assigned without the prior approval of the Commission. If approval is granted, the assignor shall remain
liable and the assignee shall be bound by all the terms of this permit.
16. EXCAVATION AND DISPOSAL OF EXCAVATED MATERIAL. The Road Commission’s Engineer shall specify if trenches or excavations under
or adjacent to the road surface shall be sheeted or shored and braced in such a manner as to prevent settlement of foundation material supporting the
pavement. Excavated material shall be stockpiled in locations that do not obstruct motorist’s vision or interfere with the flow of traffic. Sod and topsoil
shall be stocked separately from other excavated material. The applicant shall dispose of all surplus and unsuitable material outside of the limits of the
highway unless permit provides for disposal at approved locations within the right-of-way. In the latter case, the material shall be leveled and trimmed
in an approved manner.
17. CROSSING ROADBED. When crossing by boring or jacking the top of casing shall be placed to a depth of not less than 4 feet below the road surface
and not less than 4 feet below the bottom of ditches. The service pipe shall be enclosed in a casing of sufficient size to permit removal and replacement
of the service pipe without removing the casing. When crossing is allowed by cutting and trenching, all work must conform to requirements included in
“Attachment for Additional Requirements.”
18. TRIMMING OR REMOVING TREES OR SHRUBS. The permission of abutting property owner must be obtained and in case of removal all timber
and branches must be properly and promptly removed from the highway right-of-way. The right of the abutting property owner to the wood resulting
from trimming or removal must be observed. All tree trimming or removal must be completed within 60 days of the date of this permit.
19. OPERATIONAL INSURANCE. Any pipeline company transporting oil, gas or other dangerous products by a pipeline located within the road
right-of-way may be required by the Board of County Road Commissioners of Ottawa County to furnish property damage and public liability
insurance and bond to protect the Board of County Road Commissioners, Ottawa County as against all liabilities for the operation of such pipeline in
an amount to be set by the Board of County Road Commissions as a condition of the granting of a permit.
DETAIL PA-1 Pg. 2 of 2
OTTAWA COUNTY ROAD COMMISSION
ROADCOMMISSIONOTTAWA COUNTY
OTTAWA COUNTY ROAD COMMISSION
ROADCOMMISSIONOTTAWA COUNTY
REPORT #
DATE
PROJECT NAME TOWNSHIP
CONTRACTOR FOREMAN'S NAME WEATHER
SUBCONTRACTOR FOREMAN'S NAME TEMPERATURE
LOW HIGH
ADDITIONAL REMARKS:
CONSTRUCTION INSPECTOR SIGNATURE PROJECT ENGINEER SIGNATURE DATE
DETAIL PA‐13 03/01/18
INSPECTOR'S DAILY REPORT
SKETCHES, COMPUTATIONS, ETC.
ITEMS OF WORK
DESCRIPTION STATION AND LOCATION QUANTITY REMARKS
14110 Lakeshore Drive
P.O. Box 739
GRAND HAVEN, MI 49417
Phone (616) 842-5400 Fax (616) 850-7237
APPLICATION REQUEST TO PLACE A BANNER WITHIN THE RIGHT-OF-WAY
APPLICATION
Banner Information Requested Timeframe
Name of Activity Date of Placement
Type of Activity Date of Removal
Township
Requested by Phone # Email
X__________________________________________________ Date: ___________________
(signature)
A permit for the installation of Banner to be placed within or over a county right-of-way
will only be issued to the local Governing Body (city, village, or township).
Description of Banner including proposed location:
Height to lowest point of Banner (18 feet minimum) _____________
Township________________________________ Section No. __________
A location map shall be attached to this Application.
IF A PERMIT IS ISSUED, THE FOLLOWING CONDITIONS APPLY:
1. The design, method of installation, and location shall not endanger persons using the right-of-way or
unduly interfere with the free movement of traffic.
2. A Banner shall not be placed so as to obstruct a clear view of traffic signals or other traffic control
devices.
3. A Banner shall not display any legend or advertisement promoting the sale of any merchandise or
commodity or to be political in nature.
4. A Banner shall not imitate or resemble a traffic control device or attempt to direct the movement of
traffic.
5. Flashing or steady burning lights will not be allowed.
DETAIL PA-14
14110 Lakeshore Drive
P.O. Box 739
GRAND HAVEN, MI 49417
Phone (616) 842-5400 Fax (616) 850-7237
APPLICATION REQUEST FOR A PARADE, CELEBRATION, FESTIVAL, OR
OTHER EVENT THAT INVLOVES A CLOSURE OF A COUNTY ROAD
APPLICATION
Event Information Requested Timeframe
Name of Activity
Date(s) of Closure
Type of Activity
Day(s) of week
Township
Time of closure
am/pm - am/pm
Requested by
Phone # Email
X__________________________________________________ Date: ___________________
(signature)
A permit for the closure or partial closure of a county road for a parade, celebration,
festival, or other event will only be issued to the local Governing Body (city, village, or
township).
Description of event:
Township________________________________ Section No. __________
A route map of the event shall be attached to this Application.
A traffic control plan and narrative shall be attached to this Application.
IF A PERMIT IS ISSUED, THE FOLLOWING CONDITIONS APPLY:
1. An acceptable detour plan shall be submitted and approved by the County Engineer prior to road
closure. Closure and/or detour shall allow alternative routes for reasonably safe convenient movement
of traffic.
2. An alternate location for the event shall be used if it allows for greater traffic safety and/or imposes
less interruption of traffic.
3. At its own expense, Applicant or Permit Holder shall arrange for necessary police supervision, as well
as furnish, install, maintain, and remove any traffic control devices deemed necessary by the OCRC.
Traffic control devices shall be in accordance with the Michigan Manual of Uniform Traffic Control
Devices.
4. Where a temporary nighttime closure is permitted, all points of potential hazards, all barricades, and
warning signs shall be lighted at the Permit Holder’s expense.
5. A permit will not be issued for the purpose of allowing private commercial activities such as
advertising or sale of any goods.
6. The Permit Holder shall notify schools and Central dispatch (i.e. 9-1-1) in advance of closure.
7. At its sole expense and immediately following the conclusion of the permitted activity, the Applicant
and/or Permit Holder shall clean up and remove any all litter and debris placed or left in the road right-
of-way.
8. The Applicant shall faithfully ensure fulfillment of all permit requirements and shall indemnify and
hold harmless the OCRC from all claims and expenses of any kind or nature arising from the permitted
activity.
DETAIL PA-15
DETAIL PA-16
VARIANCE REQUEST FOR DEVIATION FROM PROCEDURES
AND REGULATIONS FOR
PERMITTED ACTIVITIES
The goal of the Board of County Road Commissioners of the County of Ottawa (Board) to use its
expertise, energy, and funds to provide the safest and most convenient road system possible. All requests
for deviations from Policy shall keep these objectives in mind.
Date: ___________________
A non-refundable Variance Request Fee is attached
Applicant Name: ________________________________________________________________
Address: _______________________________________________________________________
_______________________________________________________________________
Daytime Phone: _________________________________________________________________
Briefly state the requested variance (citing the specific section(s) of the Procedures and Regulations
for Permitted Activities from which you are seeking a variance)**:
_______________________________________________________________________________
_______________________________________________________________________________
_______________________________________________________________________________
_______________________________________________________________________________
_______________________________________________________________________________
_______________________________________________________________________________
_______________________________________________________________________________
_______________________________________________________________________________
_______________________________________________________________________________
_______________________________________________________________________________
_______________________________________________________________________________
_______________________________________________________________________________
** (Use Attachments if Necessary)
DETAIL PA-16
Page 2
Variance Request Form
Please check all the items below which are applicable to your request for variance:
1. The situation which causes you to seek a variance does not result from any action of yours.
2. The request for variance is based upon conditions and circumstances described on the attached
sheet which are unique to your situation and not generally applicable in normal situations.
3. Compliance with the Procedures and Regulations for Permitted Activities would unreasonably
prevent you from using the ROW or would be unnecessarily burdensome.
Narrative Statement:
Please attach a narrative statement setting forth:
a. The reason your project cannot be accomplished within the Procedures and Regulations for
Permit Activities.
b. All the alternatives that have been sought and reviewed prior to seeking the variance request.
c. Why you need the variance.
d. The specific decision you seek.
Site and/or Construction Plan:
Two (2) copies of a detailed, scaled site plan showing the nature of the variance request, including, but
not limited to property boundaries, existing and proposed structures, and other pertinent information.
Additional information may be required by the County Engineer.
The Board may attach conditions to the granting of a variance.
Please be advised that substantial steps toward implementing the variance must be taken within twelve
(12) months of approval of a variance, or the variance will automatically become null and void.
Date: ___________________
___________________________________
Signature of Applicant
_________________________________
Print Name
Ottawa County Road Commission
14110 Lakeshore Drive Grand Haven, Michigan 49417
(616) 842-5400 [email protected] Since 1911
Stay Updated, Stay Connected. www.ottawacorc.com
ADDENDUM #1
To
OTTAWA COUNTY ROAD COMMISSION
PROCEDURES AND REGULATIONS
FOR
PERMITTED ACTIVIES
Adopted by the Board of County Road Commissioners, County of Ottawa on September 26,
2019 and effective September 26, 2019.
End of Table of Contents an ADDENDUM section was added.
On Pages 29 & 30 under Section VI. Driveway Standards & Requirements, C.
Residential Driveway Requirements, 5. Driveway Construction Standards was revised
and replaced.
Detail PA-2 was revised and replaced.
Detail PA-8 was revised and replaced.
5. Driveway Construction Standards
If the adjacent roadway has a bituminous valley curb or concrete curb and gutter, the residential
driveway approach shall be hard surfaced with either HMA or concrete materials. A gravel
surface will not be permitted. (See Detail PA-8).
If the adjacent roadway does NOT have a bituminous valley curb or concrete curb and gutter, the
residential driveway approach can be hard surfaced with HMA only or have a gravel surface. A
concrete surface will not be permitted within ten (10) feet of the road pavement edge (or 10
feet from the shoulder point of a gravel road). (See Detail PA-8).
Recommended Minimum Residential Driveway Construction
a. Subbase - MDOT Granular Material Class II, 12 inches minimum
b. Aggregate Base - MDOT Dense-Graded Aggregate 22A, 6 inches minimum
c. HMA Surface - MDOT HMA 36A, 3 inches (2 lifts) minimum
d. Concrete Surface - Minimum 5 inches
*Concrete is not permitted on uncurbed roads within ten (10) feet of the road
pavement edge nor within 10 feet of the shoulder point of a gravel road.
Ottawa County Road Commission
14110 Lakeshore Drive Grand Haven, Michigan 49417
(616) 842-5400 [email protected] Since 1911
Stay Updated, Stay Connected. www.ottawacorc.com
ADDENDUM #2
To
OTTAWA COUNTY ROAD COMMISSION
PROCEDURES AND REGULATIONS
FOR
PERMITTED ACTIVIES
Adopted by the Board of County Road Commissioners, County of Ottawa on December 19, 2019
and effective December 19, 2019.
On Page 29 under Section VI. Driveway Standards & Requirements, C. Residential
Driveway Requirements, 4. Driveway Geometrics was revised and replaced.
Detail PA-8 was revised and replaced.
4. Driveway Geometrics
A residential driveway approach shall conform to Detail PA-8.
a. Width
A residential driveway shall have a minimum width of ten (10) feet and maximum width of
thirty-two (32) feet within the road right-of-way.
b. Radii
A driveway may have a radius on both sides of the driveway. Each radius is included in the
maximum driveway width measurement of thirty-two (32) feet within the road right-of-way.
c. Flare
A driveway may have a flare on both sides of the driveway. Each flare is included in the
maximum driveway width measurement of thirty-two (32) feet within the road right-of-way.
d. Joint Driveways
When property owners of adjoining properties agree, a joint driveway may be constructed.
The driveway shall meet the same requirements regarding residential driveways.
Ottawa County Road Commission
14110 Lakeshore Drive Grand Haven, Michigan 49417
(616) 842-5400 [email protected] Since 1911
Stay Updated, Stay Connected. www.ottawacorc.com
ADDENDUM #3
To
OTTAWA COUNTY ROAD COMMISSION
PROCEDURES AND REGULATIONS
FOR
PERMITTED ACTIVIES
Adopted by the Board of County Road Commissioners, County of Ottawa on December 3, 2020
and effective January 1, 2021.
On Page 12 under Section IV. Permitting Process, A. Permit Application, 5. Bonds was
revised and replaced.
Detail PA-1 was revised and replaced.
5. Bonds
Bonds shall be required for all construction activity within the public ROW to protect OCRC
against the cost of completing construction or repairing deficiencies. Acceptable types of bonds
are cash, certified or cashier's checks, and money orders payable to the Ottawa County Road
Commission. Table 1 indicates the minimum permit bonding amounts for the various types of
work in the ROW. The County Engineer may require a higher bonding amount based on the
proposed work and impact to the ROW.
Table 1. Minimum Bonding Requirements for Permits
Permit Type Bond Amount
Commercial Driveway $5,000
Residential Driveway $200*
Field or Temporary Driveway $200
Utility $5,000
Sidewalk and Path $5,000
Road Open-Cut/Reconstruction $10,000
Other As determined by County Engineer
*A $5,000 Annual Performance Bond may be posted in lieu of bonding individual
residential driveway permits. No bond is required to resurface an existing residential
driveway.
When an Annual Performance Bond is furnished, a permit is still required for each
individual project within the ROW requiring a permit. Annual Performance Bond funds
may be retained by the OCRC to recoup any costs and expenses incurred in relationship
to any non-permitted work performed during the year by the Principal of the Annual
Performance Bond.
After receipt of a written request by the Permit Holder and satisfactory completion of the
permitted activity as verified by the County Engineer, any unused bond amount (driveway bonds
only) will be returned to the Applicant or Permit Holder within fifteen (15) business days.
In any action by the OCRC against a Permit Holder to enforce the latter’s permit related obligations
(or to collect on a bond deposited in connection with the same), the Permit Holder shall be required to
reimburse the OCRC for all of its associated costs and attorney fees that are in excess of the bond or
are not collectable from the bonding agent.