39
Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli, Bruno Puccio.

Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

Embed Size (px)

Citation preview

Page 1: Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

Preparation for Beam commissioning

Mike LamontAcknowledgements: Brennan Goddard, Verena Kain,Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli, Bruno Puccio.

Page 2: Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

LHC status 218/01/2008

Objectives

All required hardware systems tested All required instrumentation deployed and tested Machine Protection system tested & qualified. All software deployed and required functionality tested Control system integrity tested Full integration tests performed with all systems driven

through operational cycles

Clear that when we finally get beam we don’t want to waste time solving problems that could have been resolved before.

Get ready for first beam

Page 3: Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

LHC status 318/01/2008

Conditions

Cool-down of remaining sectors Extensive Hardware Commissioning of circuits Installation of remaining components Individual system commissioning Roll out of controls infrastructure Roll out of beam interlock system Roll out of beam instrumentation Software development and deployment, roll out of

magnet model etc… Commissioning of access system (DSO tests etc.) While starting-up and operating SPS/PS etc.

Page 4: Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

LHC status 418/01/2008

HWC - baseline

Cooling and Ventilation Cryogenics Plant Cryostat Instrumentation Electrical Network Beam Vacuum [warm & cold] QRL Vacuum Insulation Vacuum Powering Interlocks QPS and energy extraction QRL Instrumentation Access Survey/Alignment

Page 5: Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

LHC status 518/01/2008

Incoming this session

Cryogenics Magnets/circuits Vacuum Injection system Beam Dump System Collimators RF Beam Instrumentation Machine protection …

Some how pull this lot together to give us a operational machine

Page 6: Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

LHC status 618/01/2008

Approach

Define objectives and prioritize (as usual) Individual System Tests/ Hardware Commissioning

Equipment groups/HWC team

Individual high level control tests From CCC using controls infrastructure and software Check the functionality of the individual systems

Integration tests (dry runs) + HWC/PGC Partial machine checkout Machine Protection commissioning Full machine checkout

Try and document it – something we’ll have to do every year

Page 7: Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

LHC status 718/01/2008

Approach

Page 8: Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

LHC status 818/01/2008

Comments

There’s a lot going on the same time This not going to be particularly tidy or particularly easy

Accept dry runs as a debugging exercise Accept it won’t be perfect first time Iterate [but at an appropriate frequency] Look for robust solutions that follow established

standards.

Page 9: Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

LHC status 918/01/2008

Integration Tests (Dry Runs)

Multi-system tests to check integration and readiness of all systems involved in a given phase of LHC operations: Check data acquisition chain Check all equipment control functionality Check timing and low synchronization Check functionality of the control system from CCC high level

applications. Drive all relevant systems in a synchronized way through the standard

operational sequence Check machine protection and interlock systems

Organization Coordinated by Operations. Preparations for, and results of, dry runs to

be discussed at LHCCWG. In close collaboration with equipment groups, technical issues to be

discussed in ABCIS meetings. Seen as a prelude to full system tests to be performed before beam.

Debugging – establishing control & integration from the CCC

Page 10: Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

LHC status 1018/01/2008

Objectives- Instrumentation

Prio

rity

Co

nc

Se

tting

s

Sta

te

Lo

gg

ing

PM

SIS

MC

S

Ap

plic

atio

n

FD

isp

lay

Da

em

on

BPM [D,I] 1 X X X XX X

BLM 1 X X X X XX X

BCT [DC, FD, FR] 1 X X

BTV 1 X X X X X X

Rest Gas [BGI] 3 X X X X X

Sync. Rad [BSRA] 1 X X X X X X

Wire Scanners [BWS] 2 X X X X X

Luminosity [BRA,S,G] 1 X X X X

Tune [BQBBQ] 1 X X X X XX

Tune [BQHT] 2 X

AGM [BSRA] 2 X X

Schottky [BQS] 2 X X X

BST [BOB] 1

Page 11: Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

LHC status 1118/01/2008

Application

XP

OC

Analog

Acquisition

Alarm

s

SIS

MC

S

PM

Tim

ing

RB

AC

INJECTION KICKERS X X X X X X X X

BEAM DUMP X X X X X X X X

POWER CONVERTERS XX X X X X X

COLLIMATORS X X X X X X X

RF XX X X X X X X

TRANVERSE FB X X X X X X

MAGNETS XX X X

MKQA etc X X X X X X

WARM MAGNETS X X X X X

RADIATION MONITORS X X

SPECTROMETERS X X X

Objectives - Hardware

Page 12: Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

LHC status 1218/01/2008

Objectives - Controls

Slow timing, fast timing, synchronization Alarms, logging, post mortem, fixed displays Equipment control & access Real-time feedback system Analogue acquisition Software: measurements, trajectory acquisition and

correction, ramping etc. etc. Controls infrastructure: servers, databases etc. Software Interlock System Management of Critical Settings Role Based Access Control

Page 13: Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

LHC status 1318/01/2008

Objectives – Deploy and Test LSA

Core Functionality Optics, ramp, squeeze, magnet model (transfer functions etc.)

Equipment Instrumentation Measurements Operational exploitation Timing On-line Models

MADX, FIDEL, Aperture Mode, data distribution Applied LSA applications

Orbit, luminosity scans etc. Data exchange

Page 14: Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

Proposed Integration Tests

Page 15: Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

LHC status 1518/01/2008

Injection/Transfer Dry Run

Kickers control, monitoring, logging, settings, FD

Timing & synchronization Events, tables, telegrams, injection requests RF pre-pulses

Instrumentation Acquisition, logging, control, FD, timing etc. for Screens, BLMs, BPMs,

BCT Applications

YASP (threading, etc) Injection Quality Checks

Modes Injection and dump, Circulate and dump, Nominal Injection

TDI Controls

RBAC, MCS, Mode, DIP BIS

Page 16: Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

LHC status 1618/01/2008

Injection & Transfer

Page 17: Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

LHC status 1718/01/2008

Injection, Ramp & Squeeze Dry Run Injection, ramp, squeeze, ramp-down, pre-cycle

Settings - full LHC parameter space Power converters, RF, Collimators FIDEL Bumps, experiments’ magnets

Trims Actual and function – full parameter space

Control RF units, cavities, loops etc., FGCs… Collimator – set, functions, limits etc.

Applications & Tools YASP, sliding bumps Multi-turn acquisition and analysis

Instrumentation Sequence, mode Power converters in SIM_VS

Page 18: Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

LHC status 1818/01/2008

Beam Dump Dry Run

LBDS Monitoring, GUI, trigger, IPOC

XPOC BETS Timing Sequence

Re-arm Monitoring Logging, fixed displays, alarms, MCS BIS

Permit loops, PM suppression etc. Dump line and point 6 instrumentation Abort gap, RF TCDQ/TCS settings and control

Page 19: Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

LHC status 1918/01/2008

Instrumentation

Every BI SW responsible will organize the continuous assessment of its instruments, ie find/organize time slots, also outside official dry runs, where conditions allowing to test functionality [see JJG]

Maintain the dashboard info up to date (color scheme and details on the box dedicated page) and prepare battle field for the next iteration

Page 20: Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

LHC status 2018/01/2008

Beam Loss Monitors - acquisition & concentration roll out

Beam Loss Monitors - XPOC, Post mortem, study buffers test, test, test

Beam Loss Monitors - Logging roll out and test

Beam Loss Monitors – OP display ops

Beam Loss Monitors – expert application To spec

Beam Loss Monitors – MCS – configuration & tests –threshold management

MCS, application and test

Bunch Current Transformers acq & display BCTDCLHC & BCTFDLHC & BCTFRLHC

Acq, log, FD

Instrumentation - DR 1/3

• Find/organize time slots, also outside official dry runs where conditions allow testing of required functionality

• Play simulated injection, ramp etc…

• Plus dedicated dry runs

Page 21: Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

LHC status 2118/01/2008

Instrumentation – DR 2/3

BPM: acquisition & concentration & publish

All modes: capture, FIFO, orbit

Logging, SDDS, roll out and test

BPM: acquisition, log, display Roll out

BPM: trajectory and orbit correction YASP

BPM: multi-turn analysis Application - test

BPM: beta beating analysis Application – deploy and test

BPM: real time feed back Deploy and test

BPMDLHC - dump line BPM XPOC

BPMITLHC – interlocked BPMs Acq/BIS, XPOC

BTVI/BTVMLHC Screens (matching monitors) Acq, Control, BIS

Page 22: Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

LHC status 2218/01/2008

Instrumentation – DR 3/3

Tune/kickers (tune, aperture, AC dipole)control- acq – timing- applications – deploy and test

Radmon (TW) acq – conc - display

BQHTLHC – head-tail Chromaticity

BSRALHC Abort gap monitor Deploy & test

BSRTFLHC/BSRTSLHC Synchrotron radiation monitors

Deploy & test

BGILHC – Rest Gas Monitor Deploy & test

BWSLHC Wire Scanner Deploy & test

Wall Current Monitors (RF) Talk to Andy

BQSLLHC - Schottky Deploy & test

BRASCLHC/BRASGLHC - Luminosity monitors Application++ +LSA

Page 23: Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

LHC status 2318/01/2008

Physics/Experiments Dry Run

Luminosity Acquisition and display, BRA application Optimization, trims, bumps etc. Scans

Experiment Instrumentation & signals BCMs, Lumi etc.

Experiment communication DIP – to & from Vetos

Interlocks Beam abort, injection inhibit

Magnets Alice/LHC dipoles and compensation

Page 24: Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

LHC status 2418/01/2008

Physics

ADJUST

entry/ Move VELO outentry/ Move Roman Pots outdo/ Monitor Roman pots

STABLE BEAMS

do/ Move roman potsdo/ RP movement inhibitdo/ Move VELO

UNSTABLE BEAMS

entry/ Move roman pots outentry/ Move VELO out

Beam Dump

do/ Fire beam dumpsdo/ Post Mortemdo/ XPOC

BEAM DUMP WARNING

OP request[ Experiments OK ]OP request / Beam dum p

MPS / Beam dumps fired

OP request[ Exps inform ed ] / m ode change

OP request / Mode change

OP request / Mode change

MPS / Beam dumps fired

OP request / mode change

Roman Pots not in lim its

OP request / Mode change

MPS / Beam dumps fired

Page 25: Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

LHC status 2518/01/2008

Beam Interlock System Complete the IST of the BIS by April.

This will be carried out by the BIS team (independently of the HWC). Perform the Commissioning of the BIS in // with the HWC.

Tricky - involves all LHC systems: Experiments, COLL, VAC, BLM, other Beam Instrumentation, RF, Access, and so on...

BICs are installed either side of IP, done for each one of the 8 points. 8 periods of ~5 days (or twice 2,5 days) during the HWC. Either inserted before the Powering tests or just after them. The possibility to have a sector(s) test is going to be taken into account

in trying to give priority to points 8, 7 and 6 (or 2,1,8). Perform a final test- dedicated week during the cold-check period.

Concerning dry-runs, we have recently installed 2 more BICs in point 6 in order to participate to the LBDS dry-runs in // with our BIS commissioning.

The goal is to do NOT disturb our commissioning and move ahead with the interfaces with you, the Timing and the Kickers.

c/o Bruno Puccio

Page 26: Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

LHC status 2618/01/2008

Machine Protection Dry Runs

As part of other dry runs Injection kickers LBDS – link to BIS, protection devices

Integration in machine cycle Resets, tests, SBF, SBP, BPF Interface to timing system/BST PM suppression Link-Unlink Injection inhibit Experiments

Page 27: Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

LHC status 2718/01/2008

PGC as part of circuit HWC

Allows us to test & check: LSA settings generation

Optics Injection - Ramp - Squeeze - Ramp-down - Pre-cycles Parameter space (Q, Q’, bumps, harmonics…)

Magnet Model (FIDEL) Calibration curves Harmonics, decay, snapback Corrections

Sequencing machine cycle Power converter functionality

Power converters Tracking, control, ramping, squeezing (constraints), real-time

Page 28: Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

LHC status 2818/01/2008

Collimation Dry Runs

Full control system functionality Machine cycle

Injection versus intensity Ramp, limits, Squeeze

Trim Parameter space, limits

Interface to BIS Monitoring, logging, FD, alarms etc Optimization procedures

Interface to BLMs etc.

Page 29: Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

LHC status 2918/01/2008

Partial Machine Checkout

Possible pre-cursor to sector test Injection & dump N sectors through full machine cycle plus RF & Collimators All distributed instrumentation from N sectors All available stand alone instrumentation All relevant software/controls Beam Interlocks

One week given extensive dry runs

Page 30: Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

LHC status 3018/01/2008

Integration & commission

Good for sector test/first turnGood for sector test/first turn

Page 31: Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

LHC status 3118/01/2008

Full Machine Checkout

INJECT AND DUMP

INJECTION PILOT

INJECTION INTERMEDIATE

INJECTION NOMINAL FLAT

TOP

SQUEEZE

STABLE BEAMS

UNSTABLE BEAMS

ADJUST

RECOVER

RAMP DOWNSETUP

CIRCULATE AND DUMP

PREPARE RAMP

RAMP

BEAM DUMP

ABORTCYCLING

BEAM DUMP WARNING

Page 32: Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

LHC status 3218/01/2008

So far…

Injection dry run – December 2007 Beam dump dry run – February 2008 PGC 4-5 – February 2008 LHCb – November 2007 Alice – February 2008

Acknowledgements: BT, BI, ATB, OP, CO, PO, HWC

Page 33: Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

LHC status 3318/01/2008

Injection Dry Run – December 2007

Page 34: Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

LHC status 3418/01/2008

Beam Dump Dry Run – February 2008

Verena Kain

Page 35: Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

LHC status 3518/01/2008

PGC – “HWC shadowing” – February 2008

Page 36: Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

LHC status 3618/01/2008

2000 4000 6000 8000 10000

5

10

15

20

TF: geometric

2000 4000 6000 8000 10000

-0.012

-0.011

-0.009

-0.008

-0.007

-0.006

-0.005TF: mdc

2000 4000 6000 8000 10000

-0.008

-0.006

-0.004

-0.002

TF: saturation

2000 4000 6000 8000 10000

0.0005

0.001

0.0015

0.002

0.0025

0.003TF: residual

Residual

Saturation

MDC

Geometric

)(45 tIMB

PGC – deployment of FIDEL

Page 37: Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

LHC status 3718/01/2008

Plans - March

Page 38: Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

LHC status 3818/01/2008

Plans - April

++

Page 39: Preparation for Beam commissioning Mike Lamont Acknowledgements: Brennan Goddard, Verena Kain, Reyes Alemany, Gianluigi Arduini, JJ Gras, Stefano Redaelli,

LHC status 3918/01/2008

Conclusions

Individual system commissioning from CCC Integrations tests (Dry Runs) Partial machine checkout Full machine checkout

When the going gets tough, the tough get operational.

We have a plan…