Upallo Khimti and Upper Khimti-II Hydropowerc Project Progress Report No. 3 May 2016 Project Name: 01 Upallo Khimti, 12MW Hydro Power Project Project Name: 02 Upper Khimti-II, 7MW Hydropower Project. Report for: Himalaya Urja Bikas Company Limited Preparation Review and Authorisation Date Prepared by Reviewed by Approved for Issue by 2016.05.06 Er. Rama Kant Gauro Eng. Saroj Kumar Upadhyay Hari Prasad Pandey Er. Lav Kumar Shrestha Eng. Saroj Kumar Upadhyay Er. Susheel Sharma Dr. Bhim Prasad Neupane Er. Kapil Acharya Er. Yam Lal Tharu Bikram Khawas COMPANY DETAILS Himalaya Urja Bikas Company Ltd. Subhidhanagar, Tinkune, Kathmamdu-35 ,Nepal GPO Box: 8973 NPC868, Tel: + 977- 1-4111 853/ 1-4111 673/ 1-4111 674/ Email: [email protected] Web Page: URL: www.himalurja.com Authorized Person: Eng. Saroj Kumar Upadhyay, M.Sc.in Civil Engineering (Hons.), M B A Director – Technical and Project Management Email: [email protected] Address: - Project Management Office Head Office Chuchure VDC-1, Ramechhap, Nepal Subhidhanagar, Tinkune-35, + 977 – 1 – 6206 742 (Technical) Admin: 6220 004 Kathmamdu, Nepal VSAT No: 9945 30032 (Admin) +977-1-4111 853/ 4111 673 Technical: 9945 30033, Director: 9945 30034

Preparation Review and Authorisation Date Prepared by ... amp House ( Office lock and Officer’s lock) New Nepal Nirman Sewa 6 Fencing with CGI sheet at JIFASA CAMP AREA New Nepal

Embed Size (px)

Citation preview

Page 1: Preparation Review and Authorisation Date Prepared by ... amp House ( Office lock and Officer’s lock) New Nepal Nirman Sewa 6 Fencing with CGI sheet at JIFASA CAMP AREA New Nepal

Upallo Khimti and Upper Khimti-II Hydropowerc Project Progress Report No. 3

May 2016

Project Name: 01 Upallo Khimti, 12MW Hydro Power Project

Project Name: 02 Upper Khimti-II, 7MW Hydropower Project.

Report for: Himalaya Urja Bikas Company Limited

Preparation Review and Authorisation

Date Prepared by Reviewed by Approved for Issue by

2016.05.06 Er. Rama Kant Gauro Eng. Saroj Kumar Upadhyay Hari Prasad Pandey

Er. Lav Kumar Shrestha Eng. Saroj Kumar Upadhyay

Er. Susheel Sharma Dr. Bhim Prasad Neupane

Er. Kapil Acharya

Er. Yam Lal Tharu

Bikram Khawas

COMPANY DETAILS

Himalaya Urja Bikas Company Ltd. Subhidhanagar, Tinkune, Kathmamdu-35 ,Nepal GPO Box: 8973 NPC868, Tel: + 977- 1-4111 853/ 1-4111 673/ 1-4111 674/ Email: [email protected] Web Page: URL: www.himalurja.com

Authorized Person: Eng. Saroj Kumar Upadhyay, M.Sc.in Civil Engineering (Hons.), M B A

Director – Technical and Project Management Email: [email protected]

Address: - Project Management Office Head Office Chuchure VDC-1, Ramechhap, Nepal Subhidhanagar, Tinkune-35, + 977 – 1 – 6206 742 (Technical) Admin: 6220 004 Kathmamdu, Nepal VSAT No: 9945 30032 (Admin) +977-1-4111 853/ 4111 673 Technical: 9945 30033, Director: 9945 30034

Page 2: Preparation Review and Authorisation Date Prepared by ... amp House ( Office lock and Officer’s lock) New Nepal Nirman Sewa 6 Fencing with CGI sheet at JIFASA CAMP AREA New Nepal

Upallo Khimti and Upper Khimti-II Hydropower Project Progress Report No. 3

i May 2016

Table of Contents

Project Details ............................................................................................................................... 1

1.1 Description ...............................................................................................................................1

1.1.1 Upallo Khimti Hydropower Project - 12 MW....................................................................1

1.1.2 Upper Khimti-II Hydropower Project -7 MW ....................................................................1

1.2 Schematic Diagram ...................................................................................................................2

1.2.1 Schematic Diagram of Upallo Khimti Hydroelectric Project-12 MW ................................2

1.2.2 Schematic Diagram of Upper Khimti Hydroelectric Project-7 MW ..................................3

1.3 The Parties ................................................................................................................................4

1.3.1 Employer...........................................................................................................................4

1.3.2 Design and Detailed Engineering Consultant ...................................................................4

1.3.3 Lot I Contract - Infrastructure Development ....................................................................4

1.3.4 Lot II Contract: Civil Construction Works .........................................................................5

1.3.5 Lot III Contract: Hydro Mechanical Works .......................................................................5

1.3.6 Lot IV Contract: Electro Mechanical Works ......................................................................5

1.3.7 Lot V: Ramechap Khimti Garjyang 132 KV Transmission Line Project .............................5

1.3.8 Due Diligence Consultant for Bill verification Works: ......................................................6

1.3.9 Lending Commercial Banks: .............................................................................................6

2. Key Dates .................................................................................................................................. 7

3. Progress Report Executive Summary .......................................................................................... 8

3.1 Introduction ..............................................................................................................................8

3.2 General .....................................................................................................................................8

3.3 Engineering Detailed Design Consultant ..................................................................................8

3.4 Communication ........................................................................................................................9

3.5 Effects of Earthquake in the Project .........................................................................................9

3.6 Effects of Terai Bandha in the Project ......................................................................................9

4. Land Acquisition and Access Road Construction........................................................................ 10

4.1 Land Acquisition .................................................................................................................... 10

4.2 Land Leasing .......................................................................................................................... 10

4.3 Access Road Construction ..................................................................................................... 10

5. Camp House ............................................................................................................................ 11

5.1 Jifasa Camp : (Camp No 1) Project Management Office ...................................................... 11

5.2 Argeli Ghari Camp : Camp No 2 ............................................................................................. 11

5.3 Garjyang Camp: Camp No 3 .................................................................................................. 11

Page 3: Preparation Review and Authorisation Date Prepared by ... amp House ( Office lock and Officer’s lock) New Nepal Nirman Sewa 6 Fencing with CGI sheet at JIFASA CAMP AREA New Nepal

Upallo Khimti and Upper Khimti-II Hydropower Project Progress Report No. 3

ii May 2016

5.4 Kharanetar Camp: Camp No: 4 .............................................................................................. 11

6. Construction Power ................................................................................................................. 12

6.1 Study of Reliability and Power Available at Site .................................................................... 12

6.2 Procurement of Material ....................................................................................................... 12

6.3 Construction of Construction Power ..................................................................................... 12

7. Lot II: Civil Works ..................................................................................................................... 13

7.1 Preliminary Works ................................................................................................................. 13

7.2 Contractor Selection .............................................................................................................. 13

7.3 Construction Materials Survey .............................................................................................. 13

7.4 Detailed Time Programme .................................................................................................... 13

7.5 Camp of the Civil Contractor ................................................................................................. 13

7.6 Personnel and Equipment of the Civil Contractor ................................................................. 13

7.7 Material Stock at Site ............................................................................................................ 14

7.8 7 MW Headworks .................................................................................................................. 14

8. Lot III Contract – Hydro Mechanical Works ............................................................................... 15

8.1 Preliminary Works ................................................................................................................. 15

8.2 Contract Award ..................................................................................................................... 15

8.3 Camp ...................................................................................................................................... 15

8.4 Personnel ............................................................................................................................... 15

8.5 Equipment ............................................................................................................................. 15

8.6 Workshop Establishment ...................................................................................................... 15

8.7 Steel Plates ............................................................................................................................ 15

9. Lot IV Contract – Electromechanical Works .............................................................................. 16

9.1 Preliminary Works ................................................................................................................. 16

9.2 Contract Award ..................................................................................................................... 16

10. Human Resources .................................................................................................................. 17

10.1 Head Office, Kathmandu ....................................................................................................... 17

10.2 Project Management Office, Chuchure ................................................................................. 17

11. Social Mitigation .................................................................................................................... 19

12. Financial Status ..................................................................................................................... 20

Page 4: Preparation Review and Authorisation Date Prepared by ... amp House ( Office lock and Officer’s lock) New Nepal Nirman Sewa 6 Fencing with CGI sheet at JIFASA CAMP AREA New Nepal

Upallo Khimti and Upper Khimti-II Hydropower Project Progress Report No. 3

iii May 2016

APPENDIX 1: CIVIL CONSTRUCTION SCHEDULE

APPENDIX 2: PHOTOGRAPHS

APPENDIX 3: LAND ACQUISTION DETAILS

APPENDIX 4: TENDER EVALUATION CRITERIA

Page 5: Preparation Review and Authorisation Date Prepared by ... amp House ( Office lock and Officer’s lock) New Nepal Nirman Sewa 6 Fencing with CGI sheet at JIFASA CAMP AREA New Nepal

Upallo Khimti and Upper Khimti-II Hydropower Project Progress Report No. 3

iv May 2016

Acronyms

AB Anchor Block AR Access Road BM Bench Mark BoQ Bill of Quantities CEC Clean Energy Consultants Pvt. Ltd DDC District Development Committee DoED Department of Electricity Development EM Electro Mechanical DTP Detailed Time Programme GCAP Gaurishankar Conservation Area Project GWh Giga Watt hour HM Hydro Mechanical HUBCL Himalaya Urja Bikash Company Limited HW Headworks kW Killo Watt IEE Initial Environmental Examination MR Monthly Report MSL Mean Sea Level MW Mega Watt NEA Nepal Electricity Authority PA Penstock Alignment PH Power House TR Tailrace ToD Time of Day UKHP-II Upper Khimti-II Hydropower Project UKHP Upallo Khimti Hydropower Project VAT Value Added Tax VDC Village Development Committee

Page 6: Preparation Review and Authorisation Date Prepared by ... amp House ( Office lock and Officer’s lock) New Nepal Nirman Sewa 6 Fencing with CGI sheet at JIFASA CAMP AREA New Nepal

Upallo Khimti and Upper Khimti-II Hydropower Project Progress Report No. 3

1 of 20 May 2016

Project Details

1.1 Description 1.1.1 Upallo Khimti Hydropower Project - 12 MW

Upallo Khimti Hydropower Project (UKHP) 12 MW is located mostly in Chuchure VDC of Ramechhap district, Janakpur Zone, Central Development Region of Nepal. The project area is located between longitudes 86o 19' 20" E to 86o 21' 40" E and latitudes 27o 39' 24" N to 27o 41' 54" N. The project components are located between elevations of 2003 m to 2303 m.

UKHP is a run-of-river hydropower project. Intake is located at near the confluence of Ghwang Khola and Khimti at altitude of 2300m form MSL, where water is taken from the Khimti River. The project will exploit a gross head of approx. 300 m on the Khimti river over a reach of about 3.5 km along the left bank of river to the tailrace outlet near Jifasa village of altitude of about 2000m form MSL. The surface powerhouse is located near Jifasa village and two horizontal axis Pelton turbine/generating units are to be installed, each of rated capacity 6.0 MW. At the installed capacity of 12 MW, it is estimated that the average annual energy production will be 73.61 GWh. The following table shows the basic feature of the project:

Feature UKHP HEP

Installed Capacity 12 MW

Gross Head 300.0 m

Annual Sellable Energy 73.61 GWh

Design Discharge 5.61 m3/s

Degree of Flow Exceedence 40%

1.1.2 Upper Khimti-II Hydropower Project -7 MW

Upper Khimti-II Hydro Power Project (UKHP-II) 7 MW is a cascade RoR type of scheme located just downstream of Upallo Khimti Hydropower Project, 12MW located in Ramechhap district. The project components are located in left bank of Khimti Khola within Chuchure VDC. The project area is located between longitudes 860 18’10”E to 860 20’10”E and latitude 270 38’20” N to 270 39’55” N. Water is taken from the Khimti River at the intake of the Upallo Khimti and is passed through the Upallo Khimti project Powerhouse and delivered directly to the Intake of the Upper Khimti project. The only source of water for the Upper Khimti project is that which passes through the Power Station of the Upallo Khimti project, supplemented to a small degree with additional water from Khimti khola The following table shows the basic feature of the project:

Feature UKHP-II HEP

Installed Capacity 7 MW

Gross Head 145.0 m

Annual Saleable Energy 42.29 GWh

Design Discharge 6.45 m3/s

Degree of Flow Exceedence 40%

Page 7: Preparation Review and Authorisation Date Prepared by ... amp House ( Office lock and Officer’s lock) New Nepal Nirman Sewa 6 Fencing with CGI sheet at JIFASA CAMP AREA New Nepal

Upallo Khimti and Upper Khimti-II Hydropower Project Progress Report No. 3

2 of 20 08 May 2016

1.2 Schematic Diagram 1.2.1 Schematic Diagram of Upallo Khimti Hydroelectric Project-12 MW

Page 8: Preparation Review and Authorisation Date Prepared by ... amp House ( Office lock and Officer’s lock) New Nepal Nirman Sewa 6 Fencing with CGI sheet at JIFASA CAMP AREA New Nepal

Upallo Khimti and Upper Khimti-II Hydropower Project Progress Report No. 3

3 of 20 08 May 2016

1.2.2 Schematic Diagram of Upper Khimti Hydroelectric Project-7 MW

Page 9: Preparation Review and Authorisation Date Prepared by ... amp House ( Office lock and Officer’s lock) New Nepal Nirman Sewa 6 Fencing with CGI sheet at JIFASA CAMP AREA New Nepal

Upallo Khimti and Upper Khimti-II Hydropower Project Progress Report No. 3

4 of 20 08 May 2016

1.3 The Parties

The project entities are listed below.

1.3.1 Employer

Himalaya Urja Bikas Company Limited (HUBCL) Subhidhanagar, Kathmandu, Nepal

1.3.2 Design and Detailed Engineering Consultant

Clean Energy Consultants Pvt. Ltd Anamanagar, Kathmandu, Nepal

1.3.3 Lot I Contract - Infrastructure Development Lot I Contracts includes Infrastructure Development works such as Access Road Construction, Camp House Construction, 11kv/400 Construction Power and other related works. Himalaya Urja Bikas Company has undertaken the construction of these activities own its own engaging local community, contractors and youth.

S.N Description of the Work Contractor

1 Landslide Treatment Works Ramechhap Panch Pokhari Nirman Sewa

2 Causeway at Chake Khola Ramechhap Panch Pokhari Nirman Sewa

3 Fencing with CGI sheet at Kharanitar Ramechhap Panch Pokhari Nirman Sewa

4 Camp House ( Jr Staff Block and Camp 2) New Nepal Nirman Sewa

5 Camp House ( Office Block and Officer’s Block) New Nepal Nirman Sewa

6 Fencing with CGI sheet at JIFASA CAMP AREA New Nepal Nirman Sewa

7 Raj Kulo at Gargang Khola J & K Construction Private Limited

8 Director’s Block-1 and Outdoor Toilet -1 J & K Construction Private Limited

9 Garage -1 & Septic Tank-2 J & K Construction Private Limited

10 Garjang Crossing (Causeway) Local Contractor

11 Camp No 2 at Argeli Gahari New Nepal Nirman Sewa

Page 10: Preparation Review and Authorisation Date Prepared by ... amp House ( Office lock and Officer’s lock) New Nepal Nirman Sewa 6 Fencing with CGI sheet at JIFASA CAMP AREA New Nepal

Upallo Khimti and Upper Khimti-II Hydropower Project Progress Report No. 3

5 of 20 08 May 2016

1.3.4 Lot II Contract: Civil Construction Works Lot II includes all the contracts related to Civil Construction Works. The bid for the work was given to the following Civil Engineering Contractors mainly A Class and experienced in Hydro Power Construction. Among Himal Hydro and General Construction Company Limited, South Asian Infrastructure (P.), High Himalaya Construction Company Limited and B P Construction (P.) Ltd the contract has been awarded to the highest ranking scorer which is B P Construction (P.) Ltd. Quality and Cost Based Evaluation, (QCBS) has been applied while evaluating the tender documents. The evaluation criteria are attached at Annexure IV. Registration Number of B P Construction (P.) Ltd is 15944/058/059 established dated 2050/05/26; License Number is 2363 A Class Contractor. VAT Registration number is 300011986 dated 2054/11/22.

1.3.5 Lot III Contract: Hydro Mechanical Works

Lot III includes all the contracts related to Hydro Mechanical Works. We have already purchased

Steel Plates from Steel Authority of India, (SAIL).that is confirming to IS-2062 BO/2011 E350 BO or

equivalent.

The bid was asked from the following contractors: Nepal Hydro & Electric Limited, (NHE), Cream Hydel (P.) Ltd and Machhapuchhre Metal and Machinery Works (P.) Ltd Quality and Cost Based Evaluation, (QCBS) has been applied while evaluating the tender document. The contract agreement has been signed with highest scorer Machhapuchre Metal and Machinery Works (P.) Ltd from Industrial District Estate, Pokhara. The evaluation criteria are attached at Annexure IV.

1.3.6 Lot IV Contract: Electro Mechanical Works Lot IV includes all the contracts related to Electro Mechanical Works Switchyard and Interconnection and the bid has been asked from the following contractors: All six bidders have submitted their bids. Tender evaluation work is on progress and will be completed by the end of Jestha 2073. Quality and Cost Based Evaluation, (QCBS) has been applied while evaluating the tender documents

1.3.7 Lot V: Ramechap Khimti Garjyang 132 KV Transmission Line Project Lot V is construction works for Ramechap Khimti Garjyang 132 KV Transmission Line Project is Nepal Electricity Authority’s Work. The land acquisition work for 132 kV sub station has been completed by NEA and the civil contract for compound wall construction work and staff quarter work at the Proposed Sub Station will be awarded soon. The proposed site is in Garjyang, Chuchure VDC in Ramechap District. A Memorandum of Understanding will be established soon between NEA and HUBCL for the speedy construction work for 30 km long 132 kV Transmission Line on Public Private Partnership Basis. HUBCL will make every effort to complete the Transmission Line Project on time.

Page 11: Preparation Review and Authorisation Date Prepared by ... amp House ( Office lock and Officer’s lock) New Nepal Nirman Sewa 6 Fencing with CGI sheet at JIFASA CAMP AREA New Nepal

Upallo Khimti and Upper Khimti-II Hydropower Project Progress Report No. 3

6 of 20 08 May 2016

1.3.8 Due Diligence Consultant for Bill verification Works: The selection of Technical Due Diligences Consultant for Bill Verification works is at Final Stage now. Proposal has been obtained from Feedback Infrastructure, Sanima Hydro and Engineering (P.) Ltd., Hydro Consult Engineering Limited. Negotiation meeting with Hydro Consult Engineering Limited is going on that will be converted into agreement. Similarly the Due Diligence selection works of Financial Consultant for Bill verification has been initiated and will be accomplished soon.

1.3.9 Lending Commercial Banks: NABIL Bank is the Lead Commercial Bank lending Project Finances. Members Banks for this consortium includes Nepal Bank Limited, Everest Bank Limited and ACE Development Bank Limited.

Page 12: Preparation Review and Authorisation Date Prepared by ... amp House ( Office lock and Officer’s lock) New Nepal Nirman Sewa 6 Fencing with CGI sheet at JIFASA CAMP AREA New Nepal

Upallo Khimti and Upper Khimti-II Hydropower Project Progress Report No. 3

7 of 20 08 May 2016

2. Key Dates

The following are the key dates: -

S.N Development and Progress Details Dates

12 MW 7MW

1 Capacity Upgrade and received new License from DoED 2066 Jestha 20

2067 Ashadh 17

2 IEE Approved 2067 Shrawan 21 2071 Ashadh 24

3 PPA signed for the project with NEA 2067 Magh 09 2069 Chaitra 09

4 Consulting Agreement has been signed with CEC 2071 Jestha 31 2071 Jestha 31

5 Generation License 2069 Jestha 09 2071 Chaitra 13

6 Financial closure 2071 Mangsir 23 2071 Chaitra 3

7 Track opening for Access Road Construction started Chaitra 11, 2071

8 Track opening upto Intake of 12 MW completed Magh 10, 2072

9 Contract for “Construction Power” line awarded Poush 2072

10 Different contract awraded under Lot – 1 Infrastructures Works

10.1 Fence around Jifasa Camp

10.2 Maintenance of a stretch of Raj Kulo

10.3 Fence around Metal Works Area in Khari Tar

11 Civil Working Drawings – Deliverable 01 (Alignment Excavation Detail) for 7 MW has been issued

Poush 2072

12 Civil Working Drawings 01 (Alignment Excavation Detail) for 12 MW has been issued

Magh 21, 2072

13 Civil Working Drawings – Deliverable 02 (Alignment Excavation Details Revised, River Protection Works on Headworks, Anchor Block, Supporting Structures) for 7 MW has been issued

Feb 29, 2016

14 Civil Working Drawings – Deliverable 02 (Alignment Excavation Details Revised, River Protection Works on Headworks, Anchor Block, Supporting Structures) for 12 MW has been issued

Feb 29, 2016

15 Civil Working Drawings – Deliverable 03 (Headworks and Headponds Drawings, River Protection Works on Headworks and Anchor Block Drawings) for 7 MW

April 01, 2016

16 Civil Working Drawings – Deliverable 03 (Retaining structures on Headworks (revision) and Anchor Blocks Drawings) for 12 MW

April 01, 2016

17 Civil Works Drawings – Deliverable 03(A) (Headworks Layout Plan Coordinates) for 7 MW

April 18, 2016

18 Lot -2 Civil Contractor mobilised on Feb 17, 2016 Feb 17, 2016

19 Lot - 3 Hydro Mechanical Contractor mobilised on Mar 21, 2016 Mar 21, 2016

20 RCOD Ashadh 31, 2075 Jestha 30, 2074

Page 13: Preparation Review and Authorisation Date Prepared by ... amp House ( Office lock and Officer’s lock) New Nepal Nirman Sewa 6 Fencing with CGI sheet at JIFASA CAMP AREA New Nepal

Upallo Khimti and Upper Khimti-II Hydropower Project Progress Report No. 3

8 of 20 08 May 2016

3. Progress Report Executive Summary

3.1 Introduction

Progress Report No. 3 has been prepared by the Project Management Office and Technical Team for the period, Falgun 2072 – Baishakh 2073. Focus has been given to complete the Civil Construction work by end of Magh 2074. Commercial Operation Date for both the plant is targeted Ashadh 2075. 3.2 General The Land Acquisition work for getting private land is complete for Access Road and Pipe Line and for all major structure of both the projects. However, land leasing work and obtaining forest clearance from Government Land is in final stage. We will obtain approval from the Government very soon. Access Road Construction, 11kV/400V Construction Power work is at final stage. Its charging will be completed in a week. Camp House No 1, which includes 4 blocks and one garage and store, at Jifasa is complete and occupied. Protection against lightning is at final stage. Civil Engineering Work has been awarded to BP Construction (P.) Ltd, Chitwan and Hydro Mechanical Work also has been awarded to Machhapuchre Metal and Machinery Works (P.) Ltd Pokhara. The Contractor selection for Electro Mechanical Work will be completed by the end of Jestha 2073. 132 kV sub-station Work from NEA site is also developing smoothly. Land Acquisition work is partly completed. Detailed Memorandum of Understanding for speedy construction of 30 km Long 132 kV Transmission Line is under final stage. Although as per NEA is planning to complete 132KV substation by end of Ashadh 2075. Thus both the projects are planned and focused to complete by end of Mangsir 2074 to meet Commercial operation date (COD) on Ashadh 2075. 3.3 Engineering Detailed Design Consultant Clean Energy Consultant (P.) Ltd has been awarded as Detailed Design Engineering Consultant. The Consultant has issued so far: 01 Woking Drawings for Alignment Excavation for Upallo Khimti 12 MW Hydro Power Project 01 Woking Drawings for Alignment Excavation for Upper Khimti-II 7 MW Hydro Power Project 02 Working Drawing for Alignment / Excavation Details (Revision), River protection works on Headworks and Anchoring / Supporting Structures for 12 MW 02 Working Drawing for Alignment / Excavation Details (Revision), River protection works on Headworks, Anchor Blocks and Anchoring / Supporting Structures for 7 MW 03 Working Drawings for Retaining Structures on Headworks (Revision) and Anchor Blocks for 12 MW 03 Working Drawings for Headworks and Headponds Drawings, River Protection Works on HW and Anchor Block Drawings for 7 MW. 03(A) Working Drawing for Headworks Layout Plan Coordinates for 7 MW However, the CEC Team is very proactively ready to furnish all the Construction Detailing and Drawing Design on time to finish the Civil Construction work by Poush 2074.

Page 14: Preparation Review and Authorisation Date Prepared by ... amp House ( Office lock and Officer’s lock) New Nepal Nirman Sewa 6 Fencing with CGI sheet at JIFASA CAMP AREA New Nepal

Upallo Khimti and Upper Khimti-II Hydropower Project Progress Report No. 3

9 of 20 08 May 2016

3.4 Communication All communication facility has been installed already at the Project Management Office, Chuchure to have fast, prompt, timely communication. Three Lines of Satellite Phone, VSAT, 2 lines of CDMA Telephone, 3 sets of CDMA mobile, 22 sets of Willkie Talkie are operational at site. Web Surfer Internet facility has been installed and operational without any problem.

3.5 Effects of Earthquake in the Project After the devastating earthquake of 12 Baisakh 2072 and 29 Baisakh 2072 over 400 aftershocks have been observed by inhabitant. No significant damage has been occurred by aftershocks. 3.6 Effects of Terai Bandha in the Project No such Terai Madesh bandha have observed during the reporting period. In order to cope up with the delayed time frame caused by six month Banda we have completed the access road construction work by working two shifts. We are also preparing ourselves to work minimum of two shifts and in cases work round the clock to meet the project schedule as targeted to achieve RCOD on Ashadh 2075. .

Page 15: Preparation Review and Authorisation Date Prepared by ... amp House ( Office lock and Officer’s lock) New Nepal Nirman Sewa 6 Fencing with CGI sheet at JIFASA CAMP AREA New Nepal

Upallo Khimti and Upper Khimti-II Hydropower Project Progress Report No. 3

10 of 20 08 May 2016

4. Land Acquisition and Access Road Construction

4.1 Land Acquisition Upallo Khimti HEP-12 MW The land acquisition works has been nearly completed for pipe alignment and access road of UKHP. The total area of private land has already been acquired/purchased. The remaining of land area is public land and need to be leased form the GoN, which is under progress and will be completed very soon. 40-14-01-01 Ropani has been purchased already. Please refer to Annexure – 3 for details. Upallo Khimti HEP-7 MW The land acquisition works has been nearly completed for pipe alignment and access road of UKHP. The total area of private land has already been acquired/purchased. The remaining of land area is public land and need to be leased form the GoN, which is under progress and will be completed very soon. A Total of 50-12-01-00 Ropani of land is required out of that 43-09-0-2 has been purchased already and 03-05-0-0 has been leased from Local School. Please refer to Annexure – 3 Land details. 4.2 Land Leasing The land leasing and clearance for the forest already proceeded. The entire document for the processes is already submitted. Ministry of forest has given in principal agreement and cabinet decision on this regards is taken place already. Very soon we will have lease agreement of public land between Government of Nepal and Himalaya Urja Bikas Company Limited. 4.3 Access Road Construction

8.5 km Access Track from Kharanetar to Headworks of 12 MW is ready and operational. 3 SIM segments and water crossing are treated locally and are in control. There are two khola crossing called Chake and Garjung. Chake crossing is complete and operational. Causeway in Garjang Khola is at final stage. Thus, all sites of the Projects are easily accessible and drive at any point. Allthough making it all wheather is remaining work, protection work, side drain work needs to be completed.

Page 16: Preparation Review and Authorisation Date Prepared by ... amp House ( Office lock and Officer’s lock) New Nepal Nirman Sewa 6 Fencing with CGI sheet at JIFASA CAMP AREA New Nepal

Upallo Khimti and Upper Khimti-II Hydropower Project Progress Report No. 3

11 of 20 08 May 2016

5. Camp House

5.1 Jifasa Camp : Camp No 1 (Project Management Office) This is the central camp. We have about 24 Ropani of Land for our Jifasa Camp. This camp has been designed to be in operation even after Commercial Operation Date as our main camp for 35 years. 24 hours back up support has been provided through 30 kVA Generator. Director Block and Guest House – It is complete and occupied with air condition facility, attached bathroom, hot / cold showers. Officers’ Block (10 rooms and kitchen) – It is complete and occupied already by our Staff. Office Block – It is ready and in use. (Director Room, Technical Room, Meeting Room, Administration Room, Account Room are in this block.) Juniors’ Block – All ten rooms are occupied. Kitchen is used as temporary store. Protection Work of all blocks against lighting is at final stage. 5.2 Argeli Ghari Camp : Camp No 2 This Camp is near to 12 MW Headworks and is at final stage. All works are completed except sanitation, which is going on. It will be occupied in 15 days. This camp has been constructed on our own purchased land with 6 ropanis of land. This camp has also been designed to be operational even after COD for the Headworks staff for 35 years. 5.3 Garjyang Camp: Camp No 3 We have lease agreement with Bhalepokhari School that will be used for 30 years. It is being used as a store. 5.4 Kharanetar Camp: Camp No: 4 We have rented one private house. The Petrol and diesel storage will be availed here. We have store facility with office and residence facility for a duration of Project Construction Phase merely. One 18,000 liter underground Diesel storage facility is availed in the camp.

Page 17: Preparation Review and Authorisation Date Prepared by ... amp House ( Office lock and Officer’s lock) New Nepal Nirman Sewa 6 Fencing with CGI sheet at JIFASA CAMP AREA New Nepal

Upallo Khimti and Upper Khimti-II Hydropower Project Progress Report No. 3

12 of 20 08 May 2016

6. Construction Power

6.1 Study of Reliability and Power Available at Site

Power availability and reliability study has already been conducted for site. Study included condition of existing 11 kV Jiri –Those feeder, available power sources at Jiri 33/11 KV substation and at Charikot 33/11 KV substation. Study also included power availability at site for construction works during off peak time and peak time (5:30 PM -9:30 PM), frequency of occurrence of fault in existing 11 kV feeder from which we are planning to tap for our energy requirements. From overall, data collected at Jiri substation, it was seen that power is available for our requirement during off peak time and reliability is also seen satisfactory. Even though, some rectification works such as bush cutting, maintain of line to ground clearance, stay installation and other minor works has to carry out for making existing 11 kV line more reliable.

6.2 Procurement of Material

Procurement of Major materials such as Mechanical items, Electrical items, Conductor and ABC cable and for distribution transformers has been completed and transported to site. 6.3 Construction of Construction Power

Construction Power works (11 KV & 0.4 KV Line) has been completed for both Projects Upallo Khimti & Upper Khimti -II. Sunita & Kabita Construction (Pvt) Ltd, Dolkha, carried out the installation works of Construction Power which has been installed along the Headrace and Penstock pipe alignment of both the projects Upallo Khimti and Upper Khimti -II Hydro Power Projects. In total six transformers has been installed. Out of six, Five Transformers has been installed of Capacity 100 KVA and one Transformer has been installed of Capacity 250 KVA. Testing of Construction power has also been completed. 6.4 Load Approval for Construction Power NEA’s Distribution and Consumer Services Ramechhap Branch has approved 500 KVA load for the construction power. Time of Day Energy Meter programming and installation workis in process that will be completed by Jestha 2073.

Page 18: Preparation Review and Authorisation Date Prepared by ... amp House ( Office lock and Officer’s lock) New Nepal Nirman Sewa 6 Fencing with CGI sheet at JIFASA CAMP AREA New Nepal

Upallo Khimti and Upper Khimti-II Hydropower Project Progress Report No. 3

13 of 20 08 May 2016

7. Lot II: Civil Works

7.1 Preliminary Works Preliminary works have been completed and the construction work has already started.

7.2 Contractor Selection

B.P Construction P. Ltd has been awarded as a civil contractor on 2072/10/25. Contractor mobilised its personnel with equipment on Falgun 05, 2072. 7.3 Construction Materials Survey Technical team of Himalaya Urja Bikas Company has visited the possible sources of construction materials especially for course and fine aggregate its quantity and quality. Basically two sites, Male and Olane, are selected. Both course (boulder from course aggregate) and fine aggregate are available at Mela, whereas only fine aggregate are available at Olane. Laboratory test results of all concerned materials satisfy the requirements of the relevant specifications and norms.

7.4 Detailed Time Programme The preliminary Detailed Schedule is prepared for the civil works construction which is attached in Annex -2. The entire Civil Construction work will be finished by end of Poush 2074 followed by EM Installation, testing and commissioning by end of Ashadh 2075.

7.5 Camp of the Civil Contractor 7.5.1 Camp 1 at Garjang This Camp includes site office, general store and a cement store. It is occupied and operational. 7.5.2 Camp 2 near site for 12 MW Power House This is for labours and to store reinforcement.

7.6 Personnel and Equipment of the Civil Contractor

SN Personnel Remarks

1 Project Manager 1

2 Resident Engineer 1

3 Construction Engineer 1

4 Civil Engineer 2

5 Sub Engineer 1

6 Accountant 1

7 Social Mobiliser 1

8 Survey Helper 2

9 Skilled Manpower 12

10 Unskilled Manpower 34

SN Equipment Ordered

1 Excavator PC210 1 At site

2 Braker 1 At site

3 Truck 1 At site

4 Tractor 4 At site

5 Crushing Plant 1 Delivered to site on

20/01/2073

6 Diesel Tank, 12000 l 1 Order is placed

Page 19: Preparation Review and Authorisation Date Prepared by ... amp House ( Office lock and Officer’s lock) New Nepal Nirman Sewa 6 Fencing with CGI sheet at JIFASA CAMP AREA New Nepal

Upallo Khimti and Upper Khimti-II Hydropower Project Progress Report No. 3

14 of 20 08 May 2016

7 Generator set 15 kVA 1 Order is placed

8 Generator set 63 kVA 1 Ready for dispatch

9 Concrete mixer 3 Order is placed

10 Concrete pumping machine 1 Order is placed

11 Tipper 1 Order for another is

placed

12 Excavator 1 Order for another is

placed

12 Total Station 1 At Site

13 Laboratory Set Up 1 Order is placed

7.7 Material Stock at Site

7.7.1 Cement - Maruti cement is approved by the Client. 200 bags at stock - Different tests have been conducted and results satisfy the relevant codes and specifications. 7.7.2 Rebar - Total 53776 kg of different sizes (10, 12, 16 and 20 mm dia) have been received. - Different tests have been performed and results are positives. - Rebar straightening and cutting for Anchor Blocks commenced and continued. 7.7.3 Sand washing and collection

Sand washing is arranged in Khimti Khola and tractors are used to transport washed sand from Khimti Khola to the yard

7.8 7 MW Headworks 7.8.1 River Diversion

First stage river diversion work is completed. 7.8.2 Left Bank Protection Wall

Excavation is commenced. Big boulders are to be removed. Work continues.

Page 20: Preparation Review and Authorisation Date Prepared by ... amp House ( Office lock and Officer’s lock) New Nepal Nirman Sewa 6 Fencing with CGI sheet at JIFASA CAMP AREA New Nepal

Upallo Khimti and Upper Khimti-II Hydropower Project Progress Report No. 3

15 of 20 08 May 2016

8. Lot III Contract – Hydro Mechanical Works

8.1 Preliminary Works

Preliminary works have been completed and the workshop establishment is in full swing to start the pipe fabrication work at site.

8.2 Contract Award The Contract is awarded to Machhapuchhare Metal and Machinery Works. Two key personnel

are mobilised site on Chaitra 08, 2073.

8.3 Camp It is hired in Kharanitar and other places in progress.

8.4 Personnel 1. Sudhodhan Lamsal - Site in-Charge

2. Birendra Sharma - Mechnaical Engineer

8.5 Equipment Hydra Mobile crane, welding machines, generators etc

8.6 Workshop Establishment 8 m * 40 m workshop establishment with crane facility is in Final stage now. This workshop will

be operational from Jestha 2073.

8.7 Steel Plates We have received Steel Plates from SAIL India confirming IS-2062 BO/2011 E350 BO from its

Bokaro and Bhilai Plant. A total of 4337 Metric Tonne steel plates have been received.

Transportation work of these plates from Birgunj is under progress. We plan to complete the

transportation these plates before monsoon starts.

Page 21: Preparation Review and Authorisation Date Prepared by ... amp House ( Office lock and Officer’s lock) New Nepal Nirman Sewa 6 Fencing with CGI sheet at JIFASA CAMP AREA New Nepal

Upallo Khimti and Upper Khimti-II Hydropower Project Progress Report No. 3

16 of 20 08 May 2016

9. Lot IV Contract – Electromechanical Works

9.1 Preliminary Works

No Preliminary works have been done.

9.2 Contract Award Tender had floated on 2072/08/22. Tender received on 2072/10/17 .

We have received bid from the following bidders.

a) Flovel Energy Private limited b) TPSC (India ) Private Limited c) VOITH Hydro Pvt.Ltd d) Hunan Allon ward Hydro-Equiptment Co.ltd e) BFL Hydro f) Andritz Hydro Private Limited

Contractor selection is in process that will be finished by end of Jestha 2073.

Page 22: Preparation Review and Authorisation Date Prepared by ... amp House ( Office lock and Officer’s lock) New Nepal Nirman Sewa 6 Fencing with CGI sheet at JIFASA CAMP AREA New Nepal

Upallo Khimti and Upper Khimti-II Hydropower Project Progress Report No. 3

17 of 20 08 May 2016

10. Human Resources

10.1 Head Office, Kathmandu

S.No. Name list Designation

Directors Head Office

1 Mr. Hari Prasad Pandey Executive Chairman

2 Dr. Bhim Prasad Neupane Director-Head Office

Head Office Employees

1 Prakash Chandra Dulal Manager-Administration

2 CA Surya Prakash Pathak Manager-Account& Finance

3 Khagendra Pandey Company Secretary /Senior Officer

4 CA Baburam Khanal Account Officer

4 Prabin Thapa Account Officer

6 Manish Dhakal Officer-Administration

7 Santosh Adhikari Ast. Officer-Account

8 Kriti Timilsina (Ms.) Receptionist

9 Shobha Khatiwada (Ms.) Administration Assistant

10 Chudamani Dahal Driver

11 Mohan Kumar Lamsal Peon

12 Krishna Bidari Guard

13 Maina Kumari Adhikari (Ms.) Office Assistant

10.2 Project Management Office, Chuchure

S.No. Name lists Designation

Director - Technical and Project Management Office

3 Eng. Saroj Kumar Upadhyay Director - Technical and Project Management

Project Management Office Employees

1 Er. Rama Kant Gauro Project Manager

2 Er. Lav Kumar Shrestha Resident Engineer

3 Er. Shyam Krishna Karki Senior Civil Engineer - Billing

4 Er. Kapil Acharya Project Engineer – Planning & Scheduling

5 Er. Sujan Raj Shrestha Site Engineer Civil

6 Er. Ashish Amatya Engineer - Head works

7 Er. Bimlesh Kumar Yadav Engineer - Power House

8 Er. Amit Singh Electrical Engineer

9 Er. Hem Raj Guvaju Site Engineer

10 Er. Pradhumna Shahi Site Engineer

11 Hemanta Mani Nepal Sr. Overseer

12 Singh Bahadur Lama Senior Surveyor/ Total Station

13 Rabin Bhattarai Surveyor / Total Station

Administrative and Logistics Staff

14 Santosh Bhattarai Admin Manager

Page 23: Preparation Review and Authorisation Date Prepared by ... amp House ( Office lock and Officer’s lock) New Nepal Nirman Sewa 6 Fencing with CGI sheet at JIFASA CAMP AREA New Nepal

Upallo Khimti and Upper Khimti-II Hydropower Project Progress Report No. 3

18 of 20 08 May 2016

15 Samir Man Rajbansi Accountant

16 Aditya Basnet Store Keeper

17 Barun Tiwari Store Keeper

18 Rajesh Thakuri Driver

19 Tika Basnet Driver

20 Surya Kusule Excavator Operator

21 Rina Bista (Ms.) Sub Overseer

22 Bishnu Bahadur Khadka Excavator Operator

23 Lhatul Sherpa Excavator Operator

24 Samar Karki Excavator Helper

25 Tilak Kumari Khadka (Ms.) Office Assistant

26 Pradip Kumar Khadka Junior Supervisor

27 Naniram Basnet Office Assistant

28 Prem Bahadur Khadka Senior Supervisor

29 Bhakta Bahadur Karki Excavator Operator

30 Bina Khadka (Ms.) Admin Assistant

31 Khagendra Bahadur Karki Guard

32 Rudra Bahadur Karki Guard

Technical Staff at Head Office 33 Er. Susheel Sharma Assistant Project Manager-Tech

34 Er. Yam Lal Tharu Electrical Engineer

35 Bikram Khawas Engineer

36 Er. Ranjan Bhushal IT Engineer

Consultants

1 Narayan Poudyal Financial Consultant

2 Ballav Basnet Legal Consultant-Project Management Office

3 Rabindra Dhungana Legal Consultant-Head office

4 Thakuri Singh Ghalan Computer Technician

5 Krishna Security Security Provider Company

6 Mohan Karki Mechanics

Page 24: Preparation Review and Authorisation Date Prepared by ... amp House ( Office lock and Officer’s lock) New Nepal Nirman Sewa 6 Fencing with CGI sheet at JIFASA CAMP AREA New Nepal

Upallo Khimti and Upper Khimti-II Hydropower Project Progress Report No. 3

19 of 20 08 May 2016

11. Social Mitigation

The company has allocated some budget in IEE for the social responsibility. Till date the company has already signed the MOU with the following institution for the intuitional support of those local institutions:

11.1 Bhale Pokhari Primary School, Chuchure-1, Ramechhap 11.2 Pathivara Bhumeshwor Primary School, Shyama-1, Dolakha 11.3 Jatteswari Higher Secondary School, Chuchure-2, Ramechhap 11.4 Chuchure Health Post, Garjyang, Chuchure-2, Ramechhap 11.5 Garjyang Savings & Credit Co-operative Ltd. Chuchure-1, Ramechhap 11.6 Gumba located in Garjyang Village , Chuchure VDC – 1, Ramechap 11.7 Sharada Higher secondary school ,Those Ramechhap 11.8 Gupteshwori Primary School Those – 7, Ramechap

11.9 Shiva Lower Secondary School, Chuchure -7, Shivalaya, Ramechhap

11.10 Seti Devi Higher Secondary School, Chuchure – 8, Ramechhap

11.11 Mahadeveshwori Primary School, Chuchure – 5, Ramechhap

11.12 Kali Devi Primary School Chuchure – 4, Ramechhap

11.13 Sharada Higher Secondary School , Those – 5, Ramechhap 11.14 Urgen Shedrub Dargyeling Monstery, Shyama – 1, Dolakha

11.15 प्राकृतिक बािाबरण सरक्षण िथा सदपुयोग समाज ,चुचुरे रामेछाप

Page 25: Preparation Review and Authorisation Date Prepared by ... amp House ( Office lock and Officer’s lock) New Nepal Nirman Sewa 6 Fencing with CGI sheet at JIFASA CAMP AREA New Nepal

Upallo Khimti and Upper Khimti-II Hydropower Project Progress Report No. 3

20 of 20 08 May 2016

12. Financial Status

The financial agreement was signed with consortium bank lead by Nabil Bank including Nepal Bank, Everest Bank and Ace Development Bank on 23 Masigar 2071 for UKHP 12 MW and on 3 Chaitra 2071 for UKHP-II, 7 MW. Based on the consortium agreement, details cost breakdown for individual particular is presented in table 12.1. Table 12.1: Summary of Budget Details

S.N Particulars UKHP,12MW

in Nrs '000 UKHP-II,7MW

in Nrs. '000

Total (UKHP,12MW+UKHP-II,7MW) in Nrs. '000

1 Pre-Operating/Development Cost 54,220.00 17,500.00 71,720.00

2 Report Preparation and Field Investigation 7,966.50 7,966.50 15,933.00

3 Infrastructure Development 40,866.29 22,500.63 63,366.92

4 Camping Facilities 10,012.43 9162.49 19,174.93

5 Vehicle 10,400.00 4200.00 14,600.00

6 Land Purchase and Lease 33,516.02 23,478.86 56,994.87

7 Office Equipment 3,350.00 3,350.00 6,700.00

8 Civil Construction 459,040.65 347,611.52 806,652.17

9 Metal Works 444,732.30 278,639.08 723,371.38

10 Electro-mechanical Equipment 392,270.70 244,796.72 637,067.42

11 Interconnection Equipment 47,474.50 54,646.18 102,120.69

12 Transmission line 60,468.53 22,187.47 82,656.00

13 Engineering & Management 79,602.50 35,450.50 115,053.00

14 Social and Environment Cost 22,245.43 11,074.00 33,319.43

15 Project Insurance during Construction 6,878.59 4,620.50 11,499.09

16 Miscellaneous 31,584.63 10,232.74 41,817.37

17 Interest During Construction 209,450.12 134,841.23 344,291.35

Total with Financing 1,914,079.19 1,232,258.42 3,146,337.619