22
Presentation to Portfolio Committee on Water and Sanitation on TCTA Integrated Annual Report 2016 - 17 5 October 2017 1

Presentation to Portfolio Committee on Water and Sanitation on …pmg-assets.s3-website-eu-west-1.amazonaws.com/171005TCTA.pdf · 2017. 10. 9. · Presentation to Portfolio Committee

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Presentation to Portfolio Committee on Water and Sanitation on …pmg-assets.s3-website-eu-west-1.amazonaws.com/171005TCTA.pdf · 2017. 10. 9. · Presentation to Portfolio Committee

Presentation to Portfolio Committee on Water and Sanitation

on TCTA Integrated Annual Report 2016 - 17

5 October 2017

1

Page 2: Presentation to Portfolio Committee on Water and Sanitation on …pmg-assets.s3-website-eu-west-1.amazonaws.com/171005TCTA.pdf · 2017. 10. 9. · Presentation to Portfolio Committee

• Manage the fundingand debt on theinfrastructure projects,on behalf of clients, in amanner that achievescost-effective funding,taking into accountcurrent and projectedmarket conditions aswell as associated risks

• Implement all aspectsof each infrastructureproject to ensure thatthe service deliveryobjectives, of the client,are met in the mostcost-effective andsocio/ environmentalsustainable manner

Page 3: Presentation to Portfolio Committee on Water and Sanitation on …pmg-assets.s3-website-eu-west-1.amazonaws.com/171005TCTA.pdf · 2017. 10. 9. · Presentation to Portfolio Committee
Page 4: Presentation to Portfolio Committee on Water and Sanitation on …pmg-assets.s3-website-eu-west-1.amazonaws.com/171005TCTA.pdf · 2017. 10. 9. · Presentation to Portfolio Committee

Ernest & Young Inc. evaluated the usefulness and reliability of the reported performance information in accordance with the criteria developed from the performance management and reporting framework

Ernest & Young Inc. did not identify any material findings on the usefulness and reliability of the reported performance information for the selected objectives

Page 5: Presentation to Portfolio Committee on Water and Sanitation on …pmg-assets.s3-website-eu-west-1.amazonaws.com/171005TCTA.pdf · 2017. 10. 9. · Presentation to Portfolio Committee

• Pre-implementation– Phase 2B of the Olifants River Water Resources Development Project– Phase 2A of the Mokolo- Crocodile River (west) Augmentation Project– Mzimvubu Water Project

• Under Construction– Acid Mine Drainage: Eastern Basin– Phase 2C of the Olifants River Water Resources Development Project

• Post-construction– Acid Mine Drainage: Central Basin– Phase 2 Of the Mooi Mgeni Transfer Scheme

• Water transfer pipeline• Water pipeline for Umgeni Water

– Phase 1 of the Mokolo- Crocodile River (west) Augmentation Project

• Operation and Maintenance– Acid Mine Drainage: Short-term Intervention (Western, Central &

Eastern Basins)– Outfall Tunnel North of the Lesotho Highlands Water Project

Page 6: Presentation to Portfolio Committee on Water and Sanitation on …pmg-assets.s3-website-eu-west-1.amazonaws.com/171005TCTA.pdf · 2017. 10. 9. · Presentation to Portfolio Committee

Short-term Intervention on Acid Mine Project

Total capacity of 234 thousand m3 per day

Commenced April 2011Completed August 2016

Cost at completion R2.6 billion

Page 7: Presentation to Portfolio Committee on Water and Sanitation on …pmg-assets.s3-website-eu-west-1.amazonaws.com/171005TCTA.pdf · 2017. 10. 9. · Presentation to Portfolio Committee

Operation and Maintenance Costsof Short-term Intervention

(Total R265 million)

Western Basin 11%

Central Basin 55%

Eastern Basin 34% R29 million

R146 million

R90 million

Page 8: Presentation to Portfolio Committee on Water and Sanitation on …pmg-assets.s3-website-eu-west-1.amazonaws.com/171005TCTA.pdf · 2017. 10. 9. · Presentation to Portfolio Committee

Outfall Tunnel North of the Lesotho Highlands Water Project

Delivered 794 million m3

Page 9: Presentation to Portfolio Committee on Water and Sanitation on …pmg-assets.s3-website-eu-west-1.amazonaws.com/171005TCTA.pdf · 2017. 10. 9. · Presentation to Portfolio Committee

Phase 2C of the Olifants River Water Resources Development Project

• The first 10 km has been able to deliver water to the water treatment works at Steelbrug since January 2014

• Supply capacity of 80 million m3 per annum• Projected capital cost at completion R2.3 billion• Projected date for completion of the balance of the works, November 2017

Page 10: Presentation to Portfolio Committee on Water and Sanitation on …pmg-assets.s3-website-eu-west-1.amazonaws.com/171005TCTA.pdf · 2017. 10. 9. · Presentation to Portfolio Committee

EMPLOYMENT

Page 11: Presentation to Portfolio Committee on Water and Sanitation on …pmg-assets.s3-website-eu-west-1.amazonaws.com/171005TCTA.pdf · 2017. 10. 9. · Presentation to Portfolio Committee

Employment on Projects under Operation & Maintenance

11

Employment

Gender Ethnic group

TotalFemale Male HDI Non-HDI

AMD O&M Eastern

Employed 17 29 36 10 46

AMD O&M Central

Employed 4 34 33 5 38

AMD O&M Western

Employed 6 22 23 5 28

LHWP

Employed 0 4 3 1 4

O&M Total

Total 27 89 95 21 116

Page 12: Presentation to Portfolio Committee on Water and Sanitation on …pmg-assets.s3-website-eu-west-1.amazonaws.com/171005TCTA.pdf · 2017. 10. 9. · Presentation to Portfolio Committee

Employment on Projects Under Construction (ORWRDP2C)

12

Employment Group

Origin Gender Ethnic group

LocalElse-

whereFemale Male HDI Non-HDI

Total

Mar-17 Mar-16

Unskilled 86 1 13 74 86 1 87 117

Semi-skilled 35 113 18 130 148 0 148 148

Other (skilled & staff) 2 48 6 44 19 31 50 59

Total 123 162 37 248 253 32 285 324

Page 13: Presentation to Portfolio Committee on Water and Sanitation on …pmg-assets.s3-website-eu-west-1.amazonaws.com/171005TCTA.pdf · 2017. 10. 9. · Presentation to Portfolio Committee

Staff Complement and Employment Equity

Classification African Coloured Indian White Foreign nationals

LevelCurrent Target Current Target Current Target Current Target Current Target

M F M F M F M F M F M F M F M F M F M F

Top management - - - - - - - - - - - - - - - - - - - -

Senior management 4 - 4 - - - - - - 1 - 1 1 1 1 1 - - - -

Professionally qualified 27 16 30 16 3 1 3 1 5 2 5 2 6 3 6 3 4 - 4 -

Skilled 15 28 13 28 1 5 1 5 - 2 - 2 - 4 - 4 - - - -

Semi-skilled 3 7 3 6 - - - - - - - - - - - - - - - -

Unskilled - - - - - - - - - - - - - - - - - - - -

Total 49 51 50 50 4 6 4 6 5 5 5 5 7 8 7 8 4 - 4 -

Page 14: Presentation to Portfolio Committee on Water and Sanitation on …pmg-assets.s3-website-eu-west-1.amazonaws.com/171005TCTA.pdf · 2017. 10. 9. · Presentation to Portfolio Committee

People Living with Disabilities

Level Current: 2016/2017 Target: 2016/2017

Top management- -

Senior management- -

Professionally qualified 1 4

Skilled 1 3

Semi-skilled- -

Unskilled- -

Total 2 7

Page 15: Presentation to Portfolio Committee on Water and Sanitation on …pmg-assets.s3-website-eu-west-1.amazonaws.com/171005TCTA.pdf · 2017. 10. 9. · Presentation to Portfolio Committee

In our opinion as Ernest & Young Inc. thefinancial statements present fairly, in allmaterial respects, the financial position ofTrans-Caledon Tunnel Authority as at 31 March2016, and its financial performance and cashflows for the year then ended in accordancewith International Financial ReportingStandards and the requirements of the PublicFinance Management Act of South Africa.

Page 16: Presentation to Portfolio Committee on Water and Sanitation on …pmg-assets.s3-website-eu-west-1.amazonaws.com/171005TCTA.pdf · 2017. 10. 9. · Presentation to Portfolio Committee

Irregular Expenditure(Services not procured in accordance with regulation but value

for money received)

• Total R49,468 million (4.6% of cash paid to service providers)– Contractor for the Operation of the Central Basin Acid

Mine Drainage Plant

– Provision of Disaster Recovery Services

– Appointment of a forensic auditor

– Appointment of Executives

– Changing criteria during the evaluation of a photocopier tender

– International travel

Page 17: Presentation to Portfolio Committee on Water and Sanitation on …pmg-assets.s3-website-eu-west-1.amazonaws.com/171005TCTA.pdf · 2017. 10. 9. · Presentation to Portfolio Committee

Fruitless and Wasteful Expenditure(Where no value as received for the expenditure incurred)

• R202 499 (13 incidents)

• 0,1% of total operating expenditure

Page 18: Presentation to Portfolio Committee on Water and Sanitation on …pmg-assets.s3-website-eu-west-1.amazonaws.com/171005TCTA.pdf · 2017. 10. 9. · Presentation to Portfolio Committee

Description Budget(R million)

Actual(R million)

Capital Unit and Bulk Operations & Royalty Charges 5 242 6 099Finance Costs 3 517 3 285

Capital Expenditure 4 880 574

Budget versus Actual

0

1000

2000

3000

4000

5000

6000

7000

Unit Charges Finance Costs Capital Expenditure

Actual Budget

Page 19: Presentation to Portfolio Committee on Water and Sanitation on …pmg-assets.s3-website-eu-west-1.amazonaws.com/171005TCTA.pdf · 2017. 10. 9. · Presentation to Portfolio Committee

Capital Expenditure per ProjectAcid Mine Drainage Budget

(R million)Actual

(R million)

Vaal River System

• Acid Mine Drainage: Short-term Intervention 296,9 84,5

• Phase 2 of the Lesotho Highlands Water Project 1 387,0 183,2

• Acid Mine Drainage: Long-term Solution 2 378,0 -

Phase 2 of the Mooi – Mgeni Transfer Scheme 77,8 83,8

Olifants River Water Resources Development Project 239,1 138,5

Mokolo – Crocodile River (west) Augmentation Project

• Phase 1 261,7 83,5

• Phase 2A 205,6 -

Other 32,2 0,1

Total 4 880,4 573,6

Page 20: Presentation to Portfolio Committee on Water and Sanitation on …pmg-assets.s3-website-eu-west-1.amazonaws.com/171005TCTA.pdf · 2017. 10. 9. · Presentation to Portfolio Committee

Total Expenditure

R130 million

Capital Expenditure 11%

Royalties, LHDA and LHWC 20%

Other Costs

(Opex)5%

Staff Costs3%

Finance Costs 61%

R3 284 million

R574 million

R1 044 million

R291 million

R162 million

Page 21: Presentation to Portfolio Committee on Water and Sanitation on …pmg-assets.s3-website-eu-west-1.amazonaws.com/171005TCTA.pdf · 2017. 10. 9. · Presentation to Portfolio Committee

Debt per Project

Vaal River System68%

Berg Water Project 2%

Vaal River Eastern Subsystem

Augmentation Project 13%

Phase 2 of the Mooi - Mgeni Transfer Scheme 7%

Komati Water Scheme Augmentation Project 5%

Mokolo Crocodile River (west) Augmentation Project 5%

R1 573 million

R1 934 million

R3 744 million

R1 313 million

R720 million

R19 427 million