PRELIMINARY VERSIONESS RFQ CDR 2TIME SCHEDULE,
PROJECT RISKS, RAMI AND SAFETY
Anne-Catherine CHAUVEAU 8th and 9th december 2015
PRELIMINARY VERSION
TIME SCHEDULE
TUNER
COUPLERS
TEST CAVITY and AUXILIARIES
PROTOTYPING COUPLER CONDITIONING
COPPER
RFQ MANUFACTURING
RFQ ASSEMBLY and TESTS
RFQ RE-ASSEMBLY and CONDITIONING
RFQ PACKING and TRANSPORTMPP planning is more than 200 lines
Manufacturer’s planning awaits confirmation| PAGE 2
Delivery to Lund due 13/03/18Formal Handover due 16/07/18
Assembly in Saclay will start in parallel with sections manufacturing
PRELIMINARY VERSION03/16
Pre-prod 08/16
Proto 06/16
TENDERS PLANNING CONNECTIONS
Vannes Copper
RFQ tenderProcess Qualif.
11/15 04/16
09/15
HIP
03/16 04/16
07/16 09/16
Sec.1 Machining
Sec.1 ass. Brazing
12/16
Sec.2 ass. Brazing
02/17
RFQ Assembly
RF testsDe-ass. Packing
RFQ partial SAR
TransportRe-
AssemblyConditioning
RFQ Handover
03/17 01/18 01/18 02/18 03/18 03/18 03/18 04/18 07/18
Tuner tender
11/15
Tuner manufact.
05/16
Aux. Copper Manuf.
Ports and test cavity
tender
10/15 04/16
09/15 01/16
Test cavity & Ports
manufact.
04/16 10/16
08/16∆= 6wks
Serie 11/16
Tuner Proto manufact.
Test cavity leak tests
06/1606/16
11/16∆= 10wks
06/16
Test cavity assembly
05/16 12/16
12/15 03/16
Sec.1. Pre-assembly.
Sec.2 Pre-assembly01/17
03/17
Preserie 09/16
Serie 12/16
07/16 02/17
Coupler tender
11/15
Coupler manufact.
05/16 05/16 02/17
02/17
12/16
02/17∆= 12mths
Coupler conditioning
02/17 03/17
20162015 2017 2018
09/1
6
∆= 13wks
∆= 17wks
Tight meeting points between tenders target dates.
RFQ cavity is the critical path
| PAGE 3
Production Ports needed for assembly and brazing on the
remaining cavity sections.10 weeks margin.
Pre-production ports needed for assembly and brazing on
the first cavity section.6 weeks margin only.
Tuner production needed for assembly of the remaining sections after delivery at
Saclay17 weeks margin.
Couplers needed for RF tuning tests
12 months margin.
Tuner pre-production needed for assembly of the first section after delivery at
Saclay13 weeks margin.
PRELIMINARY VERSIONLund delivery on february 2019 Lund delivery on march 2018
Whole RFQ fully tested.Partial tests done on single sections to 4
assembled sections. Partial tests on full RFQ
Assembly tools validation Assembly tools validation
Alignment
Tuners RF tuning Tuners RF tuning
Leak tests under full vacuum Partial Leak test
Vacuum system and control validation First full assembly of vacuum system done in Lund
Bead Pull measurement and voltage law Bead Pull measurement and voltage law
Cooling system and control validation FAT for the SKID under simulated load drops
Cooling piping system congestion verification First assembly of cooling system done in Lund
Verification of mechanical behavior under vacuumRFQ first time under operational vacuum will be done in Lund.
IO plates brazed finger RF verification IO plates with brazed fingers will be checked in Lund.
Lund delivery on february 2019 Lund delivery on march 2018
Whole RFQ fully tested.Partial tests done on single sections to 4
assembled sections. Partial tests on full RFQ
Assembly tools validation Assembly tools validation
Alignment
Tuners RF tuning Tuners RF tuning
Leak tests under full vacuum Partial Leak test
Vacuum system and control validation First full assembly of vacuum system done in Lund
Bead Pull measurement and voltage law Bead Pull measurement and voltage law
Cooling system and control validation FAT for the SKID under simulated load drops
Cooling piping system congestion verification First assembly of cooling system done in Lund
Verification of mechanical behavior under vacuumRFQ first time under operational vacuum will be done in Lund.
IO plates brazed finger RF verification IO plates with brazed fingers will be checked in Lund.
CHALLENGING TIME SCHEDULE
In order to meet the ESS target date for delivery, CEA has worked on reducing the project planning.Test planning has been reduced by 6 months and manufacturing by 4 months thus adding risks on the time schedule
| PAGE 4
PRELIMINARY VERSION
0, 0, 22, 0, 5, 57, 22, 57 IdentificationRating Pre-Mitigation
DispositionRating Post-
Mitigation
Risk LabelLevel Treatment Mitigation Strategy / main actions Level
("As a result of...") ("There is a risk that...") ("Resulting in...")
Time schedule reduction of RFQ contract
Auxilairies + Tuner + couplers contracts nor reaching RFQ contract on target time (from schedule point of view)
Interruption in RFQ cavity manufacturing (assembly step) + RFQ final assembly
64VERY HIGH
Mitigation
Set sub-critical contracts as priority in order to put them outside the critical path : ressources allocations, special adlinstrative procedure, pre-selection of bidders. Close follow-up of adminstrative durations
32 HIGH
Time schedule reduction of RFQ contract
No single manufacturer able to sustain the schedule constraint
No offer avaialble > Schedule 32 HIGH Transfert Delay to be tranfered to ESS 32 HIGH
Time schedule reductionProcurement financial offers should be higher than expected
Overcost 32 HIGH Transfert Additional cost to be transfered to ESS 32 HIGH
Time schedule reduction > Cooling system FAT only, no SAT (leak test, skid performance test)
Cooling system performance not reaching its specifications during check-out at Saclay
Investigation to be done directly in Acceleraor tunnel - defaut to be corrected > time schedule
32 HIGH Mitigation
Mitigation : Water loss of pressure simulations in FAT (new in contract), Transfert : Cooling system assembly and leak test to be performed directly by ESS / Delays and additional cost to be tranfered to ESS to correct problem after shipment
32 HIGH
Only partial tests at sacalyMore manmpower needed in Lund to finish CEA contribution
Overcost 32 HIGH MitigationChange contract approach (with limitation in ressources according to intial cost) + all correcivtes cost to be supported by ESS => Cost & fee
32 HIGH
Time schedule reduction > End plate final assembly no RF tested (only dummy finger tested)
End plate RF specification not achieved (with final components)
End plate parts (gaskets ,fingers, assembly process) defaut to be corrected > time schedule
16 HIGH Transfert Delays and additional cost to be tranfered to ESS 16 HIGH
Time schedule reduction > No final vacuum system integrated and tested @ Saclay
Vacuum system performance not reaching its specifications (RFQ vacuum integrity still tested ) during validations at Saclay
Investigation to be done directly in Acceleraor tunnel - defaut to be corrected > time schedule
16 HIGH TransfertDelays and additional cost to be transfered to ESS if issues arise after shipment.
16 HIGH
Time schedule reduction > No final vacuum control system integrated and tested @ Saclay
Vacuum control system not reaching its specifications during validations at Saclay
Investigation to be done directly in Acceleraor tunnel - defaut to be corrected > time schedule
16 HIGH Mitigation
Vacuum CS partially tested on vacuum chamber (Control system could be partially tested on 1 RFQ section ONLY if this can be done on hidden time thus not impacting time schedule.
8MEDIUM
Set sub-critical contracts as priority in order to put them outside the critical path (ie: tuner prototype)No mitigation
No mitigation Mitigation : Water loss of pressure simulations in
FAT Issues discovered in Lund
will take longer to solve
Change contract approach with limitation in
ressources according to intial cost and correctives cost to be supported by
ESS
More CEA manpower needed in Lund to finish
CEA contribution.Overcost
Cooling system performance not reaching its specifications first time
Procurement financial offers should be higher
than expected
Auxilairies + Tuner + couplers contracts not
reaching RFQ contract on target time (from schedule
point of view)
No single manufacturer able to sustain the
schedule constraint of 20 months
CHALLENGING TIME SCHEDULE RISKS
| PAGE 5
PRELIMINARY VERSION
IdentificationRating Pre-Mitigation
Disposition Rating Post-Mitigation
Risk LabelLevel Treatment Mitigation Strategy / main actions Level
("As a result of...") ("There is a risk that...")
Organization / Specific managerial aspects
ERIC finalisationUnknown admistrative process with potential impact on-going call for tenders and schedule
32 HIGH Mitigation Mitigations at management level (see Management RR) 16 HIGH
Accelerator System team not stabilized. Engineering process not stable
External RFQ interfaces not frozen in due time (CDR2) to finalize Tech Specs
64 VERY HIGH Mitigation
CDR2 before manufacturing with high priority interfaces specification.Interface specification reviewed both by CEA and ESS
8 MEDIUM
Individual components performance
Beam Dynamics design issues …RFQ RF design does not match the all the performance requirements
32 HIGH Mitigation CDR0 has reviewed all design topics / Qualification plan / Bead pull / 16 HIGH
Peak power very high, design based on SP2 under installation, Couplers not reaching specifications (800 kW)
64 VERY HIGH Mitigation
The couplers will be tested on the test cavity / One coupler spare / Additional windows spares / Qualification plan (progressive steps)
32 HIGH
Procurements
Not enough applicants, over cost from tenderers, bad tendering process
tenders process not concluded in due time 32 HIGH MitigationAnticipate as much as possible call for tenders even if specifications are not completely defined.The markets are closely followed.
8 MEDIUM
Several company to deliver the auxiliairies parts, technological challenges (SS/Cu brazing), process qualification to reach, manufacturing schedules slippage
Auxiliaries parts (esp. RFQ ports) to braze delivered too late to RFQ manufacturer
32 HIGH Mitigation Close follow-up of manufacturers, Enhanced QA 4 MEDIUM
Manufacturing workload and internal bad arbitration from the manufacturer
RFQ manufacturer late delivery 32 HIGH Mitigation
Define precise steps with the manufacturer to follow process datesWe will request frequent meetings with manufacturer to follow process.Higher delivery penalties / incitationsMarket survey (Industry proper selection)
16 HIGH
ESS issuesVacuum and its control system not delivered on time by ESS
16 HIGH Mitigation
Enhance communication with vacuum and control teams. If possible, the pump used for all anticipated tests during prototyping and RFQ assembly will be identical to the final pumps in order to prove mechanical adjustment.Send 3D to vacuum team ASAP
16 HIGH
Manufacturing process
Bad behaviour of materials during brazing, senstive and new process for the selected company
Difficulties to perform RFQ sections brazing
64 VERY HIGH Mitigation
Check brazing experience prior to tender approval / Follow up process during manufacturing / Brazing process qualification / Cu Spare parts / Brazor expert is working with us to help on and follow brazing procedure.
16 HIGH
Difficult manufacturing process (ceramic window brazing …)No manufacturing acceptance of Couplers (leaks, conditioning barriers, …)
64 VERY HIGH Mitigation
One coupler spare + Manufacturing process with validation steps (NOT considered in current risk analysis : 2 or 3 spares in option / pre-serie qualification inc conditioning / Contract provisions)
32 HIGH
Acceptance
RF archs damaging critical parts of the cavity RFQ compromised during conditioning 64 VERY HIGH Mitigation
Progressive RF power ramp / Cleanliness cautions during manufacturing and assembly at Lund / RF expert for conditionning
16 HIGH
Progressive RF power ramp.Cleanliness cautions during
manufacturing and assembly. RF expert for
conditioning
One coupler spare + Manufacturing process with validation steps.
Brazor expert is working with us to help on and
follow brazing procedure.
The couplers will be tested on the test cavity /
One coupler spare
Interface specification reviewed both by CEA
and ESS
RFQ compromised during conditioning (RF arcs
damaging cavity)
Manufacturing process issues for the couplers
(ceramic window)
Difficulties to perform RFQ sections brazing
Couplers not reaching specifications because peak power is very high
External RFQ interfaces not frozen in due time
(CDR2) to finalize Tech Specs
OTHER RISKS
| PAGE 6
PRELIMINARY VERSION
| PAGE 7
PROJECT RISKS SUMMARY
Level 64 Level 32 Level 16 Level 8 level 40123456789
10
6
9
4
0 0
RISKS LEVEL BEFORE MITIGATION
Risk level
Num
ber
of r
isks
Level 64 Level 32 Level 16 Level 8 level 40
1
2
3
4
5
6
7
8
9
0
78
3
1
RISKS LEVEL AFTER MITIGATION
Risk level
Num
ber
of r
isks
No “Very High” level risks after mitigation
Most risks concern the time schedule as it contains no margin.
Most critical technical part is the coupler because it is a complex part and the power required is very high.
Risk Workshop due in Lund on the 14th of january
PRELIMINARY VERSION
| PAGE 8
RAMI AND SAFETY
RAMI: Reliability – Availability – Maintainability – Inspectability
Very little maintenance on the RFQ itself if kept under vacuum (hydraulic channels cleaning), most are on the coupler (EPDM gasket, view ports replacement).
No statistics on RFQ life time. Cooling system will be delivered with maintenance manual.
CEA will provide technical inputs for the RAMI workshop.
SAFETYNo specific hazard under CEA responsibility on the RFQ.
CEA applies the standard European safety rules and regulations.During work in Sweden, CEA will follow the Swedish rules and regulations.List of materials used will be provided to ESS (>90% consists in copper and
stainless steel)
CEA Saclay/Irfu projet ESS | DATECommissariat à l’énergie atomique et aux énergies alternatives
Centre de Saclay | 91191 Gif-sur-Yvette Cedex
T. +33 (0)1 69 08 xx xx | F. +33 (0)1 69 08 99 89
Etablissement public à caractère industriel et commercial | RCS Paris B 775 685 019
| PAGE 9
有點不耐煩毀掉一個偉大工程
A small impatience ruins a great project.
En liten otålighet ruiner ett stort projekt
Confucius
PRELIMINARY VERSION
APPENDIX: RISK QUOTATION
| PAGE 10