Upload
linus-irwin
View
48
Download
0
Tags:
Embed Size (px)
DESCRIPTION
Princeton University External Independent Review (EIR) of NCSX March 13-14, 2008 Cost and Schedule Ron Strykowsky. Topics. Cost, Schedule and Contingency Development Process Basis and Assumptions Contingency Cost Summary Schedule Summary Cost Profile Staffing EIR Summary Assessment. - PowerPoint PPT Presentation
Citation preview
Strykowsky 1PU External Independent Review March 13-14, 2008
Princeton UniversityExternal Independent Review (EIR)
of
NCSX
March 13-14, 2008
Cost and Schedule
Ron Strykowsky
Strykowsky 2PU External Independent Review March 13-14, 2008
Topics
• Cost, Schedule and Contingency Development Process
• Basis and Assumptions
• Contingency
• Cost Summary
• Schedule Summary
• Cost Profile
• Staffing
• EIR Summary Assessment
Strykowsky 3PU External Independent Review March 13-14, 2008
Process of Establishing a New Project Baseline
• Job Managers Reviewed and Updated WAF’s (realistic not best case)•Additional scope per August Lehman review recommendations•Critically reviewed all job estimates to reflect current design maturity & experiences to date
• Internal Engineering Department Review for Critical and Large Job Estimates• Updated overhead and labor rates• Updated resource Loaded Schedule
•Focus on critical path optimization•Off critical path scope (maximize free float)•Fit Program funding targets
• Expanded and quantified project risks• Contingency analysis process (probabilistic approach)• March 13-14 PU Review• Follow-up actions complete data processing and analysis• Final Updates, Packaging, Documentation• Submit New Baseline Proposal to OFES March 26• Office of Science Review April 8-10• Submit Baseline Change Proposal to OECM April 21• External Independent Review May 20-22
•The WAF’s are the basis of all estimates•The resource loaded schedule is the master schedule and cost estimate data base
Strykowsky 4PU External Independent Review March 13-14, 2008
Refined Estimating packages (table 1 of 6)
Table 1 - Work Approval Form
Strykowsky 5PU External Independent Review March 13-14, 2008
Refined Estimating packages (table 2 of 6)
Table 2 - Design
Strykowsky 6PU External Independent Review March 13-14, 2008
Refined Estimating packages (table 3 of 6)
Materials and Procurements
Strykowsky 7PU External Independent Review March 13-14, 2008
Refined Estimating packages (table 4 of 6)
Fabrication and Assembly
Strykowsky 8PU External Independent Review March 13-14, 2008
Refined Estimating packages (table 5 of 6)
Estimate Uncertainty and Risk
Strykowsky 9PU External Independent Review March 13-14, 2008
Refined Estimating packages (table 6 of 6)
Basis of estimate
Strykowsky 10PU External Independent Review March 13-14, 2008
Key Planning Basis and Assumptions
• ETC forward from February 1st, 2008• Cost Incurred from April 1, 2003 (MIE project inception)
• Every Job Reviewed, most re-estimated• GPP and Infrastructure not part of MIE project. (Progress coordinated and
tracked by Erik Perry)
• Program BA constraints • Institutional Overhead Rates (CAS Compliant)
• Standard work week 8 hrs/day 5 days/week (Exceptions: Field period assy
(sta3 FPA#3, station 5, and Final Machine assy make use of select 2 shift operations). No
overtime or Saturday work planned.
• Holidays• Contingency Allocation by fiscal year (commensurate with risk & cost
uncertainty)
• Task durations - more detail on critical path and near term
Strykowsky 11PU External Independent Review March 13-14, 2008
• Based on deliverables and/or tasks identified by the job managers• Input varied from resource loaded schedules to deliverables and resource
estimate only
• Established tasks, internal milestones (PDR’s, FDR’s, contract awards)
• Task durations based on realistic resource loadings & crew sizes
• Logically linked (2,170 tasks, 2900 individual resource loadings)
• Non-critical path tasks scheduled within BA constraints with free
float to critical path
• Schedule iterated based on• Optimizing the critical path. (use of 2 shift operations, floor space for
assembly tasks, metrology/back-office support, crane utilization studies)
• Maximizing free float for non critical path tasks (ie procurements)
• Front end loading system designs
• Annual contingency set-asides
• Resource leveling exercises to optimize techs and key engineers (did not
impact critical path or cost)
Scheduling - Process
Strykowsky 12PU External Independent Review March 13-14, 2008
Cost Basis - Resource types and Rates
• Resource Types, labor and overhead rates
Overhead and escalation rates
Labor Skills (hourly rates)
Non-Labor Resource
Strykowsky 13PU External Independent Review March 13-14, 2008
Contingency - Process
• Structured process - probabilistic risk analysis based (Monte Carlo Analysis)
• Objective was to assess and analyze all areas of uncertainty and risk that
might affect the cost and schedule estimates
• Project Risk Registry key input (grown from 36 to 88 risks & monitored monthly)
• Job Manager and Project Team input
• Cost and schedule contingencies quantified
• Contingency Allowance Range - 90% and 80% confidence levels analyzed
Chris Gruber to provide comprehensive analysis
Strykowsky 14PU External Independent Review March 13-14, 2008
Contingency – Results
•Need to finalize our contingency proposal going forward•Use 90% confidence case for preliminary analysis being presented
Strykowsky 15PU External Independent Review March 13-14, 2008
Results –Cost Reconciliation
NCSX Project TEC Budget Reconciliation
WBS
Baseline (ECP-31 DOE
Directed re-baseline April
2005)EAC JUNE
2007Increase from
April 2005ETC from 2/1/08
Proposed Baseline EAC MARCH 2008
Increase from June 2007
Total increase
from April 2005
12 Vacuum Vessel $9,531 $9,909 $378 4% $1,356 $11,099 $1,190 12% $1,568 16%13 Conventional Coils $4,790 $6,686 $1,896 40% $4,472 $8,302 $1,616 24% $3,512 73%14 Modular Coils $28,091 $40,447 $12,356 44% $2,636 $40,808 $361 1% $12,716 45%15 Structures $1,413 $1,602 $189 13% $1,569 $2,119 $517 32% $706 50%16 Coil Services $1,140 $864 -$276 -24% $1,141 $1,144 $280 32% $4 0%17 Cryostat & Base Support
Structure$1,361 $1,215 -$146 -11% $1,069 $1,558 $343 28% $197 14%
18 Field Period Assembly $5,430 $13,573 $8,143 150% $14,564 $20,104 $6,531 48% $14,674 270%19 Stellarator Core Mgmt & Integr $2,752 $3,748 $996 36% $2,259 $4,576 $828 22% $1,824 66%1 Stellarator Core $54,508 $78,045 $23,536 43% $29,066 $89,710 $11,665 15% $35,201 65%2 Auxiliary Systems $783 $589 -$194 -25% $828 $1,176 $587 100% $393 50%3 Diagnostics $1,143 $1,671 $528 46% $815 $1,946 $274 16% $802 70%4 Electrical Power Systems $3,301 $3,145 -$156 -5% $2,674 $3,289 $144 5% -$12 0%5 I&C Systems $2,050 $1,169 -$881 -43% $2,097 $2,130 $961 82% $80 4%6 Facility Systems $691 $1,403 $712 103% $1,838 $1,862 $459 33% $1,171 169%7 Test Cell Prep & Machine $4,413 $8,914 $4,501 102% $8,586 $9,294 $380 4% $4,881 111%81 Project Management and
Oversight$4,509 $7,714 $3,206 71% $5,568 $9,593 $1,879 24% $5,085 113%
82 Project Engineering $4,885 $11,198 $6,314 129% $7,631 $14,131 $2,933 26% $9,246 189%84 Project Physics $470 $470 $0 0% $470 $0 0% $0 0%85 Integrated Systems Testing $1,189 $765 -$424 -36% $771 $771 $6 1% -$418 -35%8 Project Oversight & Support $11,052 $20,147 $9,095 82% $13,970 $24,965 $4,818 24% $13,913 126%
Allocations $1,577 $2,874 $1,296 82% $1,867 $3,659 $785 27% $2,082 132%
Subtotal $79,521 $117,957 $38,436 48% $61,741 $138,031 $20,074 17% $58,509 74%
Contingency $12,804 ### $14,380 28% on ETC $23,670 38% on ETC (90% confidence)DCMA $75 $75 $75
TOTAL $92,401 $132,412 $40,011 43% $61,741 $161,776 $29,364 22% $69,375 75%
Planned Finish = Feb-09 Jan-11 23 mo. Increase Dec-11 10.4 mo. Increase 33.5 mo. IncreaseCD-4 = Jul-09 Dec-11 29 mo. Increase Jul-13 18.8 mo. Increase 47.8 mo. IncreaseSchedule Contingency = 5 mo. 11 mo. 19.4 mo. (90% confidence)
Strykowsky 16PU External Independent Review March 13-14, 2008
Cost growth by category
August 2007 (ETC from
5/1/07)
March 2008 (ETC from
5/1/07)Increase ($K)
CorrectionsDesign Maturity
Risk Reduction
New Scope
Schedule Stretch
12 Vacuum Vessel $156 $1,346 $1,190 100%13 Conventional Coils $3,462 $5,077 $1,615 100%14 Modular Coils $6,246 $6,608 $397 50% 50%15 Structures $1,262 $1,779 $517 50% 25% 25%16 Coil Services $861 $1,141 $280 100%17 Cryostat & Base Suprt Structure $784 $1,127 $343 100%18 Field Period Assembly $10,104 $16,636 $6,522 32% 23% 16% 10% 19%19 Stellarator Core Mgmt & Integr $1,620 $2,444 $824 45% 55%
2 Auxiliary Systems $241 $828 $587 100%3 Diagnostics $717 $991 $274 100%4 Electrical Power Systems $2,425 $2,569 $144 100%5 I&C Systems $1,136 $2,097 $961 100%6 Facility Systems $1,379 $1,838 $459 50% 50%7 Test Cell Prep & Machine Assy $7,951 $8,331 $380 36% 64%
81 Project Management and Oversight
$5,795 $8,460 $2,665 70% 30%82 Project Engineering $5,949 $8,880 $2,931 30% 10% 25% 15% 20%85 Integrated Systems Testing $765 $771 $6 100%
$50,853 $70,924 $20,096 18% 15% 20% 30% 17%New Scope,
30%
Risk Reduction,
20%
Design Maturity, 15%
Corrections, 18%
Schedule Stretch, 17%
Strykowsky 19PU External Independent Review March 13-14, 2008
Results – Cost by RLM and Job (con’t)
LOE NON-LOE
$ % $ % ETC (bottoms-up) from 2/1/08
WBS 81 7,435 100% - 0% 7,435
WBS 82 7,342 96% 289 4% 7,631
WBS 19 2,255 100% - 0% 2,255
WBS 18/7 Field supervision,oversight & support
7,494 100% 0% 7,489
Balance 3,894 11% 33,027 89% 36,927
TOTAL 28,420 46% 33,317 54% 61,737
LOE budgeting applies mainly to management, supervision, & technical support functions-basis of estimates shown in WAF’s.
Strykowsky 20PU External Independent Review March 13-14, 2008
Results – Program BA Profile
FUNDING PROFILE2003-07 2008 2009 2010 2011 2012 2013
target = 16.6 20.3 20.8 38.7 52.3 52.8
NCSX Program by Activity 16.7 20.3 20.8 38.7 57.6 52.8 Research 0.7 0.7 0.7 2.5 16.5 17.0 TEC EAC
MIE Project 74.2 16.0 19.6 20.1 21.6 10.2 - 161.8
Operations - - - 14.6 30.9 35.8 Facility Ops - - - 4.5 11.0 22.8
Facility Upgrades - - - 9.0 13.3 9.0 Diagnostic Upgradess - - - 1.1 6.6 4.0
MIE Project by Institution 72.5 16.0 19.6 20.1 21.6 10.2 - contingency included in total line - 2.5 3.7 9.4 8.2
PPPL 1.6 14.1 18.2 19.1 20.7 4.7 - ORNL 0.2 1.8 1.4 1.0 0.9 0.2
carryover
•Delayed research start•Schedule requires further iteration to improve contingency distribution
Strykowsky 21PU External Independent Review March 13-14, 2008
Results – Schedule (Summary)
•Critical path through field period assembly, final machine assembly and start-up operations•Major procurement of components as well as ancillary system have ample schedule margin (months off critical path)
Stellarator Core Critical Procurements Schedule Margin
job Procurement
Estimated Fabrication Lead Time
Months off critical path
schedule margin
1260 Neutral Beam Transition Ducts 12 10 83%1270 Heater control system 12 7.4 62%1361 TF Coils (10 left) 7.5 23.2 309%1352 PF Coils 16.5 14 85%1354 Trim Coils 6 10 167%1353 Central Solenoid Support structure 6 7 117%1550 Coil Support Structure 5 7 140%1451 Last Modular Coil (3 reminaining) 8 5 63%1601 Coil Services -Lead stubs & LN manifolds 4.3 9.3 216%1601 Coil Services -Cables 6 21 350%1752 Base Support Structure 8 8.1 + 101%1751 Cryostat 9.3 8.1+ 87%1803 Station 5 Fixtures 5 10 200%1803 Station 6 Fixtures 7 9 129%
Strykowsky 22PU External Independent Review March 13-14, 2008
Results – Milestones
• Milestones provide good metric of schedule progress• Distribution of milestones reasonable• Must still set DOE dates by adding schedule contingency
Strykowsky 23PU External Independent Review March 13-14, 2008
Results – Resource Loaded Schedule
Resource skill and hours (from
WAF)
Cost (= hours x rates)
Total float in working days (~1 month = 21 days)Planning assumption: 1
shift per day or 2 shifts per day
Strykowsky 24PU External Independent Review March 13-14, 2008
Staffing Requirements- Technicians
• Staffing requirements achievable and being satisfied
TFTR D&D manpower profile for comparison
Strykowsky 25PU External Independent Review March 13-14, 2008
Future needs achievable with new hires to provide depth & backup
TOTAL DESIGNERS
0
1
2
3
4
5
6
7
8
9
10
FEB FY08
APR FY08
JUN FY08
AUG FY08
OCT FY09
DEC FY09
FEB FY09
APR FY09
JUN FY09
AUG FY09
OCT FY10
DEC FY10
FEB FY10
APR FY10
JUN FY10
AUG FY10
OCT FY11
DEC FY11
FEB FY11
APR FY11
JUN FY11
AUG FY11
OCT FY12
staff as of August 2007 = 8
current staff = 10
TOTAL EA Engineers
0
2
4
6
8
10
12
14
16
18
FEB F
Y08
APR F
Y08
JUN F
Y08
AUG F
Y08
OCT F
Y09
DEC F
Y09
FEB F
Y09
APR F
Y09
JUN F
Y09
AUG F
Y09
OCT F
Y10
DEC F
Y10
FEB F
Y10
APR F
Y10
JUN F
Y10
AUG F
Y10
OCT F
Y11
DEC F
Y11
FEB F
Y11
APR F
Y11
JUN F
Y11
AUG F
Y11
OCT F
Y12
TOTAL Electrical ENGINEERS
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
18
19
FEB F
Y08
MAR F
Y08
APR F
Y08
MAY F
Y08
JUN F
Y08
JUL
FY08
AUG F
Y08
SEP F
Y08
OCT F
Y09
NO
V FY09
DEC F
Y09
JAN F
Y09
FEB F
Y09
MAR F
Y09
APR F
Y09
MAY F
Y09
JUN F
Y09
JUL
FY09
AUG F
Y09
SEP F
Y09
OCT F
Y10
NO
V FY10
DEC F
Y10
JAN F
Y10
FEB F
Y10
MAR F
Y10
APR F
Y10
MAY F
Y10
JUN F
Y10
JUL
FY10
AUG F
Y10
SEP F
Y10
OCT F
Y11
NO
V FY11
DEC F
Y11
JAN F
Y11
FEB F
Y11
MAR F
Y11
APR F
Y11
MAY F
Y11
JUN F
Y11
JUL
FY11
AUG F
Y11
SEP F
Y11
OCT F
Y12
NO
V FY12
current staff = 19
staff as of August 2007 = 18
TOTAL EA Engineers
0
2
4
6
8
10
12
14
16
18
F
EB
FY
08
M
AR
FY
08
A
PR
FY
08
M
AY
FY
08
JU
N F
Y08
JU
L F
Y08
A
UG
FY
08
S
EP
FY
08
O
CT
FY
09
N
OV
FY
09
D
EC
FY
09
JA
N F
Y09
F
EB
FY
09
M
AR
FY
09
A
PR
FY
09
M
AY
FY
09
JU
N F
Y09
JU
L F
Y09
A
UG
FY
09
S
EP
FY
09
O
CT
FY
10
N
OV
FY
10
D
EC
FY
10
JA
N F
Y10
F
EB
FY
10
M
AR
FY
10
A
PR
FY
10
M
AY
FY
10
JU
N F
Y10
JU
L F
Y10
A
UG
FY
10
S
EP
FY
10
O
CT
FY
11
N
OV
FY
11
D
EC
FY
11
JA
N F
Y11
F
EB
FY
11
M
AR
FY
11
A
PR
FY
11
M
AY
FY
11
JU
N F
Y11
JU
L F
Y11
A
UG
FY
11
S
EP
FY
11
O
CT
FY
12
N
OV
FY
12
current staff = 18
staff as of August 2007 = 16
TOTAL FO&M ENGINEERS
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
FEB F
Y08
MAR F
Y08
APR F
Y08
MAY F
Y08
JUN F
Y08
JUL
FY08
AUG
FY08
SEP F
Y08
OCT F
Y09
NO
V FY09
DEC F
Y09
JAN F
Y09
FEB F
Y09
MAR F
Y09
APR F
Y09
MAY F
Y09
JUN F
Y09
JUL
FY09
AUG
FY09
SEP F
Y09
OCT F
Y10
NO
V FY10
DEC F
Y10
JAN F
Y10
FEB F
Y10
MAR F
Y10
APR F
Y10
MAY F
Y10
JUN F
Y10
JUL
FY10
AUG
FY10
SEP F
Y10
OCT F
Y11
NO
V FY11
DEC F
Y11
JAN F
Y11
FEB F
Y11
MAR F
Y11
APR F
Y11
MAY F
Y11
JUN F
Y11
JUL
FY11
AUG
FY11
SEP F
Y11
OCT F
Y12
NO
V FY12
TOTAL FO&M ENGINEERS
0
1
2
3
4
5
6
7
8
9
10
11
12
13
14
15
16
17
FEB F
Y08
MAR F
Y08
APR F
Y08
MAY F
Y08
JUN F
Y08
JUL
FY08
AUG
FY08
SEP F
Y08
OCT F
Y09
NO
V FY09
DEC F
Y09
JAN F
Y09
FEB F
Y09
MAR F
Y09
APR F
Y09
MAY F
Y09
JUN F
Y09
JUL
FY09
AUG
FY09
SEP F
Y09
OCT F
Y10
NO
V FY10
DEC F
Y10
JAN F
Y10
FEB F
Y10
MAR F
Y10
APR F
Y10
MAY F
Y10
JUN F
Y10
JUL
FY10
AUG
FY10
SEP F
Y10
OCT F
Y11
NO
V FY11
DEC F
Y11
JAN F
Y11
FEB F
Y11
MAR F
Y11
APR F
Y11
MAY F
Y11
JUN F
Y11
JUL
FY11
AUG
FY11
SEP F
Y11
OCT F
Y12
NO
V FY12
current staff = 17
staff as of August 2007 = 14
Staffing Requirements- Engrs & Designers
Strykowsky 26PU External Independent Review March 13-14, 2008
Metrology staff
0
2
4
6
8
10
FEB F
Y08
APR F
Y08
JUN F
Y08
AUG F
Y08
OCT F
Y09
DEC F
Y09
FEB F
Y09
APR F
Y09
JUN F
Y09
AUG F
Y09
OCT F
Y10
DEC F
Y10
FEB F
Y10
APR F
Y10
JUN F
Y10
AUG F
Y10
OCT F
Y11
DEC F
Y11
FEB F
Y11
APR F
Y11
JUN F
Y11
AUG F
Y11
OCT F
Y12
ORNL Engrs/Designers
0
2
4
6
8
10
FEB F
Y08
APR F
Y08
JUN F
Y08
AUG F
Y08
OCT F
Y09
DEC F
Y09
FEB F
Y09
APR F
Y09
JUN F
Y09
AUG F
Y09
OCT F
Y10
DEC F
Y10
FEB F
Y10
APR F
Y10
JUN F
Y10
AUG F
Y10
OCT F
Y11
DEC F
Y11
FEB F
Y11
APR F
Y11
JUN F
Y11
AUG F
Y11
OCT F
Y12
Staffing Requirements- ORNL & Metrology
Strykowsky 27PU External Independent Review March 13-14, 2008
EIR Summary Assessments
1. Resource loaded Schedule• Organized by WBS (refer to WBS and WBS Dictionary)• Resource estimate loading based on detail WAF packages signed
by Job managers. (see detailed WAF packages)• Estimates based on prior experience, vendor quotes, fabrication
estimates, design calculations. Basis of estimates include in WAF’s. (requires analysis and verification of resource loading)
• Task durations based on realistic manpower loadings and crew sizes. Balance of task durations based on reasonable loadings Schedule detail commensurate with schedule criticality (e.g. wbs 18 job 1810. minimum task duration 1 day).
• Proposed baseline BCWS and contingency profile consistent with anticipated funding levels.
• Shows estimate detail and priced cost estimate (see resource loaded schedule)
Strykowsky 28PU External Independent Review March 13-14, 2008
EIR Summary Assessments (continued)
2. Key Project Cost and Schedule Assumptions
• Standard 8 hour/day 5 day/week work assumed except where 2 shift operations called out in resource loaded schedule. (see slide 10)
• Institutional overhead and labor rates utilized (see slide 11)• Contingency quantified based on estimate uncertainty and risk
using Monte Carlo simulation plus a subjective increment based on project management experience. (see slides 12 & 13 and detailed contingency analysis)
• Contingency distributed annually consistent with needs. (NO -WORK IN PROGRESS).
Strykowsky 29PU External Independent Review March 13-14, 2008
EIR Summary Assessments (continued)
3. Critical Path
• See critical path plot on wall • See detail Primavera predecessor & successor report for logic
linkages
4. Funding Profile
• Project proposed baseline consistent with preliminary guidance (see slide 17)
5. Work Breakdown Structure
• Resource loaded schedule is organized by WBS (see WBS and WBS Dictionary)
Strykowsky 30PU External Independent Review March 13-14, 2008
SUMMARY
• Project has followed a disciplined path for updating its cost and
schedule estimates highlighted by;• Formal & consistent basis of estimate
• Independent reviews by PPPL engineering and PU
• Focus on obtaining realistic estimates from job managers
• Project has followed a methodical process for quantifying cost as
well as schedule contingency.
• Project has expanded its risk registry and incorporated into monthly
status review meetings
• Project has proposed a sound baseline cost estimate backed-up by
a resource loaded schedule and detailed estimate basis.
• Completion of data analysis and verification of resource loaded
schedule required to ensure completeness
Strykowsky 32PU External Independent Review March 13-14, 2008
DETAILED STAFFING BACKUP
Analysts/Mechanical Engineers (EA)
Strykowsky 33PU External Independent Review March 13-14, 2008
DETAILED STAFFING BACKUP
Electrical and FO&M Engineers