7
Problem- 4 (Material & Labour) The following details relating to the product ‘X’ during the month March, 2011 are available. You are required to compute: i.Material Price Variance. ii.Material Usage Variance. iii.Material Cost Variance iv.Labour Rate Variance. v.Labour Efficiency Variance. vi.Labour Cost Variance.

Problem- 4 (Material & Labour) The following details relating to the product ‘X’ during the month March, 2011 are available. You are required to compute:

Embed Size (px)

Citation preview

Page 1: Problem- 4 (Material & Labour) The following details relating to the product ‘X’ during the month March, 2011 are available. You are required to compute:

Problem- 4(Material & Labour)

The following details relating to the product ‘X’ during the month March, 2011 are available. You are required to compute: i. Material Price Variance. ii.Material Usage Variance. iii.Material Cost Variance iv.Labour Rate Variance. v.Labour Efficiency Variance. vi.Labour Cost Variance.

Page 2: Problem- 4 (Material & Labour) The following details relating to the product ‘X’ during the month March, 2011 are available. You are required to compute:

Contd…

You are also required to reconcile the standard and actual cost with help of such variances. Standard Cost per unit: Material 50 Kg. @ ` 40 per kg.Labour 400 hrs. @ ` 1.00 per kg.

Actual Cost for the month: Material 4,900 Kg. @ ` 42 per kg.Labour 39,600 hrs. @ ` 1.10 per kg.Actual production – 100 units

Page 3: Problem- 4 (Material & Labour) The following details relating to the product ‘X’ during the month March, 2011 are available. You are required to compute:

Problem -5 (Labour & Variable Overhead)

The following information has been extracted from the books of Goru Enterprises which is using standard costing system:

Actual output 9,000 units Direct wages paid 1,10,000 hours at ` 22 per hour, of

which 5,000 hours, being idle time, were not recorded in production

Standard hours 10 hours per unitLabour efficiency variance ` 3,75,000 (A)Standard variable overhead ` 150 per unitActual variable overhead ` 16,00,000

You are required to calculate: (i) Idle time variance; (ii) Variable overhead expenditure variance; (iii) Total variable overhead variance and (iv) Variable overhead efficiency variance.

Page 4: Problem- 4 (Material & Labour) The following details relating to the product ‘X’ during the month March, 2011 are available. You are required to compute:

Problem -6 (Fixed Overheads)

AKASH LTD. operates a system of Standard Costing. The company has normal monthly machine hour capacity of 100 machines working 8 hours per day for 25 working days in the month of April 2014.

i.The Standard time required to manufacture one unit of products is 4 hours. The Budgeted fixed overhead was 1,50,000.

ii.In the month of April 2014, the company actually worked for 24 days for average 750 machine – hours per day.

Page 5: Problem- 4 (Material & Labour) The following details relating to the product ‘X’ during the month March, 2011 are available. You are required to compute:

Contd…

(iii)The Actual production was, 4,500 units, and the actual fixed overhead was 1,60,000.

You are required to compute: A. Fixed overhead efficiency variance B. Fixed overhead capacity variance C. Fixed overhead calendar variance D. Fixed overhead expenditure variance E. Fixed overhead volume variance F. Fixed overhead cost variance.

Page 6: Problem- 4 (Material & Labour) The following details relating to the product ‘X’ during the month March, 2011 are available. You are required to compute:

Problem – 7 (Overheads)

The following budget was prepared for the overhead of Department X:

Budget for period

Fixed overhead ` 5,600Variable overhead ` 10,400Machine hours 1,600Standard hours of production 1,600

After the period the actual results were:

Total overhead ` 17,400

Machine hours 1,630Standard hours produced 1,590

You are required to calculate the overhead variances for the period.

Page 7: Problem- 4 (Material & Labour) The following details relating to the product ‘X’ during the month March, 2011 are available. You are required to compute:

Contd…

At the end of the period, a price of ` 3.00 was agreed to

have been an efficient buying price in the period. The

standard costing system shows a direct material total

variance of ` 8,800 made up of:-

Material usage variance ` 2,000 (A)

Material Price Variance ` 16,800 (A)

Management wishes to distinguish between controllable

and uncontrollable effects on performance.