Upload
others
View
0
Download
0
Embed Size (px)
Citation preview
Dr Christopher J Gippel
For
Goulburn-Murray Water
September 2012
Preliminary hydrological modelling for Kerang Lakes bypass
investigation project
Page i
Preliminary hydrological modelling for Kerang Lakes bypass investigation project
Goulburn-Murray Water
by Dr Christopher J Gippel
Fluvial Systems Pty Ltd
Please cite as follows:
Gippel, C.J. 2012. Preliminary hydrological modelling for Kerang Lakes bypass investigation project. Fluvial Systems Pty Ltd, Stockton. Goulburn-Murray Water, Shepparton, September.
Document history and status
Revision Date issued Reviewed by Approved by Date approved Revision type
A 19/08/2012 Project Reference Group C. Gippel 19/08/2012 Draft
B 11/09/2012 Project Reference Group C. Gippel 11/09/2012 Draft
C 15/09/2012 Project Reference Group C. Gippel 15/09/2012 Draft
D 21/09/2012 Project Reference Group C. Gippel 21/09/2102 Final
Distribution of copies
Revision Copy no Quantity Issued to
A 1 1 Peter Roberts, Pat Feehan
B 1 1 Peter Roberts, Pat Feehan
C 1 1 Peter Roberts, Pat Feehan
D 1 1 Peter Roberts, Pat Feehan
Printed: Not printed
Last saved: 21/09/2012
File location: C:\...\12002_NVIRP_Kerang Lakes\Reports\Preliminary modelling of water regime options and water savings for Kerang Lakes.docx
Author: Dr Christopher J Gippel
Project manager:
Chris Gippel
Name of organisation:
Goulburn-Murray Water
Name of project: Kerang Lakes and Gunbower Lagoons Bypass Investigation Project
Name of document:
Report on water balance modelling
Document version:
Final
Fluvial Systems Pty Ltd PO Box 49 Stockton NSW 2295 [email protected] Ph/Fax: 02 49284128; Mobile: 0404 472 114
Page ii
Disclaimer
Fluvial Systems Pty Ltd prepared this report for the use of Goulburn-Murray Water, and any other parties that may rely on the report, in accordance with the usual care and thoroughness of the consulting profession. It is based on generally accepted practices and standards at the time it was prepared. No other warranty, expressed or implied, is made as to the professional advice included in this report. It is prepared in accordance with the scope of work and for the purpose outlined in the Proposal.
Fluvial Systems Pty Ltd does not warrant this document is definitive nor free from error and does not accept liability for any loss caused, or arising from, reliance upon the information provided herein.
The methodology adopted and sources of information used by Fluvial Systems Pty Ltd are provided in this report. Fluvial Systems Pty Ltd has made no independent verification of this information beyond the agreed scope of works and Fluvial Systems Pty Ltd assumes no responsibility for any inaccuracies or omissions. No indications were found during our investigations that information contained in this report as provided to Fluvial Systems Pty Ltd was false.
This report is based on the conditions encountered and information reviewed at the time of collection of data and report preparation. Fluvial Systems Pty Ltd disclaims responsibility for any changes that may have occurred after this time.
This report should be read in full. No responsibility is accepted for use of any part of this report in any other context or for any other purpose or by third parties. This report does not purport to give legal advice. Legal advice can only be given by qualified legal practitioners.
Copyright
The concepts and information contained in this document are the copyright of Fluvial Systems Pty Ltd and Goulburn-Murray Water. Use or copying of this document in whole or in part without permission of Fluvial Systems Pty Ltd and Goulburn-Murray Water could constitute an infringement of copyright. There are no restrictions on downloading this document from a Goulburn-Murray Water website. Use of the information contained within this document is encouraged, provided full acknowledgement of the source is made.
Page iii
Table of Contents
Disclaimer _______________________________________________________________ ii Copyright ________________________________________________________________ ii 1 Introduction _________________________________________________________ 1
1.1 Background to this study _____________________________________________ 1
1.2 Objectives of this report ______________________________________________ 2
1.3 Previous investigations_______________________________________________ 3 1.3.1 Net Evapotranspiration (current regime)____________________________________ 3 1.3.2 Seepage ____________________________________________________________ 3 1.3.3 Potential for water savings ______________________________________________ 4
2 Method _____________________________________________________________ 4
2.1 SWET model structure _______________________________________________ 4 2.1.1 Model concept ________________________________________________________ 4 2.1.2 Model algorithm _______________________________________________________ 5 2.1.3 Model parameters, data sources and scenarios ______________________________ 5 2.1.4 Modelling platform _____________________________________________________ 7
2.2 Bathymetry data ____________________________________________________ 8
2.3 Inflow data ________________________________________________________ 8
2.4 Inflow/outflow hydraulics _____________________________________________ 8
2.5 Climate data _______________________________________________________ 8
2.6 Groundwater exchange ______________________________________________ 9
2.7 Irrigation demand ___________________________________________________ 9
2.8 Lake management regime options ______________________________________ 9 3 Results ____________________________________________________________ 10
3.1 Summary of potential losses and savings _______________________________ 10
3.2 First (Reedy) Lake _________________________________________________ 11 3.2.1 Current regime ______________________________________________________ 11 3.2.2 Episodic regime ______________________________________________________ 13 3.2.3 Intermittent regime ___________________________________________________ 14 3.2.4 Semi-permanent regime (8 in 10) ________________________________________ 15 3.2.5 Semi-permanent regime (9 in 10) ________________________________________ 16
3.3 Middle (Reedy) Lake _______________________________________________ 17 3.3.1 Current regime ______________________________________________________ 17 3.3.2 Episodic regime ______________________________________________________ 18 3.3.3 Intermittent regime ___________________________________________________ 19 3.3.4 Semi-permanent regime (8 in 10) ________________________________________ 20 3.3.5 Semi-permanent regime (9 in 10) ________________________________________ 21
3.4 Third (Reedy) Lake _________________________________________________ 22 3.4.1 Current regime ______________________________________________________ 22 3.4.2 Episodic regime ______________________________________________________ 23 3.4.3 Intermittent regime ___________________________________________________ 24 3.4.4 Semi-permanent regime (10 in 10) _______________________________________ 25
3.5 Little Lake Charm (including Scott’s Swamp) _____________________________ 26 3.5.1 Current regime ______________________________________________________ 26 3.5.2 Episodic regime ______________________________________________________ 27 3.5.3 Intermittent regime ___________________________________________________ 28 3.5.4 Semi-permanent regime (8 in 10) ________________________________________ 29 3.5.5 Semi-permanent regime (9 in 10) ________________________________________ 30
3.6 Racecourse Lake __________________________________________________ 31 3.6.1 Current regime ______________________________________________________ 31 3.6.2 Episodic regime ______________________________________________________ 32 3.6.3 Intermittent regime ___________________________________________________ 33 3.6.4 Semi-permanent regime (9 in 10) ________________________________________ 34
3.7 Comparison with previous estimates of losses and savings _________________ 35
Page iv
3.7.1 Net Evapotranspiration (current regime)___________________________________ 35 3.7.2 Seepage ___________________________________________________________ 35 3.7.3 Potential for water savings _____________________________________________ 36
3.8 Inter-annual variability of savings ______________________________________ 36 4 Sensitivity of savings estimates to model parameters_________________________ 37
4.1 Sensitivity of savings estimates to inherent model parameter values __________ 37 4.1.1 Evapotranspiration estimate: Pan versus physical model _____________________ 38 4.1.2 Evapotranspiration estimate: wind speed assumption in physical model _________ 38 4.1.3 Initial loss parameters _________________________________________________ 39
4.2 Sensitivity of savings estimates to management regime parameter values _____ 39 4.2.1 Maximum rate of filling ________________________________________________ 40 4.2.2 Date of beginning the filling phase _______________________________________ 40 4.2.3 Duration of the filling phase ____________________________________________ 40
4.3 Summary of variability of savings and model sensitivity ____________________ 41 5 Conclusion _________________________________________________________ 42 6 References _________________________________________________________ 42 7 Appendix – Bathymetry data ____________________________________________ 45
Page 1
1 Introduction
1.1 Background to this study
The Kerang Lakes are part of an extensive wetland system of over 100 wetlands that
occurs within the Loddon-Murray Region (DSE, 2004). The Kerang Lakes Ramsar
Site, listed in 1982, consists of 23 wetlands which receive water from the Murray
River via the Torrumbarry Irrigation System, the Avoca River and the Loddon River.
These wetlands, which include both regulated and unregulated wetlands, are used
for a variety of purposes including as part of the irrigation supply, as salt disposal
lakes and as natural feature reserves receiving Environmental Water Allocations
(DSE, 2010) (Figure 1).
Figure 1. Torrumbarry Irrigation Area, showing location of Kerang Lakes. Map modified from North Central CMA (2007).
The Kerang Lakes bypass investigation project is investigating the feasibility of a
concept to construct bypass channels around five of the Kerang Lakes (NVIRP,
2012). First Reedy, Middle Reedy and Third Reedy lakes, Little Lake Charm and
Racecourse Lake (Figure 1 and Figure 2) have had permanent water regimes since
the 1920s when they were filled to become part of the TIA. The altered regimes
reduced or resulted in the loss of biodiversity (DSE, 2004, p. 16). The bypass would
Page 2
provide the opportunity to implement alternative hydrological regimes in the lakes.
Alternative regimes could lead to improvements in the ecological values of the lakes.
Also, by periodically lowering the lake levels during summer months, water savings
would be achieved through reduced evaporation losses.
Figure 2. Sketch of possible options under investigation in the Kerang Lakes bypass investigation project. Map modified from NVIRP (2012).
1.2 Objectives of this report
The key objective of this hydrological modelling component of the investigation is to
develop numerical models of 5 Kerang Lakes that can be used to:
estimate long term losses under existing conditions and possible future
operational regimes, so that water savings potential of the bypass intervention
can be estimated, and
predict long-term daily water level regimes under a range of possible
operational regimes so that their potential for ecological rehabilitation can be
evaluated, and the regimes refined accordingly.
Page 3
This hydrologicial modelling component of the Kerang Lakes bypass investigation
project was undertaken in two Stages:
Stage I.
Preliminary estimates of losses and savings potential for five Kerang Lakes
wetlands under a wide range of possible water regimes, from existing
(permanent) to dry (episodic wetting). The focus is on model development,
model sensitivity and broad-scale estimation of water savings potential.
Stage II.
Pending the outcome of Stage I, refine a narrow set of water balance models
that have the highest potential for conjointly achieving sufficiently high water
savings, and potential for improving ecological values.
This report documents the methods and outcomes of Stage I.
1.3 Previous investigations
North Central CMA (2011) reviewed previous estimates of losses and potential for
water savings at Kerang Lakes. The various estimates are outlined below in terms of
evapotranspiration, seepage and potential for savings.
1.3.1 Net Evapotranspiration (current regime)
Evapotranspiration (ET) is a term that covers both evaporation from wet surfaces
(evaporation), and vegetation (transpiration), so it can be applied to wetlands whether
vegetated or not. Net evapotranspiration (net ET) is the sum of evapotranspirative
losses and precipitation gains.
North Central CMA (2011) listed estimates of average annual evapotranspiration
losses from the five Kerang lakes that were attributed to Lugg et al. (1989). These
were expressed as net ET estimates by subtracting long term (1889 – 2012) average
annual rainfall of 352 mm (from DataDrill) (Table 1). SKM (2010) estimated average
annual net ET (in ML) for the five Kerang lakes using the Pan coefficient method
(applying an annual Pan factor of 0.78) and Morton’s shallow lake method (Table 1).
The Kerang Lakes REALM model also uses the Pan coefficient method (Table 1).
These data show that estimates of water loss are highly dependent on the method
used, and the input data used (lake surface area and climate data).
1.3.2 Seepage
SKM (2010) estimated that under the current regime, seepage loss from First, Middle
and Third Reedy lakes would total up to 500 ML/year under dry climate conditions,
and 320 ML/year for medium conditions. North Central CMA (2011) listed the degree
of groundwater interaction for the lakes, attributed to Lugg et al. (1989), as “minor
intrusion: nil”, except for Little Lake Charm which was a possible source of
groundwater recharge (i.e. loss from the lake to groundwater).
Page 4
Table 1. Previous estimates of average annual net evapotranspiration (net ET) for five Kerang lakes. Lugg et al. (1989) estimated ET and net ET was calculated by subtracting long term (1889 – 2012) average annual rainfall of 352 mm (from DataDrill). Kerang Lakes REALM model data provided by Seker Mariyapillai (pers. comm., DSE, Melbourne.
19/09/2012).
Lake Lugg et al. (1989) SKM (2010) REALM model
ET (ML/yr)
Net ET (minus
352 mm rainfall) (ML/yr)
Net ET, Pan
coefficient method (ML/yr)
Net ET, Morton’s method (ML/yr)
Net ET, Pan
coefficient method (ML/yr)
Reedy (First) 2,500 1,802 1,883 1,921 1,460
Middle (Reedy) 2,700 2,019 1,883 1,642 1,460
Third (Reedy) 3,000 2,190 2,131 2,002 1,825
Little Lake Charm 1,580 1,101 565 n/a n/a
Racecourse 3,300 2,456 2,182 2,341 1,825
TOTAL (excl. L’t. Lake Charm)
8,467 8,079 7,906 6,570
1.3.3 Potential for water savings
RMCG (2009) estimated net savings from two Bypass options: Little Lake Charm and
Racecourse Lakes Bypass (815 ML/year) and Reedy Lakes Bypass (1,250 ML/year).
The total was 2,065 ML/year.
SKM (2010) estimated that the total savings for the entire Kerang Lakes Bypass
system ranged from 4,200 – 12,400 ML/year, and an alternative operating regime
with different ecological values would save 1,400 – 9,600 ML/year. The range in
savings estimates relates to differences in wet and dry years. Middle (Reedy) was
assessed to have no potential for savings, and Little Lake Charm had potential for
only a small volume of savings. SKM (2010) were of the view that the savings
actually achieved would be on the low end of the estimated range.
2 Method
2.1 SWET model structure
2.1.1 Model concept
SWET is not a particular computer program (although originally a template did exist),
but an approach to wetland water balance modelling that incorporates all of the water
balance components, uses best available data, runs on a daily time step, and has
standard way of defining and calculating the “savings” under alternative operating
scenarios.
The SWET water balance modelling concept was initially developed to accurately
predict water savings potential at individual wetlands in the River Murray System
(Gippel 2005a, Gippel 2005b, Gippel 2005c). After development of the SWET
modelling approach was completed in 2005, it was reviewed by technical
Page 5
representatives of state and commonwealth agencies responsible for management of
the River Murray System, and then endorsed as a suitable modelling procedure for
listings on The Living Murray Developmental Register (the first stage of approval for a
water recovery measure).
A model run based on current conditions returns a value of current losses of water
from the system to the wetland. Run for a future scenario (i.e. current hydrology or
hydrology with climate change assumptions, but with a regulating structure to control
flows to and from the wetland to achieve the ecologically desirable hydrological
regime in the wetland), the model returns a value of future losses of water from the
system to the wetland. The value of current losses minus the value of future losses is
the volume of water that can potentially be recovered from the system. As well as
estimating losses, the water balance produces a daily time series of wetland water
level. Run for a pre-regulation scenario, the model characterises a wetland’s natural
hydrological regime. This can be used to guide development of a future water level
management regime for a wetland. Run for a current scenario, the model
characterises the wetland’s current hydrological regime, enabling identification of
aspects of the hydrology that may be ecologically limiting.
Although the SWET approach was originally devised mainly for the purpose of
estimating the potential for water savings at river-connected wetlands, the
hydrological principles are equally applicable to the problem of modelling the time
series of wetland water levels to assist ecological research (e.g. Catford et al., 2011),
or development of ecologically-appropriate wetland water management regimes (e.g.
Ecological Associates, 2008; Gippel, 2010).
2.1.2 Model algorithm
The SWET model attempts to estimate all the components of the hydrological cycle
that influence daily water level in a wetland (cf. Dooge, 1975; Gosselink and Turner,
1978; Winter, 1981; Duever, 1988; U.S. Army Corps of Engineers, 1993; Gippel,
1993; LaBaugh, 1996; Woo and Rowsell, 1993). The daily water budget is described
by:
ΔV = [Qir + (a Alo R) + (b Aexp R) – (Qor + Qox + Qp)] – [I] + [Gi - Go] + [Awet (R – ET)]
where: ΔV = daily change of water quantity stored in the wetland (m3); Qir = volume of
surface water spilling into the wetland from the source (m3); a = a local catchment
runoff coefficient; Alo = wetland local catchment area (m2); R = local precipitation (m);
b = a runoff coefficient for the exposed part of the wetland bed; Aexp = area of the
exposed part of the wetland bed (m2); Qor = volume of surface water flowing out of the
wetland back to the source (m3); Qox = volume of surface water flowing out of the
wetland external of the river-wetland system (permanently lost) (m3); Qp = volume of
pumped extraction (m3); I = volume of initial loss of inflowing surface water to voids in
the dry wetland bed (m3); Gi = volume of groundwater gained by the wetland (m3); Go
= volume of water lost by the wetland to groundwater (m3); Awet = wet surface area of
wetland (m2); and ET = evapotranspiration from the wet surface of the wetland (m).
2.1.3 Model parameters, data sources and scenarios
The wetland volume (V), surface area (Awet and Aexp) and water elevation (Hw) are
interchanged in the SWET model through bathymetric relationships derived from a
Page 6
digital elevation model of the wetland (generated from ground and hydrographic
survey data). The direction and rate of flow of water between the wetland and the
inflow determine the net losses from the inflow source, ΔQr = Qir – Qor – Qox. The
values of Qir, Qor, and Qox are calculated daily within the model, as determined by the
relationship between the elevation of the wetland water surface (Hw), the adjacent
source river water surface (Hr) (a model input value), and the sill separating them (a
model input value derived from survey), and also by the hydraulics of the inflowing
and outflowing connections. The hydraulics are described by standard equations for
open channel flow, pipe flow or weir flow, as appropriate. Source river water surface
elevation (Hr) is converted from river flow records (either gauged or modelled) on the
basis of a local hydraulic model of the river. For a terminal or in-line wetland (such as
Kerang Lakes) with a direct connection between the inflow source and the wetland,
these calculations are simpler. Runoff coefficients a and b are set using appropriate
values for the surface characteristics and can be made variable according to rainfall
intensity. Wetland local catchment area is determined from topographic analysis.
Precipitation data are obtained from local gauges or from a modelled source. In
Australia, modelled climate daily time series data (with records from the late 1800s
up to the present day) are available for any location from the SILO DataDrill service
provided through the Department of Environment and Resource Management,
Queensland Government. The DataDrill accesses grids of data derived from
interpolation of point station records. Pumped extraction data are obtained from local
records.
Evapotranspiration is a critical component of the water budget and should be
carefully considered. Early SWET models used the time series of modelled Class A
Pan evaporation from SILO DataDrill, factored using empirical monthly pan to open
water coefficients derived for a wetland near Griffith, western NSW (Hoy and
Stephens, 1979). More recently applied SWET models incorporated a combination
physical method recommended for the Murray-Darling Basin by McJannet et al.
(2009) that uses the Penman-Monteith method with a deBruin adjustment to the
amount of energy available for evaporation based on changes in heat storage within
the water body. The key assumption of this physical model is that the water body is
well mixed and that no thermal stratification develops. The Kerang Lakes vary in
maximum depth from 1.4 to 2.6 m. While stratification might develop under calm,
warm and sunny conditions, wind and nocturnal heat loss would normally disrupt the
stratification at the sub-daily time scale. The combination physical method requires
an estimate of daily wind speed. While the factored pan and physical model
approaches produce different estimates of evaporation at the daily time scale
(McJannet et al., 2009), at the scale of annual estimated wetland water savings, the
differences tend to be systematic, as determined by the selected pan factor/s.
Initial losses of water to bed sediments as the wetland fills represent a permanent
loss of water, because the water is ultimately evaporated from the bed sediments as
the wetland draws down. The initial loss is calculated as the percent of the bed
material that is void space multiplied by the depth of the bed layer (these values are
determined by field sampling). Most riverine wetlands in the lowland areas of the
River Murray have a clay bed that cracks upon drying and seals upon wetting. The
groundwater component in SWET models the daily flux between river and wetland
using Darcy’s Law. The hydraulic conductivity value is selected on the basis of local
Page 7
soil type. The daily time series of hydraulic head is determined from the relative
levels of the adjacent source river (SWET model input data) and the wetland
(predicted within SWET). In the lowland part of the River Murray System,
groundwater exchange is not normally a large component of wetland water budgets
due to low hydraulic conductivity of the wetland bed, and low head differences
between the adjacent river and wetland. Any wetland with strong connectivity to the
groundwater system would be a poor candidate for obtaining water savings, as a
regulating structure would be ineffective in disconnecting the wetland from the river
inflow source.
Including a regulating structure in the water balance model under a future scenario
alters the pattern of water transfer between the wetland and the inflowing river. The
height of the structure is a variable in the model, which allows for iterative trade-off of
water savings and wetland water level regime. Draft operating rules for the structure
are ideally set by a panel of scientific experts, managers and stakeholders, but these
remain flexible within the model to allow for iterative trade-off of the joint objectives of
maximising savings and generating an ecologically desirable water level regime. The
final operating rules might represent a compromise, or could favour either the
ecological or water savings objectives, depending on the local priorities.
Water savings, S, are calculated by subtracting the net long-term exchange of water
between the inflowing river and the wetland under a future (f) scenario, ∑ΔQr(f), with
that under the current (c) scenario, ∑ΔQr(c). The exchange of water between the
inflow source and wetland can be episodic. Water can flow to or from the wetland, so
on a daily basis the exchange can be positive or negative. The long-term exchange is
usually expressed as a distribution of values of annual total exchange over the
modelled period. Thus, the long-term savings is expressed as a distribution of annual
savings over the modelled period. Savings can be expressed as a single value using
the mean or median of the modelled annual values, supported by an expression of
dispersion (such as standard deviation or inter-quartile range). In most applications to
date, the SWET models have been run over 100 years or longer, because long-term
modelled climate and river flow data have usually been available.
2.1.4 Modelling platform
Most SWET models have been developed within Microsoft Excel™. The main reason
for this is that the widespread availability of, and familiarity with, Microsoft Excel™
allows for the possibility of river managers being able to use the model with very little
training. While there is no commercial or public domain software that has been
specifically designed for this purpose, commercial hydrodynamic models could
potentially be used. However, such models are normally relatively costly to run (due
to high set-up costs and long model run times), and operate at the event or sub-
annual time-scale, while the problem addressed by the SWET model requires:
(i) analysis of a long time series (to fully characterise the wetland water level regime,
and assess the potential for water savings under the full range of natural hydrological
conditions), (ii) capacity to vary water level operational regimes inter-annually, or
dependent on antecedent conditions, and (iii) inexpensive modelling costs due to the
large number of wetlands that have potential for water savings and environmental
benefits.
Page 8
2.2 Bathymetry data
The five lakes were professionally surveyed using standard techniques. Bathymetric
data were provided for each lake as a digital file of water surface area and volume for
a range of water levels (see Appendix – Bathymetry data). In addition, bathymetric
survey plans were provided. Where the lowest elevation (zero area and volume) was
not provided, this was assumed to be 0.01 m lower than the lowest provided
elevation.
2.3 Inflow data
Daily inflows to First (Reedy) Lake under the baseline (existing conditions) were
obtained from a water resource allocation model (REALM) of the Kerang Lakes
system (SKM, 2007). The modelling period is 1/01/1891 to 1/07/2010.
The REALM inflows comprise regulated and unregulated inflow. The preliminary
SWET models described here do not distinguish between these two flow types. The
future scenario models assume only controlled inflows, sufficient to just achieve the
desired water levels. However, in reality, flood flows will continue to occur in the
future, and these will disrupt some drying cycles. In one sense, these food inflows will
interfere with the expected pattern of water savings, but in another sense, the
unregulated water is low cost water compared to regulated water, so filling the lakes
from flood events, although perhaps untimely, could be viewed as a windfall. It is
likely that in Stage II of this hydrological modelling project the distinction between
regulated and unregulated will be made, and flood inflows will occur during the future
scenarios.
2.4 Inflow/outflow hydraulics
The preliminary SWET models described here have no hydraulic constraints on the
inflows and outflows. In baseline (existing condition) models, inflows to the system
are specified by the REALM model. Outflows to the next downstream lake are
calculated each day using the SWET algorithm as the surplus after losses. In reality,
there would be noticeable attenuation of inflows at times of floods due to the storage
effect of the lake itself. The effect of reducing the flood inflow peak, and extending the
duration, is apparent from gauged lake water level records. This effect would have
only a minor influence on water savings potential (because it is an infrequent event).
However, this flood inflow attenuation effect will be simulated in the models
developed in Stage II of this hydrological modelling project.
2.5 Climate data
Separate DataDrill climate files were obtained for First, Middle, Third and Lake
Charm and Racecourse lakes. The DataDrill grid is 0.05 x 0.05 degrees of latitude
and longitude, and the centre of Lake Charm and Racecourse lakes fell within the
same grid. The climate series was obtained for the period 1/01/1891 to 1/07/2010.
The Kerang Lakes SWET models retain the option of using factored Pan evaporation
data. Pan coefficients are usually borrowed from a similar water body (i.e. similar
depth and area) in a similar latitude and altitude where the Pan coefficient has been
measured. It is not uncommon practice to apply a single Pan coefficient throughout
the year, although the Pan coefficient is known to vary seasonally in nearly all
situations. The default Pan coefficients in the LMWP model are monthly variable
Page 9
values from Lake Wyangan (Griffith, NSW) (Hoy and Stephens, 1979), which are
considered the most appropriate values for wetlands in this region.
In the original application of the combination evaporation method by McJannet et al.,
(2009), the water body surface area and depth were assumed constant, but this was
clearly inappropriate for the application to management of water bodies with highly
variable water levels. Thus, in the SWET model, the estimated surface area and
depth at the end of a day become input data for the estimate of evaporation rate for
the next day. Wind speed data were obtained from the Bureau of Meteorology for
Kerang meteorological station, with a start date of 1962. Data were daily-read wind
speed at 9 AM and 3 PM. Average wind speed was assumed to be the average of
these two readings. Although this is only an approximation, it is consistent with the
way mean daily temperature is derived for the CSIRO evaporation model. In this
case, mean daily temperature is estimated from the average of maximum and
minimum daily readings. The lack of measured wind speed data prior to 1962 was
overcome by assuming a value of 2 m/s, which is the same assumption made by the
Department of Environment and Resource Management (QLD) when they estimate
reference crop evapotranspiration using the Penman-Monteith method for the SILO
DataDrill. The estimates of water use by water bodies are better if measured or
modelled wind speed data are used, but the assumption of 2 m/s does not
compromise the integrity of the model.
2.6 Groundwater exchange
The preliminary models reported here did not include groundwater exchange. This
would require generation of a daily time series of the local water table elevation, and
while possible, would not be trivial. Stage II of this hydrological modelling project will
consider the inclusion of groundwater exchange.
2.7 Irrigation demand
The Kerang Lakes have a relatively small irrigation demand that was not included in
the preliminary models reported here. This demand is not expected to have any
impact on water savings estimates, because it does not have a significant impact on
lake water levels. However, for completeness, irrigation demands will be included in
the baseline models developed in Stage II of this hydrological modelling project.
2.8 Lake management regime options
The lake future management regime options were provided by North Central CMA
(2012). The process for developing alternative wetland water regime scenarios was
informed by consideration of: (i) ecological values previously recorded at the
wetlands, (ii) wetland water regime definitions and classifications and (iii) previous
work to define water regimes for the wetlands.
At each wetland four alternative water regime scenarios were developed:
no change
episodic
intermittent
semi-permanent
Page 10
These alternative scenarios were developed for planning purposes and no particular
scenario has been selected or recommended for future management purposes.
The management scenarios modelled here were intended as preliminary regimes for
the purpose of estimating the magnitude of savings possible for the four water regime
scenario types. Any regimes that show potential will be refined in Stage II of this
hydrological modelling project.
Some assumptions were made for these preliminary models:
Lake filling began on 1 August
Maximum rate of rise from inflows was set at 50 mm per day
There was no local catchment area
The capacity to supply water to meet the desired water level was unlimited
When the lake bed dried it was assumed to develop a cracked bed to a depth
of 0.3 m with 25% void space
Some of these assumptions might be altered in later versions of the management
scenarios. The sensitivity of the estimated water savings to the potential range of
values of these parameters was tested in this report.
3 Results
3.1 Summary of potential losses and savings
The SWET model was used to calculate net losses (net evapotranspiration plus initial
losses) from the lakes over a daily time step. These losses were summed over
periods of one year or longer, depending on the management regime. The baseline
regime is the same every year, so the losses were reported for every year. The
potential future management regimes involved multi-year cycles of filling and drying,
so the losses were highly variable from year to year depending on the stage of the
cycle. In these cases the losses were reported for the period of each complete cycle.
Water savings were calculated over each cycle. For each scenario, average annual
savings represent annualized values of the savings estimated over all the completed
cycles of the modelled period. The maximum length of the modelled period was 118
years. The losses reported for the baseline (Current) scenario were calculated over
118 years, but shorter baseline periods were used for some future scenarios (in
cases where an incomplete management cycle occurred at the end of the modelled
period).
The potential water savings from alternative management of the lakes varies
significantly depending on the regime type (Table 2). The smaller Little Lake Charm
has a smaller surface area than the other lakes, so for an alternative management
regime that is mostly dry, it has lower potential for savings (Table 2). However, this
lake is shallower than the others, so its surface area reduces more rapidly during
draw down. Thus, for alternative management regimes that involve partial or less
frequent drying, it can produce savings that are comparable with or greater than
those of the others (Table 2).
Page 11
The preliminary estimates made here of total (for the five lakes) mean annual savings
were:
6,123 ML/yr for the episodic regime,
3,095 ML/yr for the intermittent regime, and
1,553 ML/yr for the semi-permanent regimes with the greatest savings.
It would not be necessary to operate all five lakes according to the same regime type,
so the above total savings represents the potential range.
Table 2. Estimated average annual net losses and potential savings from a range of
management options for five Kerang Lakes. Net loss is equivalent to the water that needs to be artificially supplied to maintain the water level regime.
Lake Scenario Period of average
(years, from 1895)
Average annual net
loss (ML/yr)
Average annual
savings* (ML/yr)
First (Reedy) Current 118 2,238 198.28 ha Episodic 115 768 1,456 Intermittent 116 1,698 531 Semi-permanent (8/10) 110 1,947 258 Semi-permanent (9/10) 110 2,130 75
Middle (Reedy) Current 118 2,235 193.40 ha Episodic 118 1,541 694 Intermittent 116 1,624 602 Semi-permanent (8/10) 110 1,854 349 Semi-permanent (9/10) 110 2,033 169
Third (Reedy) Current 118 2,652 230.13 ha Episodic 116 1,278 1,364 Intermittent 117 2,203 443 Semi-permanent (10/10) 110 2,580 34
L’t. Lake Charm Current 118 1,559 136.05 ha Episodic 116 385 1,170 Intermittent 115 423 1,127 Semi-permanent (8/10) 110 871 668 Semi-permanent (9/10) 110 975 563
Racecourse Current 118 2,812 239.65 ha Episodic 116 1,363 1,440 Intermittent 117 2,400 407 Semi-permanent (9/10) 110 2,529 244 * Savings is not always the given 118 year average current loss minus future scenario loss, as
the benchmark (current) loss was re-calculated over the same period of each future scenario;
the length of the scenario periods varied because they always ended on a complete cycle.
3.2 First (Reedy) Lake
3.2.1 Current regime
The Current regime was used as the benchmark against which future scenarios were
compared. The Current regime is based on a relatively constant water level held at
full supply level (FSL) of 74.88 m. The level is not actually constant, as, on any day,
Page 12
inflows may not be sufficient to account for evapotranspirative losses. The inflows
were as determined by the REALM model estimates for Wandella Creek and
Washpen Creek flows. The SWET model does not exactly reproduce the gauged
water levels, measured from 1986. The reasons are:
In the SWET model the outflows are unconstrained, when in reality, there will
be attenuation at times of very high inflows. Thus, the recorded flood peak
lake levels are not predicted.
The REALM model assumes current operation rules, and these many not
have applied throughout history. The data suggest that this was the case.
The recorded level of the lake would vary depending on where it is gauged.
The SWET model calculates an average lake level.
The differences between the gauged and modelled lake levels are relatively small.
Model parameter Model setting
Supply of inflows According to REALM assumptions
Controlled filling frequency and levels Not applicable
Durations of filling phases Not applicable
Assumed maximum rate of rise Not applicable
Start of filling Not applicable
Assumed local contributing area None
Water use calculation period From 1 August
Estimated long-term mean annual net losses were 2,238 ML.
Figure 3. Predicted water levels and percentage of bed dry for Current (baseline) regime, First (Reedy) Lake.
71.5
72.0
72.5
73.0
73.5
74.0
74.5
75.0
75.5
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Wat
er
leve
l (m
AH
D)
71.5
72.0
72.5
73.0
73.5
74.0
74.5
75.0
75.5
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Wat
er
leve
l (m
AH
D)
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
Page 13
3.2.2 Episodic regime
Model parameter Model setting
Supply of inflows Assumed unlimited capacity to supply Controlled filling frequency and levels
1 in 5 years to 74.88 m
Durations of filling phases Alternating 4 then 3 months (includes filling phase)
Assumed maximum rate of rise 50 mm/day
Start of filling 1 August
Assumed local contributing area None
Water use calculation period From 1 August
Estimated long-term mean annual net losses were 768 ML, and mean annual water
savings were 1,456 ML.
Figure 4. Predicted water levels and percentage of bed dry for Episodic regime, First (Reedy) Lake.
71.50
72.00
72.50
73.00
73.50
74.00
74.50
75.00
75.50
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Wat
er
leve
l (m
AH
D)
71.50
72.00
72.50
73.00
73.50
74.00
74.50
75.00
75.50
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Wat
er
leve
l (m
AH
D)
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
Page 14
3.2.3 Intermittent regime
Model parameter Model setting
Supply of inflows Assumed unlimited capacity to supply Controlled filling frequency and levels
3 in 4 years; Year 1 to 74.88 m; Years 2 and 3 to 73.6 m
Durations of filling phases Alternating 10, 8 then 7 months (includes filling phase)*
Assumed maximum rate of rise 50 mm/day
Start of filling 1 August
Assumed local contributing area None
Water use calculation period From 1 August * The filling durations were set to give the best chance of achieving full drawdown.
Estimated long-term mean annual net losses were 1,722 ML, and mean annual water
savings were 516 ML.
Figure 5. Predicted water levels and percentage of bed dry for Intermittent regime, First (Reedy) Lake.
71.50
72.00
72.50
73.00
73.50
74.00
74.50
75.00
75.50
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Wat
er
leve
l (m
AH
D)
71.50
72.00
72.50
73.00
73.50
74.00
74.50
75.00
75.50
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Wat
er
leve
l (m
AH
D)
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
Page 15
3.2.4 Semi-permanent regime (8 in 10)
Model parameter Model setting
Supply of inflows Assumed unlimited capacity to supply Controlled filling frequency and levels
8 in 10 years to 74.88 – 74.28 m. Drawdown over a 2 year period.
Durations of filling phases
2 months (including filling time) at 74.88 m then draw down to 74.28 mm for remaining months of the year
Assumed maximum rate of rise
50 mm/day
Start of filling 1 August
Assumed local contributing area
None
Water use calculation period
From 1 August
Estimated long-term mean annual net losses were 1,947 ML, and mean annual water
savings were 258 ML.
Figure 6. Predicted water levels and percentage of bed dry for Semi-permanent regime (8 in 10), First (Reedy) Lake.
71.50
72.00
72.50
73.00
73.50
74.00
74.50
75.00
75.50
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Wat
er
leve
l (m
AH
D)
71.50
72.00
72.50
73.00
73.50
74.00
74.50
75.00
75.50
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Wat
er
leve
l (m
AH
D)
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
Page 16
3.2.5 Semi-permanent regime (9 in 10)
This regime is the same as the Semi-permanent regime (8 in 10), except that the full
drawdown occurs over only one year instead of two. The savings for a regime that
varied between 8 in 10 and 9 in 10 full would lie between the two estimates.
Model parameter Model setting Supply of inflows Assumed unlimited capacity to supply
Controlled filling frequency and levels
9 in 10 years to 74.88 – 74.28 m. Drawdown over a 1 year period.
Durations of filling phases
2 months (including filling time) at 74.88 m then draw down to 74.28 mm for remaining months of the year*
Assumed maximum rate of rise
50 mm/day
Start of filling 1 August
Assumed local contributing area
None
Water use calculation period
From 1 August
* The duration of 2 months always allows for filling to the maximum level
The lake does not fully draw down under this regime.
Estimated long-term mean annual net losses were 2,130 ML, and mean annual water
savings were 75 ML.
Figure 7. Predicted water levels and percentage of bed dry for Semi-permanent regime (9 in 10), First (Reedy) Lake.
71.50
72.00
72.50
73.00
73.50
74.00
74.50
75.00
75.50
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Wat
er
leve
l (m
AH
D)
71.50
72.00
72.50
73.00
73.50
74.00
74.50
75.00
75.50
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Wat
er
leve
l (m
AH
D)
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
Page 17
3.3 Middle (Reedy) Lake
3.3.1 Current regime
The Current regime was used as the benchmark against which future scenarios were
compared. The Current regime is based on a relatively constant water level held at
full supply level (FSL) of 74.88 m. The level is not actually constant, as, on any day,
inflows may not be sufficient to account for evapotranspirative losses. The inflows
were as determined by the modelled outflows from the Current SWET model for First
(Reedy) Lake. The SWET model does not exactly reproduce the gauged water levels,
measured from 1986. The reasons are the same as noted for First (Reedy) Lake.
Model parameter Model setting
Supply of inflows According to REALM assumptions, SWET modelled losses from First (Reedy), and no hydraulic constraints
Controlled filling frequency and levels
Not applicable
Durations of filling phases
Not applicable
Assumed maximum rate of rise
Not applicable
Start of filling Not applicable
Assumed local contributing area
None
Water use calculation period
From 1 August
Estimated long-term mean annual net losses were 2,235 ML
Figure 8. Predicted water levels and percentage of bed dry for Current (baseline) regime, Middle (Reedy) Lake.
71.5
72.0
72.5
73.0
73.5
74.0
74.5
75.0
75.5
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Wat
er
leve
l (m
AH
D)
71.5
72.0
72.5
73.0
73.5
74.0
74.5
75.0
75.5
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Wat
er
leve
l (m
AH
D)
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
Page 18
3.3.2 Episodic regime
Model parameter Model setting
Supply of inflows Assumed unlimited capacity to supply Controlled filling frequency and levels
1 in 2 years to 74.85 m*
Durations of filling phases Alternating 2, 3, 4 then 5 months (includes filling phase)
Assumed maximum rate of rise 50 mm/day
Start of filling 1 August
Assumed local contributing area None
Water use calculation period From 1 August * For these scenarios, the FSL was given by North Central CMA (2012) as 74.85 m, but First
(Reedy) FSL is 74.88 m, and the lakes are connected. An elevation of 74.85 m was modelled
for the future scenarios, and 74.88 m for the Current scenario.
The lake does not always fully draw down under this regime.
Estimated long-term mean annual net losses were 1,541 ML. Estimated long-term
mean annual savings were 694 ML.
Figure 9. Predicted water levels and percentage of bed dry for Episodic regime, Middle (Reedy) Lake.
71.5
72.0
72.5
73.0
73.5
74.0
74.5
75.0
75.5
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Wat
er
leve
l (m
AH
D)
71.5
72.0
72.5
73.0
73.5
74.0
74.5
75.0
75.5
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Wat
er
leve
l (m
AH
D)
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
Page 19
3.3.3 Intermittent regime
Model parameter Model setting
Supply of inflows Assumed unlimited capacity to supply Controlled filling frequency and levels
3 in 4 years; Year 1 to 74.85 m; Years 2 and 3 to 73.85 m*
Durations of filling phases Yr 1 is 10, Yrs 2 and 3 are 12 months (includes filling phase)†
Assumed maximum rate of rise 50 mm/day
Start of filling 1 August
Assumed local contributing area None
Water use calculation period From 1 August * For the scenarios, the FSL was given by North Central CMA (2012) as 74.85 m, but First
(Reedy) FSL is 74.88 m, and the lakes are connected. An elevation of 74.85 m was modelled
for the future scenarios, and 74.88 m for the Current scenario
† The duration at FSL was not specified by North Central CMA (2012), so 10 months was
assumed
Estimated long-term mean annual net losses were 1,624 ML. Estimated long-term
mean annual savings were 602 ML.
Figure 10. Predicted water levels and percentage of bed dry for Intermittent regime, Middle (Reedy) Lake.
71.5
72.0
72.5
73.0
73.5
74.0
74.5
75.0
75.5
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Wat
er
leve
l (m
AH
D)
71.5
72.0
72.5
73.0
73.5
74.0
74.5
75.0
75.5
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Wat
er
leve
l (m
AH
D)
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
Page 20
3.3.4 Semi-permanent regime (8 in 10)
Model parameter Model setting
Supply of inflows Assumed unlimited capacity to supply Controlled filling frequency and levels
8 in 10 years to 74.85 – 74.45 m. Drawdown over a 2 year period.
Durations of filling phases
2 months (including filling time) at 74.85 m then draw down to 74.45 mm for remaining months of the year*
Assumed maximum rate of rise
50 mm/day
Start of filling 1 August
Assumed local contributing area
None
Water use calculation period
From 1 August
* The duration of 2 months always allows for filling to the maximum level
This regime is allows for near complete drawdown once every 10 years.
Estimated long-term mean annual net losses were 1,854 ML. Estimated long-term
mean annual savings were 349 ML.
Figure 11. Predicted water levels and percentage of bed dry for Semi-permanent regime (8 in 10), Middle (Reedy) Lake.
71.5
72.0
72.5
73.0
73.5
74.0
74.5
75.0
75.5
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Wat
er
leve
l (m
AH
D)
71.5
72.0
72.5
73.0
73.5
74.0
74.5
75.0
75.5
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Wat
er
leve
l (m
AH
D)
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
Page 21
3.3.5 Semi-permanent regime (9 in 10)
This regime is the same as the Semi-permanent regime (8 in 10), except that the full
drawdown occurs over only one year instead of two. The savings for a regime that
varied between 8 in 10 and 9 in 10 full would lie between the two estimates.
Model parameter Model setting Supply of inflows Assumed unlimited capacity to supply
Controlled filling frequency and levels
9 in 10 years to 74.85 – 74.45 m. Drawdown over a 1 year period.
Durations of filling phases
2 months (including filling time) at 74.85 m then draw down to 74.45 mm for remaining months of the year*
Assumed maximum rate of rise
50 mm/day
Start of filling 1 August
Assumed local contributing area
None
Water use calculation period
From 1 August
* The duration of 2 months always allows for filling to the maximum level
The lake does not fully draw down under this regime.
Estimated long-term mean annual net losses were 2,033 ML. Estimated long-term
mean annual savings were 169 ML.
Figure 12. Predicted water levels and percentage of bed dry for Semi-permanent regime (9 in 10), Middle (Reedy) Lake.
71.5
72.0
72.5
73.0
73.5
74.0
74.5
75.0
75.5
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Wat
er
leve
l (m
AH
D)
71.5
72.0
72.5
73.0
73.5
74.0
74.5
75.0
75.5
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Wat
er
leve
l (m
AH
D)
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
Page 22
3.4 Third (Reedy) Lake
3.4.1 Current regime
The Current regime was used as the benchmark against which future scenarios were
compared. The Current regime is based on a relatively constant water level held at
full supply level (FSL) of 74.56 m. The level is not actually constant, as, on any day,
inflows may not be sufficient to account for evapotranspirative losses. The inflows
were as determined by the modelled outflows from the Current SWET model for
Middle (Reedy) Lake. The SWET model does not exactly reproduce the gauged
water levels, measured from 1986. The reasons are the same as noted for First
(Reedy) Lake.
Model parameter Model setting Supply of inflows According to REALM assumptions, SWET modelled losses
from Middle (Reedy), and no hydraulic constraints
Controlled filling frequency and levels
Not applicable
Durations of filling phases
Not applicable
Assumed maximum rate of rise
Not applicable
Start of filling Not applicable
Assumed local contributing area
None
Water use calculation period
From 1 August
Estimated long-term mean annual net losses were 2,652 ML.
71.5
72.0
72.5
73.0
73.5
74.0
74.5
75.0
75.5
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Wat
er
leve
l (m
AH
D)
71.5
72.0
72.5
73.0
73.5
74.0
74.5
75.0
75.5
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Wat
er
leve
l (m
AH
D)
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
Page 23
3.4.2 Episodic regime
Model parameter Model setting
Supply of inflows Assumed unlimited capacity to supply Controlled filling frequency and levels 1 in 4 years to 74.56 m
Durations of filling phases 10 months (includes filling phase)
Assumed maximum rate of rise 50 mm/day
Start of filling 1 August
Assumed local contributing area None
Water use calculation period From 1 August
Estimated long-term mean annual net losses were 1,278 ML. Estimated long-term
mean annual savings were 1,364 ML.
Figure 13. Predicted water levels and percentage of bed dry for Episodic regime, Third (Reedy) Lake.
71.5
72.0
72.5
73.0
73.5
74.0
74.5
75.0
75.5
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Wat
er
leve
l (m
AH
D)
71.5
72.0
72.5
73.0
73.5
74.0
74.5
75.0
75.5
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Wat
er
leve
l (m
AH
D)
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
Page 24
3.4.3 Intermittent regime
Model parameter Model setting
Supply of inflows Assumed unlimited capacity to supply Controlled filling frequency and levels
2 in 3 years; Year 1 to 74.85 m; Year 2 to 74.2 m
Durations of filling phases Alternating 10, 9, 8 then 7 months (includes filling phase)
Assumed maximum rate of rise 50 mm/day
Start of filling 1 August
Assumed local contributing area None
Water use calculation period From 1 August
Estimated long-term mean annual net losses were 2,203 ML. Estimated long-term
mean annual savings were 443 ML.
Figure 14. Predicted water levels and percentage of bed dry for Intermittent regime, Third (Reedy) Lake.
71.5
72.0
72.5
73.0
73.5
74.0
74.5
75.0
75.5
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Wat
er
leve
l (m
AH
D)
71.5
72.0
72.5
73.0
73.5
74.0
74.5
75.0
75.5
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Wat
er
leve
l (m
AH
D)
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
Page 25
3.4.4 Semi-permanent regime (10 in 10)
Model parameter Model setting
Supply of inflows Assumed unlimited capacity to supply Controlled filling frequency and levels
10 in 10 years to 74.56 m
Durations of filling phases
12 month; exception is 2 consecutive years of fill for 2 months at 74.56 m, then draw down to 73.74 m for remainder of year*
Assumed maximum rate of rise
50 mm/day
Start of filling 1 August
Assumed local contributing area
None
Water use calculation period
From 1 August
* The frequency of the two consecutive years of drawdown to 73.74 m was not specified by
North Central CMA (2012). It was set to once every 10 years.
The lake does not fully draw down under this regime.
Estimated long-term mean annual net losses were 2,580 ML. Estimated long-term
mean annual savings were 34 ML.
Figure 15. Predicted water levels and percentage of bed dry for Semi-permanent regime, Third (Reedy) Lake.
71.5
72.0
72.5
73.0
73.5
74.0
74.5
75.0
75.5
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Wat
er
leve
l (m
AH
D)
71.5
72.0
72.5
73.0
73.5
74.0
74.5
75.0
75.5
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Wat
er
leve
l (m
AH
D)
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
Page 26
3.5 Little Lake Charm (including Scott’s Swamp)
3.5.1 Current regime
The Current regime was used as the benchmark against which future scenarios were
compared. The Current regime is based on a relatively constant water level held at
full supply level (FSL) of 73.95 m. The level is not actually constant, as, on any day,
inflows may not be sufficient to account for evapotranspirative losses. The inflows
were as determined by the modelled outflows from the Current SWET model for Third
(Reedy) Lake.
Model parameter Model setting
Supply of inflows According to REALM assumptions, SWET modelled losses from Third (Reedy), and no hydraulic constraints
Controlled filling frequency and levels
Not applicable
Durations of filling phases
Not applicable
Assumed maximum rate of rise
Not applicable
Start of filling Not applicable Assumed local contributing area
None
Water use calculation period
From 1 August
Estimated long-term mean annual net losses were 1,559 ML.
Figure 16. Predicted water levels and percentage of bed dry for Current (baseline) regime, Little Lake Charm.
71.5
72.0
72.5
73.0
73.5
74.0
74.5
75.0
75.5
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Wat
er
leve
l (m
AH
D)
71.5
72.0
72.5
73.0
73.5
74.0
74.5
75.0
75.5
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Wat
er
leve
l (m
AH
D)
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
Page 27
3.5.2 Episodic regime
Model parameter Model setting
Supply of inflows Assumed unlimited capacity to supply Controlled filling frequency and levels
1 in 4 years to 73.95 m
Durations of filling phases Alternating 2 and 5 months (includes filling phase)
Assumed maximum rate of rise 50 mm/day
Start of filling 1 August
Assumed local contributing area None
Water use calculation period From 1 August
Estimated long-term mean annual net losses were 385 ML. Estimated long-term
mean annual savings were 1,170 ML.
Figure 17. Predicted water levels and percentage of bed dry for Episodic regime, Little Lake Charm.
71.5
72.0
72.5
73.0
73.5
74.0
74.5
75.0
75.5
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Wat
er
leve
l (m
AH
D)
71.5
72.0
72.5
73.0
73.5
74.0
74.5
75.0
75.5
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Wat
er
leve
l (m
AH
D)
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
Page 28
3.5.3 Intermittent regime
Model parameter Model setting
Supply of inflows Assumed unlimited capacity to supply Controlled filling frequency and levels
4 in 5 years; Year 1 to 73.95 m; Year 2, 3 and 4 to 72.75 m
Durations of filling phases 4 months (includes filling phase)
Assumed maximum rate of rise 50 mm/day
Start of filling 1 August
Assumed local contributing area None
Water use calculation period From 1 August
Estimated long-term mean annual net losses were 423 ML. Estimated long-term
mean annual savings were 1,127 ML.
Figure 18. Predicted water levels and percentage of bed dry for Intermittent regime, Little Lake Charm.
71.5
72.0
72.5
73.0
73.5
74.0
74.5
75.0
75.5
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Wat
er
leve
l (m
AH
D)
71.5
72.0
72.5
73.0
73.5
74.0
74.5
75.0
75.5
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Wat
er
leve
l (m
AH
D)
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
Page 29
3.5.4 Semi-permanent regime (8 in 10)
Model parameter Model setting
Supply of inflows Assumed unlimited capacity to supply Controlled filling frequency and levels
8 in 10 years to 73.95 – 72.95 m. Drawdown over a 2 year period.
Durations of filling phases
2 months (including filling time) at 73.95 m then draw down to 72.95 mm for remaining months of the year*
Assumed maximum rate of rise
50 mm/day
Start of filling 1 August
Assumed local contributing area
None
Water use calculation period
From 1 August
* The duration of 2 months always allows for filling to the maximum level
Estimated long-term mean annual net losses were 871 ML. Estimated long-term
mean annual savings were 668 ML.
Figure 19. Predicted water levels and percentage of bed dry for Semi-permanent (8 in 10) regime, Little Lake Charm.
71.5
72.0
72.5
73.0
73.5
74.0
74.5
75.0
75.5
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Wat
er
leve
l (m
AH
D)
71.5
72.0
72.5
73.0
73.5
74.0
74.5
75.0
75.5
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Wat
er
leve
l (m
AH
D)
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
Page 30
3.5.5 Semi-permanent regime (9 in 10)
This regime is the same as the Semi-permanent regime (8 in 10), except that the full
drawdown occurs over only one year instead of two. The savings for a regime that
varied between 8 in 10 and 9 in 10 full would lie between the two estimates.
Model parameter Model setting Supply of inflows Assumed unlimited capacity to supply
Controlled filling frequency and levels
9 in 10 years to 73.95 – 72.95 m. Drawdown over a 2 year period.
Durations of filling phases
2 months (including filling time) at 73.95 m then draw down to 72.95 mm for remaining months of the year*
Assumed maximum rate of rise
50 mm/day
Start of filling 1 August
Assumed local contributing area
None
Water use calculation period
From 1 August
* The duration of 2 months always allows for filling to the maximum level
Estimated long-term mean annual net losses were 975 ML. Estimated long-term
mean annual savings were 563 ML.
Figure 20. Predicted water levels and percentage of bed dry for Semi-permanent (9 in 10) regime, Little Lake Charm.
71.5
72.0
72.5
73.0
73.5
74.0
74.5
75.0
75.5
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Wat
er
leve
l (m
AH
D)
71.5
72.0
72.5
73.0
73.5
74.0
74.5
75.0
75.5
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Wat
er
leve
l (m
AH
D)
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
Page 31
3.6 Racecourse Lake
3.6.1 Current regime
The Current regime was used as the benchmark against which future scenarios were
compared. The Current regime is based on a relatively constant water level held at
full supply level (FSL) of 73.95 m. The level is not actually constant, as, on any day,
inflows may not be sufficient to account for evapotranspirative losses. The inflows
were as determined by the modelled outflows from the Current SWET model for Little
Lake Charm Lake.
Model parameter Model setting
Supply of inflows According to REALM assumptions, SWET modelled losses from Little Lake Charm, and no hydraulic constraints
Controlled filling frequency and levels
Not applicable
Durations of filling phases
Not applicable
Assumed maximum rate of rise
Not applicable
Start of filling Not applicable Assumed local contributing area
None
Water use calculation period
From 1 August
Estimated long-term mean annual net losses were 2,812 ML.
Figure 21. Predicted water levels and percentage of bed dry for Current (baseline) regime, Racecourse Lake.
70.5
71.0
71.5
72.0
72.5
73.0
73.5
74.0
74.5
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Wat
er
leve
l (m
AH
D)
70.5
71.0
71.5
72.0
72.5
73.0
73.5
74.0
74.5
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Wat
er
leve
l (m
AH
D)
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
Page 32
3.6.2 Episodic regime
Model parameter Model setting
Supply of inflows Assumed unlimited capacity to supply Controlled filling frequency and levels
1 in 4 years to 73.93 m
Durations of filling phases Alternating 2 and 5 months (includes filling phase)
Assumed maximum rate of rise 50 mm/day
Start of filling 1 August
Assumed local contributing area None
Water use calculation period From 1 August
Estimated long-term mean annual net losses were 1,363 ML. Estimated long-term
mean annual savings were 1,440 ML.
Figure 22. Predicted water levels and percentage of bed dry for Episodic regime, Racecourse Lake.
70.5
71.0
71.5
72.0
72.5
73.0
73.5
74.0
74.5
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Wat
er
leve
l (m
AH
D)
70.5
71.0
71.5
72.0
72.5
73.0
73.5
74.0
74.5
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Wat
er
leve
l (m
AH
D)
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
Page 33
3.6.3 Intermittent regime
Model parameter Model setting
Supply of inflows Assumed unlimited capacity to supply Controlled filling frequency and levels
2 in 3 years; Year 1 to 73.93 m; Year 2 to 72.57 m
Durations of filling phases Alternating 10 and 7 months (includes filling phase)
Assumed maximum rate of rise 50 mm/day
Start of filling 1 August
Assumed local contributing area None
Water use calculation period From 1 August
The lake fully draws down infrequently under this regime.
Estimated long-term mean annual net losses were 2,400 ML. Estimated long-term
mean annual savings were 407 ML.
Figure 23. Predicted water levels and percentage of bed dry for Intermittent regime, Racecourse Lake.
70.5
71.0
71.5
72.0
72.5
73.0
73.5
74.0
74.5
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Wat
er
leve
l (m
AH
D)
70.5
71.0
71.5
72.0
72.5
73.0
73.5
74.0
74.5
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Wat
er
leve
l (m
AH
D)
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
Page 34
3.6.4 Semi-permanent regime (9 in 10)
Model parameter Model setting
Supply of inflows Assumed unlimited capacity to supply Controlled filling frequency and levels
9 in 10 years to 73.93 – 72.93 m. Drawdown over a 2 year period.
Durations of filling phases
2 months (including filling time) at 73.93 m then draw down to 72.93 mm for remaining months of the year*
Assumed maximum rate of rise
50 mm/day
Start of filling 1 August
Assumed local contributing area
None
Water use calculation period
From 1 August
* The duration of 2 months always allows for filling to the maximum level
The lake does not fully draw down under this regime.
Estimated long-term mean annual net losses were 2,529 ML. Estimated long-term
mean annual savings were 244 ML.
Figure 24. Predicted water levels and percentage of bed dry for Semi-permanent (9 in 10) regime, Racecourse Lake.
70.5
71.0
71.5
72.0
72.5
73.0
73.5
74.0
74.5
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Wat
er
leve
l (m
AH
D)
70.5
71.0
71.5
72.0
72.5
73.0
73.5
74.0
74.5
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Wat
er
leve
l (m
AH
D)
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/2
00
0
1/0
7/2
00
0
1/0
1/2
00
1
1/0
7/2
00
1
1/0
1/2
00
2
1/0
7/2
00
2
1/0
1/2
00
3
1/0
7/2
00
3
1/0
1/2
00
4
1/0
7/2
00
4
1/0
1/2
00
5
1/0
7/2
00
5
1/0
1/2
00
6
1/0
7/2
00
6
1/0
1/2
00
7
1/0
7/2
00
7
1/0
1/2
00
8
1/0
7/2
00
8
1/0
1/2
00
9
1/0
7/2
00
9
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
1/0
1/1
93
4
1/0
1/1
93
8
1/0
1/1
94
2
1/0
1/1
94
6
1/0
1/1
95
0
1/0
1/1
95
4
1/0
1/1
95
8
1/0
1/1
96
2
1/0
1/1
96
6
1/0
1/1
97
0
1/0
1/1
97
4
1/0
1/1
97
8
1/0
1/1
98
2
1/0
1/1
98
6
1/0
1/1
99
0
1/0
1/1
99
4
1/0
1/1
99
8
1/0
1/2
00
2
1/0
1/2
00
6
1/0
1/2
01
0
Pe
rce
nta
ge o
f b
ed
are
a e
xpo
sed
Page 35
3.7 Comparison with previous estimates of losses and savings
3.7.1 Net Evapotranspiration (current regime)
The average values estimated by SKM (2010) were compared with estimates made
on the basis of SILO DataDrill climate data from First (Reedy) Lake (assume at FSL)
for the 10 year period 1/7/200 to 30/6/2010. The three estimates made here were
based on rainfall combined with evapotranspiration estimated by: (i) factored Pan
evaporation (using a factor of 0.78), (ii) FAO56 Reference Crop PET (Penman-
Monteith), and (iii) a combination method of Penman-Monteith with deBruin
adjustment for changes in heat storage of the water body, as recommended by
McJannet et al. (2008) for use in estimating evaporation from open water in the
Murray Darling Basin. This comparison shows that the combination method produces
a significantly higher estimate of evapotranspiration that the other methods (Table 2).
The difference is mostly associated with higher estimated summer season
evapotranspiration (Figure 25). Despite the combination method appearing to be the
odd one out, it remains the preferred method for this purpose (McJannet et al., 2008),
and it has the advantage of sensitivity to the depth of the water body.
Table 3. Estimated average annual net evapotranspiration from First (Reedy) Lake at Full
Supply Level (FSL).
Pan coefficient Morton’s FAO56 PET Combination
SKM (2010) 1883 1921 - -
This study 1903 - 2096 2645
Figure 25. Estimated evapotranspiration using three methods for First (Reedy) Lake over a 10 year period, based on SILO DataDrill data. Pan data are not factored.
3.7.2 Seepage
The SWET model did not attempt to estimate groundwater exchange. This would
require generation of a daily time series of the local water table elevation, and while
0
2
4
6
8
10
12
14
16
18
20
Dail
y e
vap
otr
an
sp
irati
on
(m
m)
Penman-Monteith with deBruin adjustment (water bodies)
Class A Pan
FAO Reference Crop PET (Penman-Monteith)
Page 36
possible, it would not be trivial. However, a standard feature of SWET is an estimate
of initial losses, which is the water lost to cracks in the dry bed upon re-wetting. Initial
losses are not relevant to the current regime, but future regimes involving draw
downs will incur initial losses.
For First (Reedy) Lake, under the episodic regime, the dry lake is filled every five
years. The average initial loss for the wetting episodes was estimated to be 107 ML.
While these initial losses were accounted for in the SWET modelling, there could also
be losses to groundwater of the order of a few hundred ML, with the volume
dependent on the management scenario.
3.7.3 Potential for water savings
The estimates of potential savings made previously by RMCG (2009) and SKM
(2010) are of the same order as those estimated here, but the figures cannot be
compared directly due to differences in assumptions regarding operating regimes.
3.8 Inter-annual variability of savings
The losses and savings were shown to be highly sensitive to the management
regime. The savings also varied from year to year, or from one management cycle to
the next. This is illustrated using the example of First (Reedy) Lake (Figure 26). While
savings are normally expressed as an annual average, when the management
regime extends over a number of years, this represents the average annualised
value. In this case, the water savings are not realised every year, but can be
calculated at the end of each cycle, and then expressed as an annual average over
the cycle. In First (Reedy) Lake the annualised savings for the four management
options varied across a fairly wide range as a function of climatic variation (Figure
26).
Page 37
Figure 26. Time series of annualised savings (averaged over the management cycle) for four management regime options for First (Reedy) Lake.
4 Sensitivity of savings estimates to model parameters
4.1 Sensitivity of savings estimates to inherent model parameter values
The losses and savings were highly sensitive to the management regime type and to
a lesser extent natural climatic variability (Figure 26). The estimates were also
dependent on inherent model parameter values. The sensitivity of the water savings
estimate to SWET model parameter values was tested for a single scenario at one
site: First (Reedy) lake for the Intermittent regime. Stage II of this hydrological
modelling project will investigate the sensitivity of all models to model parameter
values.
0
1000
2000
1892
1896
1900
1904
1908
1912
1916
1920
1924
1928
1932
1936
1940
1944
1948
1952
1956
1960
1964
1968
1972
1976
1980
1984
1988
1992
1996
2000
2004
2008
An
nu
alis
ed s
avin
gs
(ML
/yr)
Episodic
0
500
1000
1892
1896
1900
1904
1908
1912
1916
1920
1924
1928
1932
1936
1940
1944
1948
1952
1956
1960
1964
1968
1972
1976
1980
1984
1988
1992
1996
2000
2004
2008
An
nu
alis
ed s
avin
gs
(ML
/yr)
Intermittent
0
200
400
1892
1896
1900
1904
1908
1912
1916
1920
1924
1928
1932
1936
1940
1944
1948
1952
1956
1960
1964
1968
1972
1976
1980
1984
1988
1992
1996
2000
2004
2008
An
nu
alis
ed s
avin
gs
(ML
/yr)
Semi-permanent (8/10)
0
50
100
150
1892
1896
1900
1904
1908
1912
1916
1920
1924
1928
1932
1936
1940
1944
1948
1952
1956
1960
1964
1968
1972
1976
1980
1984
1988
1992
1996
2000
2004
2008
An
nu
alis
ed s
avin
gs
(ML
/yr)
Semi-permanent (9/10)
Page 38
4.1.1 Evapotranspiration estimate: Pan versus physical model
The combination physical model approach of McJannet et al. (2009) produced higher
estimates of water savings than did the factored Pan evaporation approach (Table 4).
This is because the evapotranspiration rates estimated by the physical model were
higher than for the Pan method (Figure 25).
Table 4. Estimated average annual water savings from First (Reedy) Lake for the Intermittent
regime using two different methods of evapotranspiration estimation.
Scenario Mean annual savings (ML/yr)
Factored Pan evaporation Physical model
First (Reedy) Intermittent (1891-2009) 398 531
4.1.2 Evapotranspiration estimate: wind speed assumption in physical model
The combination physical model approach of McJannet et al. (2009) uses local wind
speed data if available. Such data are available for Kerang from 1962 onwards,
although there were gaps in the data. A wind speed of 2 m/s was assumed for the
period 1891 to 1961.
The first test of sensitivity to wind speed data was to run the Current (baseline) and
Intermittent models for the period 1962 to 2009 with measured wind speed data, and
then with the assumption of 2 m/s for each day (Table 5). All other parameter values
were maintained at their default values.
The measured wind speed data gave a higher saving than the assumption of 2 m/s
every day (Table 5). This is explained by the measured wind speed being generally
higher than 2 m/s, and higher wind speed increases the evaporation rate.
Table 5. Estimated average annual water savings from First (Reedy) Lake for the Intermittent regime using the physical model evapotranspiration estimation with measured wind
speed and constant 2 m/s wind speed. Estimate for the period 1962 – 2009 only.
Scenario Mean annual savings (ML/yr)
Assume 2 m/s Measured wind speed
First (Reedy) Intermittent (1962–2009) 535 622
The second test of sensitivity to wind speed was to run the model for the entire
modelled period using a constant wind speed, and varying the wind speed over the
range 1 – 4 m/s (Table 6). All other parameter values were maintained at their default
values.
The higher the wind speed, the higher was the saving (Table 6), because high wind
speed increases the evaporation rate.
Page 39
Table 6. Estimated average annual water savings from First (Reedy) Lake for the Intermittent
regime using the physical model evapotranspiration estimation with a range of constant wind speeds.
Scenario Mean annual savings (ML/yr)
1 m/s 2 m/s 3 m/s 4 m/s
First (Reedy) Intermittent (1891-2009) 401 496 567 623
4.1.3 Initial loss parameters
The default parameter values for initial loss used here were 25% void space and
300 mm depth of voids. This refers to the properties of the bed of the lake after drying
out. The greater the total void space, the higher is the initial loss. These parameters
were varied over the range 20% void space and 200 m depth to 30% void space and
400 mm depth (Table 7). All other parameter values were maintained at their default
values.
Varying the initial loss parameter values over a reasonable range had only a small
effect on savings (Table 7). The larger was the total void space, the higher was the
initial loss, which had the effect of decreasing savings.
Table 7. Estimated average annual water savings from First (Reedy) Lake for the Intermittent
regime using a range of initial loss parameter values.
Scenario Mean annual savings (ML/yr)
20% and 200 mm
25% and 300 mm
30% and 400 mm
First (Reedy) Intermittent (1891-2009)
543 531 515
4.2 Sensitivity of savings estimates to management regime parameter values
The losses and savings were highly sensitive to the management regime type. The
estimates were sensitive to parameter values selected for the regimes. The key
variables are:
Maximum rate of rise of lake levels while filling
Date of beginning the filling phase
Duration of the filling period
The sensitivity of the water savings estimate to these regime parameter values was
tested for a single scenario at one site: First (Reedy) lake for the Intermittent regime.
Stage II of this hydrological modelling project will investigate the sensitivity of all
models to regime parameter values.
Page 40
4.2.1 Maximum rate of filling
The default maximum rate of rise while filling was set at 50 mm/day, which
corresponds with the upper limit of the range normally acceptable for ecological
reasons. This parameter was varied over the range 10 – 1,000 mm/day (Table 8). All
other parameter values were maintained at their default values.
The way the scenarios were configured, the total duration of being full included the
period of filling. Thus, the low range of filling rate increased savings (Table 8),
because this reduced the duration that the lake was at its maximum target level.
There was no benefit in water saving by increasing the rate of rise beyond
50 mm/day, because although the lake was at the maximum level for slightly longer,
this increase in duration occurred during August, which is a month of low evaporation.
Table 8. Estimated average annual water savings from First (Reedy) Lake for the Intermittent
regime using a range of maximum fill rates.
Scenario Mean annual savings (ML/yr)
10 mm/d 20 mm/d 50 mm/d 100 mm/d 1,000 mm/d
First (Reedy) Intermittent (1891-2009)
599 536 531 531 531
4.2.2 Date of beginning the filling phase
The default start of the filling phase was 1 August. This parameter was varied over
the range 1 July to 1 September (Table 9). All other parameter values were
maintained at their default values.
A later start date for filling had the effect of reducing the savings (Table 9), mainly
because this delayed the start of the draw down. Thus, the lake was full for a longer
period of time over the summer when evaporation rates are high.
Table 9. Estimated average annual water savings from First (Reedy) Lake for the Intermittent
regime using a range of filling start dates.
Scenario Mean annual savings (ML/yr)
1/July 1/August 1/September
First (Reedy) Intermittent (1891-2009) 597 531 488
4.2.3 Duration of the filling phase
The default filling cycle durations were successively, 10, 8 and 7 months. This
parameter was varied by reducing and increasing the duration by one month (Table
10). All other parameter values were maintained at their default values.
Increasing the duration of the fill reduced the savings, and decreasing the duration of
the fill increased the savings (Table 10). Increasing the fill duration meant that the
lake was full for a longer time through summer, when evaporation rates are high.
Decreasing the duration had the opposite effect.
Page 41
Table 10. Estimated average annual water savings from First (Reedy) Lake for the Intermittent
regime using a range of filling cycle durations.
Scenario Mean annual savings (ML/yr)
9, 7 and 6 months
10, 8 and 7 months
11, 9 and 8 months
First (Reedy) Intermittent (1891-2009) 601 531 474
4.3 Summary of variability of savings and model sensitivity
The sensitivity testing undertaken for Phase I of this hydrological investigation was
limited to one lake and one scenario. While the results (Table 11) are specific to that
case, some of the results can be generalised to the other four lakes and other
scenarios.
Table 11. Summary of sensitivity of long-term mean annual savings estimates to model
parameters, based on testing of First (Reedy) Lake Intermittent regime.
Parameter/factor Variability/sensitivity of savings
Natural climate variation over time High variability [±50% in annualised
saving from cycle to cycle; will affect
some scenarios more (±80%) and some
less (±25%)]
Evaporation estimate method Mod. sensitivity (25% lower for Pan
method than physical method; will affect
all scenarios to a variable degree)
Assumed wind speed relative to
assumed 2 m/s
Mod. sensitivity (19% lower for 1 m/s,
14% higher for 3 m/s, 26% higher for
4 m/s; will affect all scenarios)
Measured relative to assumed 2 m/s
wind speed
Mod. sensitivity (14% lower for 2 m/s; will
affect all scenarios)
Date of beginning filling Low – mod. sensitivity (±12%, but
depends on whether duration of being full
is fixed)
Duration of the filling phase for a given
regime type
Low – mod. sensitivity (±13%, but highly
scenario specific)
Groundwater exchange Low – mod. sensitivity (estimate - not
quantified)
Initial loss parameters Low sensitivity (±3%)
Maximum lake filling rate Low sensitivity (but could be moderate if
duration of being full is fixed)
Page 42
5 Conclusion
Preliminary hydrological (water balance) models were developed for five Kerang
Lakes. Even though the models were based on the best available understanding of
the hydrology of the lakes, there is uncertainty with input data and with a number of
model parameters. This uncertainty was explored by undertaking sensitivity analysis.
This revealed that the estimate of savings was quite sensitive to the method of
estimating evaporation, but it was not very sensitive to initial loss parameters.
The physical combination method of estimating evaporation from the lakes produced
estimates of mean annual net evapotranspiration that were 17% higher than the
method used by Lugg et al. (1989), 23% higher than the factored Pan method used
by SKM (2010), 26% higher than Morton’s method used by SKM (2010) and 51%
higher than the factored Pan method used in the Kerang Lakes REALM model. It is
not clear which method produces the most accurate estimate of evaporation, so it will
be necessary in Phase II of this hydrological investigation project to test the methods
against local measured lake level data.
As well as being sensitive to inherent model parameter values, the estimate of
savings was sensitive to the management regime parameter values. While it was
obvious that frequency of filling cycles would have a major impact on potential for
savings, other important variables were the date of the beginning of filling and the
duration of the filling cycle. The rate of filling had only a minor impact on the savings.
The estimates of savings made here are of the same order as those estimated in
previous investigations, but the estimates cannot be compared directly due to
differences in assumptions regarding operating regimes.
The total savings possible from alternative management of the Kerang Lakes varies
across a wide range, depending on how frequently, for how long, and how far the
lakes would be drawn down. It would be technically possible to devise a set of refined
management scenarios involving intermittent and episodic regimes that would
together achieve a long term average annual savings of at least 4 GL.
6 References
Catford, J., Downes, B., Gippel, C.J. and Vesk, P. 2011. Flow regulation reduces native plant cover and facilitates exotic invasion in riparian wetlands. Journal of Applied Ecology 48(2): 432-442. DOI: 10.1111/j.1365-2664.2010.01945.x.
Dooge, J.C.I. 1975. The water balance of bogs and fens. In Hydrology of Marsh-Ridden Areas, Proceedings of the Minsk Symposium, 1972, The UNESCO Press, Paris, pp. 233-271.
Duever, M.J. 1988. Hydrologic processes for models of freshwater wetlands. In Mitsch, W.J., Straskraba, M. and Jorgensen, S.E. (Eds) Wetland Modelling, Developments in Environmental Modelling, Vol. 12, Elsevier, Amsterdam, pp. 9-39.
DSE 2004. Kerang Wetlands Ramsar Site, Strategic Management Plan. Parks Victoria. The State of Victoria, Department of Sustainability and Environment, East Melbourne. URL: http://www.dse.vic.gov.au/__data/assets/pdf_file/0010/100135/Kerang_Wetlands_Ramsar_Site_Strategic_Management_Plan.pdf (accessed 9 September 2012).
Page 43
DSE 2010. Kerang Wetlands Ramsar Site, ecological character description. Arthur Rylah Institute for Environmental Research, Heidelberg. The State of Victoria, Department of Sustainability and Environment, East Melbourne.
Ecological Associates. 2008. Determination of environmental water requirements for Mosquito Creek Catchment and Bool and Hacks Lagoon. Final Report. South East Natural Resources Management Board, Mount Gambier, South Australia, August.
Gippel, C.J. 1993. Hydrological management of a lake with floating islands near Pirron Yallock, Victoria, Australia. Journal Environmental Management 37: 219-238, DOI: 10.1006/jema.1993.1018.
Gippel, C.J. 2005a. Operational procedure to calculate water recovery from wetlands and lakes at the source (individual wetlands). Fluvial Systems Pty Ltd, Stockton, NSW. The Living Murray, Murray-Darling Basin Commission, Canberra, Australian Capital Territory.
Gippel, C.J. 2005b. Model to calculate water recovery from wetlands and lakes at the source (individual wetlands) - Example application to Euston Lakes and Edward Gulpa wetlands. Fluvial Systems Pty Ltd, Stockton, NSW. The Living Murray, Murray-Darling Basin Commission, Canberra, Australian Capital Territory.
Gippel, C.J. 2005c. SWET (Savings at Wetlands from Evapotranspiration daily Time-Series). A model to calculate water recovery from wetlands and lakes at the source (individual wetlands). Model Manual. Fluvial Systems Pty Ltd, Stockton, NSW. The Living Murray, Murray-Darling Basin Commission, Canberra, Australian Capital Territory.
Gippel, C.J. 2010. Modeling the conjoint provision of ecological water requirements and generation of water savings at wetlands. Proceedings, ISE 2010 - the 8th International Symposium on ECOHYDRAULICS (ISE 2010), September 12-16, 2010, Seoul, South Korea, International Association for Hydraulic Engineering and Research (IAHR).
Gosselink, J.G. and Turner, R.E. 1978. The role of hydrology in freshwater wetland ecosystems. In Good, R.E., Whigham, D.F., Simpson, R.L. and Jackson, Jr, C.G. (Eds) Freshwater Wetlands: Ecological Processes and Management Potential, Proceedings of the Symposium on Freshwater Marshes: Present Status, Future Needs, February 1977, Rutgers University, New Brunswick, New Jersey. Academic Press, New York, pp. 63-78.
Hoy, R.D. and Stephens, S.K. 1979. Field study of lake evaporation – analysis of data from phase 2 storages and summary of phase 1 and phase 2. Australian Water Resources Council Technical Paper No. 41. Department of National Development, Australian Water Resources Council. Australian Government Publishing Service, Canberra, Australian Capital Territory.
LaBaugh, J.W. 1986. Wetland ecosystem studies from a hydrologic perspective. Water Resources Bulletin 22: 1-10, DOI: 10.1111/j.1752-1688.1986.tb01853.x.
Lugg, A., Heron, S., Fleming, G., and O’Donnell, T. 1989. Conservation value of the wetlands in the Kerang Lakes area, Report to Kerang Lakes Area Working Group, Department of Conservation Forests & Lands, Bendigo, October.
McJannet, D.L., Webster, I.T., Stenson, M.P. and Sherman, B.S. 2008. Estimating open water evaporation for the Murray Darling Basin. A report to the Australian Government from the CSIRO Murray-Darling Basin Sustainable Yields Project. CSIRO, Australia. 50pp.
Page 44
North Central CMA 2007. Loddon and Campaspe Irrigation Region, Land and Water Management Plan. The State of Victoria, North Central Catchment Management Authority, Huntley.
North Central CMA 2011. Kerang Lakes Water Savings Project Investigation: Literature Review. Prepared for the Northern Victoria Irrigation Renewal Project, North Central Catchment Management Authority, Huntly.
North Central CMA 2012. Environmental Watering Scenarios for Kerang Lakes Bypass Investigation Project – Phase 1. Prepared for the Goulburn-Murray Water Connections Project, North Central Catchment Management Authority, Huntly
NVIRP 2012. Kerang lakes bypass investigation project. Newsletter No. 1, May. Northern Victoria Irrigation Renewal Project.
RMCG 2009. TRAMS Update Final Report, prepared for NVIRP, RMCG, Bendigo, Victoria.
SKM 2007. Kerang Lakes REALM modelling for refinement of the MDBC BSMS register. Sinclair Knight Merz. Goulburn-Murray Water, Shepparton.
SKM 2010. Environmental water regime requirements of the Kerang Lakes. Review of system losses, identification of environmental water regimes, and potential water savings. Goulburn-Murray Water, March.
U.S. Army Corps of Engineers 1993. Wetland water surface processes. Wetlands Research Program (WRP) Technical Note HY-EV-2.1. U.S. Army Engineer Waterways Experiment Station, Vicksburg, MS, January.
Winter, T.C. 1981. Uncertainties in estimating the water balance of lakes. Water Resources Bulletin 17: 82-115, DOI: 10.1111/j.1752-1688.1981.tb02593.x.
Woo, M.K. and Rowsell, R.D. 1993. Hydrology of a prairie slough. Journal of Hydrology 146: 175-207, DOI: 10.1016/0022-1694(93)90275-E.
Page 45
7 Appendix – Bathymetry data
Area and volume table for First (Reedy) Lake.
Elevation (m AHD)
Area (ha)
Volume (ML)
Elevation (m AHD)
Area (ha)
Volume (ML)
72.69 0.00 0.00 74.20 189.03 1996.69
72.70 0.01 0.01 74.30 190.45 2186.43
72.80 1.44 0.36 74.40 191.83 2377.57
72.90 39.86 14.93 74.50 193.14 2570.06
73.00 85.85 79.07 74.60 194.40 2763.84
73.10 109.36 177.78 74.70 195.70 2958.87
73.20 128.93 297.17 74.80 197.14 3155.29
73.30 141.96 432.99 74.88 198.28 3313.48
73.40 152.27 580.09 74.90 198.55 3353.16
73.50 161.96 737.53 75.00 200.23 3552.46
73.60 169.53 903.46 75.10 203.69 3754.28
73.70 175.54 1076.03 75.20 206.64 3959.61
73.80 180.48 1254.11 75.30 208.28 4167.12
73.90 184.04 1436.55 75.40 209.77 4376.17
74.00 185.99 1621.60 75.50 210.79 4586.51
74.10 187.56 1808.39
Page 46
Area and volume table for Middle (Reedy) Lake.
Elevation (m AHD)
Area (ha)
Volume (ML)
Elevation (mAHD)
Area (ha)
Volume (ML)
71.77 0.000 0.000 73.40 112.1 302.85
71.80 0.001 0.000 73.45 115.8 359.84
71.85 0.003 0.001 73.50 119.1 418.59
71.90 0.007 0.004 73.55 121.9 478.84
71.95 0.01 0.01 73.60 124.5 540.44
72.00 0.04 0.02 73.65 126.9 603.31
72.05 0.1 0.04 73.70 129.1 667.34
72.10 0.1 0.08 73.75 131.1 732.40
72.15 0.1 0.13 73.80 133.1 798.45
72.20 0.1 0.20 73.85 135.1 865.49
72.25 0.2 0.27 73.90 137.1 933.52
72.30 0.2 0.37 73.95 139.1 1002.55
72.35 0.2 0.48 74.00 141.2 1072.62
72.40 0.3 0.61 74.05 143.7 1143.80
72.45 0.3 0.75 74.10 147.9 1216.66
72.50 0.3 0.92 74.15 152.3 1291.66
72.55 0.4 1.10 74.20 159.9 1369.53
72.60 0.4 1.30 74.25 169.3 1451.06
72.65 0.5 1.52 74.30 175.5 1537.30
72.70 0.5 1.76 74.35 178.8 1626.03
72.75 0.5 2.02 74.40 180.6 1715.89
72.80 0.6 2.30 74.45 181.7 1806.49
72.85 1.0 2.68 74.50 182.5 1897.56
72.90 2.0 3.40 74.55 183.3 1989.02
72.95 5.1 4.96 74.60 184.1 2080.87
73.00 15.3 9.66 74.65 184.8 2173.09
73.05 30.1 20.88 74.70 186.5 2265.87
73.10 48.1 40.04 74.75 188.7 2359.69
73.15 66.4 68.82 74.80 191.1 2454.66
73.20 79.8 105.56 74.85 193.4 2550.80
73.25 91.3 148.35 74.90 195.4 2648.01
73.30 99.8 196.29 74.95 197.0 2746.13
73.35 107.1 247.97
Page 47
Area and volume table for Third (Reedy) Lake.
Elevation (m AHD)
Area (ha)
Volume (ML)
Elevation (m AHD)
Area (ha)
Volume (ML)
72.89 0.00 0.00 74.30 221.63 1872.03
72.90 0.02 0.01 74.40 224.86 2095.28
73.00 0.05 0.04 74.50 228.10 2321.76
73.10 0.12 0.12 74.56 230.13 2459.23
73.20 11.11 2.67 74.60 231.50 2551.56
73.30 76.53 38.61 74.70 233.67 2784.18
73.40 124.59 135.01 74.80 235.63 3018.84
73.50 152.59 272.63 74.90 237.51 3255.41
73.60 174.32 435.64 75.00 239.21 3493.79
73.70 187.41 616.31 75.10 240.67 3733.75
73.80 199.02 809.59 75.20 241.97 3975.08
73.90 206.59 1012.64 75.30 243.17 4217.65
74.00 211.51 1221.77 75.40 244.29 4461.39
74.10 215.21 1435.18 75.50 245.35 4706.21
74.20 218.42 1652.00
Area and volume table for Little Lake Charm.
Elevation (m AHD)
Area (ha)
Volume (ML)
Elevation (m AHD)
Area (ha)
Volume (ML)
72.25 0.00 0.00 73.40 77.88 520.73
72.30 0.47 0.08 73.45 81.36 560.52
72.35 2.10 0.63 73.50 84.88 602.08
72.40 7.08 2.79 73.55 88.73 645.44
72.45 16.01 8.44 73.60 93.91 691.10
72.50 24.21 18.77 73.65 98.54 739.22
72.55 29.86 32.30 73.70 103.21 789.64
72.60 34.88 48.52 73.75 112.24 843.52
72.65 39.17 67.08 73.80 119.94 901.66
72.70 42.91 87.59 73.85 125.73 963.11
72.75 46.69 110.00 73.90 130.79 1027.25
72.80 50.34 134.27 73.95 136.05 1093.97
72.85 53.15 160.19 74.00 141.55 1163.35
72.90 55.23 187.30 74.05 147.32 1235.56
72.95 57.35 215.42 74.10 153.35 1310.97
73.00 60.79 245.02 74.15 156.73 1388.52
73.05 63.09 276.03 74.20 159.43 1467.59
73.10 65.60 308.30 74.25 161.46 1547.84
73.15 67.16 341.48 74.30 162.84 1628.95
73.20 68.87 375.48 74.35 163.82 1710.62
73.25 70.49 410.34 74.40 164.62 1792.73
73.30 72.19 446.00 74.45 165.31 1875.21
73.35 74.45 482.61
Page 48
Area and volume table for Racecourse Lake.
Elevation (m AHD)
Area (ha)
Volume (ML)
Elevation (m AHD)
Area (ha)
Volume (ML)
71.20 0.00 0.00 73.50 227.50 3680.59
71.30 5.28 1.14 73.60 230.63 3909.73
71.40 46.73 26.73 73.70 233.88 4141.84
71.50 81.54 91.92 73.80 236.33 4376.94
71.60 103.04 185.23 73.90 238.73 4614.48
71.70 123.02 297.07 73.93 239.65 4686.25
71.80 139.24 428.60 74.00 241.26 4854.60
71.90 149.90 573.43 74.10 243.00 5096.68
72.00 157.14 727.09 74.20 244.28 5340.33
72.10 163.90 887.61 74.30 245.50 5585.22
72.20 169.54 1054.34 74.40 246.68 5831.34
72.30 175.13 1226.69 74.50 247.76 6078.57
72.40 180.17 1404.36 74.60 248.82 6326.88
72.50 185.17 1587.03 74.70 249.81 6576.19
72.60 190.50 1775.17 74.80 250.73 6826.46
72.70 196.11 1968.25 74.90 251.58 7077.62
72.80 201.66 2167.07 75.00 252.56 7329.75
72.90 207.04 2371.54 75.10 253.26 7582.67
73.00 211.35 2580.79 75.20 253.83 7836.22
73.10 215.72 2794.08 75.30 254.33 8090.31
73.20 218.66 3011.32 75.40 254.75 8344.85
73.30 221.45 3231.38 75.50 255.14 8599.80
73.40 224.60 3454.55