Presentation of Arsenic

Embed Size (px)

DESCRIPTION

about arsenic water

Citation preview

  • Presentation on

    Supply of arsenic free water for rural people

    Presented To

    Dr. Salehuddin Ahmed professor, BRAC Business School

    Course ID# FIN 603 Sec: 01

  • Presented by:

    Dilruba Khanam 13364005

    Adrita Razzque 13364063

    Oishee Manee 13164115

    Mohammad Shahidul Islam Khan 13364056

    June 16, 2015

  • Out line of our presentation:

    Arsenic Problem in Bangladesh

    Background and Justification

    Objectives of this project

    Project Implementation and Management Plan

    Project Monitoring and Evaluation

    Project Budget

  • Arsenic Problem in Bangladesh Arsenic in tube well water was first founded in Bangladesh in

    1993 by the Department of Public Health Engineering (DPHE) in Chapai Nawabganj.

    At present prevalence of arsenic in drinking water has been identified 61 out of 64 districts in Bangladesh.

    black foot disease, cardiovascular disease, neuropathy and cancer.

    Maximum permissible limit for Bangladesh 0.05 mg/l. WHO guideline value 0.01 mg/l.

  • Background and Justification

    'Action Research on Community-Based Arsenic Mitigation' project

    for the period June 1999- June 2000 of BRAC- There was

    dangerous arsenic contamination in water of Sonargaon upazila.

    90% tube wells were tested.

    among them 62% of the wells contain arsenic above 100 ppb1,

    had dangerous concentration.

  • 74% villages of Sonargaon had more than half of their wells contaminated.

    Therefore we selected the village pakundia of sonargoan upozila, Narayanganj district, for our project implementation.

    Emphasis will be placed on that the community to be involved as an integral part of the implementing force. Like: involvement in awareness program, arsenic test, contribution of fund, land, bamboo etc.

    This project proposal will help Government to meet Millennium Development Goals of Bangladesh for ensuring safe drinking water supply for the inhabitants by the year 2015.

  • Map of arsenic pollution in Sonargaon upazila

  • Objectives of this project

    Development objective:

    To ensure the supply of arsenic free pure drinking water.

    Immediate objective:

    Awareness raising against arsenic pollution both in local and national level.

    To develop resource map for the village of the project area.

  • Project Activities and work plan:

    Selected village for implementation of the project: Pakundia village of Sonargoan upazila in Narayanganj district.

    Supply of arsenic free water, Awareness campaign, Arsenic mitigation activities etc.

    Duration time of the project: 1st June 2015-31st July 2015

    Funded by: donor funded, self funded, community contribution, personal donor.

    Total cost of this project: TK.230,200/=

    Project Implementation and Management Plan

  • Work plan:

    Days Work activities Responsible person

    1.06.2015 -15.06.2015 Survey about arsenic OisheeManeeDilrubaKhanam

    and AdritaRazzaque

    16.06.2015 Analysis information Md. FirozAlam

    17.06.2015 5.07.2015 Fund collection Mohammad Shahidul Islam

    Khan

    6.07.2015 20.07.2015 Installation deep hand tube well Broewell Limited

    21.07.201526.07.2015 Build platform Broewell Limited

    27.07.2015 Sing board and message write Mohammad Shahidul Islam

    Khan

    28.07.2015 Arsenic test BRAC

    31.07.2015 Handling the deep tube wall to

    community

    BRAC

  • Project Beneficiaries:

    40 Families

    200 peoples

    Among them150 women and children

    Implementing agent management:

    a) BRAC and Broewell Limited

    b) BRAC: arsenic test kits, awareness mechanisms, training, fund.

    c) Broewell Limited : Installation of Deep hand tube well.

  • Deep Hand Tube Well:

  • Project Monitoring and Evaluation

    This project will be monitored by us and Mr. Amir Hossain who is the filed manager of BRAC. He will report to head of projector. According to report chief engineer will direct the worker or construction company about the project.

  • Project Budget

  • Financing for the DHTW project

  • Contribution of different donor:

    11% 9%

    18%

    17%

    28%

    17%

    contribution of different donor

    Cummunity Contribution

    personal donation

    Mutual Trust Bank Ltd

    City Group

    BRAC

    Jamuna Bank Ltd

  • Thank You