Upload
korede-akinseye
View
15
Download
0
Tags:
Embed Size (px)
Citation preview
Why use a formal Project Management Method?
A piece of work which is directed toward producing some deliverable, 'value added' outcome
What is a Project?
Why use a formal Project Management Method?
A piece of work which is directed toward producing some deliverable, 'value added' outcome
To try to ensure that the project is completed on time and within budget
What is a Project?
What can go wrong?
Those who manage a project and those who work on it may have different ideas and agenda's
For a project to succeed all parties need to be clear about why the Project is needed, what it is intended to achieve, how the outcome isTo be measured, and what their responsibilities are.
Existing management structures will NOT have this capability built inSo unmanaged projects almost invariably go overtime and budget.
Characteristics of a Prince2 project
•Finite lifespan
•Defined / measurable business products
•Activities to achieve products
•Defined resources
•Organisational structure
•ComponentsA system of organisation, a business case, plans etc.
•ProcessesPlanning, controlling a stage, managing product delivery etc.
•Techniques'Quality review', 'Change Control','Product Based Planning'.
Common elements of any project according to Prince2
•ComponentsA system of organisation, a business case, plans etc.
•ProcessesPlanning, controlling a stage, managing product delivery etc.
•Techniques'Quality review', 'Change Control','Product Based Planning'.
Common elements of any project according to Prince2
The 'Environment' of the project
Imagine the project is to bake a cake.
The 'cake project' is not run just 'for the sake of it'.
At least three groups of people will have an interest;
The suppliers of raw materials
The 'Owners' of the cake shop
The 'Users'
The 'Environment' of the project
The representatives of this group make up the 'Project Board'
Senior Supplier Executive Senior User
Accountable to the 'Project Board' is the 'Project Manager'
Senior Supplier Executive Senior User
Project Manager
Project Manager
Accountable to the 'Project Manager' are 'Teams' or 'Team Managers'
Project Team
Quality standards.Product Delivery incl; progress, risk, change, timeProduct based plans and work packagesReports to Project Board
Produces work packagesReports to Project Manager
strategy Problem
Corporate or programme management
Project Brief
Project Board
Snr Supplier Executive Snr User
Project Manager
Project Team(s)
The key role of the Project Board
•The board only meets when necessary, management is 'by exception'.•The board provides the Project Plan.• Gives ‘next stage authorisation’.•The Board must assess and authorise each stage and providea 'Post Project Review'.
Controlled Progress – the ‘stages’
Stages in Price2 are the points where the ‘products’ that make up The project are delivered.
The number of stages will depend upon the cost, complexity and risks.
Controlled Progress – the ‘stages’
•Stages provide a ‘firebreak’ for decision making.
•Facilitate control
•Facilitate staff changes
•Facilitates accurate estimation of progress
Stages in Price2 are the points where the ‘products’ that make up The project are delivered.
The number of stages will depend upon the cost, complexity and risks.
Stages are defined in the ‘Project Initiation Document (PID). This isA vital piece of paper and needs to be safely stored.
It says; what, who, how, when, and very importantly, the limit oftolerance based on the business case.
Controlled Progress – the ‘stages’
Stages also allow a ‘Controlled Close’ to the project.
Controlled Progress – the ‘stages’
•End Project Notification•Lessons Learned Report•Follow-on recommendations•End Project Report•Post Project Review
•All Products delivered•Support organised•Statistics passed on•Benefits realised
SuccessFailure
Product Based Planning
The first step is ‘Product Breakdown Structure’. Breaking down a product into it’s constituent sub-products help to identify and clarify all the worknecessary for it’s creation.
There are two sorts of product;
Management Products
Specialist Products
Moved Shed
1. Old Shed 4. Re-Assembled Shed
3. New Requirements
2. Dismantled Shed
Product Based Planning --- Example PBS
4.1ShedDimensions
3.1 New Pieces
2.1 Rotten Pieces
2.2 Re-Usable Pieces
3.2 Transported Pieces
4.2 New PieceRequirements
4.3Prepared Site
4.4New Fixtures & Fittings.
4.5 Fixtures & Fittings List
Moved Shed
1. Old Shed 4. Re-Assembled Shed
3. New Requirements
2. Dismantled Shed
Product Based Planning --- Example PBS
4.1ShedDimensions
3.1 New Pieces
2.1 Rotten Pieces
2.2 Re-Usable Pieces
3.2 Transported Pieces
4.2 New PieceRequirements
4.3Prepared Site
4.4New Fixtures & Fittings.
4.5 Fixtures & Fittings List
Moved Shed
1. Old Shed
Product Based Planning --- Example PFD
4.1ShedDimensions
3.1 New Pieces
2.1 Rotten Pieces 2.2 Re-Usable
Pieces
3.2 Transported Pieces
4.2 New PieceRequirements
4.3Prepared Site
4.4New Fixtures & Fittings.
4.5 Fixtures & Fittings List
Product Based Planning
Each stage will correspond with the delivery of one or more products.
The delivery of the products, as previously explained, will never Overlap the stage boundaries.
Having identified the products using a PBS and the order in which the Products must be delivered using a PFD, an activity table must be drawn Up.
Product Based Planning
Activities are passed on the the Project Teams as work packages.
The plans are passed to the Project Board for approval.
Two, final planning functions are risk assessment and the establishment Of acceptable tolerance.
Completion of a plan would mean;1. Finalising the text2. Agreeing tolerance levels