25
21st Gulf Engineering Forum Construction projects: navigating the claims minefield Presentation ———— February 2018

Presentation ———— February 2018 21st Gulf …gef21.org/Downloads/14.40-15.05-Presentation-Cheryl...Focus on Variations What is a variation? FIDIC 4th Clause 51.1 gives power

  • Upload
    lekien

  • View
    214

  • Download
    2

Embed Size (px)

Citation preview

21st Gulf Engineering Forum Construction projects: navigating the claims minefield

Presentation ———— February 2018

Top tips

Top tips

● Claims on Construction Projects

● Tips for the Project Team and importance of

contemporaneous records

● How to defend a claim

● Focus on Variations

● Focus on Delay

Claims on Construction Projects

Contractor Claims on Construction Projects

● Claims for varied and additional works

● Extensions of time and associated prolongation and

disruption claims

● Claims for unforeseen physical conditions

● Measurement disputes

Employer Claims on Construction Projects

● Liquidated damages claims for delay

● Claims arising from defective works

● Claims for additional costs of an alterative contractor to

complete where original contractor terminated

How to evidence a claim on a construction

project

● Written records and documentary evidence

• Tender

• Contract documents

• Programme

• Drawings

• Instructions

• Requests for Information

How to evidence a claim on a construction

project

● Written records and documentary evidence contd:

• Correspondence

• Minutes of meeting

• Notices

• Site records, progress reports, photographs

• Financial and cost records

● Use a document management system

How to evidence a claim on a construction

project

● Witness evidence

• Key personnel with first hand knowledge

● Expert evidence

• Early technical input

How do you defend a claim?

How do you defend a claim?

● On receiving a claim priority is likely to be to defeat it

entirely

● Generally difficult, but circumstances can include:

• Claim brought in wrong forum

• Time bar of limitation

• Fundamental difficulty with claim

• Failure to comply with notice requirements

How do you defend a claim?

● Majority of claims are likely to involve a genuine dispute

● Claims are brought where there is entitlement to somepayment in addition

● Amount claimed by contractors tends to be inflated

● What should you do?

• Ascertain likely outcome of case

- Short summary of key differences

- Where’s the money?

• Consider settlement

- BUT be careful and consult with legal team

Focus on Variations

Focus on Variations

● What is a variation?

● FIDIC 4th Clause 51.1 gives power to the Engineer to “make any variation of the form, quality or quantity of the Works” by requiring the Contractor to:

• Increase or decrease the quantity of any work included in the Contract

• Omit any such work

• Change the character or quality or kind of any such work

• Change the levels, lines, position, dimension of any part of the works

• Execute additional work of any kind necessary for completion of the Works or

• Change any specified sequence or timing of construction of any part of the Works

Focus on Variations

● Why have Variations?

• Preserves the contract while allowing changes

• Gives the Employer the flexibility

• Gives the Employer a mechanism for extra work

• Ensures Contractor is paid for providing extra or

different work or materials

• Allows Employer to have more work carried out at

the same or similar prices

• Ensures that the contract is not frustrated

Focus on Variations

● Common issues:

• Already included in the contract?

• Does the contract allow Variations?

• Can work be deleted or omitted?

• Is the contractor entitled to be paid for a variation?

• Notice provisions?

• Any condition precedent to payment imposed by

the contract?

• Valuation of a Variation?

Focus on Delay

Typical Contractor delay events

● Variations

● Instructions

● Access

● Delays to

• Instructions

• Approvals

● Disruption to planned methodology

● Problems with Employer free issue items / materials

If you receive correspondence or claims listing any of

these items BEWARE

Typical Employer responses to claims of delay

● Under-resourced

● Inadequate time allowed

● Delays to Design / Approvals

● Late procurement

● Defects requiring remediation

● Poor contract management

● Issues with Subcontractors / Suppliers

Tools to assist identifying delay

● Factual witnesses

● Programmes

● Regular progress reports / meetings

● Instructions

● RFIs and Responses

● Notices of any defects

● Resourcing – planned vs actual

● Progress indicators / schedules

● Commissioning / handover schedules

Analysis of delay

● Forensic examination of project documents

● Delay analysis

• Contract requirements?

• Methodology – what fits with issues / project?

• What supporting records are available?

• Time available

Conclusion

Conclusion

● Ensure all key personnel aware of relevant contract

provisions

● Use your contact as a tool

● Document management system – put it in place and

use it

● Be constantly vigilant for potential claims and give

earliest possible notice

● Avoid advancing unmeritorious claims or position

Questions?

Contact

© Trowers & Hamlins LLP 2017

Trowers & Hamlins LLP is a limited liability partnership registered in England and Wales with registered number OC 337852 whose registered office is at 3 Bunhill Row, London EC1Y

8YZ. Trowers & Hamlins LLP is authorised and regulated by the Solicitors Regulation Authority. The word “partner” is used to refer to a member of Trowers & Hamlins LLP or an

employee or consultant with equivalent standing and qualifications or an individual with equivalent status in one of Trowers & Hamlins LLP’s affiliated undertakings. A list of the members

of Trowers & Hamlins LLP together with those non-members who are designated as partners is open to inspection at the registered office.

Trowers & Hamlins LLP has taken all reasonable precautions to ensure that information contained in this document is accurate, but stresses that the content is not intended to be legally

comprehensive. Trowers & Hamlins LLP recommends that no action be taken on matters covered in this document without taking full legal advice.

(c) Copyright Trowers & Hamlins – October 2017 – All Rights Reserved. This document remains the property of Trowers & Hamlins LLP. No part of this document may be reproduced in

any format without the express written consent of Trowers & Hamlins LLP.

Cheryl Cairns

International Construction Partner

d +971 (0)4 351 9201

e [email protected]