CarolloBlueTemplateWithLogo.pptx 1 Presentation to Council Transportation, Technology & Infrastructure Committee Department of Public Works & Engineering November 12, 2015 Northeast Water Purification Plant Expansion DRAFT

Presentation to Council Transportation, Technology ... · 12.11.2015  · 320 MGD expansion with early 80 MGD milestone is being planned . 80 MGD module . on-line no later than Aug

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: Presentation to Council Transportation, Technology ... · 12.11.2015  · 320 MGD expansion with early 80 MGD milestone is being planned . 80 MGD module . on-line no later than Aug

Car

ollo

Blu

eTem

plat

eWith

Logo

.ppt

x

1

Presentation to Council

Transportation, Technology & Infrastructure

Committee

Department of Public Works

& Engineering

November 12, 2015

Northeast Water Purification Plant Expansion

DRAFT

Page 2: Presentation to Council Transportation, Technology ... · 12.11.2015  · 320 MGD expansion with early 80 MGD milestone is being planned . 80 MGD module . on-line no later than Aug

Car

ollo

Blu

eTem

plat

eWith

Logo

.ppt

x

2

NEWPP EXPANSION

• History/Purpose of the Project • Procurement Process • Procurement Activities • Appropriation

DRAFT

Page 3: Presentation to Council Transportation, Technology ... · 12.11.2015  · 320 MGD expansion with early 80 MGD milestone is being planned . 80 MGD module . on-line no later than Aug

Car

ollo

Blu

eTem

plat

eWith

Logo

.ppt

x

History and Purpose

DRAFT

Page 4: Presentation to Council Transportation, Technology ... · 12.11.2015  · 320 MGD expansion with early 80 MGD milestone is being planned . 80 MGD module . on-line no later than Aug

Car

ollo

Blu

eTem

plat

eWith

Logo

.ppt

x

4

Project History and Purpose

• Regulatory Requirements to transition to surface water sources due to effects of subsidence

• Trinity River Water Rights were planned to meet this mandate: – Luce Bayou Inter-Basin Transfer (underway) – NEWPP Expansion (in procurement) – New Transmission Pipeline (underway)

DRAFT

Page 5: Presentation to Council Transportation, Technology ... · 12.11.2015  · 320 MGD expansion with early 80 MGD milestone is being planned . 80 MGD module . on-line no later than Aug

Car

ollo

Blu

eTem

plat

eWith

Logo

.ppt

x

5

NEWPP Expansion is one piece of overall plan

to deliver & treat Trinity River supply

Luce Bayou Transfer (CWA Project)

New Lake Intake & Pump Station

New Plant & Existing Plant

Upgrades

Transmission Pipelines

DRAFT

Page 6: Presentation to Council Transportation, Technology ... · 12.11.2015  · 320 MGD expansion with early 80 MGD milestone is being planned . 80 MGD module . on-line no later than Aug

Car

ollo

Blu

eTem

plat

eWith

Logo

.ppt

x

6

NEWPP expansion is needed to meet

conversion mandate (HGSD & FBSD)

0%

10%

20%

30%

40%

50%

60%

70%

80%

90%

current requirement January 2025requirement

January 2035requirement

% o

f w

ate

r d

em

an

d s

up

pli

ed

b

y s

urf

ace w

ate

r

DRAFT

Page 7: Presentation to Council Transportation, Technology ... · 12.11.2015  · 320 MGD expansion with early 80 MGD milestone is being planned . 80 MGD module . on-line no later than Aug

Car

ollo

Blu

eTem

plat

eWith

Logo

.ppt

x

7

NEWPP Expansion Partnership with

Regional Water Authorities

Pro-rata Cost

Share

(%)

Phase I

(1st 80 MGD)

(%)

Phase II

(remaining 240 MGD)

(%)

NHCRWA 35.313 63.813 25.813

CHCRWA 1.525 0.575 1.842

NFBWA 21.406 14.325 23.767

WHCRWA 25.756 21.288 27.246

COH 16.000 0.000 21.333

Totals 100.000 100.000 100.000

Cost Share

Authorities: 84%

CoH 16% August 31, 2021 June 30, 2024

DRAFT

Page 8: Presentation to Council Transportation, Technology ... · 12.11.2015  · 320 MGD expansion with early 80 MGD milestone is being planned . 80 MGD module . on-line no later than Aug

Car

ollo

Blu

eTem

plat

eWith

Logo

.ppt

x

8

320 MGD expansion with early 80 MGD

milestone is being planned

80 MGD module on-line no later than Aug. 2021*

Add’l 240 MGD on-line no later than June 2024

*Early completion of Phase I driven by incremental conversion mandate

DRAFT

Page 9: Presentation to Council Transportation, Technology ... · 12.11.2015  · 320 MGD expansion with early 80 MGD milestone is being planned . 80 MGD module . on-line no later than Aug

Car

ollo

Blu

eTem

plat

eWith

Logo

.ppt

x

9

NEWPP Expansion – First Steps (complete)

• Hire Project Advisor/Technical Consultant (PATC) • Review existing & historical data; Evaluate current

plant capabilities • Develop/assess various options to meet mandate • Evaluate various delivery methods • Determined 2-Phase Design-Build Process was only

means to achieve req’d delivery milestones (Aug 2021/June 2024)

• Negotiate 2nd Supplement Agreements between CoH & Authorities w/ Council approval

• Seek out TWDB funding

DRAFT

Page 10: Presentation to Council Transportation, Technology ... · 12.11.2015  · 320 MGD expansion with early 80 MGD milestone is being planned . 80 MGD module . on-line no later than Aug

Car

ollo

Blu

eTem

plat

eWith

Logo

.ppt

x

10

Reasons for 2-phase Design-Build

• Best opportunity to achieve Phase I Delivery Milestone

• Reduces overall schedule risk • High degree of cost certainty • Better ability to adapt to market conditions • Reduces interface risk - One entity responsible

for both design & construction • Preserves City’s ability to collaborate & influence

design decisions DRAFT

Page 11: Presentation to Council Transportation, Technology ... · 12.11.2015  · 320 MGD expansion with early 80 MGD milestone is being planned . 80 MGD module . on-line no later than Aug

Car

ollo

Blu

eTem

plat

eWith

Logo

.ppt

x

11

Preliminary Services:

• Design development • Pre-construction services • Guaranteed Max. Price (GMP) for Phase II

services Final Design and Construction Services:

• Complete design & construction • Post-construction tasks

• Commissioning • Performance testing • O&M advisory services • Warranty

Design-Builder’s Tasks

DRAFT

Page 12: Presentation to Council Transportation, Technology ... · 12.11.2015  · 320 MGD expansion with early 80 MGD milestone is being planned . 80 MGD module . on-line no later than Aug

Car

ollo

Blu

eTem

plat

eWith

Logo

.ppt

x

Procurement Process

DRAFT

Page 13: Presentation to Council Transportation, Technology ... · 12.11.2015  · 320 MGD expansion with early 80 MGD milestone is being planned . 80 MGD module . on-line no later than Aug

Car

ollo

Blu

eTem

plat

eWith

Logo

.ppt

x

13

The Procurement Process

• Texas Statute, Title 10, Chap. 2269 governs • Request for Qualifications (RFQ) • Establish Qualified Firms Short List • Request for Proposals (RFP) • Evaluation & Scoring • Selection • Award DRAFT

Page 14: Presentation to Council Transportation, Technology ... · 12.11.2015  · 320 MGD expansion with early 80 MGD milestone is being planned . 80 MGD module . on-line no later than Aug

Car

ollo

Blu

eTem

plat

eWith

Logo

.ppt

x

14

Procurement & Contract conforms

to TX Statute (Title 10, Chapter 2269) • Contract Documents (RFQ, RFP, Design-Criteria

Package, Design-Build Agreement) • Technical-Legal Team Coordination:

– Collaborated on RFQ, RFP, Contract – Conference calls – Face-to-face meetings – Obtained input from outside bond & insurance

experts – Meetings & collaboration with Authorities – Review & comment by industry partners

DRAFT

Page 15: Presentation to Council Transportation, Technology ... · 12.11.2015  · 320 MGD expansion with early 80 MGD milestone is being planned . 80 MGD module . on-line no later than Aug

Car

ollo

Blu

eTem

plat

eWith

Logo

.ppt

x

Procurement Activities

DRAFT

Page 16: Presentation to Council Transportation, Technology ... · 12.11.2015  · 320 MGD expansion with early 80 MGD milestone is being planned . 80 MGD module . on-line no later than Aug

Car

ollo

Blu

eTem

plat

eWith

Logo

.ppt

x

16

RFQ Process & establishment of

Shortlist of Qualified Candidates

• Pre-RFQ notification & Market Research • RFQ issued 3/20/15 • Conducted pre-submittal meeting on 4/8/15 • Received SOQs on 4/21/15 • 3 Respondents; all determined qualified

DRAFT

Page 17: Presentation to Council Transportation, Technology ... · 12.11.2015  · 320 MGD expansion with early 80 MGD milestone is being planned . 80 MGD module . on-line no later than Aug

Car

ollo

Blu

eTem

plat

eWith

Logo

.ppt

x

17

Collaborative RFP Process

• RFP issued 4/30/15 • Conducted pre-proposal meeting 6/11/15 • 12 Addenda issued based on comments &

questions received during public comment period • Extensive opportunity for input on Design-Build

Agreement • Proposals Received 10/27/15 • Stipends offered (1/2 of 1%) of Awarded Contract

Amount

DRAFT

Page 18: Presentation to Council Transportation, Technology ... · 12.11.2015  · 320 MGD expansion with early 80 MGD milestone is being planned . 80 MGD module . on-line no later than Aug

Car

ollo

Blu

eTem

plat

eWith

Logo

.ppt

x

18

• Criteria & relative weighting provided in RFP • Technical weighted higher than price • Sealed price proposals evaluated after technical

evaluation completed • Thorough responsiveness review

(Legal/MWBE/Risk Mgmt/Technical/Financial) • Selection Panel evaluated & scored technical

proposal, & then price proposals independently of support panels

Evaluation process

DRAFT

Page 19: Presentation to Council Transportation, Technology ... · 12.11.2015  · 320 MGD expansion with early 80 MGD milestone is being planned . 80 MGD module . on-line no later than Aug

Car

ollo

Blu

eTem

plat

eWith

Logo

.ppt

x

Appropriation

DRAFT

Page 20: Presentation to Council Transportation, Technology ... · 12.11.2015  · 320 MGD expansion with early 80 MGD milestone is being planned . 80 MGD module . on-line no later than Aug

Car

ollo

Blu

eTem

plat

eWith

Logo

.ppt

x

20

Appropriation Plan

• (Dec.) Award Preliminary Services, Component 1 – Preliminary engineering & provide basis of design

• (Future) Award Preliminary Services, Component 2 – Continue engineering – Early Work Package GMPs – Provide Guaranteed Max. Price

• (Future) Award Early Work Package GMPs • (Future) Award GMP for Final Design &

Construction

DRAFT

Page 21: Presentation to Council Transportation, Technology ... · 12.11.2015  · 320 MGD expansion with early 80 MGD milestone is being planned . 80 MGD module . on-line no later than Aug

Car

ollo

Blu

eTem

plat

eWith

Logo

.ppt

x

21

Preliminary Services Final Design & Construction Services

Basis of Design

Contract Award & NTP

Component 1 NLT 6/30/24

Phase 2 (240 mgd) milestone

Final Completion

Final Acceptance

Transition & Warranty Services

Phase 1 (80 mgd) milestone

NLT 8/31/21

NEWPP Construction

GMP Amendment Approval

GMP Proposal

Early Work Packages

Component 2

Amendment No. 1 Approval

DRAFT

Page 22: Presentation to Council Transportation, Technology ... · 12.11.2015  · 320 MGD expansion with early 80 MGD milestone is being planned . 80 MGD module . on-line no later than Aug

Car

ollo

Blu

eTem

plat

eWith

Logo

.ppt

x

22

Next Steps

• Consensus Vote by Authorities • Presentation of RCA to City Council • Award • NTP for Preliminary Services, Component 1 • NTP + approx 10 months:

– Negotiated agreement for Preliminary Services (Component 2) for Council Consideration DRAFT

Page 23: Presentation to Council Transportation, Technology ... · 12.11.2015  · 320 MGD expansion with early 80 MGD milestone is being planned . 80 MGD module . on-line no later than Aug

Car

ollo

Blu

eTem

plat

eWith

Logo

.ppt

x

23

Q & A

Northeast Water Purification Plant

Expansion

DRAFT