Presentation Masonry & Finishing

Embed Size (px)

DESCRIPTION

for storage purposes

Citation preview

FRONT ELEVATION OVERVIEWACTIVE LEVEL (STRUCTURAL)

FORMWORKS

WETWORKS

DRYWORKS

TOG

1

2

3

4

5

6

789

10

WETWORKS

39TH

38TH

37TH

36TH

PRECAST WALL CHB LAYING(PERIMETER WALL)

DOOR JAMBINSTALLATION

ZOCALLO(T&B)

BOX ALIGNMENT

PLASTERING (PERIMETER)

RUBBED CONCRETE(INTERIOR)

CHB LAYING(PARTITION & T&B WALL)

RUBBED CONCRETE(EXTERIOR)

ALUMINUM DOORS & WINDOW INSTALLATION

(PERIMETER)

WATERPROOFING APPLICATION

(T&B)

PLASTERING(LDK & T7B)

PUNCHLIST

PRIMER PAINTAPPLICATION(EXTERIOR)

SKIMCOAT APPLICATION(PRECAST)

SKIMCOAT APPLICATION(INTERIOR)

ALUMINUM DOORS & WINDOW INSTALLATION

(HALLWAY)

…back to Front Elevation

DRYWORKS

T&B TILES

TOG INSPECTION

789

10

PUNCHLIST (T&B) DRYWALL,CLADDING, CEILING FRAMING

MAIN DOOR HALLWAY WINDOWS

BOXSETTING/ WIRING SKIM COAT (T&B) LDK TILES DRYWALL CLOSURE

INTERMEDIATE PAINT INSTALLATION OF DEVICES BASEBOARD INSTALLATION SPRINKLER HEADS INSTALLATION

…back to Front Elevation

T&B Tiles Installation (DMCI)Status•Manpower: 12 Masons•Productivity: 24 T&B’s per wk/ 9 days per floor•Actual no. of floors from structural – 9 floors•Target no. of floors from structural – 7 floors•Floors delayed: 2 floor •Reason for delayed: Manpower

…back to Front Elevation

Punchlist T&B (Masonry Subcon)Status•Manpower: 2 Masons and 2 Concrete Planer•Productivity: 3 T&Bs per day per subcon•Actual no. of floors from structural – 9 floors•Target no. of floors from structural – 7 floors•Floors delayed: 2 floor •Reason for delayed: Other Trade (T&B Tiles Installation)

…back to Front Elevation

Drywall, Cladding, Ceiling Framing (Estolano)Status•Manpower:

Drywall/Cladding - 6 installersT&B Ceiling – 4 Installers

•Productivity: Drywall/Cladding – 12 units per dayT&B Ceiling Frame – 10 t&b per day

•Actual no. of floors from structural – 10 floors•Target no. of floors from structural – 7 floors•Floors delayed – 3 floors•Reason for delayed – other trades (Rubbed Concrete, Skim Coat and Ext Window)

…back to Front Elevation

Main Door Installation (DMCI)Status•Manpower: 2 Carpenters•Productivity: 6 Doors per day/ 7 days per floor•Actual no. of floors from structural – 9 floors•Target no. of floors structural – 8 floors•Floors delayed – 1 floor•Reason for delayed - Manpower

…back to Front Elevation

Hallway Windows (SPI)Status•Manpower: 2 installers•Productivity: 12 units per day/ 2 days per floor•Actual no. of floors from structural – 10 floors•Target no. of floors structural – 8 floors•Floors delayed – 2 floors•Reason for delayed – Other Trades (Rubbed Concrete)

…back to Front Elevation

Box Setting / Electrical Wiring (Anvic)

Status•Manpower: 4 persons•Productivity: 6 units per day/ 4 days per floor•Actual no. of floors from structural – 10 floors•Target no. of floors structural – 8 floors•Floors delayed – 2 floors•Reason for delayed – Other Trades (Hallway Windows)

…back to Front Elevation

Skim Coat Application T&B Wall (JBLS)Status•Manpower: 7 groups (2 persons each)•Productivity: 1 unit per 2 days/ 8 days per floor•Actual no. of floors from structural – 11 floors•Target no. of floors structural – 8 floors•Floors delayed – 3 floors•Reason for delayed – Other Trades (Masonry Punchlist)

…back to Front Elevation

Tiling LDK (DMCI)Status•Manpower: 5 groups (2 tilers each, 1 solo)•Productivity: 1 unit per 1.5 days/ 8 days per floor•Actual no. of floors from structural – 10 floors•Target no. of floors structural – 8 floors•Floors delayed – 2 floors•Reason for delayed – Other Trades (Masonry Punchlist)

…back to Front Elevation

Drywall, Cladding and Ceiling Closure (Estolano)Status•Manpower: 20 persons (6 installers, 14 jointers )•Productivity:

Drywall/ Cladding Closure – 1 unit/2days

Jointer – 2 units/day•Actual no. of floors from structural – 11 floors•Target no. of floors structural – 8 floors•Floors delayed – 3 floors•Reason for delayed – Other Trades (Box Setting)

…back to Front Elevation

Intermediate Paint (JBLS)Actual•Manpower: 10 groups ( 2 persons each)•Productivity: 2.5 days per unit•Actual no. of floors from structural – 11 floors•Target no. of floors structural – 9 floors•Floors delayed – 2 floors•Reason for delayed – Other Trades

…back to Front Elevation

Installation of Devices (Anvic)Status•Manpower: 4 persons•Productivity: 20 units per week•Actual no. of floors from structural – 11 floors•Target no. of floors structural – 9 floors•Floors delayed – 2 floors•Reason for delayed – Other Trades (Intermediate Paint)

…back to Front Elevation

Baseboard Installation (DMCI)Status•Manpower: 5 Carpenters•Productivity: 20 units per week•Actual no. of floors from structural – 11 floors•Target no. of floors structural – 9 floors•Floors delayed – 2 floors•Reason for delayed – Other Trades (Intermediate Paint)

…back to Front Elevation

Sprinkler Heads (Alpa)Status•Manpower: 1 Installer•Productivity: 20 units per week•Actual no. of floors from structural – 11 floors•Target no. of floors structural – 9 floors•Floors delayed – 2 floors•Reason for delayed – Other Trades (Intermediate Paint)

…back to Front Elevation

TOG INSPECTION

Status•Productivity: 20 units per week•Actual no. of floors from structural – 11 floors•Target no. of floors structural – 10 floors•Floors delayed – 1 floor

•Total Accepted – 338 units•Total Balance – 659 units•Projected end of turnover 20 units per week

- July 18, 2014…back to Front Elevation

PRECAST WALL

PRECAST WALL FABRICATION

Status : 24th floor

•Manpower: 2 carpenters•Productivity: 6 panels per day•Gap on Structural: 4 floors

PRECAST WALL INSTALLATION

Status : 24th floor

•Manpower: 2 carpenters•Productivity: 5 panels per day•Gap on Structural: 4 floors

•Target productivity: 10 panels per day•Additional manpower: 2 Carpenters

…back to Front Elevation

RUBBED CONCRETE(EXTERIOR)

Status: 21st Floor

•Manpower: 18 mason•Productivity: 10 days/floor•Gap from Structural: 7 Floors

•Target Productivity: 8 days/Floor•Additional manpower: 6 masons

…back to Front Elevation

CHB LAYING(EXTERIOR)

Status: 24TH Floor

•Manpower: 3 mason & 3 labor•Productivity: 3 days/floor•Gap from Structural: 4 Floors

…back to Front Elevation

DOOR JAMBINSTALLATION

Status: 24TH Floor

•Manpower: 2 Carpenters•Productivity: 8 Jambs/day•Gap from Structural: 4 Floors

…back to Front Elevation

ZOCALLO FORMWORKSINSTALLATION

(T&B)

Status: 24TH Floor

•Manpower: 1 Carpenter•Productivity: 4 units/day•Gap from Structural: 4 Floors

•Target Productivity: 8 units/day•Additional manpower: 1 Carpenter

…back to Front Elevation

BOX ALIGNMENT

Status: 24TH Floor

•Manpower: 2 PAX•Productivity: 5 days/floor•Gap from Structural: 4 Floors

…back to Front Elevation

PLASTERING(PERIMETER WALL)

Status: 23TH Floor

•Manpower: 5 Mason & 5 Labor•Productivity: 2 days/floor•Gap from Structural: 5 Floors

…back to Front Elevation

Punchlist(Exterior)

Status: 19TH Floor

•Manpower: 1 Mason (subcon)2 masons (dmci)

•Productivity: 3 days/floor•Gap from Structural: 9 Floors

…back to Front Elevation

RUBBED CONCRETE(INTERIOR)

Status: 18TH Floor

•Manpower: 24 Mason•Productivity: 10 days/floor•Gap from Structural: 10 Floors

•Target gap: 4 floors•Target productivity: 7 days/floor•Cause of delay: lack of manpower•Additional manpower needed: 24 masons until 3rd week of January

…back to Front Elevation

CHB LAYING(PARTITION & T&B)

Status: 23RD Floor

•Manpower: 15 Mason & 15 Labor•Productivity: 7 days/floor•Gap from Structural: 5 Floors

…back to Front Elevation

WATERPROOFINGAPPLICATION

(T&B))

Status: 20TH Floor

•Manpower: 3 pax•Productivity: 6 days/floor•Gap from Structural: 7 Floors

•Target Productivity: 3 days/floor•Target gap: 5 floors•Cause of delay: lack of manpower•Additional manpower needed: 4 pax

…back to Front Elevation

PLASTERING WORKS

PLASTERING (LDK)

Status : 22ND floor

•Manpower: 21 Mason & 21 Labor•Productivity: 7 days/floor•Gap on Structural: 6 floors

PLASTERING (T&B)

Status : 19th floor

•Manpower: 9 Mason & 9 Labor•Productivity: 7 days/floor•Gap on Structural: 9 floors

•Cause of Delay: Waterproofing application

…back to Front Elevation

PUNCHLIST

PUNCHLIST (LDK)

Status : 17TH & 18TH floor

•Manpower: 2 Mason & 2 Labor•Productivity: 7 days/floor•Gap on Structural: 9 floors

•Target Productivity: 4 days/floor•Target gap: 6 floors•Cause of delay: lack of manpower•Additional Manpower: 1 mason & 1 labor

PUNCHLIST (T&B)

Status : 17th floor

•Manpower: 3 Mason & 2 Labor•Productivity: 7 days/floor•Gap on Structural: 10 floors

•Taret Productivity: 4 days/floor•Target gap: 7 floors•Cause of Delay: tiling works•Additional Manpower: 1 Mason & 1 Labor

…back to Front Elevation

PRIMER PAINTAPPLICATION(perimeter)

Status: 20TH Floor

•Manpower: 1 Pax•Productivity: 3 days/floor•Gap from Structural: 7 Floors

•Target Productivity: 2 days/floor•Target gap: 5 floors•Cause of delay: Exterior Rubbed Concrete, punchlist

…back to Front Elevation

SKIMCOAT APPLICATION(perimeter)

Status: 18TH Floor

•Manpower: 1 Pax•Productivity: 5 days/floor•Gap from Structural: 9 Floors

•Target Productivity: 2 days/floor•Target gap: 5 floors•Cause of delay: Punchlist

…back to Front Elevation

ALUMINUM DOORS& WINDOWS(perimeter)

Status: 18TH Floor

•Manpower: 7 Pax•Productivity: 7 days/floor•Gap from Structural: 9 Floors

•Target Productivity: 3 days/floor•Target gap: 5 floors•Cause of delay: Skimcoat Application

…back to Front Elevation

SKIMCOAT APPLICATION

(interior)

Status: 17TH Floor

•Manpower: 14 Pax•Productivity: 7 days/floor•Gap from Structural: 10 Floors

•Target Productivity: 5 days/floor•Target gap: 6 floors•Cause of delay: Interior rubbed Concrete, Punchlist

…back to Front Elevation

ALUMINUM DOORS& WINDOWS

(hallway)

Status: 17TH Floor

•Manpower: 7 Pax•Productivity: 7 days/floor•Gap from Structural: 10 Floors

•Target gap: 5 floors•Cause of delay: Interior Rubbed concrete, Punchlist

…back to Front Elevation