Integrated Sciences Complex (ISC)

▸ Under construction next to Quinn/Healey Library▸ Primarily a research building – labs for Biology, Chemistry, Psychology, Physics, and School for the Environment (formerly EEOS) Two research centers:

• Developmental Science Research Center (DSRC)• Center for Personalized Cancer Therapy (CPCT)

▸ 4 Biology Teaching Labs

Page 3: Presentation Title | May 4, 2009 Move to the ISC Campus Master Plan

Presentation Title | May 4, 2009

Integrated Sciences Complex (ISC)

▸ Certificate of Occupancy will be August 20th

▸ Move Planning currently under way, will begin in Spring with Purge/Surplus Process▸ Departments will vacate existing spaces in Wheatley, McCormack, Science Center

Page 4: Presentation Title | May 4, 2009 Move to the ISC Campus Master Plan

Presentation Title | May 4, 2009

Integrated Sciences Complex (ISC)Spring 2013 Engaged Move Planning consultant: Diversified Project Management (DPM)

Summer 2013

Began regular meetings with ISC design/construction team and DPM

Assigned ISC lab and office spaces to researchers

Distributed Move Planning information to departments at kickoff meeting

Established departmental lab move coordinators

Refined lab equipment inventories

Fall 2013 Continued coordination and communication

Began exploring move routes

January 2014 Began compiling information for comprehensive ‘Practical Guide for Moving into the ISC’

February 2014 Meet with departments to discuss schedule and processes

Discuss records management

March 2014 Initiate purge process

Distribute records retention policy

April 2014 Distribute move guide and materials to departments

Finalize move route and workaround for University Drive South closure

May 2014 Surplus and removal of excess furniture

June 2014 Begin packing existing equipment and items

Office furniture delivery

July 2014 Lobby and public furniture delivery

New equipment delivery

August 2014 Existing equipment move

8/20 Certificate of Occupancy (substantial building completion)

August/Sept 2014 Relocate researchers to ISC

Fall 2014 Relocate vivarium animals to ISC

January 2015 Begin classes in Biology teaching labs