Upload
vantram
View
232
Download
5
Embed Size (px)
Citation preview
Preliminary InformationMemorandum
Rajasthan Vidyut Utpadan Nigam LimitedDisinvestment of 2320 MW Chhabra Thermal PowerPlant
Preliminary Information Memorandum Page 2 of 70
Contents
Disclaimer 4
Abbreviations Used ............................................................................................................................. 5
1 Executive Summary ..................................................................................................................... 7
1.1 Introduction ......................................................................................................................... 7
1.2 Project Status ...................................................................................................................... 7
1.3 Clearances and Approvals...................................................................................................... 9
1.4 Fuel Supply Agreement ....................................................................................................... 10
1.5 Power Purchase Agreement................................................................................................. 12
2 Introduction .............................................................................................................................. 14
3 Project Overview ....................................................................................................................... 16
3.1 Project overview ................................................................................................................. 16
3.2 Site location and accessibility .............................................................................................. 16
3.3 Land details........................................................................................................................ 17
3.4 Details of BOP and BTG contract .......................................................................................... 19
3.5 Water Source ..................................................................................................................... 23
3.6 Power Evacuation ............................................................................................................... 23
3.7 Operational Performance of CTPP ........................................................................................ 24
3.8 Plant Organizational Structure and details of employees ........................................................ 27
3.9 Project Cost and Means of Finance ....................................................................................... 29
4 Power Purchase Agreement ....................................................................................................... 35
5 Fuel Supply Arrangement ........................................................................................................... 38
5.1 Unit 1 & 2 ........................................................................................................................... 38
5.2 Unit 3 & 4 .......................................................................................................................... 40
5.3 Unit 5 & 6 ........................................................................................................................... 42
6 Approvals and Clearances .......................................................................................................... 46
7 Structure for Disinvestment ....................................................................................................... 49
7.1 Proposed structure for disinvestment ................................................................................... 49
7.2 Key Investment Consideration ............................................................................................. 50
8 Profile of RVUN ......................................................................................................................... 52
8.1 Company background .......................................................................................................... 52
8.2 Board of Directors .............................................................................................................. 52
Preliminary Information Memorandum Page 3 of 70
8.3 Details of Operational Assets ............................................................................................... 53
8.4 Ongoing Projects of RVUN ................................................................................................... 54
8.5 Financials of RVUN ............................................................................................................. 55
9 Market Scenario and Assessment ............................................................................................... 57
9.1 Existing Demand and Supply scenario in Rajasthan ................................................................ 57
9.2 Future Demand and Supply scenario in Rajasthan .................................................................. 58
9.3 Existing generation capacity (RVUN, IPPs, Central) ............................................................... 59
9.4 Planned capacity addition in generation in Rajasthan (RVUN, IPPs, Central) ............................ 60
9.5 Comparative analysis of generation tariff.............................................................................. 60
9.6 Competitive Bid scenarios (Case 1) in India ........................................................................... 61
10 Annexure .................................................................................................................................. 63
Preliminary Information Memorandum Page 4 of 70
Disclaimer
This Preliminary Information Memorandum (“PIM”) has been prepared by RVUN’s advisor and intendsto provide information about the Chhabra thermal power plant (“CTPP”, “Project”).
The PIM does not purport to be all-inclusive or necessarily to contain all the information that prospectiveBidders may desire in examining the CTPP. The PIM contains selected information to assist therecipient in making an initial decision to proceed with further investigation. The PIM is not intended toform the basis of any investment decision by prospective Bidders. Bidders should carry out their owninvestigations and analysis of CTPP and of the data referred to in the PIM and should consult their ownadvisors before proceeding with any offer. The information contained in the PIM will not constitute orform part of any offer for sale of CTPP nor will any such information form the basis of any contract inrespect thereof. Any Bidder must rely on the terms and conditions contained in such a contract subjectto such limitations and restrictions as may be specified therein.
No representation or warranty, express or implied, is given by the RVUN or any of their respectivedirectors, partners, officers, affiliates, employees, advisors or agents (and any warranty expressed orimplied by statute is hereby excluded) as to the accuracy or completeness of the contents of this PIM orany other document or information supplied, or which may be supplied at any time or any opinions orprojections expressed herein or therein, nor is any such party under any obligation to update the PIM orcorrect any inaccuracies or omissions in it which may exist or become apparent.
In no circumstances will RVUN or any of its subsidiaries or affiliates or its advisors be responsible forany costs or expenses incurred in connection with any appraisal or investigation of the RVUN/CTPP orfor any other costs or expenses incurred by prospective Bidders in connection with the proposedinvestment in the CTPP. In providing this PIM, RVUN and its advisors undertake no obligation to invitethe recipient to proceed with a further investigation of the RVUN/CTPP and its subsidiary companiesnor to provide the recipient with any additional information, nor otherwise to negotiate with or treat withthe recipient in respect of those companies.
Subject to confidentiality under the EoI, a Bidder who deposits Application Processing Fees should bebound by confidentiality as mentioned in the EoI.
Preliminary Information Memorandum Page 5 of 70
Abbreviations UsedACQ Annual Contracted Quantity
AVVNL Ajmer Vidyut Vitran Nigam Ltd
BOP Balance of Plant
BTG Boiler Turbine Generator
CAGR Compounded Annual Growth Rate
CERC Central Electricity Regulatory Commission
COD Commercial Operations Date
DPR Detailed Project Report
DM Demineralization
EPC Engineering, Procurement and Construction
GCV Gross Calorific Value
GoR Government of Rajasthan
JVVNL Jaipur Vidyut Vitran Nigam Ltd
JdVVNL Jodhpur Vidyut Vitran Nigam Ltd
KwH Kilowatt Hour
LD Liquidated Damages
MDO Mine Developer and Operator
MMT Million Metric Tonnes
MoU Memorandum of Understanding
MT Metric Tonnes
MW Mega Watt
MU Million Units or Million KWH
PFC Power Finance Corporation
PGCIL Power Grid Corporation of India Limited
PPA Power Purchase Agreement
PLF Plant Load Factor
PT Pre- Treatment
PWD Public Works Department
REC Rural Electrification Corporation
RERC Rajasthan Electricity Regulatory Commission
RfP Request for Proposal
RVPN Rajasthan Rajya Vidyut Prasaran Nigam Limited
RVUN Rajasthan Rajya Vidyut Utpadan Nigam Limited
SHR Station Heat Rate
SLDC State Load Dispatch Centre
Preliminary Information Memorandum Page 6 of 70
SPV Special Purpose Vehicle
Y-o-Y Year on Year
YTD Year to Date
The words and expressions beginning with capital letters and defined in this document shall, unless
repugnant to the context, have the meaning ascribed thereto herein, and the words beginning with
capital letters and not defined herein shall have the meaning as ascribed to them in the Invitation of
Expression of Interest (“EoI”).
Preliminary Information Memorandum Page 7 of 70
1 Executive Summary
1.1 Introduction
Rajasthan Rajya Vidyut Utpadan Nigam Ltd. (RVUN) is a GoR undertaking under the aegis of
Department of Energy. RVUN was established upon unbundling of erstwhile Rajasthan State
Electricity Board (RSEB) into separate companies for generation, transmission and distribution
functions. Pursuant to the restructuring of the erstwhile RSEB, RVUN took over the entire
power generation business under the State ownership w.e.f. 19.7.2000. Present installed capacity
of RVUN is 5957.35 MW. During the budget speech of Financial Year 2014-15, the GoR announced
disinvestment of at least 10% of its stake in RVUN. However, after subsequent discussions and
deliberations, it was felt that an individual plant wise disinvestment strategy would be more beneficial
for RVUN. Subsequently, in January 2016, the GoR decided to go for disinvestment of Chhabra
Thermal Power plant (CTPP), both the operational units (4X250) and units under advance stage of
construction (2*660) together through one transaction.
1.2 Project Status
Project status as on date is summarized in the below table:
Unit No. Capacity Status COD
Unit1 250 MW Operational 11.06.2010
Unit 2 250 MW Operational 15.10.2011
Unit 3 250 MW Operational 19.12.2013
Unit 4 250 MW Operational 30.12.2014
Unit 5 660 MW Under construction Expected COD 30.12.2016
Unit 6 660 MW Under construction Expected COD-30.06.2018
1.2.1 Project Location and Accessibility
Chhabra Thermal Power Project is located near village Chowki Motipura in Tehsil Chabbra, Distt.
Baran (Rajasthan), which is 22 km from Chabbra Town, 10 Km from interstate border of Madhya
Pradesh, 147 Km from Kota. The coordinates are 24.24° N, 77.03° E.
Plant site is well connected to State Highway-51 & located on Bina-Kota line of West Central Railway.
The nearest railway station is Motipura Chowki which is in between Beena- Kota Section. The site lies
between North Latitudes 24 degree 24 inches and East Longitude 77 Degree 03 inches.
Preliminary Information Memorandum Page 8 of 70
1.2.2 Water Resource System
Water requirement for units 1, 2, 3 and 4 is 800 MCFT/ Year (38500 M3/ day) fulfilled through
following sources:
a. 200 MCFT from Bethali
b. 100 MCFT from Parvati River
c. 500 MCFT from Hindlot Dam
Water Requirement for units 5 & 6 would be 1570 MCFT/ Year. Required water would be supplied
from following projects:
a. 300MCFT from Lhasi Irrigation Project
b. 500 MCFT from Audheri Irrigation Project, and
c. 770 MCFT from Parvan Irrigation Project
1.2.3 Power Evacuation
The Power evacuation for CTPP is being done by 400kV Double circuit lines to Dahra Pooling Station
located 130 km away from this plant by Quad Moose conductors. Power evacuation is also being done
through 2 Nos. interconnectors between Phase –III and Phase II 400kV Switchyards of the CTPP.
The proposed 2 X 660 MW units have a 400 kV Switchyard, which is working on one and half breaker
scheme having facility to connect 2 Nos. 400 kV Lines for the purpose of Power evacuation. In order
to evacuate the power as mentioned above, the generated power of the proposed 2 X 660 MW Power
plant will be stepped up to 400kV using 3 Nos. single phase 21kV/400kV/√3 Generator
Transformers. Bus connected Reactors of 50 MVAR capacity shall be used in the 400 KV Switchyard.
The approval of Power evacuation system has been issued by Rajasthan Rajya Vidyut Prasaran Nigam
Limited (RVPN) vide letter no. 595 dated 04.08.09. Power shall be evacuated by 400KV /220 kv
Switchyard with Inter-connecting Transformers (ICT) through 400KV Bhilwara, 400KV Hindaun,
400KV Adani and 220 KV Jhalawar & 200 KV Kawai-Dahara feeders. Detail of tramission lines for
unit 5 and 6 provided below;
Feeder Status
400kV Anta-I Feeder Ready
400kV Anta-II Feeder Ready
1.2.4 Operational Performance of CTPP
Unit wise PLF for operational units i.e. units 1, 2, 3 & 4 is tabulated below:
Unit Name Deemed PLF (April’16)
Unit 1 77.29%
Preliminary Information Memorandum Page 9 of 70
Unit 2 97.6%
Unit 3 88.21%
Unit 4 97.16%
Average PLF 90.06%
1.2.5 Details of EPC Contract
The BTG equipment for unit 1, 2, 3 & 4 has been provided by BHEL and the turnkey contract for unit
5 & 6 is being done by L&T. Detailed terms are mentioned in section 3.4.
1.3 Clearances and Approvals
Units 1 to 4 of CTPP are already operational and “consent to operate” has already been obtained for
the same. For under construction units all the required approval and clearances are in place.The
status of all the approvals is given in the table below:
S. No. Clearances and approvals Status
Operational Units
1 Consent to operate for Unit 1 & 2 Expired on 31.08.2015. renewal application filed
with renewal awaited
2 Consent to operate for Unit 3 & 4 Expired on 23.01.2015. renewal application filed
with renewal awaited
Under construction Units Unit 5 Unit 6
1 Administrative and Financial
Approval of State GovernmentApproval is on record Approval is on record
2 Water availability Approval on record for allocation of water for
both units
3 Environmental Clearance Clearance is on record Clearance is on record
4 Rajasthan State Pollution Control
Board
Approval on record and valid till 31.08.2018 or
till the date of commissioning, whichever is
earlier
5 NOC for Height Clearance Approval on record and valid till 26.10.2015 for
completion of building/chimney. One time
approval is sufficient for this
6 NOC for construction of chimney NOC on record, one time approval is sufficient
Preliminary Information Memorandum Page 10 of 70
1.4 Fuel Supply Agreement
The following table summarizes the fuel requirement and sources of fuel to CTPP:
(All figures in MTPA)
Year 2016-17 2017-18 2018-19 2019-20 2020-21Raw Coal Requirement 5.10 7.64 9.71 9.71 9.71Availability of Raw Coal from different sources to RVUN for CTPPSECL 1.85 1.85 1.85 1.85 1.85Parsa East & Kanta Basan 2.75 4.33 6.13 6.13 6.37Parsa 0 0 0 0.2 0.2Kente Ext. 0 0 0 0.33 1.29Total 4.60 6.18 7.98 8.51 9.71
Short fall to be met throughallocation of Bridge Linkage 0.50 1.48 1.73 1.20 0
Presently, coal deficit for units 1 & 2 is being met through arrangement of additional coal from SECL,
however in future; the deficit is proposed to be met from coal blocks allotted to RVUN, wherein there
is provision of transfer of coal from coal block to power projects, other than power projects having
linkage with CIL.
Till completion of common rail corridor up to mine head of ‘Parsa East & Kanta Basan’, as well as
commencement of mining operations at ‘Parsa” and ‘Kente Extn’ coal blocks, RVUN vide letters dated
16.05.2016 applied to Ministry of coal for grant of bridge linkage for units 3 & 4 (2x250 MW) and
units 5 & 6 (2x660 MW) respectively in line with the “policy guidelines for grant of ‘Bridge Linkage’
issued by Ministry of Coal, GoI on 08.02.2016.
Preliminary Information Memorandum Page 11 of 70
Unit Annual Fuel
Requirement
Sources Transportation
Unit 1 & 2 The annual
requirement is
estimated to be
about 1.85 MT
per annum (FY
17-21)
,considering G11
grade coal at 85%
PLF
Fuel Supply Agreement has
been signed between RVUN
and SECL dated 24.04.12 to
supply coal for 20 years.
As per the FSA, 100% of
‘Annual Contracted Quantity’
(ACQ) (including 5%
imported coal for FY 2016-
17) is committed by SECL.
Currently, the entire coal
required by RVUN for
running units 1 & 2 is being
provided by SECL. The
deficit for Unit 1 & 2 shall be
calculated in accordance
with the CEA guidelines
published, in December
2015.
Mode of transport for delivery will
be either through rail or road
transport. Third party/contractor
has been deployed which lifts coal
from SECL Korba mine, transports
raw coal from Korba mine to
beneficiation plant, beneficiates raw
coal and transports washed coal
from beneficiation plant to railway
siding and further loading onto
railway wagons.
Unit 3 & 4 The annual
requirement is
estimated to be
about 2.33 MT
per annum (FY
17-21) ,
considering a
Gross Calorific
Value of 4500
Kcal/Kg at 85%
PLF
Government of India has
allotted Parsa East & Kanta
Basan coal mine to RVUNL
on 31-03-2015 and Parsa
coal mine on 08-09-2015
vide order no
103/13/2015/NA for
utilization in end use plant in
accordance with the
provisions of the coal Mines
(Special Provisions) Second
Ordinance, 2014 and the
Coal Mine (Special
Provisions) Rules, 2014.
For units 3 & 4, coal is supplied
from Parsa East & Kanta Basan Coal
Mine situated in Chhattisgarh. Due
to non-availability of rail link upto
mine head, coal is transported via
road for a stretch of 62/85/110 KM
up to nearest railway siding of
Ramanujnagar/ Kamalpur/ Karonji
and rest through rail. Rail link of 37
kms up to mine head is scheduled to
be completed by July
2017.
33 Km of phase-1 from Surajpur
station of Indian Railways to
Ramanujnagar has been completed
and is in operation. Phase-II from
Preliminary Information Memorandum Page 12 of 70
Unit Annual Fuel
Requirement
Sources Transportation
Ramanujnagar to mine head is
under implementation and
scheduled to be commissioned by
July'2017.
Unit 5 & 6 The annual
requirement of
coal for Unit 5 &
6 of CTPP has
been estimated
to be about 0.92
MTPA for FY17,
which shall
increase to 5.53
MTPA
subsequently (FY
18 to FY 21),
considering a
Gross Calorific
Value of 4500
Kcal/Kg at 85%
PLF
Government of India has
allotted Parsa East & Kanta
Basan coal block to RVUN on
31-03-2015 vide order no
103/13/2015/NA for
utilization in end use plant in
accordance with the
provisions of the coal Mines
(Special Provisions) Second
Ordinance, 2014 and the
Coal Mine (Special
Provisions) Rules, 2014 and
also allotted Kente Extn.
coal block to RVUN on 31-
03-2015 vide order no
13016/26/2004-CA-I/CA-
III(Pt.)(Vol. II) for end use
power under Rule 4 of the
“Auction by Competitive
Bidding of Coal Mines Rules,
2012”
33 Km of phase-1 from Surajpur
station of Indian Railway to
Ramanujnagar has been completed
and is in operation. Phase-II from
Ramanujnagar to mine head is
under implementation and
scheduled to be commissioned by
July'2017.
1.5 Power Purchase Agreement
The PPA for CTPP as well as other RVUN generating units was signed between RVUNL and the three
distribution utilities of Rajasthan on 23.06.2004. Subsequently the amendments to the PPA were
done on 30 April 2005, 07 June 2007, 18 May 2010, and 15 December 2010. Declared Capacity of
RVUN mentioned in supplementary PPA signed on May 18, 2010 includes operational plants as well
as the upcoming plants (which include Unit 5 and Unit 6 of CTPP). As per PPA, 95% of the installed
capacity of CTPP is tied with distribution utilities namely AVVN, JVVN and JdVVN and rest 5% of the
Preliminary Information Memorandum Page 13 of 70
installed capacity is considered as unallocated capacity and the allocation would be done under the
guidance of GoR.
As per existing PPA, the entire generation capacity of RVUN is tied up with the three distribution
companies in the following ratio:
JdVVNL, 32%
JVVNL, 40%
AVVNL, 28% JdVVNL
JVVNL
AVVNL
PPA Break Up
Preliminary Information Memorandum Page 14 of 70
2 Introduction
RVUN is a GoR undertaking, entrusted with the job of development of power projects, in the state
along with operation & maintenance of state owned power stations. The installed capacity of RVUN is
5957.35 MW. As per audited financial for the year 2015, RVUN has accumulated losses of Rs. 4,014.
17 Crore.
In order to bring in operational efficiencies and reduce the burden on the Govt. of Rajasthan (GoR) to
infuse equity for future projects, in the budget for financial year 2014-15, GoR decided the for the
disinvestment of at least 10% of its stake in RVUN. However, after subsequent discussions and
deliberations, it was felt that an individual plant wise disinvestment strategy would be more beneficial
for RVUN. Subsequently, in January 2016, the GoR decided to go for disinvestment of CTPP, both the
operational units (4X250) and units under advance stage of construction (2*660) together through
one transaction
This disinvestment is expected to reduce the monetary burden on GoR as it shall not be required to
infuse the remaining equity for the under-construction units of CTPP. These government funds may
be used for other welfare projects running under the GoR. Moreover, the disinvestment would reduce
the debt burden of RVUN. As per the decision of the GoR, it is proposed that CTPP shall be
disinvested and transferred to the Selected Bidder or SPV as the case may be. The exact mode of
transfer of CTPP to the Successful Bidder shall be mentioned in the RFP document. All the CTPP
assets as well as agreements/linkages and approvals shall be transferred to the Successful Bidder.
All the relevant documents, agreements etc., for the purpose of due-diligence, shall be provided to
the Shortlisted Bidders at the Request for Proposal (RFP) stage. The transfer as well as details of
such transfer of the employees shall be provided at the RFP Bid Stage. It is anticipated that
disinvestment of CTPP shall improve operational efficiency, generate resources for state, and achieve
lower tariff for the consumers.
This PIM provides the details about CTPP, however Bidders are suggested to carry out their own due
diligence before submission of their Applications.
This PIM is divided into the following categories:
· Chapter – 3: Project Overview – This section contains project specific information such as
project’s site location and accessibility, land details, BOP and BTG contract details, water
source, power evacuation, operational performance, organizational structure, project’s cost
and means of finance.
· Chapter – 4: Power Purchase Agreement – This section highlights PPA details of CTPP with
distribution utilities along with the major terms and conditions of PPA including allocation of
power, tariff, effective date an duration of agreement, governing laws etc.
Preliminary Information Memorandum Page 15 of 70
· Chapter - 5: Fuel Supply Details – This section summarizes annual fuel requirement, fuel
linkage details, fuel transportation, fuel pricing and coal deficit plans of CTPP’s units 1 to 6.
· Chapter - 6: Approvals and Clearances – This section contains details of statutory and other
clearances of CTPP’s units.
· Chapter - 7: Structure for Disinvestment - This section comprises of proposed model of
disinvestment and investment highlights
· Chapter - 8: Profile of RVUN – This section comprises of RVUN’s background, RVUN’s board
of directors, details of operational assets, RVUN’s ongoing projects (coal, gas and hydel
projects) and financial performance of RVUN in the financial years of FY13, FY14 and FY15.
· Chapter - 9: Market scenario and assessment – This section provides an overview of the
existing demand and supply scenario of power in Rajasthan, future projections, existing
generation capacity in Rajasthan, planned capacity addition in generation in Rajasthan,
comparative analysis of generation tariff, bid scenarios in India.
· Annexures: Annexures highlight CTPP’s unit wise details inclusive of salient features, asset
details and technology inclusive of BTG and BOP equipment details, employee strength at
CTPP’s units 1 to 6, summary of key milestones for units 5 and 6 and ceiling price details
Preliminary Information Memorandum Page 16 of 70
3 Project Overview
3.1 Project overview
CTPP is a coal based thermal power project having an operational capacity of 1000 MW and advanced
stage under construction capacity of 1320 MW. Unit wise details are as follows:
Unit No. Stage/ Phase Capacity Status COD
Unit1 Stage I/Phase I 250 MW Operational 11.06.2010
Unit 2 250 MW Operational 15.10.2011
Unit 3 Stage I, Phase II 250 MW Operational 19.12.2013
Unit 4 250 MW Operational 30.12.2014
Unit 5 Stage II, Phase III 660 MW Under construction Expected COD 30.12.2016
Unit 6 660 MW Under construction Expected COD-30.06.2018
3.2 Site location and accessibility
CTPP is located near village Chowki Motipura in Tehsil Chabbra, Distt. Baran (Rajasthan) which is 22
Km from Chabbra Town, 10 Km from interstate border of Madhya Pradesh, 147 Km from Kota. The
coordinates are 24.24° N, 77.03° E.
District Baran can be located on the map as given below:
Preliminary Information Memorandum Page 17 of 70
Figure: Location of Baran District
CTPP site is well connected to State Highway-51 & located on Bina-Kota line of West Central Railway.
The nearest railway station is Motipura Chowki which is in between Beena- Kota Section. The site lies
between North Latitudes 24 degree 24 inches and East Longitude 77 Degree 03 inches. Tabulated
below is the snapshot of the accessibility and linkage nodes from the CTPP site location.
From Approximate Distances (Kms.)
Chhabra Railway Station 30 to 35
Chhabra Town 25 to 30
Jaipur Airport 300 to 350
Kota City 125 to 130
Baran Town 60 to 70
3.3 Land details
The land under CTPP’s units 1 to 4 & residential colony measures to a total area of approximately
2,134 bigha including private land, which is spread over 4 different villages. Tabulated below is the
breakup of khasra nos. along with land area:
S. No. Village Khasrano.
Govt. land(figures inbigha)
Gazettenotificationdate of privateland
Private land(figures inbigha)
Remarks
1 Bhatkhedi 143 524.14 12.09.2005 111.14 Land acquiredfor Unit 1 to 4(Stage -I)
2 Chowki 81 392.06 340.153 Mawasavyas 21 112.12 2.01
Preliminary Information Memorandum Page 18 of 70
S. No. Village Khasrano.
Govt. land(figures inbigha)
Gazettenotificationdate of privateland
Private land(figures inbigha)
Remarks
4 Leetarkhedi 162 570.11 9.02Sub Total 1,598.43 462.32
5 Niyamatpur 8 15.0026.12.2006 Land Acquired
for Unit 1 to 4(Stage I) &also BethaliPump
6 Bhatkhedi 13 14.10
7 Chowki 16 41.04Total
70.148 Teetakhedi
3.11Sub Total
3.11Total 1,671.68 462.32
The land area mentioned above comprises of main power house building, cooling towers, ash handling
plant, ESP units, marshaling yard, switchyard & control room, hydrogen generation unit etc. along
with residential colony which has staff quarters, guest house and recreational areas within the
colony. The surplus land allocated to RVUN for CTPP, shall not be transferred to Selected Bidder
along with the CTPP assets.
Units 5 and Unit 6 are in advanced stages of construction, land required for the project is in
possession of RVUN and the detail of land acquired is tabulated below:
Sr.No. Village Khasra
no.
Govt. land(figures inbigha)
Gazzettenotificationdate of privateland
Privateland(figures inbigha)
Remarks
1 Mawasvyas 157 465.00
17.07.2009
116.08
Landacquiredfor unit 5to 6 (Stage-II)
2 Teetakhedi 115 577.03 126.04
3 AmanpuraNayagaon 58 300.14 4.05
4 Arniyapar 41 230.09 57.17
5 Hanavatkhedapar 166 596.07 45.06
6 Akodiyapar 18 74.08 89.14Sub Total 2,242.41 437.54
7 Hanavatkhedapar 5 20.03
21.11.2011Addt. landacquiredfor Unit 5to 6(Stage -II)
8 AmanpuraNayagaon 7 20.12
9 Teetakhedi 13 30.0210 Akodiyapar 10 63.0011 Arniyapar 9 51.13
Sub Total 184.30
Preliminary Information Memorandum Page 19 of 70
Sr.No. Village Khasra
no.
Govt. land(figures inbigha)
Gazzettenotificationdate of privateland
Privateland(figures inbigha)
Remarks
Total 2,426.71 437.54
3.4 Details of BOP and BTG contract
Details of BOP and BTG contracts for units 1 to 4 and other contracts of units 5 & 6 of CTPP are
tabulated below:
S.
No.Particular Of Unit
Type Of
Contract
Name Of
Contractor
Date Of
Sanction COD
Details of BOP and other contracts
1.Unit 1 & 2
(2X250 MW)BOP
M/s Punj Lloyd,
New Delhi11.08.2005
Unit 1 – 11.06.2010
Unit 2- 15.10.2011
2.Unit 3 & 4
(2X250 MW)BOP
M/s Indure Pvt.
Ltd., New Delhi31.01.2007
Unit 3- 19.12.2013
Unit 4 – 31.12.2014
Details of BTG Contract
1.Unit 1 &2
(2X250 MW)BTG
M/s BHEL, New
Delhi11.08.2005
Unit 1 – 11.06.2010
Unit 2- 15.10.2011
2.Unit 3 &4
(2X250 MW)BTG
M/s BHEL, New
Delhi31.01.2007
Unit 3- 19.12.2013
Unit 4 – 31.12.2014
Details of turnkey contracts for units 5 & 6
7 Unit 5 and Unit 6
On-shore
supplies,
Off-shore
supplies
and Civil
works*
L&T -Unit 5 and Unit 6 are
expected to becommissioned by
Dec’16 and Jun’18respectively
*Contract Details in below table
It is further provided that river water system, railway siding system required for all the units are in
place.
Preliminary Information Memorandum Page 20 of 70
Summary of major terms and conditions of EPC contract for Units 5 & 6 (Onshore, Offshore and
EPC) are tabulated below:
All the three contracts pertaining to onshore, offshore and EPC have been awarded to L&T. A brief
summary of the costs as well as major terms and conditions is as follows:
Particular $-million Yen-Million Rs. Crore
Total contractvalue
(in crore)
Off Shore Supplies 31.49 2032.11 5.72 315.44
On shore Supplies 86.06 3059.47 3,489.62 4,170.0
Providing all Services, Erection, Testing,Commissioning & Civil Works
1,202.58 1,202.58
Total Contract Price 117.55 5091.58 4,697.92
Total Contract price in equivalent INR withapplicable Exchange rate as on03.12.2012 1US$ = Rs. 55.12 & 100Japanese Yen = Rs. 67.34 5,688.72
(In Words Rupees Five Thousand Six Hundred Eighty Eight Crores Seventy Two LacsSeventy Nine Thousand One Hundred Four Only)
I. Any variation in rate of applicable Indian taxes, duties, levies etc, variation in applicable
taxes, introduction of new taxes etc. shall be to the account of RVUN
II. Terms of payment
· 5% of the contract price for on shore services as first initial advance against
acceptance of LOI, submission of unconditional bank guarantee
· 5% of contract price for on shore services as second and final advance within 6
months from date of issue of LOI
· 80% of the price of EPC, Civil & Architectural works plus price adjustment along with
100% applicable taxes to be paid on pro rata basis
· 10% of the price for providing all services, erection, testing etc. component of the
contract price plus price adjustment on issuance of Final takeover certificate
III. Project Schedule: The contractual commissioning schedule period for the units shall be 42
months and 45 months for units 5&6 respectively.
IV. LD @0.5% of the contract price of each unit per week subject to a maximum of 10%.
V. LD for shortfall in Guaranteed performance parameters
a. If performance test results during performance guarantee tests deviate from
the guaranteed values, the contractor shall correct the equipment at its own
Preliminary Information Memorandum Page 21 of 70
expense. In case of un-remedied shortfall in guaranteed performance
parameters, the contractor shall pay LD to RVUN as stipulated below:
a) For every 1 kW shortfall in gross power output Rs.0.45 million
b) For every 1T/H decrease in steam flow at SG super-heater outlet
Rs. 5 million
c) For every 1 kW increase in auxiliary powerconsumption
Rs.0.45 million
d) For every 1 kW increase in transformer losses Rs.0.45 million
e) For every 1 kCal/KwH increase in weighted averagegross unit heat rate per unit
Rs. 30 million
f) For every 1 mwc increase in cooling water pressuredrop across condenser
Rs. 50 million
g) For every tonne differential per annum of 33% HCl Rs. 54,000
h) For every tonne differential per annum of 48% NaOH Rs. 5 lakhs
Contract price adjustment
a. Price adjustment in this contract shall not exceed 20% ofb. Escalation to be governed by the following formula
EC1= EC0 (0.2+a.A1/A0 x f1 + b.B1/B0 x f2 + c.C1/C0 x f3 + 0.25 L1/L0 x f4)
Where,
EC0 Ex-works / FOB supply price-component less advance paid (without taxes and
duties, transport, Insurance etc.) of the contract price for equipment, shipment-
wise.
EC1 Adjusted supply price—component of equipment (without Taxes & duties,
transport & insurance, etc) Shipment-wise
a Co-efficient of steel material involved in the Ex-Works /FOB price of the
equipment / materials
b,c Co-efficient of any other material involved in the Ex-Works / FOB price of the
equipment / materials to be selected by the Contractor and indicated in the bid.
a+b+c=0.55
Co-efficient of labour component in the Ex-Works/FOB price of the equipment/
materials = 0.25
A,
B,
C
published price indices of materials corresponding to a.b,c.
L Labour index
Subscript ‘o‘ refers to indices as on 30 days prior to date set for opening of
Preliminary Information Memorandum Page 22 of 70
techno commercial bid
Subscript ‘ I‘ refers to indices as on
One month prior to the date of shipment. for labour and
at the expiry of two—third (2/3) period from the zero date to the date of
Shipment, for materials
fl, f2 and f3 are Exchange Rate Correction Factors for the respective materials
and f4 is the Exchange Rate Correction Factor for labour with reference to the
currency of the country of origin of index and the respective contract currency,
such that
f=Z0/Z1
Where Z is the no. of units of the currency of the country of the origin of index,
which is equivalent to one unit of the respective Contract currency. The
exchange rates to be used for calculation of factor ‘F shall be as per Bills Selling
Exchange Rates Established by the STATE BANK OF INDIA.
For ‘Z0’ subscript ‘o' refers to exchange rates as on the date thirty (30) days
prior to the date of opening of bid Cover No. I
subscript ‘1' refers to exchange rates as of
one month prior to the date of shipment, for labour and
at the expiry of two-third (2/3) period from the’ zero date to the date of
shipment for material
For purposes of this clause, in the event of shipments beyond scheduled date
for supply completion the price adjustment shall be as worked out based on the
(1) supply scheduled completion date and (2) actual date of shipment &
whichever is lesser shall be payable
Summation of EC1 shall be limited to (100 +/- 20)% (Hundred plus / minus
twenty) percentage of total ex-work/FOB price for supply ofequipments
The above formula for price adjustment will be applicable in the currency in
which
The contract price is expressed is different from the currency of origin of labour
and
Material indices. In other cases, formula shall be applied without the exchange
rate
Correction factor ”f”.
II Contract Price Adjustment for the ex-works / FOB price for supply of
mandatory spares
The Contract Price Adjustment for the ex-works / FOB price for supply of
Preliminary Information Memorandum Page 23 of 70
mandatory spares shall be as per the formula for price adjustment of Ex-Works
/ FOB price for the supply of equipment’s, limited to (l00 +/- 20)% (Hundred
plus /minus twenty) percent of the ex-works /FOB price for supply of mandatory
spares.
3.5 Water Source
Water requirement for units 1, 2, 3 and 4 is 800 MCFT/ Year (38500 M3/ day) fulfilled through
following sources:
a. 200 MCFT from Bethali
b. 100 MCFT from Parvati River
c. 500 MCFT from Hindlot Dam
Water Requirement for units 5 & 6 would be 1570 MCFT/ Year. Required water would be supplied
from following projects:
d. 300MCFT from Lhasi Irrigation Project
e. 500 MCFT from Audheri Irrigation Project, and
f. 770 MCFT from Parvan Irrigation Project Parvan Irrigation Project will provide 770 MCFT.
3.6 Power Evacuation
The power evacuation for CTPP is being done by 400 KV Double circuit lines to Dahra Pooling Station
located 130 KMS away from this plant by Quad Moose conductors. Power evacuation is also being
done through 2 Nos. interconnectors between Phase –III and Phase II 400 KV Switchyards of the
CTPP.
The proposed 2 X 660 MW units have a 400 KV Switchyard working on one and half breaker scheme
having facility to connect 2 Nos 400 KV Lines for the purpose of Power evacuation. In order to
evacuate the power as mentioned above, the generated power of the proposed 2 X 660 MW Power
plant will be stepped up to 400kV using 3 Nos. single phase 21kV/400kV/√3 generator transformers.
Bus connected Reactors of 50 MVAR capacity in the 400 KV Switchyard. The approval of power
evacuation system has been issued by RVPN vide letter no. 595 dt. 04.08.09. Power shall be
evacuated by 400KV /220 kv Switchyard with Inter-Connecting Transformers (ICT) through 400 KV
Bhilwara, 400KV Hindaun, 400KV Adani and 220 KV Jhalawar & 200 KV Kawai-Dahara feeders.
Details of transmission lines for unit 5 and 6 are provided below;
Feeder Status
400kV Anta-I Feeder Ready
400kV Anta-II Feeder Ready
Preliminary Information Memorandum Page 24 of 70
3.7 Operational Performance of CTPP
A comparative analysis of PLF of CTPP verses RERC approved PLF is presented in a graph below
Unit wise PLF for operational units i.e. Unit 1, 2, 3 & 4 is tabulated below
Unit Name Deemed PLF (April’16)
Unit 1 77.29%
Unit 2 97.6%
Unit 3 88.21%
Unit 4 97.16%
Total 90.06%
Monthly deemed Plant load Factor for CTPP for FY2015-16 is tabulated in the table below:
DeemedPLF (%)
Apr-15 May-15
Jun-15
Jul-15
Aug-15
Sep-15
Oct-15
Nov-15
Dec-15
Jan-16
Feb-16
Mar-16
Unit 1 100.07 60.36 0.00 0.00 1.95 0.00 0.00 0.00 0.00 0.00 0.00 20.34
Unit 2 90.9 93.8 99.0 28.7 0.0 17.4 80.0 98.0 61.6 89.9 97.6 88.6
Unit 3 68.2 26.2 51.6 81.8 49.1 75.4 17.0 90.1 94.7 93.8 92.4 98.0
Unit 4 50.9 92.7 88.8 85.0 54.7 73.6 46.0 58.2 94.7 95.9 88.0 93.5
70.50%
66.76%63.27% 64.39%
58.01%
80% 80% 80% 80% 80%
50.00%
55.00%
60.00%
65.00%
70.00%
75.00%
80.00%
85.00%
FY12 FY13 FY14 FY15 FY16
RVUN
RERC
Preliminary Information Memorandum Page 25 of 70
Deemed generation at base load is the units that will be generated if the station was operating as per
the injection schedule without being asked to back down and average actual generation is the units
generated by the station after receiving SLDC’s advice for back down. The PLF calculated based on
deemed generation is known as deemed PLF.
As can be seen from the above, the deemed PLF of the station for 2015-16 was around 60%,
however, this happened as Unit 1 was shut for almost 6 months due to occurrence of fire at the
generator transformer. Some issues pertaining to manpower, tripping, and synchronization of unit 4
were encountered during first half of the year, however, in the period Nov’15 onwards, the PLF has
shown significant improvement and is being maintained at 90% levels. This trend is expected to
continue in the future as all the units have stabilized and no major issues, which may have an adverse
impact on the PLFs, are envisaged.
Power station wise Auxiliary Power Consumption variation
Power station wise Specific Coal Consumption variation
0.00
20.00
40.00
60.00
80.00
100.00
120.00
Unit Wise Deemed PLF
Unit 1 Unit 2 Unit 3 Unit 4
11.60%
10.69% 10.63% 10.70%10.45%
9% 9% 9% 9% 9%
8.00%
8.50%
9.00%
9.50%
10.00%
10.50%
11.00%
11.50%
12.00%
FY12 FY13 FY14 FY15 FY16
RVUN
RERC
Preliminary Information Memorandum Page 26 of 70
Power station wise Specific Oil Consumption variation
0.660.64 0.65
0.680.65
0.51 0.51 0.51 0.51 0.51
0.40
0.45
0.50
0.55
0.60
0.65
0.70
FY12 FY13 FY14 FY15 FY16
RVUN
RERC
3.15
1.65
2.74
2.15
3.84
0.5 0.5 0.5 0.5 0.5
0
0.5
1
1.5
2
2.5
3
3.5
4
4.5
FY12 FY13 FY14 FY15 FY16
RVUN
RERC
Preliminary Information Memorandum Page 27 of 70
3.8 Plant Organizational Structure and details of employees
3.8.1 Plant Organizational Structure
At CTPP, the organizational structure shown below:
Working cells and functional structure of Operations blocks are given below:
Working cells and functional structure of maintenance blocks are given below:
Working cells and functional structure of purchase and stores blocks are given below:
Chief Engineer
Additional ChiefEngineer
Deputy ChiefEngineer (O)
Deputy ChiefEnginner (E)
Deputy ChiefEnginner (M)
ElectricalMaintenance
MechanicalMaintenance C&I Maintenance Maintenance
Planning
Power PlantOperations
CoalHandling Unit
Ash HandlingUnit
CoolingTower andPT Unit
Operationsservices andTariff cell
Superintendent Engineer
Executive Engineer
Preliminary Information Memorandum Page 28 of 70
Working cells and functional structure of Administration blocks are given below:
Working cells and functional structure of Construction blocks are given below
3.8.2 Details of Employees
CTPP employs around 572 people in different catergories. A snap shot of employees is provided in the tablebelow
Employee category No. of employees
Executives 239
Non-Technical Officers 13
Administration Staff 48
Technical Workmen 272
Total employees strength 572
Category wise detail is provided in Annexure III.
MaterialPlanning Procurement
ContractsCell Stores Purchase Cell
TrainingEmployeeBenefits
Townshipand plantsecurity
TownshipMaintenance
Finance andAccounts
IT Cell Safety Legal CellPublicRelation
RegulatoryAffairs
Projectmanagement
CivilConstruction
Mech/ElectConstruction
C&I and ITinstallation
ProjectCommission
Preliminary Information Memorandum Page 29 of 70
3.9 Project Cost and Means of Finance
This section provide the detailed actual project cost, cost approved by RERC and means of finance foroperational and under construction unit of CTPP
3.9.1 Project Cost
Unit 1 and 2
The detailed cost of the unit 1 and 2 are provided in the table below:
(Rs. In crore)
S. No. ParticularsCapex up to15.10.2011
Allocation inUnit 1
Allocation inUnit 2
1 Land and site development 11.41 5.71 5.72 Supply of boiler TG and ESP work 1004.31 508.43 495.883 ETC work of boiler TG and ESP 111.83 59.07 52.764 Balance of work plant supply 810.28 411.53 398.75
5River water system work &supply 41.39 20.57 20.82
6 Const. of township boundary etc. 50.56 25.28 25.287 C& I work & supply 25.89 12.61 13.288 Const of 33 kv Gas & supply 2.72 1.36 1.369 400kv spare bay line 0.82 0.41 0.41
10 Supply of dozers (3 nos.) 4.34 2.17 2.17
11Balance of works for power supply to flyash systems 10.93 5.46 5.47
12 Supply of hydra/ locomotive 7.98 3.99 3.9913 Supply of misc. pumps 0.17 0.09 0.0814 Supply of fire tender 0.86 0.43 0.4315 Other Building 2.15 1.07 1.0816 IDC and capitalised expenditure 521.4 198.13 323.2717 Furniture and fixtures 0.65 0.33 0.3218 Office equipment 0.37 0.18 0.1919 Vehicles 0.11 0.05 0.0620 Other expanses capitalised 30.69 13.81 16.88
21Const. of annicat and raising ofdam 29.53 14.76 14.77
22 Railway siding 50.00 25.00 25.00Total 2718.39 1310.44 1407.95
An additional capex of Rs. 101.61 Cr has been incurred after 15.11.2011 on the unit 1 and 2
resulting total cost of unit 1 and 2 amounted to Rs. 2820.
The details of actual cost and approved cost along with disallowed items are provided in the table
below:
Preliminary Information Memorandum Page 30 of 70
(Rs. In crore)
UnitNo. COD RERC order
ActualCost Approved cost Disallowance
1 11.06.201006.06.2013 2,820.00 2,416.00 404.00
2 15.10.2011
List of disallowed items is as follows:
(Rs. In crore)
Disallowed Elements (Rs. Cr.) Unit 1&2
Work contract tax 22.46Liquidated damages 64.18Interest during construction 149.31Diversion from unit 1&2 to 3&4 66.49Additional Capitalization 101.56Total 404.00
Unit 3 and 4
The detailed cost of the unit 3 and 4 are provided in the table below:
(Rs. In crore)
S.No. Particulars Enhanced cost
Allocation inUnit 3
Allocation inUnit 4
1 Furniture& Fixtures and Office equipment 0.94 0 0.94
2 Generator Island( Steam & Turbine) 1223.37 695.24 528.13
4 BoP (Mechanical & Electrical) 879.34 499.73 379.61
5 Control & Instrumentation 33.56 19.07 14.49
6 Civil Works 40.00 22.73 17.27
7 Water Supply System 79.16 44.98 34.18
8 Water reservoir 11.79 6.70 5.09
9 Colony & Residential Quarter 28.08 15.96 12.12
10 Pre-Fabrication Rooms 5.29 3.01 2.28
11 Other 2.33 1.32 1.01
12 Construction Road 29.00 16.48 12.52
13
Construction and pre commissioningexpenses, Development And pre-operative including overheads,Establishment or AdministrationExpenses, Design EngineeringContingencies and consultancy Charges
21.89 13.37 8.52
14 IDC & FC 689.83 312.02 377.81
15 Entry Tax & Labour Welfare Cess 7.73 0 7.73
Preliminary Information Memorandum Page 31 of 70
S.No. Particulars Enhanced cost
Allocation inUnit 3
Allocation inUnit 4
16 BHEL Spares17 Total Cost incurred as on COD 3052.31 1650.62 1401.69
Sum diverted from unit 1 & 2 (orderdated – 06.06.2013) 66.51Total Capital Cost 3052.31 1650.62 1468.20
The details of actual cost and approved cost along with disallowed items are provided in the tablebelow:
(Rs. In crore)
UnitNo. COD RERC order
ActualCost
Capital costtill COD
Provisionallyapproved cost
Disallowance
3 19.12.2013 22.05.20153,052.31 2966.95 2593.84 373.11
4 30.12.2014 27.10.2015
List of disallowed items
(Rs. In crore)
Disallowed Elements Unit 3&4Construction road 14.40Other Civil work 0.18Furniture 0.94Fab. Rooms 2.28Entry tax 7.73C&I 0.14Others 0.15IDC 347.48Total 373.11
Unit 5 and 6 – Under Construction
A detail of the current estimated cost is provided in the table below:
S. No. Particulars
TotalEstimatedcost
1 Preliminary Investigation 15.001 Land and site development 100.002 Steam Generator Island 3500.003 BOP 2330.00
4Hydro structure for raw water system including water transportto plant 600.00
5 External coal transportation system 100.006 Project Management & contingency 50.007 IDC & Financing cost 1225.00
Preliminary Information Memorandum Page 32 of 70
S. No. Particulars
TotalEstimatedcost
Total 7,920.00
The current cost estimates for unit 5 and 6 is Rs. 7,920 Cr. However, the cost estimates of both units
5 & 6 are currently under revision. For the avoidance of doubt, it is further clarified that any cost
implication which may occur as a result of requirements mentioned under the Gazette of India,
notification number 2620 dated 08.12.2015 has not been considered in the above mentioned cost.
Major Milestones for Unit 5 & 6 are provided in the Annexure IV.
3.9.2 Means of finance
The following table summarizes the sources of funds for project cost:
Disbursement schedule of the project cost for Unit 5&6 and the break-up of the cost along with themeans of finance for the operational units are summarized below:
(Rs. In crore)Particulars Total cost Total Debt Total Equity
Unit 1&2 2,820.00 2,256.00 564.00
Unit 3&4 3,033.50* 2,426.90 606.60
Total 5,835.50 4,682.90 1,170.60
‘* Actual cost of for unit 3 and 4 was Rs. 3052.31 Cr. Balance Rs. 18.81 cr has been arranged
through internal accruals by RVUN.
The estimated project cost, project cost incurred and means of finance for unit 5 and 6 are providedin the table below
(Rs. In crore)Particulars Total cost Total Debt Total Equity
Estimated cost and means offinance
7,908.00* 6,324.00 1,584.00
Actual cost and means offinance
5,361.83 4,296.83 1,065.00
‘*Total project cost for unit 5 and 6 is Rs. 7920.00 Cr. but the funds tied up till date are Rs. 7908.00
Cr. The balance funds of Rs. 18.00 Cr may be arranged through internal accruals, as and when
required.
Preliminary Information Memorandum Page 33 of 70
The schedule of disbursement of debt and equity infusion is provided in the table below:
(Rs. In crore)
ParticularsFinancial Year
2012-13 2013-14 2014-15 2015-16Total
disbursedState Equityinfusion
150.00 190.00 225.00 500.00 1,065.00
PFC Loan - 770.59 770.58 1,696.49 3,227.66REC loan - 50.00 388.08 631.09 1,069.17Total 150.00 1,010.59 1,383.66 2,817.58 5,361.83
3.9.3 Details of outstanding debt
The details of outstanding debt balance for different stages of CTPP are tabulated below:
(Rs. In crore)
Stage Lender Sanctioned Amount Outstanding as on31.03.2016
Unit 1&2 PFC 2,256.00 1530.05Unit 3&4 PFC 1465.14 1465.14Unit 3&4 REC 961.76 846.82
Unit 5&6 (U/C) PFC 3794 1541.17
Unit 5&6 (U/C) REC 2530 438.08
Total 11006.9 5821.26
The major terms and conditions as per the sanction letter for the Unit 5 & 6 are summarized below;
· Installment of interest and tax payable quarterly on 15th April, 15th July, 15th October and
15th January.
· PFC shall have the Right to reset the rate of interest, at its discretion, from third/tenth year
beginning from date of disbursement.
· Loan to be repaid in 60 equal quarterly installments and first installment will become due on
15th July’15
· Prepayment of loan only after obtaining prior permission from PFC. Such approval may be
granted subject to such conditions as PFC deems fit.
· In case of payment default, additional rate of interest of 2.0%
· Loan shall be guaranteed fully by State govt or SBI or else
o the loan shall be secured with the prescribed coverage ratio of 1.35.
Preliminary Information Memorandum Page 34 of 70
o a first pari passu charge by way of mortgage of all immovable properties of units
5&6.
o A first charge by way of hypothecation of all RVUN’s movable assets
· RVUN to open an escrow account for entire pendency of loan with coverage factor as 1.35
· RVUN shall not sell/transfer or abandon the project at any stage without prior consent of
PFC.
Preliminary Information Memorandum Page 35 of 70
4 Power Purchase Agreement
The PPA for CTPP as well as other RVUN generating units was signed between RVUNL and the three
distribution utilities of Rajasthan on 23.06.2004. Subsequently, the amendments to the PPA were
done on 30.04.2005, 07.06.2007, 18.05.2010, and 15.12.2010. Declared capacity of RVUN
mentioned in supplementary PPA signed on 18.05.2010, mentions operational plants as well as the
upcoming plants, which includes Unit 5 and Unit 6 of CTPP. As per existing PPA, the entire
generation capacity of RVUN - CTPP is tied up with the three Distribution companies in the following
ratio:
Summary of major terms and conditions of PPA:
Parties to the agreement: The agreement was signed between RVUN on one hand and AVVN, JVVN,
and JdVVN. Rajasthan Rajya Vidyut Prasaran Nigam Limited (RVPN) is the co-signatory of the power
supply agreement. The PPA governs the terms and conditions for sale of power from all RVUN plants
including CTPP. (RVUN to provide details on RVPN’s role)
1. Allocation of Power: As per PPA, 95% of the installed capacity of CTPP is available for
allocation to Distribution Utilities. Rest 5% of the installed capacity is considered as unallocated
capacity and the allocation would be done under the guidance of GoR.
2. Third Party sale of energy: The PPA does not allow RVUN to supply power generated by its
generating stations directly to third party except in a situation where total demand of all the
distribution utilities combined together becomes less than RVUN’s capacity and SLDC advises
RVUN to back down its generation, and such third party sale can be done only:
a. With consent of distribution utility; or
JdVVNL, 32%
JVVNL, 40%
AVVNL, 28% JdVVNL
JVVNL
AVVNL
PPA Break Up
Preliminary Information Memorandum Page 36 of 70
b. if the procurer i.e. distribution utilities does not clear its dues to RVUN as per
schedule.
3. Default to PFC: In case of default of payment to PFC by RVUN, PFC shall have the right to
transfer the project to themselves or to their agents, who will run the plant and sell the
electricity to third party.
4. Start-up and auxiliary back up power: Start-up and auxiliary back up power required by RVUN
power stations as reflected in the energy account shall be adjusted on annual basis from the
energy sent out.
5. Tariff: The tariff of generating units is currently being determined by Hon’ble Rajasthan
Electricity Regulatory Commission as per regulations specified by the commission. The
different component of the tariff are given below:
· Annual Fixed Cost
o O&M Expenses
o Depreciation
o Interest & Finance Charges
o Interest on transitional loan
o Interest on working capital
o Lease Rentals
o Insurance on fixed assets
o Return on Equity (15.50 % allowed as per RERC norms)
o Additional Contribution towards Pension and Gratuity Fund
o Prior Period Charges
o Non-Tariff Income (Subtracted)
· Variable Charge
o Per unit cost of secondary fuel
o Per unit cost of fuel
As a result of above components, the fixed charges determined by RERC for Unit (1 to 2) for
2015-16 of CTPP is Rs 437.64 Cr and variable charge is 2.20 Rs/Kwh. The above mentioned
fixed charge is without return on equity as RVUN has been operating on the principle of “No
Profit No Loss”. However, from April 1, 2016, RERC has allowed ROE in tariff of generating
units of RVUN in a phased manner.
In Interim tariff order for FY 2016-17, Hon’ble RERC allowed an interim tariff of Rs.
3.860/KWh for unit 3 and Rs. 3.268/KWh for unit 4.
6. Effective Date and Duration of Agreement: As per PPA, the agreement shall remain operative
till March 31st, 2029, provided that agreement may be mutually extended, renewed or replaced
by another agreement on such terms and for such further period of time as the parties may
mutually agree. It is clarified that as on the date of the Transaction, the PPA transferred to the
Preliminary Information Memorandum Page 37 of 70
Selected Bidder shall be valid for 25 years from the COD of respective units. The PPA shall have
a provision to mutually extend its term post expiry of said 25 year period.
7. Billing and Payment: According to PPA, all charges shall be billed by RVUN and shall be paid by
distribution utilities with following provisions:
a) RVUN shall raise the bills by 15th of each month for energy supplied to distribution from
its power station as per applicable tariff. Distribution Utilities shall arrange the payment of
such bills within 30 days of.
b) Irrevocable Revolving Letter of Credit shall be opened by distribution utilities in favor of
RVUN for the amount of average monthly billing
8. Force Majeure : No party shall be liable for any claim for any loss or damages whatsoever
arising out of failure to carry out the terms of the agreement to the extent that such a failure is
due to force majeure events such as war, rebellion, mutiny, civil commotion, riots, strike, lock-
out, forces of nature, accident, act of God, and any other reason beyond the control of
concerned party
9. Governing laws: The Electricity Act, 2003, all rules and regulation made thereunder and the
government notification dated February 28, 2004 governs the agreement.
10. Dispute Resolution: All the disputes pertinent to the PPA between the parties should be settled
either through negotiation or through arbitration as provided in Electricity Act 2003 read with
Arbitration and Conciliation Act 1996.
Preliminary Information Memorandum Page 38 of 70
5 Fuel Supply Arrangement
Coal is procured through different sources for ensuring sustainable operation of CTPP. For unit 1 and
2, the fuel Supply agreement has been signed with SECL for 20 years. For unit 3 and 4 and unit 5 and
6, the fuel is sourced from operational ‘Parsa East & Kanta Basan’ and under development ‘Parsa’
(expected to become operational by FY20) coal blocks. For Unit 5 and 6, the fuel shall be sourced
from operational ‘Parsa East & Kanta Basan’ and under development ‘Kente Extn’ (expected to
become operational by FY20) coal blocks. As per the RERC Tariff Regulations, 2014 clause no. 51,
the energy (variable) charges for thermal generating stations shall cover the cost of landed fuel. The
landed cost of fuel shall include price of fuel corresponding to the grade/quality/calorific value of fuel
inclusive of royalty, taxes and duties as applicable, transportation cost by rail/road/gas pipe line or
any other means. Energy charges shall consider landed fuel cost and shall be arrived at after
considering normative transit and handling losses as percentage of the quantity of fuel dispatched by
the fuel supply company during the month.
Summary of Fuel Supply
S no Unit Capacity AnnualRequirement (MT)
Source
1 1 & 2 2x250 MW 1.851 SECL – Korba West
2 3 & 4 2x250 MW 2.332 Parsa East & Kanta Basan and Parsa
3 5 & 6 2x660 MW 5.533 Parsa East & Kanta Basan and Kente Extn.
5.1 Unit 1 & 2
5.1.1 Annual Fuel Requirement
The annual requirement of coal for Unit 1 & 2 of CTPP is estimated to be about 1.85 MT, considering a
Grade 11 coal at 85% PLF.
5.1.2 Fuel Linkage
RVUN procures coal from SECL – Korba West for units 1 & 2 of the Project. On April 24, 2012, Fuel
Supply agreement (FSA) has been signed with SECL for supplying coal to RVUN, for Unit 1 & 2 of
CTPP for a period of 20 years. As per the FSA, 100% of ‘Annual Contracted Quantity’ (ACQ) (including
5% imported coal for FY 2016-17) is committed by SECL. This quantity of coal is sufficient to operate
these units at 65% to 70% PLF.
1 Considering Grade 11 coal at 85% PLF2 Considering a Gross Calorific Value of 4500 Kcal/Kg at 85% PLF for FY 213 Considering a Gross Calorific Value of 4500 Kcal/Kg at 85% PLF for FY 21
Preliminary Information Memorandum Page 39 of 70
This coal is being beneficiated by deploying a contractor, who is lifting the coal from SECL mines on
behalf of RVUN and after beneficiation, supplies washed coal to RVUN.
5.1.3 Fuel Transportation
Mode of transport for delivery will be either through rail or road transport.
Rail Transport- Wagons will be booked on “Freight to Pay” basis as per the arrangements with the
purchaser.
Road Transport- RVUN shall arrange for trucks to lift coal according to arrangements with the SECL.
In case, SECL delivers the coal, transport charges shall be payable by RVUN, if the delivery point is 3
Km beyond the pithead.
5.1.4 Fuel Pricing
The fuel pricing is “As delivered price of coal” and shall be the sum of base price, sizing/crushing
charges, statutory charges and other charges as applicable at the time of delivery of coal.
Components of fuel price
Type of Charges Description
Base Price To be decided on the basis of grade type and vary from time to time
Sizing/Crushing Charges Charges to maintain a diameter of top size of 250 mm
Rapid Loading Charges Pertinent to the contract
Statutory Charges Royalties, Duties, Cesses, Levies, and Taxes
Other Applicable Charges To be specified by CIL/SECL from time to time
As on 30 May 2016 post revision of prices by CIL, landed cost of coal supplied from SECL for CTPP
Unit 1 & 2 is INR 3,739.11 per metric tonne (MT).
5.1.5 Coal Deficit Plans
The deficit for Unit 1 & 2 shall be calculated in accordance with the CEA guidelines published, in
December 2015.
5.1.6 Summary of Terms & Conditions of Fuel Supply agreement
► Fuel Supply Agreement has been signed on April 24, 2012with SECL for supplying coal to
RVUNL for 20 years
► The Annual contracted capacity (ACQ) is 18.49 LTPA
► Quarterly Quantity (QQ) Schedule of SECL supply, given in the contract is as follows:
Preliminary Information Memorandum Page 40 of 70
1st Quarter ( April – June) 25% of ACQ
2nd Quarter (July-September) 22% of ACQ
3rd Quarter (October- December) 25% of ACQ
4th Quarter (January – March) 28% of ACQ
► The monthly Scheduled Quantity (SQ) shall be one third (1/3rd) of the QQ.
► The seller shall make adequate arrangement to access the quality and monitor the same
endeavour that un-graded coal is not loaded into purchaser’s container. If the seller sends any
quantity of such coal the purchaser shall limit the payment of cost of coal to rupees one.
► Sample of coal for quality check shall be collected jointly either manually or through mechanical
sampling method at each of the delivery points
► Samples collected at the loading end shall be analysed as per BIS standard (IS:1350 Part I-
1984) and for determination of ash and moister content as per (IS:1350 Part II-1970)
► The coal will be weighed at the loading end at electronic weighbridge and printouts of actual
weight shall be provide
► The seller shall raise source wise bill for coal supplied on declared grade basis.
5.2 Unit 3 & 4
5.2.1 Annual Fuel Requirement
The annual requirement of coal for Unit 3 & 4 of CTPP is estimated to be about 2.33 MTPA for FY17
to FY21, considering a Gross Calorific Value of 4500 Kcal/Kg at 85% PLF. The year wise coal
requirement of units 3 & 4, availability of coal from Coal allocation for unit 3 & 4 (in MT)
Year 2016-17 2017-18 2018-19 2019-20 2020-21
Raw Coal Requirement 2.33 2.33 2.33 2.33 2.33
Availability of Raw Coal from Coal Mines allocated to RVUN to above TPP
Parsa East & Kanta Basan1.83 1.83 2.13 2.13 2.13
Parsa 0.00 0.00 0.00 0.20 0.20
Total 1.83 1.83 2.13 2.33 2.33
Short fall to be met through allocation ofBridge Linkage
0.5 0.5 0.2 0 0
5.2.1.1 Fuel Sources
Preliminary Information Memorandum Page 41 of 70
Government of India has allotted Parsa East & Kanta Basan coal mine to RVUNL on 31-03-2015 and
Parsa coal mine on 08-09-2015 vide order no 103/13/2015/NA for utilization in end use plant in
accordance with the provisions of the coal Mines (Special Provisions) Second Ordinance, 2014 and
the Coal Mine (Special Provisions) Rules, 2014.
The required quantity of coal can be mined and supplied from ‘Parsa East & Kanta Basan’ coal blocks,
but the production has to be regulated upto road transportation limits, as there has been no rail
connectivity between mine head and nearest railway siding for transportation of coal. The
construction of railway line up to the coal mine head is partially completed and is expected to be fully
operational by July 2017.
Therefore, till completion of Common Rail Corridor up to mine head of ‘Parsa East & Kanta Basan’
coal mine as well as commencement of mining operations at ‘Parsa’ coal block allotted to RVUN,
Ministry of Coal, GoI has been requested to grant above ‘Bridge Linkage’ of coal against ‘Parsa’ coal
block in line with the Ministry of Coal Memorandum dated 08.02.2016 in respect of Policy guidelines
for grant of Bridge Linkage to specified end use plants which have been allotted coal mines.
5.2.2 Fuel Transportation
Rail - The contract between RVUN and Mine developer and operator (MDO) states that company shall
arrange for transportation of coal from mines on “Freight Paid” basis.
For unit-3&4, coal is supplied from Parsa East & Kanta Basan Coal Mine situated in Chhattisgarh. Due
to non-availability of Rail link up to mine head, coal is transported via road for a stretch of
62/85/110 KM up to nearest railway siding of Ramanujnagar/ Kamalpur/ Karonji and rest through
rail. Rail link of 37 kms up to mine head is scheduled to be completed by July 2017. Rail track
corridor up to mine head is being developed by SPV. 33 Km of phase-1 from Surajpur Road station of
Indian Railway to Ramanujnagar has been completed and is in operation. Phase-II from
Ramanujnagar to mine head is under implementation and scheduled to be commissioned by
July'2017. A Track Access Agreement has been executed with SPV.
M/s SRCPL by RVUN for accessing the track & paying the track access charges.
Road - The limit of coal being transported is currently restricted to road transportation limits, as there
is no rail connectivity. Transportation through road is being done by MDO.
5.2.3 Fuel Pricing
MDO has been appointed for development of Parsa East & Kante Basan and Parsa coal blocks, RVUN
shall pay contracted price per MT to the MDO based on the performance of work and delivery of coal
to the delivery point. The contract price should not exceed the ceiling price and comprise of base
price, reimbursable (which shall mean railway freight charge for the delivered coal), service tax and
any other statutory taxes.
Preliminary Information Memorandum Page 42 of 70
As per Coal Mining and Development Agreement, celling price includes; then, current published price
of pithead F Grade Coal less a discount of 8.5% plus Royalty; SED, Crushing charges, taxes (Sales
Tax); Beneficiation Charges, yield losses (increase in cost due to beneficiation) and all other charges
(Transit loss of.1.5 % of total delivered cost, interest charges on Railway fright @ SBI prevailing rate
for private lending for 22-days). Ceiling Price details are given in Annexure V.
As on 1 June, 2016, landed cost of washed coal supplied from Parsa East & Kanta Basan coal block to
CTPP’s Unit 3 & 4 is INR 3,947.17 per metric tonne (MT).
5.2.4 Coal Deficit Plans
Till completion of Common Rail Corridor up to mine head of ‘Parsa East & Kanta Basan’, as well as
commencement of mining operations at ‘Parsa’ coal block, RVUN vide letters dated 16.05.2016
applied to Ministry of coal for grant of bridge linkage for 2x250 MW CTPP unit-3&4 in line with the
“policy guidelines for grant of ‘Bridge Linkage’ issued by Ministry of Coal, GoI on 08.02.2016.
Requirement of bridge linkage (in MT) for Unit 3 & 4 is stated below:
TPP 2016-17 2017-18 2018-19
CTPP, Units 3 & 4 0.5MTPA 0.5MTPA 0.2 MTPA
Approval from Bridge linkage has been awaited from Ministry of coal.
5.3 Unit 5 & 6
5.3.1 Annual Fuel Requirement
The annual requirement of coal for units 5 & 6 of CTPP has been estimated to be about 0.92 MTPA
for FY17, considering a Gross Calorific Value of 4500 Kcal/Kg at 85% PLF. The year wise coal
requirement, availability of coal from operational ‘Parsa East & Kanta Basan’ and under development
‘Kente Extn’ coal blocks with coal reserves of 200 MT and peak rated capacity of 7 MTPA (scheduled
to be operative by Sept’ 2019 as per Milestone prescribed in Allotment Agreement executed with
Ministry of Coal, GoI) and shortfall of coal is described as per following table:
Coal allocation for unit 5 & 6 (in MT)
Year 2016-17 2017-18 2018-19 2019-20 2020-21
Raw Coal Requirement0.92 3.46 5.53 5.53 5.53
Availability of Raw Coal from Coal Mine allocated to RVUN to above TPP
Preliminary Information Memorandum Page 43 of 70
Parsa East & Kanta Basan0.92 2.50 4.0 4.0 4.24
Kente Ext0.00 0.00 0.00 0.33 1.29
Total 0.92 2.5 4.0 4.32 5.53
Short fall to be met through allocation of BridgeLinkage
0.00 0.96 1.53 1.21 0.00
5.3.2 Fuel Supply from allotted coal blocks
Government of India has allotted Parsa East & Kanta Basan coal mine to RVUN on 31-03-2015 vide
order no 103/13/2015/NA for utilization in end use plant in accordance with the provisions of the
coal Mines (Special Provisions) Second Ordinance, 2014 and the Coal Mine (Special Provisions) Rules,
2014 and also allotted Kenta Extn. Coal block mine to RVUNL on 31-03-2015 vide order no
13016/26/2004-CA-I/CA-III(Pt.)(Vol. II) for end use power under Rule 4 of the “Auction by
Competitive Bidding of Coal Mines Rules, 2012”.
The required quantity of coal can be mined and supplied from ‘Parsa East & Kanta Basan’ coal blocks,
but the production has to be regulated up to road transportation limits, as there has been no rail
connectivity between mine head and nearest railway siding for transportation of coal. The
construction of railway line up to the coal mine head is partially completed and is expected to be fully
operational by July 2017.
Therefore, till completion of Common Rail Corridor up to mine head of ‘Parsa East & Kanta Basan’
coal mine as well as commencement of mining operations at ‘Kente Extn’ coal block allotted to RVUN,
Ministry of Coal, GoI has been requested to grant above ‘Bridge Linkage’ of coal against ‘Kente Extn’
coal block in line with the Ministry of Coal Memorandum dated 08.02.2016 in respect of Policy
guidelines for grant of Bridge Linkage to specified end use plants which have been allotted coal
mines.
5.3.3 Fuel Transportation
Rail - The contract between RVUN and MDO states that RVUN shall arrange for transportation of coal
from mines on “Freight Paid” basis.
The Railway line doesn’t exist as of now, however its construction up to the coal mine head is partially
completed and is expected to be fully operational by July’2017.
Road - The limit of coal being transported is currently restricted to road transportation limits, as
there is no rail connectivity. Transportation through road is being done by MDO.
5.3.4 Fuel Pricing
Preliminary Information Memorandum Page 44 of 70
MDO has been appointed for development of the allocated Parsa East & Kante Basan and Kente Extn
coal blocks, RVUN shall pay contracted price per MT to the MDO based on the performance of work
and delivery of coal to the delivery point. The contract price shall not exceed the ceiling price and
comprise of base price, reimbursable (which shall mean railway freight charge for the delivered coal),
service tax and any other statutory taxes.
As per Coal Mining and Development Agreement, celling price includes; then, current published price
of pithead F Grade Coal less a discount of 8.5% plus Royalty; SED, Crushing charges, taxes (Sales
Tax); Beneficiation Charges, yield losses (increase in cost due to beneficiation) and all other charges
(Transit loss of.1.5 % of total delivered cost, interest charges on Railway fright @ SBI prevailing rate
for private lending for 22-days). Ceiling price details are given in Annexure V.
As on 1 June, 2016, landed cost of washed coal supplied from Parsa East & Kanta Basan coal block
for Units 5 & 6 is INR 3,947.17 per metric tonne (MT).
5.3.5 Coal Deficit Plans
Till completion of Common Rail Corridor up to mine head of ‘Parsa East & Kanta Basan’, as well as
commencement of mining operations at ‘Kente Extn’ coal block, RVUN vide letters dated 16.05.2016
applied to Ministry of coal for grant of bridge linkage for units 5 & 6 (2x660 MW) in line with the
“policy guidelines for grant of ‘Bridge Linkage’ issued by Ministry of Coal, GoI on 08.02.2016.
Requirement of bridge linkage (in MT) for Unit 5 & 6 is stated below:
TPP 2016-17 2017-18 2018-19
Unit 5 & 6 (2x660 MW) 0.96 MTPA 1.53 MTPA 1.21 MTPA
Approval from Bridge linkage has been awaited from Ministry of coal.
5.3.6 Summary
Summary of coal allocation from various sources for CTPP (in MT) is given below:
Year 2016-17 2017-18 2018-19 2019-20 2020-21Raw CoalRequirement 5.10 7.64 9.71 9.71 9.71
Availability of Raw Coal from Coal Mines allocated to RVUN to above TPPSECL 1.85 1.85 1.85 1.85 1.85Parsa East &Kanta Basan 2.75 4.33 6.13 6.13 6.37
Parsa 0 0 0 0.2 0.2Kente Ext 0 0 0 0.33 1.29Total 4.60 6.18 7.98 8.51 9.71
Preliminary Information Memorandum Page 45 of 70
Year 2016-17 2017-18 2018-19 2019-20 2020-21Short fall to bemet throughallocation ofBridge Linkage
0.50 1.48 1.73 1.20 0
Preliminary Information Memorandum Page 46 of 70
6 Approvals and Clearances
Below mentioned table summarizes the approvals and clearances required for the operation of units 1
to 4 and development of units 5 & 6 respectively. Units 1 to 4 have already started commercial
operations and only consent to operate is required for its operations whereas units 5 & 6 are under
advanced stages of construction for which consent to establish is required. Brief status:
S. No Item Agency Validity Current Status
Units 1 & 2
Statutory Clearances
1. Consent toOperate
Rajasthan StatePollution ControlBoard (RSPCB)
Consent to Operate undersection 25/26 of the Water(Prevention & Control ofPollution) Act, 1974 and undersection 21(4) of Air(Prevention & Control ofPollution) Act, 1981. issued byRSPCB was valid upto31.08.2015
Renewalapplication forconsent tooperate filed on26.04.2016
2. Renewal isawaited
1. Consent toOperate
Rajasthan StatePollution ControlBoard (RSPCB)
Consent to Operate undersection 25/26 of the Water(Prevention & Control ofPollution) Act, 1974 and undersection 21(4) of Air(Prevention & Control ofPollution) Act, 1981. issued byRSPCB was valid upto23.01.2015
Renewalapplication forconsent tooperate filed on27.04.2016
2. Renewal isawaited
Units 3 & 4
Statutory Clearances
1. Consent to
Operate
Rajasthan State
Pollution Control
Board
Previous letter issued was
valid upto 23.01.2015 or the
date of commissioning of the
project, (whichever is earlier)
expired
Renewal and fresh
application for
consent to
operate
(air/water) under
section 21 of the
Air (Prevention
and Control of
Pollution) Act,
1981 filed on 27th
April 2016 by
RVUN for Unit 3
Preliminary Information Memorandum Page 47 of 70
S. No Item Agency Validity Current Statusand Unit 4
respectively.
Renewal is
awaited.
Units 5 & 6
Statutory Clearances
1. Administrative andFinancial Approvalof StateGovernment
GoR, EnergyDepartment
Approval of State Govt.issued on 2nd March 2009for setting up 2*660 MWcoal based extensionproject at CTPP underStage-II (Unit 5 & 6) atChhabra
Only one timeapproval isrequired
2. Water availability Office of theChiefEngineer,WaterResourcesDepartment
Letter dated 11th August2009, gave allocation of1,570 Mcft water forproposed Stage-II
Letter dated22nd November2010, madepartialmodification ofwater allocationto 1,585 Mcftwithamendments inwater sources tobe used
3. EnvironmentalClearance
Governmentof India,Ministry ofEnvironmentand Forests(MoEF)
Environment clearance isissued by MOEF throughletter date 02.02.2015
4. Consent toEstablish
RajasthanState PollutionControl Board
Consent to establish forStage II, Unit 5 & 6extended till 31.08.2018 ortill the date ofcommissioning of unit 5 & 6whichever is earlier andissued by RSPCB on20.04.2015
Consent toestablish forunits 5 and 6issued by RSPCB
Preliminary Information Memorandum Page 48 of 70
S. No Item Agency Validity Current Status
Other Clearances
5. NOC for HeightClearance
AirportsAuthority ofIndia
Certificate issued on 26th
April 2010Validity of 5years from dateof issue (In casebuilding/chimney is notconstructed &completedwithin 5 years, itwill be requiredto obtain a freshNOC fromChairman, AAIor GM (Aero)NorthernRegion)
6. NOC forconstruction ofchimney to supercritical units ofCTPP (Unit 5 & 6)
Governmentof India,Ministry ofDefense
NOC issued on 20th August2010 with validity upto 3years from the date of issue
One timeapproval isrequired
Preliminary Information Memorandum Page 49 of 70
7 Structure for Disinvestment
7.1 Proposed structure for disinvestment
Proposed structure for disinvestment is summarized in the schematic below:
As per the decision of the Government of Rajasthan, it is proposed that CTPP shall be disinvested and
transferred to the Selected Bidder or to special purpose vehicle i.e. a company
constituted/established as per the provisions of Companies Act, 2013 for specific purpose of
purchasing CTPP (activities of which are limited to those for accomplishing the purpose of the
company) (“SPV”), as the case may be. The CTPP may be either:
· Directly transferred to the balance sheet of the Successful Bidder
· Directly transferred to a SPV, which shall be formed by the Successful Bidder; or
· Be first transferred to an existing or new SPV of RVUN and then such SPV shall be
transferred to the Successful Bidder
The exact mode of transfer of CTPP to the Successful Bidder shall be mentioned in the RFP
document. All the CTPP assets as well as agreements/linkages and approvals shall be transferred to
the Successful Bidder/SPV.
The bidding shall be conducted by adopting a two-stage Bidding Process for selection of the
Successful Bidder. The Qualification Stage of the process involves Qualification of interested parties,
whether as a single Bidder or Consortium, who makes an Application in accordance with the
provisions of this EoI. At the end of this stage, RVUN shall notify the Shortlisted Bidders and invite
Directly transferred to aSPV of the SuccessfulBidder
First trans. to an existing ornew SPV of RVUN and thensuch SPV be transferred tothe Successful Bidder
Directly transferred to thebalance sheet of theSuccessful Bidder
CTPP RVUN
Preliminary Information Memorandum Page 50 of 70
them for participation in the second stage of the Bidding Process. The RFP shall be issued only to the
Shortlisted Bidders upon payment of such fees as may be mentioned in the RFP.
7.2 Key Investment Consideration
7.2.1 No offtake risk
The entire capacity of CTPP is tied up under long term PPAs with the Rajasthan
distribution utilities. Power Ministry, Rajasthan and its distribution utilities had signed an
agreement under the Ujwal Discom Assurance Yojana (UDAY) on 27.01.2016, for
operational and financial turnaround of these utilities. The outstanding debt of the
distribution utilities of the state as on 30.15.2015, stood at Rs 80,500 crore, out of
which 75% or Rs 60,500 crore would be taken over by the state. The scheme shall reduce
the financial burden on the utilities, making more reliable in terms of payments.
7.2.2 Fuel linkages
Fuel linkages from SECL (for units 1 & 2) and from captive mines Parsa, Parsa East,
Kanta Basan and Kente extn (for units 3, 4, 5 & 6) are already tied up. Rail infrastructure
will get completed by Jun 2017. Out of the above mentioned coal blocks, only Kente
extension block is under development, other mines are already operational.
7.2.3 Approvals and clearances
Implementation risk mitigated with all the approvals and clearances in place – all 4 units
are operational for more than 2 years now. However, consent to operate application has
been filed for renewal for units 1 to 4 with renewal awaited. Approvals and clearances
for under construction units 5 & 6 are also in place. Sufficient power evacuation
infrastructure is available for transfer of power.
7.2.4 Past Liabilities
It is proposed that the past liabilities of CTPP pertaining to a period prior to the
Transaction date shall be retained with RVUN and will not be transferred to the Selected
Bidder. Only the existing debt or other specified liabilities may be transferred to the
Selected Bidder subject to lender’s approval.
However,
(a) any liabilities which pertain to a period prior to the Transaction date but which
arise or come to the knowledge of RVUN and the Successful Bidder after a period
of 1(one) year from the Transaction date will be borne by the Successful Bidder.
Preliminary Information Memorandum Page 51 of 70
(b) any liabilities occurring due to Selected Bidder’s actions on or after the
Transaction date or which pertains to a period on or after the Transaction date
shall not be attributable to RVUN and shall be borne by the Successful Bidder.
7.2.5 Location
Strategically located in the state of Rajasthan, due to which it has the shortest distance,
amongst all RVUN plants, from the allocated mines resulting in lower coal transportation
costs leading to lower variable charges. CTPP is first in merit order dispatch amongst all
RVUN plants.
7.2.6 Highly reliable vendor group
Globally reputed equipment manufacturers like BHEL have been involved in the
construction of operational units 1 to 4. Units 5 & 6 are being constructed by L&T.
7.2.7 Favorable Financing
Financing with PFC and REC at a debt equity ratio of 80:20 is already in place for all the
6 units.
Preliminary Information Memorandum Page 52 of 70
8 Profile of RVUN
8.1 Company background
RVUN was established in the year 2000 by GoR under the provisions of the Rajasthan Power Sector
Reforms Act, 1999 upon unbundling of erstwhile Rajasthan State Electricity Board (RSEB) into a
Generation Company, a Transmission Company and three Distribution Companies (Discoms) w.e.f.
July 19, 2000 the unbundled entities were:
· Rajasthan Rajya Vidyut Utpadan Nigam Ltd. (RVUN), the generation Company.
· Rajasthan Rajya Vidyut Prasaran Nigam Ltd. (RVPN), the transmission Company.
· Jaipur Vidyut Vitran Nigam Ltd. (JVVNL) , a regional distribution company.
· Ajmer Vidyut Vitran Nigam Ltd. (AVVNL) a regional distribution company.
· Jodhpur Vidyut Vitran Nigam Ltd. (JdVVNL) a regional distribution company.
RVUN is the state power generation utility and has been entrusted with the job of development of
power projects under state sector, along with operation & maintenance of state owned power
stations. RVUN supplies power to state DISCOM’s namely; JVVNL, AVVNL and JDVVNL. Being a GoR
undertaking, RVUN’s Board of Directors is appointed by the GoR and its management has rich
industry experience.
8.2 Board of Directors
No Name Designation Place of Posting Director IdentificationNumber (DIN)
01. Sh. N. M. Mathur Chairman & MD, RVUN 03033375
02. Sh. Sanjay Malhotra, IAS Pr. Secretary (Energy), GoR &Chairman & MD, RVPN
00992744
03. Sh. Praveen Gupta, IAS Secretary Finance (Revenue), GoR 03521006
04. Sh. Ram Gopal Gupta Adviser, Energy Deptt., GoR 00173937
05. Sh. Arun Kumar Gupta Director (Finance), RVPN 06948144
06. Sh. Shyam Swaroop Meena Director (Technical), RVUN 03319346
07. Sh. Mahesh Kumar Agarwal Director (Project), RVUN 07316044
Preliminary Information Memorandum Page 53 of 70
8.3 Details of Operational Assets
At present the installed capacity of RVUN is 5957.35 MW. The details of its operational assets along
with capacity are as follows:
S. No Power Station Present Capacity
1. Suratgarh STPS, Suratgarh, Distt-Shriganganagar 1500 MW
2. Kota STPS, Kota 1240 MW
3. Chhabra Thermal Power Project, Chhabra, Distt. Baran 1000MW
4. Kalisindh Thermal Power Station, Kalisindh, Distt. Jhalawar 1200 MW
5. Dholpur CCPS ,Dholpur 330 MW
6. Giral Lignite TPS, Giral, Distt. Barmer 250 MW
7. Ramgarh Gas Thermal Power Station, Distt. Jaisalmer 273.50MW
8. Mahi Hydel Power Station, Distt-Banswara 140 MW
9. Mini Micro Hydel Schemes (10) 23.85 MW
Total 5957.35 MW
RVUN is also managing and operating the following inter-state projects:
S. No Power Station Present Capacity
1. Rana Pratap Sagar Hydel PS (4X43 MW) 172 MW
2. Jawahar Sagar Hydel PS (3X33 MW) 99 MW
Total 271 MW
Preliminary Information Memorandum Page 54 of 70
8.4 Ongoing Projects of RVUN
The projects of RVUN currently under construction are as follows:
S. No Name of unit Capacity Commissioning target
1. Ramgarh Gas Thermal Power Project Stage IV GT 110 MW Jan-2017
2. Ramgarh Gas Thermal Power Project Stage IVSTG 50 MW Mar- 2017
3. Suratgarh Supercritical Thermal Power StationUnit 7 660 MW April 2017
4. Suratgarh Supercritical Thermal Power StationUnit 8 660 MW Aug 2017
5. Chhabra Supercritical Thermal Power StationUnit 5 660 MW Dec 2016
6. Chhabra Supercritical Thermal Power StationUnit 6 660 MW June 2018
83%
10%
3%4%
Generation Mix of RVUN (operational assets)
Coal gas Hydro Power Project O&M of Interstate Hydel Project
Preliminary Information Memorandum Page 55 of 70
8.5 Financials of RVUN
A brief of the Balance sheet for the last 3 years is as follows:
Particulars (in Rs. Cr.) As at 31st March2013
As at 31stMarch 2014
As at 31stMarch 2015
Equity And LiabilitiesShareholders’ funds
Share Capital 5,805 6,574 7,289Reserves & Surplus -374 -695 -3,317Share application money pending 161 132 299
Non-current liabilitiesLong-Term Borrowings 11,962 14,278 2,014Other Long Term Liabilities 609 615 55
Current liabilitiesShort-Term Borrowings 500 500 738Trade Payables 787 382 1,485Other Current Liabilities 3,415 3,210 3,467Short-Term Provisions 289 252 247
23,154 25,247 30,890AssetsNon-current assets
Fixed AssetsTangible Assets 8,210 9,782 15,860Capital Work-In-Progress 9,776 10,567 8,049
Non-Current Investments 0 0 185Deferred Tax Assets (Net)
- - -Long-Term Loans and Advances 1,673 2,197 1,329Other Non-Current Assets 221 201 215
Current AssetsInventories 868 552 1,092Trade Receivables 1,556 991 2,784Cash and Bank Balances 341 114 114Short-Term Loans and Advances 140 325 484Other Current Assets 370 517 778
23,155 25,247 30,890
Preliminary Information Memorandum Page 56 of 70
A brief of profit and loss statement for RVUN for last 3 years is as follows:
Particulars (in Rs. Cr.) FY13 FY14 FY15Revenue
Revenue From Operations 8781 8401 9081Other Income 45 25 30
Total Revenue 8827 8426 9110
ExpensesGeneration & Other Direct Expenses 7166 6908 8854Repairs & Maintenances 222 239 281Employee Benefit Expenses 174 189 223Finance Costs 796 752 1393Depreciation & Amortization Expense 616 593 905Administrative & Other Expenses 54 57 73
Total Expenses 9027 8737 11729
Profit/(Loss) Before Prior Period Item& Tax
-200 -311 -2619
Prior Period Income/(Expenses) 15 -2 -18Profit/(Loss) Before Tax -185 -313 -2637Tax ExpenseCurrent Tax 0 0 0Income Tax (Earlier Year Tax) 0 0 0Deferred Tax 0 0 0Profit/(Loss) For The Year -185 -313 -2637PAT Margin -2.11% -3.72% -29.04%
Preliminary Information Memorandum Page 57 of 70
9 Market Scenario and Assessment
9.1 Existing Demand and Supply scenario in Rajasthan
The power sector in Rajasthan has witnessed substantial improvement over the past decade because
of increase in generation capacity and strengthening of network infrastructure leading to an
improvement in the overall power supply position of the state. However, there are areas in the state
which experience unduly long interruptions in power supply due to inadequacies in the distribution
infrastructure. Moreover, a large portion of non-agriculture consumers in rural areas are supplied
through single phase only. Further, there is a large section of households in the state i.e. about 29 %,
which are yet to be electrified.
Year Demand vs Supply Gap Demand vs Supply Gap
(Peak Hours)
FY 15 ( Till Dec 2014) ~1% ~0.5%
FY 12 3.9% 7.1%
Rajasthan got benefit of about 2339 MW (excluding renewable energy sources) from the power
projects commissioned during 11th Plan
19%
55%
23%
3%
Benefit During 11th Plan
Central State Private Mundra UMPP
Preliminary Information Memorandum Page 58 of 70
9.2 Future Demand and Supply scenario in Rajasthan
The present energy requirement of Rajasthan is of the order of 58.9 BU per year and the introduction
of 24X7 supplies across the State is likely to increase the electricity consumption substantially in the
State.
The demand can be classified in three broad categories:-
a) Demand on account of 24X 7 power supply to already electrified households (MU)
Source: 24*7-Power for all - Rajasthan
b) Demand from electrification of un-electrified households (MU)
Source: 24*7-Power for all - Rajasthan
49055592
631270666969
79108910
9944
0
2000
4000
6000
8000
10000
12000
2015-16 2016-17 2017-18 2018-19
Rural
Urban
821
1369
2008
2738
447739
1077
1460
0
500
1000
1500
2000
2500
3000
2015-16 2016-17 2017-18 2018-19
Rural
Urban
Preliminary Information Memorandum Page 59 of 70
c) Demand on account of 24X7 power supply to already electrified other than domestic category
(MU)
Source: 24*7-Power for all - Rajasthan
The projections are in line with 18th EPS of CEA report, according to which the projected energy
requirement of Rajasthan is 89,792 MU by 2018-19. Assuming a load factor of 64% for Rajasthan,
the anticipated Peak demand of the state would be around 16004 MW.
It has been expected that implementation of Time of Day (TOD) tariff in state, adoption of demand
side management, use of energy efficient appliances may reduce the peak demand by around 1000
MW by 2018-19.
9.3 Existing generation capacity (RVUN, IPPs, Central)
The total installed capacity as on November 2015 (including allocated share in Joint & Central
Sector plants) was 17,228 MW from different sources as shown in the chart.
Total Installed Capacity as on Nov 2015 from different sources
39,72143,178
46,96351,108
0
10,000
20,000
30,000
40,000
50,000
60,000
2015-16 2016-17 2017-18 2018-19
55%
5%3%
10%
27% Coal
Gas
Nuclear
Hydel
Other RE
Preliminary Information Memorandum Page 60 of 70
The installed capacity has grown from 15,021 MW to 17,228 MW which is a growth of over 14.7 %
per annum during the last two and a quarter year i.e. from 30.06.2014 to 31.11.2016
Rajasthan is currently meeting its peak demand; however for providing 24X7 power supplies to the
State, the present energy requirement which is of the order of 58.29 BU per year and is likely to
increase to 89.6 BU per year by 2018-19. Therefore the additional contracted capacity required for
meeting the peak demand is tabulated below:
(All numbers in MW) ConventionalNon-
ConventionalTotal
Existing Capacity 11561 3640 15201
Capacity addition by 2018-19 5520 625 6145
Total Capacity by 2018-19 17081 4265 21346
Capacity Available out of Total capacity
to meet the peak demand by 2018-1911957 341 12298
Additional Capacity required to meet
the peak demand of 16000 MW by
2018-19
3702
Source: 24*7-Power for all - Rajasthan
9.4 Planned capacity addition in generation in Rajasthan (RVUN,IPPs, Central)
GoR has planned coal based projects of 4520 MW in the state, which includes projects of 2920 MW in
state sector, i.e. Kalisindh TPS Units 3 & 4 (2 X 660 MW) & Banswara TPS Units 1 & 2 (2 X 800 MW)
and projects of 1600 MW, i.e. Banswara TPS Units 1 & 2 (2 X 800 MW) under case -2. Also, 3600 MW
of renewable energy has also been planned to be available for the state, beginning FY19. In addition
to these, 2 units of 660 MW (CTPP) are also under construction.
9.5 Comparative analysis of generation tariff
Tariff for CTPP has been compared against the tariff of some other generating plants having similar
technology i.e. 2x250 MW. A comparison has been tabulated in the chart below:
Preliminary Information Memorandum Page 61 of 70
9.6 Competitive Bid scenarios (Case 1) in India*
Many distribution utilities or state nodal agencies such as KSEB, TPDDL, APSPDCL are procuring long
term power through competitive bidding route under DBFOO (Design, Built, Finance, Own, and
Operate) framework.
Under the framework:-
1) Bidders are asked to deliver the power at the state periphery, thereby avoiding Central
Transmission Charges and Central Transmission Losses.
2) Bidders are also asked to bear auxiliary power consumption and dedicated line losses.
3) The fixed charges are generally indexed to change in wholesale price index while variable
charges in case of linkage coal are passed through on actuals while keeping standard
parameters.
4) In case coal is sourced from captive mine the variable charges are also indexed to change in
whole sale price index while maintaining the sanctity of coal mine allotment agreement and
coal mine development and production agreement whichever is applicable.
Below table captures the bid quoted by successful Bidders.
StateBid
Date
Quantum
Awarded
(MW)
L1 Bidder
1st Year
Capacity
Charge
1st Year
Energy
Charge
1st Year
Transmission
Losses &
Charges
1st Year Total
Tariff (cons.
Respective W
points excl. STU)
Start Date
Bihar
BSPHCL,April-16 700 2.930 0.91 N/A 3.84 31st
December,
437.64519.18
386.4
2.2 2.1033.21
0
2
4
6
8
10
0
100
200
300
400
500
600
Chhabra Thermal Power Station(CTPS) -Unit (1 to 2) for FY16
Bina Thermal Power Station -65% Installed Capacity(FY15)
Parichha Extension II (2x250)MW for FY FY16
Fixed Charge (INR Cr. Variable Charge (INR/Kwh)
Preliminary Information Memorandum Page 62 of 70
StateBid
Date
Quantum
Awarded
(MW)
L1 Bidder
1st Year
Capacity
Charge
1st Year
Energy
Charge
1st Year
Transmission
Losses &
Charges
1st Year Total
Tariff (cons.
Respective W
points excl. STU)
Start Date
2017
TPDDL Sep-15 400 3.226 0.764
Included in
Energy
charge
3.991st April
2017
Andhra
Pradesh
(APSPDCL)
Jun-15 2400 2.86 1.41 NA 4.271st January
2017
Kerala Aug-14 400 3.25 1.04 NA 4.29
Kerala Aug-14 200 2.74 0.86 NA 3.60
Many Utilities such as BSPHCL and REMCL also went for midterm (3 Years) power procurement
through competitive bidding route under FOO (Finance Own Operate) framework. Similar trends are
observed in quotes of winning Bidders.
The above analysis in clauses 6.5 and 6.6 respectively clearly indicates that the total tariff for CTPP
is competitive when compared with similar sized plants as well as the current case 1 trends in the
country. Currently, CTPP stands first in merit order dispatch in the state of Rajasthan.
‘* EY analysis
Preliminary Information Memorandum Page 63 of 70
10 Annexure
Annexure – I: Unit wise Details
a. Salient Features Of 4x250 Mw Subcritical Units 1, 2, 3 & 4 (Stage I, Phase I & II)
(1) Installed Capacity 2X250 MW Stage- I, Phase- I2X250 MW Stage- I, Phase- II
(2) Estimated Cost 2820 Crores (Phase- I)
3033 Crores (Phase- II)(3) Land Acquired 526 Hectares (Stage-I)(4) Height of chimney 220 Meter each for Phase-I & II(5) ESP Efficiency 99.89%(6) Coal Requirement and Linkage 5.0 Million Tons per year
Unit-1&2- SECL, Kobra (C.G.) through washery circuit.
Unit-3&4- Parsa East & Kante Basen Coal Blocksthrough Parsa & Kante Colleries Ltd., Ambikapur (C.G.)
(7) Water Requirement 800 MCFT/ Year (38500 M3/ day)(For Phase I&II fromnearby Parvati, Bethali & Hinglot Dam.
(8) Power Evacuation 400KV /220 kv Switchyard with Inter-connectingTransformers (ICT) through 400KV Bhilwara, 400KVHindaun, 400KV Adani and 220 KV Jhalawar & 200KV Kawai-Dahara feeders.
(9) Date of COD Phase -I & IIUnit 1- COD achieved on 11.06.2010Unit 2- COD achieved on 15.10.2011Unit 3- COD achieved on 19.12.2013Unit 4-Commissioned on 30.06.14 & COD is on30/12/14
(10) Environmental Features Zero discharge concept adoptedETP & STP established. Re-cycled water utilization forgreen belt development.100% (Approx.) Fly Ash Utilization by cement & near-by bricks industries.
a. Salient Features Of 2x660 Mw Supercritical Units 5 & 6 (Stage II, Phase III)
(1) Installed Capacity 2X660 MW Stage-II, Phase- III
(2) Estimated Cost 7920 Crores Rs.
(3) Land Acquired 2361 Bigha (597.43 Hec.)
(4) Height of Chimney 275 Meter (Twin Flue)
(5) ESP Efficiency 99.89%
Preliminary Information Memorandum Page 64 of 70
(6) Fuel Requirement
Coa l- 6.5 MTPA
Unit 5 - Parsa East & Kante Basan Coal Block
Unit 6 - Kante Basan Extension Coal Block.
HSD/FO - 11563 KL/Year (for both units)
(7) Water Requirement
1570 MCFT/ YEAR
Lhasi Irrigation Project- 300MCFT
Parvan Irrigation Project- 1270 MCFT
(8) Scheduled Date of CommissioningUnit 5 - September 2016
Unit 6 - June 2018
Preliminary Information Memorandum Page 65 of 70
Annexure – II: Asset Details and Technology
Details of Main BTG & BOP equipment installed at units 1 to 4 (4x250 MW) at CTPP are given below:
S. No. Package Supplier1 Turbine & Auxiliaries BHEL2 Boiler & its Auxiliaries BHEL
3 Generator & its Auxiliaries BHEL
4 All rotary equipments viz. ID, FD, PA fans and Coalmills
BHEL
5 ESP BHEL6 Cooling Tower Paharpur7 Chlorination & Water treatment Plant Triveni Engg. & Industries ltd.8 DM Plant & Pretreatment Plant Triveni Engg. & Industries ltd.9 DM Plant Make-up System Remi Edelstahl Tubulars Ltd.10 Bulk Ammonia, Hydrazine & Phosphate system
Triveni Engg. & Industries ltd.11 Effluent Treatment Palnt12 CW Treatment System Industrial Devices13 Coal Handling System TRF Limited14 DE & DS System WRC15 Bottom Ash Handling System Indure16 Air Conditioning & Ventilation Package C Doctor & Co. Pvt. Ltd.17 Hydrogen Generation plant package Airox Nigen18 Elevators Alikraft/Thysenkrupp19 Electrical BOP- Supply ABB Ltd.20 Transformers ABB Ltd.21 Switchyard ABB Ltd.22 IPBD Reep23 SPBD C&S24 Reactors ABB Ltd.25 MV Switchgear ABB Ltd.26 LV Switchgear C&S27 Service Transformer (Dry & Oil) Voltamp28 CW & ACW KBL29 FPS New age fire protection, HD Fire30 Stop Log Gate Macmet31 Idlers, Pulleys & Spares Elecon32 Belt Vulcanising Machine Nilos India33 Hoists Mangla34 EoT Crane Reva35 Belt Weigher Prayas Engg.36 Stacker cum Reclaimer TRF Limited37 Twin Tripper Elecon
Preliminary Information Memorandum Page 66 of 70
Annexure III - Employee Strength
List of executives employed in CTPP is tabulated hereunder:
S.No. Name Of Post
Pay Scale (Running Pay Band +
Grade Pay)
CTPP,Chhabra(O&M of
Units 1 to4)
CTPP - Units5 & 6
A. Technical Officers:
1 Chief Engineer (E&M) 37400-67000 + 10000 1 1
2 Addl. Chief Engineer (E&M) 37400-67000 + 8700 1
3 Addl. Chief Engineer (Civil) 37400-67000 + 8700 - 1
4 Dy. Chief Engineer (E&M) 15600-39100 + 8200 3 2
5 Dy. Chief Engineer (Civil) 15600-39100 + 8200 0 1
6 Superintending Engineer (E&M) 15600-39100 + 7600 9 5
7 Superintending Engineer (C&I) 15600-39100 + 7600 - 1
8 Superintending Engineer (Civil) 15600-39100 + 7600 2 2
9 Chief Chemist 15600-39100 + 7600 - 1
10 Executive Engineer (E&M) 15600-39100 + 6600 23 19
11 Executive Engineer (C&I) 15600-39100 + 6600 1 3
12 Executive Engineer (Civil) 15600-39100 + 6600 6 5
13 Senior Chemist 15600-39100 + 6600 1 1
14 Assistant Engineer (E&M) 15600-39100 + 5400 45 54
15 Assistant Engineer (C&I) 15600-39100 + 5400 5 8
16 Assistant Engineer (Civil) 15600-39100 + 5400 12 17
17 Assistant Engineer (F&S) 15600-39100 + 5400 1 1
18 Chemists 15600-39100 + 5400 4 3
Total (A) 114 125
List of non-technical officers employed in CTPP is tabulated hereunder:
S.No. Name Of Post
Pay Scale (Running Pay
Band + Grade Pay)
CTPP, Chhabra(O&M Of
Units 1 To 4)
CTPP - Units5 & 6
C. Non- Technical Officers:
1 Chief Accounts Officer 15600-39100 +7600 1
2 Dy. Director (Personnel &Admn.)
15600-39100 +6600 1
3 Sr. Accounts Officer 15600-39100 +6600 1
4 Personnel Officer 15600-39100 + 2
Preliminary Information Memorandum Page 67 of 70
S.No.
Name Of Post Pay Scale(Running Pay
CTPP, Chhabra(O&M Of
CTPP - Units5 & 65400
5 Asstt. Secretary/ Admo/ Eo/Ps
15600-39100 +5400 1
6 Accounts Officer 15600-39100 +5400 3
7 Asstt. Accounts Officer 9300-34800 +4800 2
8 Medical Officer 15600-39100 +5400 2
Total- Non Technical Officers (C) 13
List of ad ministerial staff employed in CTPP is tabulated hereunder:
S. No. Name Of PostPay Scale
(Running Pay Band +Grade Pay)
CTPP, Chhabra(Including Super
Critical Units 5&6)
A. Ministerial Staff:
1 P.A / Stenographer -I 9300-34800 + 4800 2
2 Accountant 9300-34800 + 4200 8
3 Asstt. Personnel Officer 9300-34800 + 4200 2
4 Office Superintendent Gr-I 9300-34800 + 4200 2
5 Compounder Gr-Ii 9300-34800 + 3600 6
6 Junior Accountant 9300-34800 + 3600 22
7 Office Superintendent Gr-II 9300-34800 + 3600 2
8 Staff Nurse 5200-20200 + 2800 4
9 U.D.C. 5200-20200 + 2800 0
Total (A) 48
List of technical workmen employed in CTPP is tabulated hereunder:
S.No. Name Of Post
Pay Scale (Running Pay Band +
Grade Pay)
CTPP, Chhabra(Including Super
Critical Units 5&6)
A. Technical Workmen:
1 Plant Supervisor 9300-34800 + 4200 15
36 Plant Attendant -I 5200-20200 + 2800 25
69 Plant Attendant -II 5200-20200 + 2400 50
75 Helper-I 5200-20200 + 2000 4
81 Plant Attendant -III 5200-20200 + 2000 160
87 Helper-II 4750-7440 + 1750 18
Total 272
Preliminary Information Memorandum Page 68 of 70
Annexure IV –Milestone for units 5 & 6Key milestones for units 5 & 6 are summarized as follows:
Unit 5Milestone BL project
StartBL ProjectFinish
Act/ExcptProject Start
Act/ExcptProject Start
Readiness for PowerEvacuation
August 30,2016
August 30,2016
Unit Synchronized November26,2016
November26,2016
Unit 6
Steam Generator: HydroTest,
June 27,2017 July 28,2017
Steam Generator: Fuel OilFiring System Readiness
October 25,2017
November 25,2017
Steam Generator:Reliability Test
July 21, 2018 August 19,2018
July 21, 2018 August 19,2018
STG: TG on Barring gear November14,2017
November14,2017
STG: Governing Systemtuning
November15,2017
November19,2017
November15,2017
November19,2017
STG: Rolling & GeneratorTesting
May 10, 2018 May 11, 2018 May 10, 2018 May 11, 2018
Control Valves: Testing &Commissioning for UnitSynchronization
August 11,2017
September 9,2017
August 11,2017
September 9,2017
Preliminary Information Memorandum Page 69 of 70
Annexure V – Ceiling PriceBelow table summarizes the calculation of ceiling price for delivery of coal from ‘Parsa East & KanteBasan’ coal block to CTPP,
S.No.
Particulars Prevailing price per MT as on01.06.16
1 Avg. GCV (ADB) of Washed coal (Kcal/kg.) 4900A Raw Coal Cost Grade G11 (Rs./MT of Raw coal)2 Base Rate / MT of SECL at Pithead 810.003 Less 8.5% discount (if applicable as per Clause
5.3)68.85
4 Royalty (if applicable) 113.405 SED (if applicable) 10.006 Chhattisgarh Environment cess 7.507 Chhattisgarh Development cess 7.508 Crushing Charges 100.009 Forest Tax 15.0010 Clean Energy Cess 400.00
Contribution to District Mineral Foundation 34.02Contribution to National Mineral Exploration Trust 2.27
11 Excise duty @ 6% on(2+4+5+6+7+8+9+DMF+NMET)
65.98
12 Total (2-3+4+5+6+7+8+9+10+DMF+NMET+11+12)
1496.82
13 CST on 12 @ 2% 29.9414 Cost of Raw Coal per MT (13+12) 1526.76B Beneficiation15 Increase in Raw Coal cost (without discount) due
to reject generated - Yield @ 77.5%/80.00% ((on(14)+(3)*(1 + CST) ) assuming Royalty SEC andcrushing charges are specific rates, not advalorem, otherwise the pro-rata amount onaccount of discount has to be added back) 15 =[(14) +{(3) X (1 + CST)}] X {(1/Yield) – 1}
463.64 399.25
EscalatedBeneficiationCharges (asper theBeneficiationContract)
Actual BeneficiationCharges
16 Beneficiation Charges including Service Tax. 276.72 341.2517 Cost of Beneficiated Coal per MT [(14+15)] + 16
[ Escalated Beneficiation Charges or ActualBeneficiation Charges per clause no. 5.3.2]
2267.12 2267.26
2267.12
Preliminary Information Memorandum Page 70 of 70
18 Railway freight per MT of washed coal incurred byRVUNL 1380.07
C Other charges ( per MT of washed Coal)19 Transit Loss @ 1.5% (of 18 + 17) 54.7120 Interest on rail freight (18) for 22 days at SBI rate
for private lending (@14.75%) 12.27
21 Total of Other Expenses (20+19) 66.98D Ceiling Price for GCV(ADB) 4900 Kcal/Kg Coal =
(17+21) 2334.10
E Ceiling Price worked out on pro-rata based onGCV (ADB) 4500 Kcal/Kg Coal. 2143.56