Preparation Of DPR And How To Monitor The Construction Works On Technical Aspect. Preparation of DPR. DPR is the based document for planning and implementing the project. DPR indicates the technical and financial strategies to be adopted for implementation. Preparation of DPR. - PowerPoint PPT Presentation

Citation preview

Page 1: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Preparation Of DPR And

How To Monitor The Construction Works

On Technical Aspect.

Page 2: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Preparation of DPR

DPR is the based document for planning and implementing the project. DPR indicates the technical and financial strategies to be adopted for implementation.

Page 3: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Preparation of DPR

DPR is broadly comprised of following things.Project background.Project definition, concept and scope Project cost Project institution framework.Project financial structuringProject phasingProject O & M framework and planningProject financial viability / sustainability.Project benefits assessments.

Page 4: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Project Background

It narrates the necessity and aim of the project.Existing status of the physical infrastructure.Base line information of users.

Page 5: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Project definition, concept and scope

The project concept comprises of several issues like :-

LandEnvironment impact assessmentEnvironment management planRehabilitation and ResettlementDetails of surveys and investigationDisaster related risk assessment and countermeasures.

Page 6: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Project Cost The project cost should clearly indicate covering all following factors:-

Land acquisition / site developmentPhysical infrastructure component-wise costEnvironmental compliance costRehabilitation & resettlement costCost of survey & investigationsCost of shifting utilitiesCost of consultancy services Finance / interest costContingency

Page 7: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Project Institution framework.

The DPR needs to provide : Role of institutions involved in the Project

A Roles / responsibility matrixInnovative approaches for better co-ordination between ULB and state government department.Manner of undertaking construction worksInvolvement of the construction agency in the O & M activities

Page 8: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Project Institution framework. Area of involvement of the private sector

in the construction phase of feasibility study, engineering design, specialized surveys, construction works, supervision consultants, Quality Assurance Consultants or any other assignments

Brief description of strategy for the overall works program including tender process.

Page 9: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Project Financial structuring

DPR must indicate the composition of fund.

Central Government.State Government.ULBs

Loan component, Private Investment etc. will have to be shown in the DPR.

Page 10: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Project Financial structuringPrivate participation can be utilized in ULB or State share.Private contribution can be recovered against O & M in the shape of user charges.The billing and collection of user charges can be entrusted with the Private Agencies.

Page 11: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Project Financial structuringLinking construction with O & M performance contract could provide the advantage of operational cost efficiency.

Private sector financing in the project is a well accepted approach under JnNURM as it curtails the financial burden on Govt. and Municipal fund.

Page 12: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Project Phasing

Project Activity Schedule to be indicated.Schedule for tendering.Schedule for State and ULB contributionSchedule for all clearances.Schedule for shifting utilities Schedule for implementation of project components

Page 13: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Project O & M planningThe DPR should indicate :-The institution to be engaged in the O&MExisting system of billing and collection.Brief analysis of the key issues and obstacles .Scope of private entity in O&M.The requirements of manpower, energy, spares etc. for O&M with proposed additional requirement.Tariff model, existing rate for all categories and forecast growth over the next 20 years.

Page 14: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Project Financial viability / sustainability.

The DPR is to provide information in Municipal level.Cash flow :

A complete cash flow covering the last 5 (five) years and projections for the next 20 (twenty) years.

An assessment of the annual impact of the project on the Municipal finances.

Page 15: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Project Financial viability / sustainability

Debt situation assessment :Debt schedules and terms for all debt taken.Debt service coverage ratioDebt-equity ratio for the project and the ULB

Other financial information :Credit rating details.

Page 16: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Project Benefits assessments

DPR is to provide the following :List of benefits (both social & economic)

Benefits are to be assessed on project outcomes and project outlays covering impact on citizen.

Page 17: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Project benefits assessmentsList of adverse impacts on following aspects:

Pollution, environmental distortions Reduced green coverReduced access to any specific user segmentsSupply interruptions etc. Displacement of inhabitantsDisruption in livelihood / reduced employment Possible haphazard development around / adjacent project site areas

Page 18: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Preparation of DPR on

Municipal Solid Waste Landfill

Page 19: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Selection of Landfill site Criteria :Lake or Pond : No landfill should be constructed within 200m of any lake or pond.River : No landfill within 100 m of a navigable river or stream. Flood Plain : No landfill within a 100 year flood plain. Highway : No landfill within 200 m of the right of way of any highway. Trees and berms are used to screen the landfill site.

Page 20: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Selection of Landfill site Habitation : A landfill site should be at least 500 m from a notified habitated area. A zone of 500 m around a landfill boundary should be declared a No-Development Buffer Zone.Public Parks : No landfill within 300 m. Wetlands : No landfill within wetlands. Ground water : No landfill in areas where water table is less than 2 m below ground surface.

Page 21: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Selection of Landfill site Airports : No landfill within 5 miles from Airport Operational Area.Water Supply Well : No landfill within 500 m of any water supply well. Unstable Zone : A landfill should not be located in potentially unstable zones such as landslide prone areas. Buffer Zone : A landfill should have a buffer zone around it

Page 22: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Land fillDPR on landfill will have following contents

Introduction Present StatusSite Characteristics Landfill Design FacilitiesLand fill Design Features and Site PlanLandfill Construction Landfill ClosureMonitoring RequirementCosting

Page 23: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

LandfillIntroduction : This is the introductory brief of activities to be performed for landfill.Also this is a review of landfill development process to ensure a landfill is constructed, operated and maintained in environmental friendly manner.

Page 24: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Land fillPresent Status :It narrates the present generation of solid waste, collection system, transportation and dumping method.

Page 25: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

LandfillSite Characteristics : It is the description of proposed land, its area, topography, access facility, climate, rainfall, temperature, humidity, ground water status, surface water and drainage system, soil properties etc.

Page 26: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Landfill Design Facilities

The essential basic steps for landfill design are

Landfill sizingSite layoutLandfill layoutLeachate managementLandfill gas management

:

Page 27: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Landfill construction

1st layer – 50 cm thick compacted soil2nd layer – Geo-synthetic clay liner3rd layer – 1.5 mm HDPE Geo-membrane

Page 28: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Landfill construction4th Layer – 30 cm thick gravel. The gravels should be smooth, and round of 12 – 15 mm in size. Leachate collection system of perforated HDPE leachate collection pipe embedded in this gravel layer

Page 29: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Landfill construction5th layer – Geo-textile for filtration.6th layer – Finally a 300 mm thick soil on the Geo-textile as a protective layerLeachate will go to leachate treatment plant for reduction of BOD, COD and suspended solids.Daily waste is leveled, compacted and covered with fresh earth to give a pleasing appearance and also to prevent odours.

Page 30: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Landfill Closure Waste will have to be graded to the necessary stable slopes. 1st layer - 200 mm thick gravel to release gas through gas vents.2nd layer - 600 mm soil.3rd layer - 1 mm thick HDPE liner to control water leaching into soil layer.4th layer - 150 mm thick gravel for drainage. 5th layer - Geo-textile to keep the soil layer separated. 6th layer - 450 mm thick soil for vegetation.

Page 31: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Monitoring RequirementGround water quality monitoring within 50 mtr. periphery of landfill site shall be periodically monitored.Ambient air quality monitoring will have to carried 4 (four) times in a year around the site.Portable methane detection units are available for the purpose.The air quality must be monitored for 15 (fifteen) years after the closure of the landfill.Surface water monitoring around the site is also necessary.

Page 32: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Cost For all activities to be performed detailed estimate on the basis of engineering details will have to be prepared to determine the project cost.

Page 33: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

How To Monitor The Construction

Works On Technical Aspect

Page 34: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Construction MonitoringIt is the process to monitor and control the activities associated with initiating, planning, executing, and closing a project. Problems during execution should be identified in a timely manner for immediate corrective measures.Construction must be monitored and measured regularly to identify deviations from the plan.

Page 35: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Construction MonitoringFree site must be ensured before any work is taken up.Site of construction is to be identified to ensure flawless layout of the work.Mobilization of manpower, materials, equipments and resources is most essential.

Page 36: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Construction MonitoringMonitoring is needed to ensure proper management on following issues :CostQualityRisk

Page 37: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Construction MonitoringCost Management :It is necessary to perform cost control process of influencing the factors that create changes to the basic cost to ensure that the changes are beneficial and according to exact requirement of the work.

Page 38: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Construction Monitoring

Quality Management :It is necessary that the quality of the work is properly ensured in terms of materials and workmanship

Page 39: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Quality ManagementQuality of materials will have to be ensured before work is taken up :-

Bricks : Bricks shall be sound, hard, homogenous in texture. Bricks shall have a minimum crushing strength of 105 kg/sq.cm.Bricks should have ringing sound if struckBrick absorbing more than 20% of its dry weight after 24 hrs. immersion shall be rejected.

Page 40: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Quality ManagementSand is the fine aggregate, which shall pass through IS: sieve designation 4.75 mm, leaving a residue not more than 10%. Sand should be collected from local river beds Sand shall not contain more than 8% of silt. It should be clean, hard and sharp.

Page 41: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Quality ManagementStone aggregate : This shall be broken from good hard stone boulder and shall be free from soft, friable, thin, elongated or laminated pieces. This shall be roughly cubical in shape and shall be clear and free from dirt and any other foreign matter.

Page 42: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Quality Management

Steel : Presently we use TMT (Thermo Mechanically Treated) steel of various brands.BIS Certification Marking should be checked in each bundle of bars before use.

Page 43: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Quality ManagementCement : Net weight of each bag of cement shall be 50 kg.Cement stored for over 6 (six) months shows signs of deterioration or contamination and should be tested before use.OPC cement and PPC cement are generally used for construction.OPC conforms to IS: 269-1989 and PPC conforms to IS: 1489-1991

Page 44: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Quality ManagementConcrete consistency : The quantity of water to be used for each mix of 50 kg. cement shall not be more than 34 ltr. for 1:3:6 mix, 32 ltr. for 1:2:4 mix., 30 ltr. for 1:1:2 mix.For vibrated concrete the limit specified may be suitably reduced.

Page 45: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Quality Management

Curing : Curing of concrete shall be done after 24 hrs. of laying with moist gunny bags, sand etc. for a minimum period of 7(seven) days. Concrete should not be disturbed by further construction during the curing period.

Page 46: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect

Risk ManagementFour steps to risk management are :Risk IdentificationRisk analysisRisk management planning andRisk reviewRisk should be reviewed periodically with the related persons so that it can be faced and tackled on time

Page 47: Preparation Of DPR  And  How To Monitor The Construction Works On Technical Aspect