27
THE FUTURE OF MERCHANT POWER PLANTS Presented by: F.T. Sparrow State Utility Forecasting Group Purdue University Presented to: 14th Annual Surface Mined Land Reclamation Technology Transfer Seminar Jasper, Indiana December 5, 2000 To download a copy of this presentation, visit our website at: http://fairway.ecn.purdue.edu/IIES/SUFG/

Presented to: Presented by - purdue.edu

  • Upload
    others

  • View
    6

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Presented to: Presented by - purdue.edu

THE FUTURE OF MERCHANTPOWER PLANTS

Presented by:

F.T. SparrowState Utility Forecasting Group

Purdue University

Presented to:

14th Annual Surface Mined Land ReclamationTechnology Transfer Seminar

Jasper, Indiana

December 5, 2000To download a copy of this presentation, visit our website at: http://fairway.ecn.purdue.edu/IIES/SUFG/

Page 2: Presented to: Presented by - purdue.edu

MAJOR CONCLUSIONS

• There is growing concern over the developing shortage ofIndiana utility-controlled generation capacity. SUFGexpects the statewide reserve margin to fall below 15percent this year when the generation deficit (including 15percent reserves) is expected to be 400 MW, or about 2percent of Indiana’s current generating capacity.

• If, as the forecast predicts, electricity sales and peakdemand grow at 1.8 percent per year (down from 2 percentin the 1996 forecast), SUFG projects the need for 2250 MWof new capacity by 2005, and an additional 5400 MW by2016, the end of the forecast horizon.

Page 3: Presented to: Presented by - purdue.edu

MAJOR CONCLUSIONS (Continued)

• If the current regulatory framework is unchanged over theforecast horizon, SUFG predicts real (inflation adjusted)prices to fall at a rate of slightly less than 1 percent per yearuntil 2003, when prices level out until the end of theforecast horizon when they are expected to increaseslightly.

• If, on the other hand, Indiana chose to allow competitionamong generators and competition works perfectly, SUFGwould initially expect market clearing prices to drop belowthe level of prices that would prevail if regulation were tocontinue. SUFG would then expect competitive prices torise quite rapidly as demand growth increases until suchprices reach a point where new units are added at the long-run cost of electricity, which is slightly above the mid-termprice under continued regulation.

Page 4: Presented to: Presented by - purdue.edu

MAJOR CONCLUSIONS (Continued)

• However, SUFG is doubtful that electricity markets will workperfectly; hence, the competitive price forecast should beconsidered as a lower limit on likely prices if competition isintroduced. If market power is exercised by sellers, actualprices are not likely to be lower and could very likely behigher than those expected with perfect competition.

• In the long run, after the transition from regulation tocompetition is complete, SUFG would expect prices withcompetition to be lower than prices with continuedregulation, as electricity generators are provided withgreater incentives to reduce costs.

Page 5: Presented to: Presented by - purdue.edu

INDIANA ELECTRICITY REQUIREMENTS IN GWh (HISTORICAL, CURRENT AND PREVIOUS

FORECASTS)

1980 1984 1988 1992 1996 2000 2004 2008 2012 201650000

60000

70000

80000

90000

100000

110000

120000

130000

140000

50000

60000

70000

80000

90000

100000

110000

120000

130000

140000

GW

h

GW

h

Year

History

1996

1994

1999(Current Forecast)

Page 6: Presented to: Presented by - purdue.edu

FORECAST ELECTRICITYCONSUMPTION (% GROWTH RATES)

Residential

Commercial

Industrial

1.01

0.36

0.23

0.66 (Customers)

1.89 (Energy-Weighted Floorspace)

1.44 (Outputs)

1.67

2.25

1.67

Utilization/Unit (%)Sector

# Units(%)

Total GrowthRates (%)

• Total residential growth primarily from increase in intensity (gadgets, AC).

• Commercial/industrial growth primarily from expansion of sector output.

Page 7: Presented to: Presented by - purdue.edu

INDIANA ENERGY REQUIREMENTSBY SCENARIO IN GWh

High

Low

1980 1985 1990 1995 2000 2005 2010 201550000

60000

70000

80000

90000

100000

110000

120000

130000

140000

150000

50000

60000

70000

80000

90000

100000

110000

120000

130000

140000

150000

GW

h

GW

h

Year

History

Base

High

Low

Page 8: Presented to: Presented by - purdue.edu

INDIANA PEAK DEMAND REQUIREMENTS INMW (HISTORY, CURRENT AND PREVIOUS

SUFG BASE FORECASTS)

1980 1984 1988 1992 1996 2000 2004 2008 2012 201610000

12000

14000

16000

18000

20000

22000

24000

10000

12000

14000

16000

18000

20000

22000

24000

MW

MW

Year

History

1996

1994

(Current Forecast) 1999

Page 9: Presented to: Presented by - purdue.edu

DEMAND AND SUPPLY IN MW (SUFG BASE)(INCLUDES 15 PERCENT RESERVES)

1980 1984 1988 1992 1996 2000 2004 2008 2012 201610000

12000

14000

16000

18000

20000

22000

24000

26000

28000

10000

12000

14000

16000

18000

20000

22000

24000

26000

28000

MW

MW

Year

Existing Resources

SUFG Planned

Projected

Supply Additions

Demand

Page 10: Presented to: Presented by - purdue.edu

INDIANA RESOURCE PLAN (SUFG BASE)

Additions (in MW)Retired Reserve

Year Dem and Capacity*Peaking Cycling Base Load

Penalty Margin (%) Comme nts

1996 16184 19216 0 143 27 0 18.7 PSI adds Wabash River Repowering Project;

SIGECO upgrades Culley Unit 31997 16596 19084 0 0 0 0 15.0

1998 17168 19050 0 0 45 0 11.0 I&M upgrades Cook Unit 2 (Nuclear)

1999 16779 19520 600 0 0 0 16.3

2000 17145 20174 300 0 0 0 17.7 I&M long-term firm sale expires

2001 17514 20460 350 0 0 0 16.8

2002 17917 20660 0 200 0 0 15.3

2003 18279 21190 0 0 500 0 15.9

2004 18620 21490 300 0 0 0 15.4

2005 18962 21810 0 0 0 0 15.0 I&M long-term firm sale expires

2006 19288 22267 0 0 500 43 15.4 NIPSCO retires Mitchell gas turbines 9A-9C

2007 19604 22547 150 0 0 70 15.0 HEREC long-term firm sale expires;

IPL retires Stout Units 3 and 42008 19936 23159 0 0 500 88 16.2 HEREC long-term firm sale expires; IPL retires

Stout gas turbines 1-3; NIPSCO retires Bailly gas turbine 10

2009 20248 23295 0 175 0 39 15.0 IPL retires Pritchard Unit 1

2010 20614 23751 150 200 0 99 15.2 I&M long-term firm sale expires;IPL retires Pritchard Unit 2; NIPSCO

retires Michigan City Unit 22011 21019 24323 0 175 500 103 15.7 IPL retires Pritchard Unit 3;

NIPSCO retires Michigan City Unit 32012 21290 24583 125 200 0 0 15.5

2013 21703 24940 275 200 0 118 14.9 IPL retires Pritchard Units 4 and 5

2014 22142 25565 125 0 500 0 15.5

2015 22443 25812 375 675 0 804 15.0 I&M retires Tanners Creek Units 1-4

2016 22789 26287 100 0 500 125 15.3

*Includes installed capacity plus firm purchases minus firm sales.Source: SUFG Modeling System and Utility IRP filings for retirements.

Page 11: Presented to: Presented by - purdue.edu

INDIANA REAL PRICE PROJECTIONS(1996 DOLLARS) (HISTORICAL, CURRENT AND

PREVIOUS FORECASTS)

1980 1984 1988 1992 1996 2000 2004 2008 2012 20161

2

3

4

5

6

7

8

9

10

1

2

3

4

5

6

7

8

9

10

Cen

ts/k

Wh

Cen

ts/k

Wh

Year

History

1999(Current Forecast)

1994

1996

Page 12: Presented to: Presented by - purdue.edu

DSM

• 150 MW; large decreasefrom 1996.

• Previously:– 1995: 250 MW– 2000: 569 MW– 2005: 792 MW– 2010: 908 MW

• Interruptible: 540 MW;slight increase.

• Source: Utility IRP data.

Page 13: Presented to: Presented by - purdue.edu

THE INDIANA ELECTRICITY INDUSTRY:TRADE AND PRICES UNDER RESTRUCTURING

• Two major assumptions:

– Perfect competition: marginal cost pricingscheme.

– Imperfect competition: market price departsfrom marginal cost.

Page 14: Presented to: Presented by - purdue.edu

PERFECT COMPETITION

• Assumptions:– Power exchange for

ECAR/MAIN.

– Producers bid theirmarginal costs.

– Consumers bid theirreservation prices.

• Hourly prices are set at themarginal cost of the mostexpensive unit that isdispatched.

• No stranded cost recovery.

Page 15: Presented to: Presented by - purdue.edu

SUFG’s 1999 COMPETITIVE MODEL

Page 16: Presented to: Presented by - purdue.edu

SCENARIO A -- BASE CASE

• Net export is 376 MW from ECAR/MAIN tosurrounding utilities. (Source: NERC 1998Summer Assessment Study)

• Yearly Forecast = energy-weighted average ofhourly marginal costs + average T&D cost +average cost of ancillary services.

Page 17: Presented to: Presented by - purdue.edu

SCENARIO B -- CASE WITH 5500 MW NETECAR/MAIN EXPORT TO OTHER REGIONS

• Assumed the higher ECAR/MAIN export is about45 percent of the maximum transmission capacitylimit.

• Yearly price calculated the same way as Case A.

Page 18: Presented to: Presented by - purdue.edu

INDIANA YEARLY ENERGY-WEIGHTEDAVERAGE PRICES--COMPETITION VS.REGULATION (1996 REAL DOLLARS)

1999 2001 2003 2005 2007 2009 2011 2013 20150

10

20

30

40

50

60

0

10

20

30

40

50

60

$/M

Wh

$/M

Wh

Year

Scenario B:

5500 MW

Scenario A:

376 MW

Continued Regulation

Page 19: Presented to: Presented by - purdue.edu

IMPERFECT COMPETITION

• Key Assumptions:– Not enough producers to ensure competitive

pricing.

Page 20: Presented to: Presented by - purdue.edu

PJM DATA: ENERGY-WEIGHTED AVERAGE MARKET CLEARINGPRICE AND MARGINAL COST

1 3 5 7 9 11 13 15 17 19 21 230

10

20

30

40

50

60

70

80

0

10

20

30

40

50

60

70

80

$/M

Wh

$/M

Wh

Hour

Market Clearing Price(August 1998)

Marginal Cost(August 1998)

Market Clearing Price(September 1998)

(September 1998)Marginal Cost

Page 21: Presented to: Presented by - purdue.edu

THE PROJECTED ENERGY-WEIGHTEDAVERAGE RETAIL PRICES FOR INDIANA

2001 2002 2003 2004 20050

10

20

30

40

50

60

0

10

20

30

40

50

60

$/MWh

$/MWh

Year

Scenario 1: Low Intensity G am ingScenario 2: M oderate Intensity G am ingScenario 3: H igh Intensity G am ing

Scenario 1

Scenario 2Scenario 3

Scenario 4: Perfect Com petition

Scenario 4

Page 22: Presented to: Presented by - purdue.edu

CONCLUSIONS

• The perfect competitionmodel has practical valuebecause the results couldbe used as a benchmark tomeasure the degree ofcompetitiveness.

• During low demandperiods, pool marketprices were close tomarginal costs.

• The imperfect competitionmodel is tailored for realworld situations whendemands are high and thecapacity margin is tight. Itcaptures the deviationsfrom a perfect world andwould give betterforecasting.

• More studies are needed.

Page 23: Presented to: Presented by - purdue.edu

1999 TOTAL DEMAND AND SUPPLY (MW)FOR INDIANA - 1999 to 2004

Conclusion: The 1680 MW installed would be sufficient IF all theMW stayed in Indiana. BUT, they are independent power producerplants, whose output will be purchased by the highest bidder, which

may not be an Indiana utility.

199920002001200220032004

167791714517514179171827918620

195202017420460206602119021490

600300350

00

300

000

20000

00000

500

16.317.716.815.315.915.4

Year Demand Capacity Peaking CyclingBaseLoad

ReserveMargin

(%)

Additions

Page 24: Presented to: Presented by - purdue.edu
Page 25: Presented to: Presented by - purdue.edu

ECAR/MAIN PROPOSED MERCHANT PLANTS (MW)

ECAR Indiana 10960 MW Michigan 8623 MW Ohio 9941 MW Pennsylvania 1170 MW West Virginia 2768 MW

Subtotal 33462 MW

MAIN Illinois 21052 MW Missouri 2022 MW Wisconsin 3528 MW

Subtotal 26602 MW

TOTAL ECAR/MAIN 60064 MW

Page 26: Presented to: Presented by - purdue.edu

THE COAL OUTLOOK

• Still true that 98% of Indiana power is generated from coal (EIA data).

• New construction mostly CTs for peaking.

• SO2 and NOx emissions standards work against coal.

• High gas fuel costs work against gas. (If all ECAR/MAIN plants come on as planned, 25% increase in gas fuel use by U.S. utilities.)

Page 27: Presented to: Presented by - purdue.edu

GENERATION COSTS -- PULVERIZED COALVS. COMBINED CYCLE (CENTS/KWh)

Capital Recovery

Fixed O&M

Variable O&M

Fuel

1.969

0.485

0.210

0.98

3.644

0.839

0.519

0.055

0.734 * Gas Price/106 Btu

?

PC CC

• Break even gas price is $3.04/106 Btu; current price volatile, but well above that.

• PC capital cost based on 0.10 lbs./ 106 Btu NOx emissions, within the proposed NOx standards.