FIELD INSPECTION REPORT ON THE SCHEME IMPLEMENTED UNDER MEGHALAYA STATE AQUACULTURE MISSION THROUGH SPA (2010-11), VALUE CHAIN (2010-11) & RKVY CORPUS FUND (2011-12), SOUTH GARO HILLS. BAGHMARA & RONGARA C&RD BLOCK. Presented by: Shri Bickyforth R. Marak - PowerPoint PPT Presentation

Citation preview

Page 1: Presented by:                   Shri  Bickyforth  R.  Marak Programme Manager, FFDA

Presented by: Shri Bickyforth R. MarakProgramme Manager, FFDA

BAGHMARA & RONGARA C&RD BLOCK

FIELD INSPECTION REPORT ON THE SCHEME IMPLEMENTED UNDER MEGHALAYA STATE AQUACULTURE MISSION THROUGH SPA (2010-11), VALUE

CHAIN (2010-11) & RKVY CORPUS FUND (2011-12), SOUTH GARO HILLS

Page 2: Presented by:                   Shri  Bickyforth  R.  Marak Programme Manager, FFDA

SPA(2010-11)Special Plan Assistant scheme under Meghalaya State Aquaculture Mission was launched in the year 2012. 100

beneficiaries each from Baghmara and Rongara C&RD Block was selected for

fish pond construction under this scheme.

Page 3: Presented by:                   Shri  Bickyforth  R.  Marak Programme Manager, FFDA

VALUE CHAIN MANAGEMENT(2010-11)

15 beneficiaries each from Baghmara and Rongara C&RD Block were selected for the Value Chain Management (2010-11) under Meghalaya State Aquaculture Mission. The training has been already given to the beneficiaries but the work order is still to be given to the farmers as the case still pending with concern

bank.

Page 4: Presented by:                   Shri  Bickyforth  R.  Marak Programme Manager, FFDA

RKVY CORPUS FUND (2011-12)90 beneficiaries were selected from the

South Garo Hills for fish pond construction measuring an area of 0.1ha under RKVY

CORPUS FUND (2011-12), Meghalaya State Aquaculture Mission. The training to the farmers was given last week but the

work order cannot be issued to the farmers due to the implementation of

election code of conduct.

Page 5: Presented by:                   Shri  Bickyforth  R.  Marak Programme Manager, FFDA

Name of scheme SPA

Area of the pond (constructed)

0.1 Ha

Actual area constructed 0.1 Ha

Crest width 1.5M

Bottom width < 3 M

Slope 1:1

Depth 1-1.5 M

Overflow pipe 4-5 inch

Drain pipe 4-6 inch

Smti. Kish Ch. Sangma

BAGHMARA BLOCK

Feedback: The beneficiary tell us that the sanction amount was not sufficient to construct the required 0.1 ha pond as the daily wages of the labour is higher than the estimated. She completed the construction with her own expenses. Fingerlings were stocked on July 2013.

Page 6: Presented by:                   Shri  Bickyforth  R.  Marak Programme Manager, FFDA

Name of scheme SPA

Area of the pond (constructed)

0.1 Ha

Actual area constructed 0.15 Ha

Crest width 1-1.5M

Bottom width < 3 M

Slope 1:1

Depth < 1 M

Overflow pipe 4-5 inch

Drain pipe 4-6 inch

Shri Omol M. Sangma

BAGHMARA BLOCK

Feedback: The beneficiary tell us that he uses his money to construct the pond measuring an area of 0.15ha. Low water table has a negative effect on fishes in the pond and the other concern that the beneficiary share is the poaching of fish. Fingerlings were stocked on July 2013.

Page 7: Presented by:                   Shri  Bickyforth  R.  Marak Programme Manager, FFDA

Name of scheme SPA

Area of the pond (constructed)

0.1 Ha

Actual area constructed 0.1 Ha

Crest width 1-1.5M

Bottom width < 3 M

Slope 1:1

Depth 1-1.5 M

Overflow pipe 4-5 inch

Drain pipe 4-6 inch

Shri Henry B. Marak

BAGHMARA BLOCK

Feedback: The beneficiary finish the construction with his own expenses. Poaching has been a great problem in rearing of fish. Fingerlings were stocked on July 2013.

Page 8: Presented by:                   Shri  Bickyforth  R.  Marak Programme Manager, FFDA

Name of scheme SPA

Area of the pond (constructed)

0.1 Ha

Actual area constructed 0.08 Ha

Crest width 1-1.5M

Bottom width < 3 M

Slope 1:1

Depth 1-1.5 M

Overflow pipe 4-5 inch

Drain pipe 4-6 inch

Smti. Sushilla B Marak

BAGHMARA BLOCK

Feedback: The beneficiary tell us that she uses her money to finish the construction of the pond measuring an area of 0.1ha. Low water table has a negative effect on the fish in the pond and the other concern which the beneficiary share is the poaching of fish. Fingerlings were stocked on July 2013.

Page 9: Presented by:                   Shri  Bickyforth  R.  Marak Programme Manager, FFDA

Name of scheme SPA

Area of the pond (constructed)

0.1 Ha

Actual area constructed 0.1 Ha

Crest width 1-1.5M

Bottom width < 3 M

Slope 1:1

Depth 1-1.5 M

Overflow pipe 4-5 inch

Drain pipe 4-6 inch

Smti. Lucy B Marak

BAGHMARA BLOCK

Feedback: Finish the construction of required area 0f .1ha by her own expenses. She is expecting to do the first harvesting of fish from his pond by July 2014. Fingerlings were stocked on July 2013.

Page 10: Presented by:                   Shri  Bickyforth  R.  Marak Programme Manager, FFDA

Name of scheme SPA

Area of the pond (constructed)

0.1 Ha

Actual area constructed 0.12 Ha

Crest width 1-1.5M

Bottom width < 3 M

Slope 1:1

Depth 1-1.5 M

Overflow pipe 4-5 inch

Drain pipe 4-6 inch

Smti. Marbina R Marak

BAGHMARA BLOCK

Feedback: The beneficiary tell us that she uses her money to finish the construction of the pond measuring an area of 0.1ha. The main concern that the beneficiary share is the poaching of fish. Fingerlings were stocked on July 2013.

Page 11: Presented by:                   Shri  Bickyforth  R.  Marak Programme Manager, FFDA

Name of scheme SPA

Area of the pond (constructed)

0.1 Ha

Actual area constructed 0.08 Ha

Crest width 1-1.5M

Bottom width < 3 M

Slope 1:1

Depth < 1 M

Overflow pipe 4-5 inch

Drain pipe 4-6 inch

Shri Anot Marak

RONGARA BLOCK

Feedback: The beneficiary tell us that he uses his money to finish the construction of the pond measuring an area of 0.08ha. Low water table has a negative effect on the fish in the pond.

Page 12: Presented by:                   Shri  Bickyforth  R.  Marak Programme Manager, FFDA

Name of scheme SPA

Area of the pond (constructed)

0.1 Ha

Actual area constructed 0.09 Ha

Crest width 1-1.5M

Bottom width < 3 M

Slope 1:1

Depth < 1 M

Overflow pipe 4-5 inch

Drain pipe 4-6 inch

Shri Benting Marak

RONGARA BLOCK

Feedback: He express his disappointment that sanction amount is not sufficient to construct the required 0.1ha. Low water table has a negative effect on fish culture. Fingerlings were stocked on July 2013.

Page 13: Presented by:                   Shri  Bickyforth  R.  Marak Programme Manager, FFDA

Name of scheme SPA

Area of the pond (constructed)

0.1 Ha

Actual area constructed 0.07 Ha

Crest width 1-1.5M

Bottom width < 3 M

Slope 1:1

Depth < 1 M

Overflow pipe 4-5 inch

Drain pipe 4-6 inch

Lemish Marak

RONGARA BLOCK

Feedback: She is happy with the department concern for helping them to better their livelihood by doing fish culture.

Page 14: Presented by:                   Shri  Bickyforth  R.  Marak Programme Manager, FFDA

Name of scheme SPA

Area of the pond (constructed)

0.1 Ha

Actual area constructed 0.08 Ha

Crest width 1-1.5M

Bottom width < 3 M

Slope 1:1

Depth 1-1.5 M

Overflow pipe 4-5 inch

Drain pipe 4-6 inch

Shri Therak Sangma

RONGARA BLOCK

Feedback: The beneficiary tell us that he uses his money to finish the construction of the pond measuring an area of 0.1 ha. and thank the concern department for helping him to do fish culture. Low water table has a negative effect on fish culture.