Upload
dwight-davidson
View
243
Download
0
Embed Size (px)
Citation preview
PRESENTATION OF THE ARMSCOR ANNUAL REPORTTO THE PORTFOLIO COMMITTEE ON DEFENCE AND MILITARY
VETERANS
MR SIPHO MKWANAZI – ACTING CEO
DATE: 10th OCTOBER 2013
Scope
1. Introduction
2. Performance of Operational Functions Acquisition Research and Development Dockyard
3. Human Resources
4. Corporate Performance versus Goals / Objectives
5. Financial Performance
6. Challenges
7. Questions & Answers
2
Introduction
Armaments Corporation of South Africa SOC Limited (Armscor) established in terms of the Armaments Corporation of South Africa, Limited Act (Act 51 of 2003)
State – owned entity as contemplated in the Companies Act, 2008
Listed as a Schedule 2 Public Entity in terms of the PFMA
Further regulated by the Regulations issued in the terms of the PFMA and the Companies Act
The Minister responsible for Armscor is the Minister of Defence & Military Veterans (MOD&MV)
The Board of Directors is the Executive Authority of Armscor
3
Introduction (Cont.)Within its mandate, Armscor’s objectives are to meet the following requirements of the DoD:
defence matériel needs technology development research & development analysis test & evaluation
effectively, efficiently and economically
Adhere to accepted principles of corporate governance and lawfulness
Highlights:
Clean Audit
Achieved level 3 BBBEE rating from level 7
Dockyard obtained ISO 9001: 2008 accreditation
Achieved a surplus of R84.6m (2012/13) against R70.2m in 2011/12
51% improvement on results of Corporate Social Investment (CSI) Flagship programme – Learner Enhancement Programme
4
MARITIME SYSTEMS
Following the delivery and commissioning of three submarines, engineering changes were made to meet:
operational
safety
support related requirements
These were initially omitted due to financial constraints
Changes are almost completed, awaiting
Department of Public Works to complete escape training facility by end Sept 2013
Availability of submarine to carry out final on-board qualification by April 2013
Performance of Operational Functions - Acquisition
5
AIRBORNE SYSTEMS
LUH - All 30 Helicopters have been delivered to SAAF & updated with latest production standards
Gripen - 9 x dual seat aircraft -17 x single seat aircraft delivered to SAAF
Aircrafts in full functionality, electronic warfare and datalink capability completed in Sept 2013
Integration of the A-Darter Missile was completed and delivered in November 2012
Hawk – Operational flight trainer has been upgraded to the same standard as the fleet
The fleet exceeded 10 000 flying training hours in October 2012
Rooivalk - Rooivalk fleet was upgraded to the MK1 deployment baseline
A depot level support was also established
Performance of Operational Functions - Acquisition (Cont.)
6
39 Oryx Medium Transport Helicopter (MTH’s)
Development of avionics upgrade was completed
The modification on the first four helicopters is progressing well
A-Darter Missile development
Jointly funded with the Brazilian Air Force
Programme is progressing well despite some technical delays experienced
Seeker head has reached an acceptable level of technology maturity
Performance of Operational Functions - Acquisition (Cont.)
7
LANDWARD SYSTEMS
Ground Based Air Defence System
New Local Warning Segment of the Ground Based Air Defence System has been completed
Phase two of the GBADS programme which entails upgrading of fire-control system of the 35 mm anti – aircraft guns has commenced
New Generation Infantry Combat Vehicle
Locally developed 30mm Camgun is undergoing final environmental test and evaluation
Advanced development was completed in December 2012 and testing commenced in February 2013
Development of an insensitive munition-compliant missile will be further explored in the next two years
Performance of Operational Functions - Acquisition (Cont.)
8
Performance of Operational Functions - Research & Development (Cont.)
TEST & EVALUATION FACILITIES aims to maintain the capability
Gerotek
28% funded from DoD transfer payment
Relying on commercial business to fund shortfall
Alkantpan
33% funded from DoD transfer payment
67% operations funded from local and foreign business
9
Performance of Operational Functions - Research & Development (Cont.)
DEFENCE SCIENCE AND TECHNOLOGY INSTITUTE
Armour Development
DoD transfer payment funds basic capability – 95%
Relying on commercial business to fund shortfall
Defence Decision Support Institute (DDSI)
100% funded from DoD transfer payment
Ergonomics Technologies (Ergotech)
95% funded from DoD transfer payment
5% funded from commercial contracts
Flamengro
75% funded from DoD transfer payment
Funded 25% of operations from local business contracts
10
Performance of Operational Functions - Research & Development (Cont.)
DEFENCE SCIENCE AND TECHNOLOGY INSTITUTES
Hazmat
100% of income generated from local commercial contract
Institute of Maritime Technology (IMT)
88% funded from DoD transfer payment
12% from local commercial work
Protechnik
98% funded from DoD transfer payment
2% from commercial contracts
11
Performance of Operational Functions - Dockyard
Obtained ISO 9001:2008 accreditation
Current financial year focus is on SHE matters
Funding based on a fixed transfer payment to deliver predetermined capabilities
Current capacity insufficient to deliver full requirements
Received R30.6m additional funding
Capacity rejuvenation
(skilled labour & equipment)
Insufficient & sustainable funding remains
Re-modernisation study completed in July 2013
Despite challenges, overall achievement 92%
versus 90% target
12
Performance of Operational Functions - Dockyard(Cont.)
Planned and unplanned maintenance projects
Frigates:
SAS Spioenkop experience challenges, eventually completed in March 2013
Patrol Vessels:
SAS ISSAC Dyoba started maintenance in March 2013 for collision damage repairs which was successfully completed
SAS Umhloti, unscheduled maintenance and repairs completed on time
SAS Umzimkulu, successfully completed unplanned maintenance
Tugs:
Tug Indlovu
Tug Demist All work successfully completed on time
Tug Tshukudu
Tug Umalusi , unscheduled maintenance planned for completion in April 2013
13
Performance of Operational Functions - Dockyard(Cont.)
Planned and unplanned maintenance projects (cont.)
Submarines:
SAS Manthatisi OEM executing refit at Dockyard, to be completed in July 2014
SAS Charlotte Maxeke completed within revised date due to unforeseen damage
SAS Queen Mojaji, activities completed within planned schedule
Independent Vessels:
SAS Protea completed in Feb 2013 vs. planned October 2012 due to unanticipated damage of valves to be removed, repaired and replaced
SAS Drankensberg completed within revised date
14
Human Resources
Improvement in overall transformation, esp. from mid management to top management
Improvement in employee satisfaction survey – 66.5% (2012/13) from 62.9% (2011/12)
90 young engineers and scientist were identified for succession planning
Skills Development Programmes Armscor Senior Management Leadership Programme Functional training Dockyard training centre Adult Basic Education and Training (ABET) Talent Development Programme
CSI Flagship programme – “Learner Enhancement Programme” in support of Maths and
Science in schools resulted to an average of 51% improvement in these subjects
15
Corporate Performance vs. Goals
Objectives 1 – 3 : Measure effectiveness of acquisition function in terms of:• Contracts to be placed: commitment of funds• Achieved cash flow against formally planned cash flow i.t.o. of
commitments
Achieved goals except for System support: Acquisition and Procurement (operational funds)
Objective 4: Management of Defence Industrial Participation: •Execution of DIP obligationsObjective not achieved
OBJECTIVES MEASURING
FUNCTIONS IN TERMS OF SLA
Objective 5 : Management & Execution of Defence Technology, Test and Evaluation requirements for DOD:•Execution by Armscor Defence Institutes of contractual milestones/ deliveriesObjective achieved
Objective 6 : DOCKYARD•Management and performance against Dockyard Mandate Objective achieved
16
Corporate Performance vs. Objectives (Cont.)
Strategic objective 1 – Funding & GrowthMeasure the expenditure compliance and effort to secure sufficient funding to sustain the organisationObjective not achieved
Strategic objective 2 – People & CapabilitiesMeasuring Armscor’s ability to attract and retain employees
through a positive organizational environmentx Objective partly achieved
ACHIEVEMENT OF STRATEGIC
OBJECTIVES
Strategic objective 3 – Organisational Effectiveness & EfficienciesMeasure the operational efficiency of Armscorx Objective partly achieved
Strategic objective 4 – Stakeholder RelationshipsMeasure the relationships with stakeholders & Armscor’s compliance to good governancex Objective partly achieved
17
Financial Overview
Armscor received an unqualified Audit Report
Net asset value (Shareholder’s interest) increased by 187% to R1 792m million due to revaluation of land and buildings
Profit of R84.6m realised against R70.2m in 2012
Total revenue increased by 1% to R308.2 million
Personnel costs remains main contributor at 74.4% of total operating cost
18
Financial Position as at 31 March 2013Assets
2012 2013 2013 2012
Rm Rm Rm Rm
ASSETS
NON-CURRENT ASSETS
48,8 938,3 Property, plant and equipment 1 322,6 236,9
- - Intangible assets 0,3 0,4
110,4 109,4 Post retirement medical benefit asset 134,0 137,7
159,2 1 047,7 1 456,9 375,0
CURRENT ASSETS
- 0,1 Non current assets held for disposal 0,2 -
2,5 2,4 Inventories 11,7 7,6
159,3 101,4 Trade and other receivables 127,9 184,1
442,6 689,8 Cash and short term deposits 685,7 440,6
180,0 40,9 Loans to subsidiaries - -
784,4 834,6 825,5 632,3
943,6 1 882,3 TOTAL ASSETS 2 282,4 1 007,3
CORPORATION GROUP
19
Financial Position as at 31 March 2013Equity and Liabilities
2012 2013 2013 2012
Rm Rm Rm Rm
EQUITY AND LIABILITIES
CAPITAL AND RESERVES
75,0 75,0 Ordinary share capital 75,0 75,0
448,0 1 271,7 Non-distributable reserves 1 717,3 549,0
523,0 1 346,7 ORDINARY SHAREHOLDERS INTEREST 1 792,3 624,0
LIABILITIES
NON-CURRENT LIABILITIES
19,0 20,4 Post retirement medical benefit liability 20,4 19,0
9,5 86,0 Deferred income 86,0 9,5
28,5 106,4 106,4 28,5
CURRENT LIABILITIES
112,7 154,4 Loans from subsidiaries - -
151,9 169,0 Trade and other payables 233,3 203,1
67,9 69,0 Provisions 93,5 92,1
59,6 36,8 Deferred income 56,9 59,6
392,1 429,2 383,7 354,8
420,6 535,6 TOTAL LIABILITIES 490,1 383,3
943,6 1 882,3 TOTAL EQUITY AND LIABILITIES 2 282,4 1 007,3
CORPORATION GROUP
20
Statements of Comprehensive Income for the year
ended 31 March 2013
2012 2013 NOTES 2013 2012
Rm Rm Rm Rm
24,2 19,9 Revenue 13 308,2 305,2
(10,4) (10,3) Cost of sales 14 (119,7) (111,9)
13,8 9,6 GROSS PROFIT 15 188,5 193,3
56,8 65,9 Other operating revenue 16 67,7 70,5
659,9 748,1Allocation for operating expenditure (Government grants)
17 748,1 659,9
(725,1) (843,6) Operating expenses 18 (949,8) (879,7)
5,4 (20,0) OPERATING PROFIT/ (LOSS) 19 54,5 44,0
31,5 30,1 Investment revenue 20 30,1 31,6
(10,1) (5,9) Finance costs 21 - (5,4)
26,8 4,2 PROFIT FOR THE YEAR 84,6 70,2
OTHER COMPREHENSIVE INCOME
- 819,5 Gains on property revaluation 2 1 083,7 -
26,8 823,7 TOTAL COMPREHENSIVE INCOME 22 1 168,3 70,2
CORPORATION GROUP
21
Armscor Challenges
Challenge Plan to overcome Insufficient Funding New funding model developed, such as
capability maintenance fee, royalties from IP and investment income
Exploitation of IP for dual use technologies Pursue acquisition opportunities for other
government department and SADC / AU countries
Resourcing of the organisation Grow human capability in line with business growth opportunities and demand Training and Skills Development Skills retention Succession planning
Implementation of Employment Equity Plan Executing of employee satisfaction survey
results
Operational inefficiencies and effectiveness Implementation of IT strategy Re-modernisation study of Dockyard
Local Industry Support Provide additional marketing support through pursuing government to government collaboration Establish strategic partnerships with international
technology know-how partners Local and international exhibitions Implementation of BEE and DIP
22
Questions & Answers
23