8/10/2019 Preocurement Schedule.pdf
1/2
ID Task Name Predecessors
1 Procurement Schedule for
redevelopment of Southmead
Hospital
2 Procurement Management plan
3 Define a procurement strategy
4 Establish packages 3
5 Analysis of s trategy plan 3FS+3 days
6 Approval of the strategic
procurement plan
5
7 Requirements
8 Define the requirements andspecifications
4
9 Define Scope of works in the
established packages
8
10 Define commercial and
technical conditions
9
11 Prequalification tendering
12 Invite interested suppliers and
companies formally
9
13 Define evaluation and
selection criteria
10
14 Technical and Commercial
analysis of all submitted
proposals on time
10,13
15 Invite all prequalified suppliers
and contractor for official
project tendering
13,14
16 Issue complete project
specification and requirements
15
17 Open clarification section for
prequalified suppliers and
contractors
15
18 Delivery of all open questions
to all qualified suppliers and
contractors
17
19 Project Tendering
20 All tenders submitted under
the define deadline
18
21 Opening of all submitted on
time tenders
20
22 Evaluation of all submitted
proposals according to the
define guidance, requirements
and compliance
21
15/12
07/01
21/01
Week -3 Week 1 Week 4 Week 7 Week 10 Week 13 Week 16 Week 19 Week 22
Task
Split
Milestone
Summary
Project Summary
External Tasks
External Milestone
Inactive Task
Inactive Milestone
Inactive Summary
Manual Task
Duration-only
Manual Summary Rollup
Manual Summary
Start-only
Finish-only
Deadline
Progress
Page 1
Project: Week 4
Date: Thu 13/11/14