Upload
vokhue
View
216
Download
2
Embed Size (px)
Citation preview
PRMSTM Manufacturing Planning
Master Production Schedule
Material Requirements Plan
Scheduling
Workbench
by
Production
Line
Work Order/
FPOMaintenance
Pick SlipPrint
Stage Request
Consolidated
Pick
SHOP
FLOOR
CONTROL
Soft BillMaintenance
Auto Allocation to
Lots
RMS/PresentVersion 2.3
A Product ofMXB - Managing the Business
100 N. Freeman RoadTucson, AZ 85748
(520) 886-5914
RMS/Teachkit PRMSTM Manufacturing Planning
Table of Contents
Sample Agenda IAttendance Sheet IIIntroduction to PRMSTM Manufacturing 3
PRMS Planning Functions.......................................................................................4PRMS Execution Functions.....................................................................................6PRMS Manufacturing..............................................................................................8
Product Structure & Master Overview 11Major Features.......................................................................................................14Primary Functions.................................................................................................16System Control......................................................................................................18Product Master Maintenance................................................................................20
Lot Sizing 26Product Structure Definition..................................................................................34Product Structure Maintenance.............................................................................35
Master Production Scheduling 39Major Features.......................................................................................................42Entering Demand....................................................................................................44
Shipment Forecasts 44Forecasting Planner Bills 45Forecast Entry Process 46Forecasting Setup Functions 48Forecast Entry 50Planner Bill Explosion 52Forecast Inquiry 54Forecast List 55
Demand Source Management.................................................................................56Setup Functions.....................................................................................................64System Control......................................................................................................66
MPS Management 67Forecast Consumption Demand Source Rule 9.0 70
Functions, Reports, Inquiries................................................................................76MPS Generation 78MPS Generation Report 84
MPS Generation Report Explained 85Production Plan Report 88Summarized MPS Valuation Report 90Projected Inventory Report 92MPS Order Maintenance 94MPS Order Inquiry 96MPS Order Report 97MPS Inquiry/Pegging 8.3 98Available to Promise Inquiry 100
C MXB, 1993, 2000 Printed in the United States
All Rights ReservedPRMS is a trademark of interBiz, a division of Computer Associates Inc.
RMS/Teachkit PRMSTM Manufacturing Planning
Table of Contents
Rough Cut Capacity Planning 103Rough Cut - Demand vs. Resources....................................................................104Major Features.....................................................................................................106Setting Up............................................................................................................110
Resource Definition 110Resource Definition Maintenance 112Resource Definition List 113Discrete and Flow Resources 114Bill of Resource Maintenance 116Resource Variance Maintenance 118Resource Variance Maintenance Purge 120Bill of Resource Report 121
Rough Cut Generation.........................................................................................122Rough Cut Analysis and Reporting.....................................................................124Rough Cut Inquiry...............................................................................................126Rough Cut Load Reports.....................................................................................127
Shop Floor Control Overview 129Shop Data Maintenance Overview 133
Routings and Work Centers.................................................................................134Major Features.....................................................................................................136Operation Lead Times.........................................................................................138Work Center Maintenance...................................................................................140Routing Maintenance...........................................................................................144
Material Requirements Planning 147What it Does........................................................................................................148Major Features.....................................................................................................152Lead Time Planning for Discrete Items................................................................154Lead Time Planning for Repetitive Products.......................................................156Functions.............................................................................................................158
System Control 160MRP Generation 172MRP Generation Reports 176
MRP Generation Report Explained 178MRP Generation Report Explained 179
MRP Inquiry/Pegging 180Suggested Work Order Report 182Suggested PO Report 184Dollars Committed Report 186
Exception Message Management.........................................................................188
C MXB, 1993, 2000 Printed in the United States
All Rights ReservedPRMS is a trademark of interBiz, a division of Computer Associates Inc.
RMS/Teachkit PRMSTM Manufacturing Planning
Table of Contents
Capacity Requirements Planning 191Load Versus Capacity..........................................................................................192Maintenance Programs and Functions.................................................................194
CRP Generation 196CRP Inquiry/Pegging 200CRP Generation Reports 202Work Center Variance Maintenance 204Work Center Variance Batch Update 206
Manufacturing Planning in Multiplant 209PRMS Multiplant................................................................................................210Planning with Multiplant.....................................................................................212
Using the Forecasting Workbench 214Not Using the Forecasting Workbench 216Managing Interplant Demand 218Defining Interplant Demand 220How it Works 8.3 222Inquiries and Maintenance 8.3 224
Hands On Workshop 227
C MXB, 1993, 2000 Printed in the United States
All Rights ReservedPRMS is a trademark of interBiz, a division of Computer Associates Inc.
PRMSTM Manufacturing Planning
Master Production Schedule
Material Requirements Plan
Scheduling
Workbench
by
Production
Line
Work Order/
FPOMaintenance
Pick SlipPrint
Stage Request
Consolidated
Pick
SHOP
FLOOR
CONTROL
Soft BillMaintenance
Auto Allocation to
Lots
RMS/PresentVersion 2.3
A Product ofMXB - Managing the Business
100 N. Freeman RoadTucson, AZ 85748
(520) 886-5914
Sample Agenda
Day 1Morning
Intro to PRMS ManufacturingProduct Structure and Product Master ReviewProduct Master/Structure Workshop
AfternoonMaster Production SchedulingMaster Production Scheduling Workshop
Day 2Morning
Master Production Scheduling WorkshopRough Cut Capacity Planning
AfternoonRough Cut Capacity WorkshopShop Floor/Shop Data OverviewShop Data Workshop
Day 3Morning
Material Requirements PlanningMRP Workshop
AfternoonCapacity Requirements PlanningCRP Workshop
Day 4Morning
Manufacturing Planning in Multiplant
Page I
Name (printed) Job Function Day 1 Day 4Day 3Day 2check (x)
Course Title
Course Dates
RMS/TeachkitManufacturing Planning
Page II
Introduction to PRMSTM Manufacturing
Master Production Schedule
Material Requirements Plan
Scheduling
Workbench
by
Production
Line
Work Order/
FPOMaintenance
Pick SlipPrint
Stage Request
Consolidated
Pick
SHOP
FLOOR
CONTROL
Soft BillMaintenance
Auto Allocation to
Lots
RMS/TeachkitPage 3
Dist.Whse
A
Dist.Whse
B
Dist.Whse
C
PostingWarehouse
ManufacturingPlant
Planned Order Releases
MXB, 2000
PRMS Planning
Forecast Maintenance
WhseFcst.Maint.
Forecasting Workbench
Capacity Requirements
Planning
Material Requirements
Planning
Rough
Cut
Capacity
Master Production Scheduling
Distribution Requirements Planning
TM
SuggestedMPS Orders
Suggested WRO's
Page 4
Dist.Whse
A
Dist.Whse
B
Dist.Whse
C
PostingWarehouse
ManufacturingPlant
PRMS Execution Functions
MXB, 2000
MPS Orders/Scheduling Workbench/Work,Firm Planned Orders,
Purchase Orders
Scheduling Workbench/Work, Firm Planned Orders/
Requisitions, Purchase Orders/
Replenishment Orders
Warehouse Replenishment Orders
TM
Page 6
AccountsReceivable
CustomerOrder
Processing
Master Production Scheduling
Material Requirements Planning
Shop FloorControl
Warehouse Replenishment
Orders
General
Ledger
Interface
RoughCut
CapacityPlanning
CapacityRequirements
Planning
MXB,2000
PlanningExecution
ForecastingWorkbench
DistributionRequirements
Planning
Vendor Managed Inventory9.0
Product Structure
ShopData
Purchasing/Receiving
AccountsPayable
Payroll/Human
ResourcesPhysical Inv./Cycle Count
QualityControl
InventoryControl
PRMS TM
PRMS is a trademark of interBiz, a division of Computer Associates, Int'l
Page 8
Product Structure & Master Overview
Master Production Schedule
Material Requirements Plan
Scheduling
Workbench
by
Production
Line
Work Order/
FPOMaintenance
Pick SlipPrint
Stage Request
Consolidated
Pick
SHOP
FLOOR
CONTROL
Soft BillMaintenance
Auto Allocation to
Lots
RMS/TeachkitPage 11
Product Structure Functionality
Product MasterEngineering
Change Control
Product Structure Simulation
Product Cost/Lead Time Rollup
Simulation Reporting
Inventory Control
Master Production Scheduling
Material Requirements Planning
Shop Floor Control
Product Costing
Product Structure Maintenance
Global Component Replacement
P/S Reorganization
MXB, 2000
8.4
Assembly/Where-Used Reporting
ECN ReportingProduction Assembly Comparison Report 8.4
Page 12
Product Structure
Major Features
PLANNER BILLS
THREE QUANTITY REQUIRED FIELDS
BATCH SIZES
EFFECTIVITY DATES
SUBSTITUTE/OPTIONS DESIGNATION
ENGINEERING CHANGE TRACKING
BY-PRODUCT DESIGNATION
MATERIAL CONTROL BY COMPONENT
BALLOON NUMBER DESIGNATION
ENGINEERING, AND PRODUCTION TEXT
POTENCY DESIGNATION
DUPLICATE COMPONENTS
ZERO QUANTITY REQUIRED
Page 14
Product Structure
Primary Functions
SYSTEM CONTROL (WCMANT)
UNIT OF MEASURE TABLE (MS0827) 8 .3
PRODUCT MASTER MAINTENANCE (MS0825)
PRODUCT STRUCTURE MAINTENANCE (PS0021)
ENGINEERING CHANGE NUMBER (PS0800)
GLOBAL COMPONENT REPLACEMENT (PS0203) 8.4
PRODUCT COST UPDATE (SC0060)
PRODUCT STRUCTURE REORGANIZATION (PS0040)
Page 16
Product Structure
System Control
ENGINEERING CHANGES SUPPORTED
ENGINEERING CHANGE NUMBER REQUIRED
SUBSTITUTES AND OPTIONS SUPPORTED
EFFECTIVITY DATES SUPPORTED
BALLOON NUMBERS SUPPORTED
BATCH QUANTITIES SUPPORTED FOR ASSEMBLY
FULL EDITING PERFORMED ON LINE
PRINT PRODUCT STRUCTURE EDIT CHANGES
NUMBER OF DAYS TO RETAIN DISCONTINUEDCOMPONENTS
OMIT SETUP COSTS FROM ROLLUP
FULL ABSORPTION OR DIRECT COSTING USED
ALLOW FOR SHRINK IN COSTS
USE ENG, MFG, OR BASE STD QTYIn Base CostsIn Current CostsIn Actual Costs
Page 18
Product Structure
Product Master Maintenance
(MS0825, MSPMP100)
Key Fields for ManufacturingGENERAL PRODUCT INFORMATION
ITEM TYPE MAKE, BUY, PHANTOM, PLANNER
DEMAND TYPE I, C, D
MODEL FLAG IS THIS A MODEL FOR F & O
IMPORT FLAG ALLOWS LANDED COST FOR BUYS
LOTS REQUIRED
LOCATIONS REQ. REQUIRES FOR ALL TRANSACTIONS
SHELF LIFE FOR CALCULATION OF
EXPIRATION
PRODUCT CLASS INVENTORY REPORTING
UNIT OF MEASURE
ALT. UNIT OF MEAS. FOR PURCHASED PARTS
CONVERSION
BUYER ID*
ORDER PT ITEM TO DESIGNATE NON-MRP ITEMS
ORDER PT & QTY WHEN AND HOW MUCH TO ORDER
INSP. REQUIRED TO CONTROL THROUGH DOCK TO
STOCK
* indicates that the value used must be previously defined
Page 20
Product Structure
Product Master Maintenance
(MS0825)
PURCHASING
Lead Times
ORDER RELEASE LEAD TIME TO CREATE ORDER
DOCK TO STOCK LEAD TIME TO PROCESS RECEIPT
DELIVERY VENDOR LEAD TIME
GENERAL MANUFACTURING
PLANNER ID MRP & MPS SORTING AND CONTROL
PROD PLAN GROUP CODE*MPS & RCC SORTING AND CONTROL
POSTING WHSE* THE WAREHOUSE A MAKE ITEM IS
POSTED TO OR THE WAREHOUSE A
COMPONENT IS PICKED FROM
MPS ITEM DESIGNATES MPS ITEMS
MFG. METHOD FLOW ORDERS OR WORK ORDERS
SCHED LEVEL FROM MPS OR MRP IN
SCHEDULING WORKBENCH
DEFAULT LINE* FOR WORKBENCH, WHICH LINE
* indicates that the value used must be previously defined
Page 22
Product Structure
Product Master Maintenance
(MS0825)
GENERAL MANUFACTURING
AUTO RESCHEDULE MRP PROCESSING CONTROL
SCHEDULE TYPE 8 .3 DENOTES THE TYPE OF MANUFACTURING ORDER THAT IS NORMALLY USED IN THE MANUFACTURE OF THIS PRODUCT, 1-WORK ORDERS, 2-FLOW
ORDERS, 3-OSF, 4-NOS
LAG TIME TYPE 8 .3 WHETHER THE LAG TIME USED BY
THE PRODUCTION SCHEDULING
WORKBENCH IS IN CALENDAR DAYS OR LINE CALENDAR DAYS
LEAD TIME OFFSET 8 .3
THE NUMBER OF DAYS BETWEEN
THE POR OF THE PARENT AND THE GROSS REQUIREMENT OF THE CHILD
Page 24
Lot Sizing
MXB, 2000
Lot Size RuleLotSize
POR beforelot sizing
POR after lot sizing
1 - Discrete 100 33 33
2 - Fixed w/Disc 100 33 100 133 133
3 - Fixed Lot 100 33 100 133 200
4 - Not Used
5 - Fixed Period Length, FPL = 5 days
Monday Tuesday Wednesday Thursday Fridaybefore
lot sizing
Lot Size = 100
afterlot sizing
Monday Tuesday Wednesday Thursday Fridaybefore
lot sizing
Lot Size = 500
afterlot sizing
100 100 100 100
400
100 100 100 100
500
Page 26
Product Structure
Product Master Maintenance
(MS0825)
MANUFACTURING PLANNING
SAFETY STOCK
If Safety Stock is used by MRP or MPS, this is the projected on hand quantitythat will be planned. MRP will issue exception messages to replenish wheneverthe projected or actual balance is below this level.
MIN/MAX SUGGESTED ORDER QUANTITY
MPS and MRP will plan to the minimum quantity and message if the plannedorder is over the maximum quantity.
LEAD TIME FENCE RULE
Determines which lead time value of the product is used to multiply by the LeadTime Multiplier to determine where a time fence is drawn.
(1) Assembly lead time, (2) Assembly plus safety lead, (3) Manufacturing leadtime, (4) Manufacturing with safety, (5) Cumulative, (6) Cumulative with safety
MPS PHANTOM LEAD TIME
If an item is a MPS Item and a Phantom, this lead time will be used by MRP.
LEAD TIME MULTIPLIER 1 AND 2The value here is multiplied by the appropriate lead time to determine the numberof days plus the MPS Generation Date where a time fence is drawn.
If no time fences are used then there is one time period, one fence equals twotime periods, two fences equals three time periods.
Page 28
Product Structure
Product Master Maintenance
(MS0825)
MANUFACTURING PLANNING
DEMAND SOURCE RULES 1, 2, 3Determines what the MPS Generation considers as demand in the time periodsdetermined by the lead time fences
(1) Actual Forecasts, (2) Smoothed Forecasts, (3) Customer Orders, (4)Demand Smoothing, (5) DRP Information, (6) Forecast Consumption Lumpy
9.0,
(7) Forecast Consumption Smoothed 9.0
.(6) and (7) = Period Forecasts - (Shipped + Booked) +Booked - Past Due
Postpones intra-period adjustments of suggestedMPS/reschedules until forecast for period isconsumed.
AUTO ACCEPT MPSDefaulted from the System Control, determines if this item will be eligible forAuto Accept in MPS Generation after the Auto Accept Time Fence.
AUTO ACCEPT MPS TIME FENCE
The number of days from the MPS Generation date after which a SuggestedMPS will be Auto Accepted into an Accepted MPS Order. Typically referred toas the 'firm' or 'frozen' schedule period.
USE DRP PLAN ORDER FENCE
A Yes indicates that your intention is to have Planned Replenishment Ordersfrom DRP drive the demand to MPS after the number of days specified in theplanned order time fence. This reduces the time horizon that ReplenishmentOrders are required to be managed.
DRP PLANNED ORDER TIME FENCE
The number of days after the MPS Generation Date in which PlannedReplenishment Orders will drive demand in MPS.
Page 29
Product Structure
Product Master Maintenance
(MS0825)
MANUFACTURING PLANNING
STANDARD LABOR AND STANDARD MACHINE
User defined and not used in PRMS.
CUM LABOR AND CUM MACHINE
Used by the Production Plan Report (MP0110) and Summarized MPS ValuationReport (MP0170).
This value is multiplied by the quantity of suggested and or accepted MPS ordersto provide bucketed summaries.
These values are not calculated from the routing file.
LOT SIZING USED
If lot sizing occurs during MPS, MRP, or not at all. System Control allowsspecification by demand type (I,C,D).
LOT SIZING RULE
The type of lot sizing that is performed
(1) Discrete lot sizing, (2) Fixed lot with discrete quantities, (3) Fixed lotmultiples, or (5) Fixed period length.
FIXED PERIOD LENGTH
For lot size rule 5 (fixed period length), the number of days of POR' s that willbe consolidated into one POR. MRP will sum the POR's within this number ofdays, increase to the lot size and place the first POR on the first day of thisperiod that the POR appears.
MRP SAFETY LEAD TIME USED
Determines is safety lead time will be considered in the POR offset. Safety leadtime releases an order earlier than the scheduled release. Auto PO Create(PO0900), Requisition Entry (PO0010) and Batch Work Order Create (SF0019)all allow the specification of an upper release date which will accomplish thissame functionality.
Page 30
Product Structure
Product Master Maintenance
(MS0825)
MANUFACTURING PLANNING
SAFETY STOCK USED
Will safety stock be planned during MPS, MRP, or neither. If safety stock isused, MRP will issue messages to replenish then inventory immediately (underlead time) when the actual or planned balances drop below the level. SystemControl allows specification by demand type (I,C,D).
ON HAND INVENTORY USED
Will on hand inventory be netted during MPS, MRP, neither or both8.4. SystemControl allows specification by demand type (I,C,D).
CONSIDER NEGATIVE ON HAND AS ZERO 9.0
MRP and the Shortage Report (SF0360) will consider negatives as zero if thisflag is 'Y'. If negative inventory is due to timing of transactions, setting flag to"Y" will cause shortages to be planned.
MRP MESSAGE FILTERS
SUPPRESS RESCHEDULE IN DAYS AND AMOUNT
The number of shop days OR base standard value that a Reschedule In messagemust exceed to generate an exception message. If set to 5 days and $100,000then no item would be rescheduled in to the first 5 days unless the valueexceeded $100,000.
SUPPRESS RESCHEDULE OUT DAYS AND AMOUNT
The number of shop days OR base standard value that a Reschedule Outmessage must exceed to generate an exception message.
SUPPRESS PAST DUE REQUIREMENTS AND POR'SThe number of days that a past due message is not considered past due and willnot issue a message.
Page 31
Product Structure
Product Master Maintenance
(MS0825)
SUPPRESS SCHEDULED RECEIPT BEFORE
GENERATION DATE
The number of days that a Scheduled Receipt (PO, WO, RO, etc.) is past duewithout issuing a message.
SUPPRESS ON HAND BELOW SAFETY STOCK
The percentage of On Hand Below Safety Stock that is allowable without issuingan immediate replenishment message. MRP will still issue reschedule in or createmessages. This filter is specifically for the "On Hand Below Safety Stock"message.
SUPPRESS QUANTITY LESS THAN MINIMUM
The percentage of Minimum that is allowable without issuing an exceptionmessage.
SUPPRESS QUANTITY GREATER THAN MAXIMUM
The percentage of Maximum that is allowable without issuing an exceptionmessage.
PRODUCT INVENTORY
TEST CYCLE DAYS FREQUENCY OF TESTING
ACTIVE INGREDIENT HAVING ACTIVE QUANTITY
POTENCY RANGE ACCEPTABLE RANGES FOR ALLOC.
INV. METHOD IN "ACTIVE" OR "PHYSICAL"
STD POTENCY DEF. DEFAULT POTENT VALUE
PHYS U/M FOR "ACTIVE" INV. METHOD
WT TO WT FACTOR FOR ALLOCATION OF FILLER
Page 32
Parent
Child Child
MXB, 1998
Child
Child/Parent
Qty Req'd
Make, Buy, Phantom, Feature, Planner
Make, Phantom, Model, Feature, Planner
By-Product
Seq. No.Qty Req'dEff. DatesOperationBkflshStageTypeECNBalloon #Plan/Cost %PotencyTextLine Init.
Product Structure Definition
Page 34
Product Structure
Product Structure Maintenance
(PS0021, PSPSP100)
DEFINES COMPONENT TO PARENT RELATIONSHIP
STATES THE ENGINEERING, MANUFACTURING AND
BASE QUANTITY REQUIRED
INDICATES IF COMPONENT IS SUBSTITUTE OR
OPTIONAL
DESIGNATES IF COMPONENT IS A BY-PRODUCT
INDICATES EFFECTIVE DATES OF COMPONENT AND
ECN NUMBER WHICH CAUSES THE CHANGE
INDICATES THE FIRST OPERATION OF THE ROUTER
THAT COMPONENT IS USED
ALLOWS BALLOON NUMBER FOR DESIGNATION AND
SORTING
IDENTIFIES AND ALLOWS MAINTENANCE OF
PRODUCTION AND ENGINEERING TEXT
INDICATES IF COMPONENT IS ACTIVE, FILLER ORNOT
DEFINES ALLOWABLE RANGE OF POTENCY FOR
INVENTORY ALLOCATION
Page 35
Product Structure
Product Structure Maintenance
(PS0021)
DESIGNATES THE STANDARD POTENCY
DESIGNATES IF COMPONENT IS USED BY
CONSOLIDATED PICK
DESIGNATES IF BACKFLUSH ISSUES TRANSACTIONS
OCCUR AND WHERE THEY OCCUR FROM
SPECIFIES QUANTITY TO INITIALIZE IN LINE
INITIALIZATION
Page 36
Master Production Scheduling
Master Production Schedule
Material Requirements Plan
Scheduling
Workbench
by
Production
Line
Work Order/
FPOMaintenance
Pick SlipPrint
Stage Request
Consolidated
Pick
SHOP
FLOOR
CONTROL
Soft BillMaintenance
Auto Allocation to
Lots
RMS/TeachkitPage 39
Forecast
Customer Orders
Customer Service Levels
Distribution Replenishment
The Production Planning Process
Determine Demand
Consider Pending Supply
Consider Inventory
Determine Net Demand
Propose Supply
Test Against Resources
Adjust
Commit to Plan
Execute Schedule
Master Production Scheduling Generation
Rough Cut Capacity Planning
Management Decision
Shop Floor Control
MXB, 2000
Page 40
Master Production Scheduling
Major Features
ForecastingInput of a Shipment Forecast
FIRM OR SPECULATIVE DESIGNATIONMPS only recognizes Firm Forecasts
PLANNER BILL EXPLOSION
Generation of end item forecasts based on a parentand percentage relationships
Master Production SchedulingDetermination and commitment to build plan
DEMAND SOURCE MANAGEMENT
MPS GENERATION
AUTO ACCEPT COMBINED DEMAND PRODUCTS
AUTO ACCEPT BY TIME FENCE
MULTI LEVEL MPS FOR BUILD TO ORDER
MPS ORDER PURGE
AVAILABLE TO PROMISE INQUIRY
Page 42
Entering Demand
Shipment Forecasts
Forecasts Can be Entered orGenerated
Entering Forecasts
FORECAST MAINTENANCE (MP0100)
PRODUCT
BEG.DATE
ENDDATE FIRM? QUANTITY
Widget
10/1/99 10/31/99 Y 1000
Only Firm Forecasts are Recognized by MPS Generation
Quantity Expected to Ship between the Beginning Date and End Date
SMOOTHED FORECASTIf October has 20 Shop Days, forecasted shipmentschedule of 50 per day
LUMPY FORECASTForecasted shipment of 1000 on October 1
Page 44
Each one of our RMS/Teachkit courses and training presentations are available for your selection.Choose the full color, 'Present' format for self-review or your presentation document for the class throughyour projection system. If you would like to print student manuals, select '+ Print' format. In addition toreceiving the 'Present', you will receive an additional file specifically configured and optimized fortwo-sided student workbook production. Submit to your own laser printer or send outside. If you prefer,you can choose the 'Present' format only and order the student manuals from us! All our printing is crisp,laser printing, two-sided, soft bound and delivered on time 100% of the time.
Present + Print Present + Print
Education & Reference
General ManufacturingWelcome to PRMS 99.00 199.00 Product Definition 199.00 349.00
PRMS Overview 199.00 349.00 Manufacturing Planning 199.00 349.00
Version 9 Enhancements 99.00 199.00 Shop Floor Control 199.00 349.00
'Canned' Reports & Inquiries 99.00 199.00 Router Training 149.00 299.00
Distribution InventoryForecasting Workbench 149.00 299.00 Inventory Control 99.00 199.00
Customer Order Processing 199.00 349.00 Cycle Count & Phys. Inv. 99.00 199.00
Order Entry Training 149.00 299.00 Lot Control 99.00 199.00
RGA's & C/D Memos 149.00 299.00 FinancialReplenishment Orders 99.00 199.00 Standard Costing 149.00 299.00
Purchasing & Receiving 199.00 349.00 Accounts Payable 149.00 299.00
Online TutorialsThe Keyboard & PRMS 99.00 Navigating PRMS 99.00
Purchasing Overview 99.00 Requisition Processing 99.00
Measuring ExecutionPerformance 99.00
Contact us: [email protected] u.s.800-304-5914, 520-886-5914, fax 520-298-5525