Presentation - Building Science Capstone Project - CIBC Bank Retrofit

Embed Size (px)

Citation preview

  • 8/12/2019 Presentation - Building Science Capstone Project - CIBC Bank Retrofit

    1/30

    CIV 498Group Design Project

    CIBC Bank

    College and Spadina

    Authors: Brett Sagert 997233845 and

    Shuliang (Peter) Sun 996007440

  • 8/12/2019 Presentation - Building Science Capstone Project - CIBC Bank Retrofit

    2/30

    Presentation Layout

    Introduction

    Sustainability Measures

    Retrofits Considered- Photovoltaics - Passive Heating

    - Non-Passive Heating - Green Roofs

    - Rainwater Capture - Energy Efficient Fixtures

    - Windows

    Final Economics

  • 8/12/2019 Presentation - Building Science Capstone Project - CIBC Bank Retrofit

    3/30

    Site Location

    North West Corner of

    College and Spadina

    268 College Street

    High Walkability and

    Transit Access

    Built Late 1980s

  • 8/12/2019 Presentation - Building Science Capstone Project - CIBC Bank Retrofit

    4/30

    Current Condition

    Three main faades

    Three EntrancesTwo Pedestrian

    Typical Roof 480 m

    A Small Parking Lot

    One Washroom

    No Lighting Schedule

  • 8/12/2019 Presentation - Building Science Capstone Project - CIBC Bank Retrofit

    5/30

    Energy Consumption Baseline

    63,000 ekWh Electrical

    Consumption

    300,000 ekWh Natural

    Gas Consumption

    282 m of Water

    Consumption

    (Assumption of 50 trips

    to washroom/day)

  • 8/12/2019 Presentation - Building Science Capstone Project - CIBC Bank Retrofit

    6/30

    Sustainability Measures

    Energy and Cost

    Significant savings to building

    Projects must payback within ten year time period

    Water Management

    Zero consumption of city water, self-reliance

    Energy efficient fixtures

    Embodied Energy

    Life cycle analysis

  • 8/12/2019 Presentation - Building Science Capstone Project - CIBC Bank Retrofit

    7/30

    Sustainability Measures

    Energy and Cost

    Significant savings to building

    Projects must payback within ten year time period

    Water Management

    Zero consumption of city water, self-reliance

    Minimal consumption of city water

    Energy efficient fixtures

    Embodied Energy

    Life cycle analysis

  • 8/12/2019 Presentation - Building Science Capstone Project - CIBC Bank Retrofit

    8/30

    Life Cycle Analysis (LCA)

    4 levels, in our analysis we look at 1st level(direct energy input)

    Manish K. Dixit, Charles H. Culp, Jose L Fernandez-Solis (2013)Our study

    when you consume anything, you are consuming energy."

  • 8/12/2019 Presentation - Building Science Capstone Project - CIBC Bank Retrofit

    9/30

    Life Cycle Analysis (LCA) II

    In a buildings life cycle theres Embodied Energy (2-38%) and

    operational energy

    In our LCA(1stlevel) we took into account the energy involved in

    the raw material acquiring and transporting raw materials,

    manufacturing, constructing, operating, decommissioning, and

    disposal.

  • 8/12/2019 Presentation - Building Science Capstone Project - CIBC Bank Retrofit

    10/30

    Life Cycle Analysis (LCA) III

    By completing a LCA we are able to see the

    effects that products, processes, and activities

    that have on local, regional or global

    environments.

    Steel Aluminum Lumber Straw bale Concrete (30 Mpa) Glass

    Virgin / Recycled

    (MJ/Kg) 32/10 191/8 8.5 0.24 1.3 15.9

    Embodied Carbon

    (kg CO2 /kg) 1.8/0.7 8/1.7 0.46 0.24 1.3

    Why is it important?

  • 8/12/2019 Presentation - Building Science Capstone Project - CIBC Bank Retrofit

    11/30

    Life Cycle Analysis (LCA) III

    By completing a LCA we are able to see the

    effects that products, processes, and activities

    that have on local, regional or global

    environments.

    Steel Aluminum Lumber Straw bale

    Concrete

    (30 Mpa) GlassRecycled

    (MJ/Kg) 10 8

    Virgin (MJ/Kg) 32 191 2.5 0.24 1.3 15.9

    Why is it important?

  • 8/12/2019 Presentation - Building Science Capstone Project - CIBC Bank Retrofit

    12/30

    Photovoltaics-Off set peak electricity. FIT 2.0 rates for photovoltaic around 0.55$/ekWh.

    -Want to install 10 kW system require about 90 m out of 478 m roof space

  • 8/12/2019 Presentation - Building Science Capstone Project - CIBC Bank Retrofit

    13/30

    Photovoltaics-Off set peak electricity. FIT 2.0 rates for photovoltaic around 0.55$/ekWh.

    -Want to install 10 kW system require about 90 m out of 478 m roof space

    LCA 1 kW 10kw system

    Embodied Energy (kWh) 5598 55,980Space needed (ft^2) 100 1,000

    (m^2) 9.7 97

    Energy Generated kWh/year 1200 12,000

    Payback Period (yrs) 5

    Sanyo HIT Power 240S

    Sanyo HIT 240S

    Rated Power (S.T.C) 240 W

    Cell Efficiency 21.6 %

    Rated Power for 42 panels 10.1 kW

    Panels per module 5 ( 1.2 kW)

    Number of modules 7

    Price per panel $560

    Total price (42 panels) $23,520

  • 8/12/2019 Presentation - Building Science Capstone Project - CIBC Bank Retrofit

    14/30

    0.00

    10.00

    20.00

    30.00

    40.00

    50.00

    60.00

    70.00

    80.00

    90.00

    0.00 90.00 180.00 270.00 360.00

    Elevation

    (degree

    s)

    Magnetic Bearing (degrees)

    Sun Position

    JulyAugustSeptember

    OctoberNovemberDecember9:00JanuaryFebruaryMarch

    42.000 -80.00042d 0m 0s -80d 0m 0s

    For LocationLocal Standard Time UTC-8 Local Standard Time UTC-8 Local Standard Time (UTC-8)

    0

    100

    200

    300

    400

    500

    600

    700

    800

    900

    1000

    0 4 8 12 16 20 24

    January

    February

    March

    April

    May

    June

    July

    August

    September

    October

    November

    December

    Time (hr)

    Isolation

    (w/m^2)

    Average Daily Insolation

    Time (hr)

    Isolation

    (w/m^2)

    Average Daily InsolationLocal Standard Time (UTC-8)

    From solar insolation design tool

  • 8/12/2019 Presentation - Building Science Capstone Project - CIBC Bank Retrofit

    15/30

    Assumptions: S.H.G.C. = 0.75 Window size: West (3.3m2) East (60 m2) South (85 m2)

    Annual =~ 340,000 ekWh

    0 2000 4000 6000 8000 10000 12000

    Jan

    Feb

    mar

    Apr

    May

    Jun

    Jul

    Aug

    Sep

    Oct

    Nov

    Dec

    Jan Feb mar Apr May Jun Jul Aug Sep Oct Nov Dec

    Series1 4636 5442 8131 9403 9717 7724 10542 9583 9915 8384 6323 4866

    Monthly solar gain from windows (ekWh)

    From solar insolation design tool

  • 8/12/2019 Presentation - Building Science Capstone Project - CIBC Bank Retrofit

    16/30

    Many potential options

    for passive lighting given

    the high glazing ratio on

    eastern and southernfaades

    Solutions:

    Eastern FaadeLightshelves and blinds

    Southern FaadeLight

    shelves, trees and blinds

    Passive Lighting and Heating

  • 8/12/2019 Presentation - Building Science Capstone Project - CIBC Bank Retrofit

    17/30

    Many potential options

    for passive lighting given

    the high glazing ratio on

    eastern and southernfaades

    Solutions:

    Eastern Faade

    Lightshelves and blinds

    Southern FaadeLight

    shelves, trees and blinds

    Passive Lighting and Heating

    Light Shelves Retrofit

    Cost ($/Light Shelf) 100 $/Light Shelf

    Amount of Shelves Required 16

    Material Cost ($) 1600 $

    Labour Cost ($) 640 $

    Total Cost ($) 2240 $

    Energy Savings 14% of Lighting Load

  • 8/12/2019 Presentation - Building Science Capstone Project - CIBC Bank Retrofit

    18/30

    Non-Passive Lighting

    LED Lighting vs CFL Lighting

    Light Sensors

  • 8/12/2019 Presentation - Building Science Capstone Project - CIBC Bank Retrofit

    19/30

    Non-Passive Lighting

    LED Lighting vs CFL Lighting

    Light Sensors

    Non-Passive Lighting Retrofits

    Cost of LED Bulb ($/Bulb) 25 $/Bulb with 5$ Rebate

    Amount of Bulbs Required 275

    Cost of Light Sensor ($/Sensor) 63$/Sensor

    Sensors Required 7

    Labour Cost 960 $

    Total Combined Cost ($) 8300 $

    Energy Savings LED Bulbs 50% of Lighting Load

    Energy Savings Light Sensors 20% of Lighting Load

  • 8/12/2019 Presentation - Building Science Capstone Project - CIBC Bank Retrofit

    20/30

    Green Roofs

    Benefits: Increase R-value of roof, reduce

    urban heat island effect.

    Intensive vs Extensive

  • 8/12/2019 Presentation - Building Science Capstone Project - CIBC Bank Retrofit

    21/30

    Green Roofs

    Benefits: Increase R-value of roof, reduce

    urban heat island effect.

    Intensive vs Extensive

    Life Cycle Analysis (LCA) Area (m^2) MJ

    Study(K.Myrans) 1 2,850

    Rooftop 478 1,361,588

    Total Savings (MJ/year) 7,170

    Payback Period (years) 190

    *saving from Green Roofs as Urban Ecosystems (2007)

  • 8/12/2019 Presentation - Building Science Capstone Project - CIBC Bank Retrofit

    22/30

    Rainwater Capture and Energy

    Efficient Fixtures

    10,000 Liter Cistern

    Replace old toilet

    13L/flush with high

    efficient toilet4.8L/flush

    Replace the old

    faucets 8L/min withhigh efficiency faucet

    3.2L/min

  • 8/12/2019 Presentation - Building Science Capstone Project - CIBC Bank Retrofit

    23/30

    Cistern Data

    -5

    0

    5

    10

    15

    20

    25

    30

    35

    WaterVolume[m3]

    Time

    Harvested Water Use Gain (L)Use (L)

    Net (L)

  • 8/12/2019 Presentation - Building Science Capstone Project - CIBC Bank Retrofit

    24/30

    Rainwater Capture and Energy

    Efficient Fixtures

    10,000 Liter Cistern

    Replace old toilet

    13L/flush with high

    efficient toilet4.8L/flush

    Replace the old

    faucets 8L/min withhigh efficiency faucet

    3.2L/min

  • 8/12/2019 Presentation - Building Science Capstone Project - CIBC Bank Retrofit

    25/30

    Rainwater Capture and Energy

    Efficient Fixtures

    10,000 Liter Cistern

    Replace old toilet

    13L/flush with high

    efficient toilet4.8L/flush

    Replace the old

    faucets 8L/min withhigh efficiency faucet

    3.2L/min

    Water Retrofits

    Cost of Cistern + Labour ($) 5380 $

    Cost of New Toilet + Labour ($) 520 $

    Cost of New Faucets + Labour ($) 210 $

    Total Combined Cost ($) 6110 $

    Original Water Consumption (m) 282

    Combined Water Savings (m) 264

    Annual Water Savings 94%

    d

  • 8/12/2019 Presentation - Building Science Capstone Project - CIBC Bank Retrofit

    26/30

    Windows

    Prominent feature of the building site.

    Currently single glazed 1/2 with aluminumframing.

    window m^2 ft^2

    West 3.3 11

    East 60 194

    South 85 274

    total =

    (N,E,S,W) 148.3 478

    the eyes to a building

    Double glazed with argon fill vs

  • 8/12/2019 Presentation - Building Science Capstone Project - CIBC Bank Retrofit

    27/30

    Double glazed with argon fill vs.

    Electro-Chromic

    http://www.efficientwindows.org/glazing_.cfm?id=6

    Study: ( G.Weier & Muneer)

    (E. Syrrakou, S.Papaefthimiou*, N.

    Skarpentzos and P.

    Yianoulis)

    Type Argon Electro chromic

    Area

    (m^2) ekWh ekWh

    *Study

    Window 1 199 51

    West 3 656 169

    East 60 11,933 3,067

    South 85 16,905 4,344

    Total =

    (N,E,S,W) 148 29,494 7,580Total savings

    (kWh/year) 16,802 22,136

    Payback period (years) 1.8 0.3

    Double Glazed Argon fill

    Double Glaze Electro Chromic

    E. Syrrakou, S. Papaefthimiou*, N. Skarpentzos and P. Yianoulis (2005)

  • 8/12/2019 Presentation - Building Science Capstone Project - CIBC Bank Retrofit

    28/30

    Retrofit Savings Summary

    Retrofit

    Material

    Cost ($)

    Number

    of Hours

    Labour

    Cost ($)

    Material

    + Labor

    Cost ($)

    Electricity

    gas

    Energy

    Savings

    (kWh)

    Fit

    Electricity

    Energy

    Savings

    (kWh)

    Water

    Savings

    (m^3)Electrical Photovoltaics 50000 24 0 50000 0 12000 0

    LED Lighting 6875 11 880 7755 8805 0 0

    Light Shelves 1600 8 640 2240 1761 0 0

    Light Sensors 441 1 80 521 1233 0 0

    Water Cistern 4100 16 1280 5380 0 0 264

    Toilet 200 4 320 520 0 0 0

    Faucets 65 1 80 145 0 0 0

    Total Savings 63,281 65 3,280 66,561 11,799 12,000 264

  • 8/12/2019 Presentation - Building Science Capstone Project - CIBC Bank Retrofit

    29/30

    75%

    12%

    3%1%

    8%

    1% 0%

    Retrofit Breakdown By Cost

    Photovoltaics

    LED Lighting

    Light Shelves

    Light Sensors

    Cistern

    Toilet

    Faucets

    51%37%

    7%5%

    Retrofit Breakdown by Electrical Savings

    Photovoltaics

    LED Lighting

    Light Shelves

    Light Sensors

    Retrofit Breakdown

  • 8/12/2019 Presentation - Building Science Capstone Project - CIBC Bank Retrofit

    30/30

    Economic Payback

    $(60,000)

    $(50,000)

    $(40,000)

    $(30,000)

    $(20,000)

    $(10,000)

    $-

    $10,000

    $20,000

    $30,000

    1 2 3 4 5 6 7 8 9 10

    Capital Over A 10 Year Time Peroid