The catastrophic failure of the main blower of a the main blower of a petrochemical plant boiler
RhidiyanWaroko
08063319350806331935
Program StudiTeknik Material
Outline
� Analyze incident report
� Identify common failure� Identify common failure
� Identify common root cause
� Identify common manifestation
Analyze incident reportSystem description
� Power of blower 500 HP, by steam turbine at 5512 rpm through a gear box
� Has a rotational speed controller and a centrifugal over speed monitoringsystem (trip valve)system (trip valve)
Event chronology
• The event took place shortly after manually latching the trip valve to resetautomatic speed control.
• The rotor of blower was destroyed and parts of rotor caused severe damageto the blower housing and adjacent facilities.
• The leading edge of a blade was punched a water wall tube.
Identify common failure
Initial incident
IncidentCatastrophic failure at
petrochemical plant boiler
Blower PipingSignalling and control system
Steam turbine and lubrication
Suspect part
Initial incident Blower
Gear box Rotor shaft Rotor/ Blade
PipingSignalling and control system
and lubrication system
a. Housing b. Rotor shaftc. Gear box shaft d. Couplinge. Back plate f. Cone
Sequence of the failure:Breakage of one or more blade �
unbalanced force � Displacement coupling� deformation of rotor shaft and gearboxshaft � blade torn away and caused damageto the near facilities.
Identify common root cause
Failure Blower
Cause
Cause
Cause Blade
Operational conditions
Over speed Over heat
Design and material
Maintenance
Cause
Cause Over speed
Controlling system
Trip valve Operator
Over heat
Identify common root cause (2)
� Two over speed events took place previously tothe failure.the failure.
� Extrapolation evidences that the turbine mighthave reached a speed of the order of 1823 rpm.(1500 rpm)
� This over speed represents a 28% increase overthe rated speed and an increase of 63% inthe rated speed and an increase of 63% incentripetal acceleration.
� Consequently stresses suffered by the materialof the rotor also increase by 63%.
Identify common root cause (3)
Final failure event: Catastrophic failure, breakage of one or more blade
Breakage blade due to impact. Impact was found due to unbalanced forced at that system
Unbalanced forced at the system is cause by overspeed of rotor
There is a system to control rotational speedThere is a system to control rotational speed
Rotational speed controller was error
Identify Common Manifestation
� Checking a rotational speed controlsystemsystem
� Full stress analysis will be performed toasses proper safety factors and maximumallowable over speed.