Presenting a silent installation method for offshore foundation piles Supported by:

Presenting a silent installation method for offshore ... · 1: Report by the European Wind Energy Association (EWEA), August 2015 0 2000 4000 6000 8000 10000 12000 14000 16000 18000

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Presenting a silent installation method for offshore ... · 1: Report by the European Wind Energy Association (EWEA), August 2015 0 2000 4000 6000 8000 10000 12000 14000 16000 18000

Presenting a silent installation method for offshore foundation piles

Supported by:

Page 2: Presenting a silent installation method for offshore ... · 1: Report by the European Wind Energy Association (EWEA), August 2015 0 2000 4000 6000 8000 10000 12000 14000 16000 18000

2

Page 3: Presenting a silent installation method for offshore ... · 1: Report by the European Wind Energy Association (EWEA), August 2015 0 2000 4000 6000 8000 10000 12000 14000 16000 18000

Growing Market for EU Offshore Windturbines

3 1: Report by the European Wind Energy Association (EWEA), August 2015

0

2000

4000

6000

8000

10000

12000

14000

16000

18000

2016 2018 2020 2022 2024 2026 2028 2030 2032

Nu

mb

er o

f win

d t

urb

ines

inst

alle

d o

ffsh

ore

Year

EWEA prediction of installed wind turbines in EU water by 20301

Low Scenario Mid Scenario High Scenario

300/year

600/year

1000/year

Page 4: Presenting a silent installation method for offshore ... · 1: Report by the European Wind Energy Association (EWEA), August 2015 0 2000 4000 6000 8000 10000 12000 14000 16000 18000

4

Page 5: Presenting a silent installation method for offshore ... · 1: Report by the European Wind Energy Association (EWEA), August 2015 0 2000 4000 6000 8000 10000 12000 14000 16000 18000
Page 6: Presenting a silent installation method for offshore ... · 1: Report by the European Wind Energy Association (EWEA), August 2015 0 2000 4000 6000 8000 10000 12000 14000 16000 18000

The problems with conventional piling methods

6

2. Long installation times

3. Fatigue damage

1. High underwater noise levels

Page 7: Presenting a silent installation method for offshore ... · 1: Report by the European Wind Energy Association (EWEA), August 2015 0 2000 4000 6000 8000 10000 12000 14000 16000 18000

Introducing the GBM Vibro-Drill

7

2. Faster installation

3. No fatigue damage

1. No underwater noise The GBM Vibro-drill

Page 8: Presenting a silent installation method for offshore ... · 1: Report by the European Wind Energy Association (EWEA), August 2015 0 2000 4000 6000 8000 10000 12000 14000 16000 18000

8

Page 9: Presenting a silent installation method for offshore ... · 1: Report by the European Wind Energy Association (EWEA), August 2015 0 2000 4000 6000 8000 10000 12000 14000 16000 18000

153 days

135 days

178 days

Gemini - base case With GBM Pile Drill With Noise Mitigation

Simulated number of days required to install 160 foundations at Gemini

Installation time Weather delay

9

Evaluation of installation procedure performed by ECN

Simulation set up: • Based on Gemini Windpark • 150 foundations using 2 ships

Findings:

• Pile drill requires less steps during installation • Secondary metal work can be pre-installed

Results:

• Shorter installation time per foundation • Smaller weather windows can be used • Decreased risk of delay due to weather

Vibro-Drill

Page 10: Presenting a silent installation method for offshore ... · 1: Report by the European Wind Energy Association (EWEA), August 2015 0 2000 4000 6000 8000 10000 12000 14000 16000 18000

Prototype 2 Prototype 1

10

Technology Prototypes

5m

1m

2016 Q3 2017

In contact with:

10cm 25cm

Page 11: Presenting a silent installation method for offshore ... · 1: Report by the European Wind Energy Association (EWEA), August 2015 0 2000 4000 6000 8000 10000 12000 14000 16000 18000

11

Prototype 1

Page 12: Presenting a silent installation method for offshore ... · 1: Report by the European Wind Energy Association (EWEA), August 2015 0 2000 4000 6000 8000 10000 12000 14000 16000 18000

12

Prototype 2

Page 13: Presenting a silent installation method for offshore ... · 1: Report by the European Wind Energy Association (EWEA), August 2015 0 2000 4000 6000 8000 10000 12000 14000 16000 18000

13

Page 14: Presenting a silent installation method for offshore ... · 1: Report by the European Wind Energy Association (EWEA), August 2015 0 2000 4000 6000 8000 10000 12000 14000 16000 18000

Lateral Bearing Capacity tests

14

Loadcell to measure

applied force

Optical displacement sensor

Page 15: Presenting a silent installation method for offshore ... · 1: Report by the European Wind Energy Association (EWEA), August 2015 0 2000 4000 6000 8000 10000 12000 14000 16000 18000

Prototype 2 Prototype 3 Prototype 4 Prototype 1

15

Future development

5m 35m 70m

1m

2016 Q3 2017 2018 2019

In contact with:

10cm 25cm

2m

8m

Page 16: Presenting a silent installation method for offshore ... · 1: Report by the European Wind Energy Association (EWEA), August 2015 0 2000 4000 6000 8000 10000 12000 14000 16000 18000

Noise Negligible sound production

Time Faster installation

Operability Decreased risk of weather delays

Scalability Can easily be scaled to any diameter foundation pile

Fatigue No fatigue damage during installation

16

Benefits of the GBM Works Pile Drill

Page 17: Presenting a silent installation method for offshore ... · 1: Report by the European Wind Energy Association (EWEA), August 2015 0 2000 4000 6000 8000 10000 12000 14000 16000 18000

Nick Noordam – [email protected] www.gbmworks.com

Presenting a silent installation method for offshore foundation piles