7
Prince William Sound Regional Citizen’s Advisory Committee Board Meeting May 4, 2007

Prince William Sound Regional Citizen’s Advisory Committee Board Meeting May 4, 2007

Embed Size (px)

Citation preview

Page 1: Prince William Sound Regional Citizen’s Advisory Committee Board Meeting May 4, 2007

Prince William SoundRegional Citizen’s Advisory Committee

Board MeetingMay 4, 2007

Page 2: Prince William Sound Regional Citizen’s Advisory Committee Board Meeting May 4, 2007

Health, Safety & Environment

Safety VMT 1Q 2007

Days Away From Work Cases

0

Recordable 0

Environment VMT 1Q 2007

Spill Volume 3.03

Number of Spills 6

Page 3: Prince William Sound Regional Citizen’s Advisory Committee Board Meeting May 4, 2007

2007 VMT Major Focus Areas

• Safety– Process Safety Management– LPS– Trend analysis– Integration of “Lessons Learned”

• 90s Tank – Vapor Recovery System• Tank 55 and Tank 56• East Tank Farm – Internal Tank Inspections• Allison Creek turbidity• 2007 Corrosion Action Plan

Page 4: Prince William Sound Regional Citizen’s Advisory Committee Board Meeting May 4, 2007

2007 VMT Projects

• BWT Vapor Recovery• BWT Pilot Studies• Tank Program• Corrosion• Main Gate

Page 5: Prince William Sound Regional Citizen’s Advisory Committee Board Meeting May 4, 2007

Ballast Water Treatment Renovation Program

• Completed the installation of the Biological Treatment Tank (BTT) recycle pump  – Currently undergoing the Functional Check Out phase

• Completed the final hookup to the Dissolved Air Floatation (DAF) BETX analyzer  – Currently undergoing the Functional Check Out phase.

• Initiated testing on the Phase Extraction Technology (PET) air stripper pilot unit -  Testing is ongoing

• Initiated testing on the PhotoCat pilot unit  – The unit is offline awaiting resolution of reliability issues before further

testing resumes • Advanced the work on the oil/water analyzer and new DAF and BTT

sump re-route work -  Project not yet completed • Continued working to install new Dissolved Oxygen and Salinity

probes throughout the BWT processes - Project on-going • Completed the tank 80 headspace nitrogen inerting system

Page 6: Prince William Sound Regional Citizen’s Advisory Committee Board Meeting May 4, 2007

VMT Operational Status

• BWT Tank 92 Spill– Temporary patch installed– Root Cause Analysis completed, and under review

• Smoking incident– Safety Stand-downs conducted– Investigation conducted

• Hydrotek steam cleaner incident– Investigation in process

• Otter Hospital– Set up completed in 48 hours; C-Plan compliance

requires 72 hours

Page 7: Prince William Sound Regional Citizen’s Advisory Committee Board Meeting May 4, 2007

VMT Operational Status Continued

• Power/Vapor “B” Boiler – Corrosion discovered during scheduled inspection– Extent of condition under evaluation

• The east potable water plant and VFF are fully operational– High turbidity from Allison Creek from the 2006 Flood

impacted the operation

• Berth 4 and Berth 5 quarterly maintenance was completed

• Fierce Conversations training