Upload
remya-r-kumar
View
215
Download
0
Embed Size (px)
Citation preview
8/13/2019 Precast concrete.docx
http://slidepdf.com/reader/full/precast-concretedocx 1/22
recast concrete is a construction product produced by casting concrete in a
reusable mold or "form" which is then cured in a controlled environment, transported to
the construction site and lifted into place. In contrast, standard concrete is poured into
site-specific forms and cured on site. recast stone is distinguished from precast
concrete by using a fine aggregate in the mixture, so the final product approaches the
appearance of naturally occurring rock or stone.
By producing precast concrete in a controlled environment (typically referred to as a
precast plant), the precast concrete is afforded the opportunity to properly cure and
be closely monitored by plant employees. Utilizing a Precast Concrete system offers
many potential advantages over site casting of concrete. The production process for
Precast Concrete is performed on ground level, which helps with safety throughout a
project. There is a greater control of the quality of materials and workmanship in a
precast plant rather than on a construction site. Financially, the forms used in aprecast plant may be reused hundreds to thousands of times before they have to be
replaced, which allows cost of formwork per unit to be lower than for site-cast
production .[1]
Prefabrication is the practice of assembling components of a structure in a factory or
other manufacturing site, and transporting complete assemblies or sub-assemblies to
theconstruction site where the structure is to be located. The term is used to distinguish this
process from the more conventional construction practice of transporting the basic materials tothe construction site where all assembly is carried out.
The term prefabrication also applies to the manufacturing of things other than structures at a
fixed site. It is frequently used when fabrication of a section of a machine or any movable
structure is shifted from the main manufacturing site to another location, and the section is
supplied assembled and ready to fit. It is not generally used to refer to electrical or electronic
components of a machine, or mechanical parts such as pumps, gearboxes and compressors
which are usually supplied as separate items, but to sections of the body of the machine which
in the past were fabricated with the whole machine. Prefabricated parts of the body of the
machine may be called 'sub-assemblies' to distinguish them from the other components.Contents
[hide]
1 The process and theory of prefabrication
2 History
8/13/2019 Precast concrete.docx
http://slidepdf.com/reader/full/precast-concretedocx 2/22
3 Current uses
4 Advantages of prefabrication
5 Disadvantages
6 Off-site fabrication
7 See also
8 External links
The process and theory of prefabrication[edit]
An example from house-building illustrates the process of prefabrication. The conventional
method of building a house is to transport bricks, timber , cement, sand, steel andconstruction
aggregate, etc. to the site, and to construct the house on site from these materials.
In prefabricated construction, only the foundations are constructed in this way, while sections
of walls, floors and roof are prefabricated (assembled) in a factory (possibly with window and
door frames included), transported to the site, lifted into place by a craneand bolted together.
Prefabrication is used in the manufacture of ships, aircraft and all kinds
of vehicles and machines where sections previously assembled at the final point of manufacture
are assembled elsewhere instead, before being delivered for final assembly.
The theory behind the method is that time and cost is saved if similar construction tasks can be
grouped, and assembly line techniques can be employed in prefabrication at a location where
skilled labour is available, while congestion at the assembly site, which wastes time, can be
reduced. The method finds application particularly where the structure is composed of repeating
units or forms, or where multiple copies of the same basic structure are being constructed.
Prefabrication avoids the need to transport so many skilled workers to the construction site, and
other restricting conditions such as a lack of power, lack of water, exposure to harsh weather or
a hazardous environment are avoided. Against these advantages must be weighed the cost of
transporting prefabricated sections and lifting them into position as they will usually be larger,
more fragile and more difficult to handle than the materials and components of which they are
made.
History[edit]
8/13/2019 Precast concrete.docx
http://slidepdf.com/reader/full/precast-concretedocx 3/22
"Loren" Iron House, at Old Gippstown inMoe, Australia
Prefabrication has been used since ancient times. For example, it is claimed that the world's
oldest known engineered roadway, theSweet Track constructed in England around 3800 BC,
employed prefabricated timber sections brought to the site rather than assembled on-site.[citation
needed ]
Sinhalese kings of ancient Sri Lanka have used prefabricated buildings technology to erect giant
structures, which dates back as far as 2000 years, where some sections were prepared
separately and then fitted together, specially in the Kingdom of Anuradhapura and Kingdom
of Polonnaruwa
In 19th century Australia a large number of prefabricated houses were imported from the United
Kingdom.
The method was widely used in the construction of prefabricated housing in the 20th century,
such as in the United Kingdom to replace houses bombed during World War II. Assembling
sections in factories saved time on-site and reduced cost. However the quality was low, and
when such prefabricated housing was left in use for longer than its designed life, it acquired a
certain stigma.[citation needed ].
The Crystal Palace, erected in London in 1851, was a highly visible example of iron and glassprefabricated construction; it was followed on a smaller scale by Oxford Rewley Road railway
station.
Current uses[edit]
8/13/2019 Precast concrete.docx
http://slidepdf.com/reader/full/precast-concretedocx 4/22
A house being built with prefabricated concrete panels.
The most widely-used form of prefabrication in building and civil engineering is the use of
prefabricated concrete and prefabricated steelsections in structures where a particular part or
form is repeated many times. It can be difficult to construct the formwork required
tomould concrete components on site, and delivering wet concrete to the site before it starts to
set requires precise time management. Pouring concrete sections in a factory brings the
advantages of being able to re-use moulds and the concrete can be mixed on the spot without
having to be transported to and pumped wet on a congested construction site. Prefabricating
steel sections reduces on-site cutting and welding costs as well as the associated hazards.
Prefabrication techniques are used in the construction of apartment blocks, and housing
developments with repeated housing units. The quality of prefabricated housing units had
increased to the point that they may not be distinguishable from traditionally-built units to those
that live in them. The technique is also used in office blocks, warehouses and factory buildings.
Prefabricated steel and glass sections are widely used for the exterior of large buildings.
Detached houses, cottages, log cabin, saunas, etc. are also sold with prefabricated elements.
Prefabrication of modular wall elements allows building of complex thermal insulation, window
frame components, etc. on an assembly line, which tends to improve quality over on-site
construction of each individual wall or frame. Wood construction in particular benefits from the
improved quality. However, tradition often favors building by hand in many countries, and the
image of prefab as a "cheap" method only slows its adoption. However, current practice alreadyallows the modifying the floor plan according to the customer's requirements and selecting the
surfacing material, e.g. a personalized brick facade can be masoned even if the load-supporting
elements are timber.
Prefabrication saves engineering time on the construction site in civil engineering projects. This
can be vital to the success of projects such as bridges and avalanche galleries, where weather
conditions may only allow brief periods of construction. Prefabricated bridge elements and
8/13/2019 Precast concrete.docx
http://slidepdf.com/reader/full/precast-concretedocx 5/22
8/13/2019 Precast concrete.docx
http://slidepdf.com/reader/full/precast-concretedocx 6/22
5. Local jobs may be lost, if the work done to fabricate the components being located in a
place far away from the place of construction. This means that there are less locals
working on any construction project at any time, because fabrication is outsourced.
Off-site fabrication[edit]
Off-Site fabrication is a process that incorporates prefabrication and pre-assembly. The process
involves the design and manufacture of units or modules, usually remote from the work site, and
the installation at the site to form the permanent works at the site. In its fullest sense, off-site
fabrication requires a project strategy that will change the orientation of the project process
from construction to manufacture to installation. Examples of off-site fabrication are wall panels
for homes, wooden truss bridge spans, airport control stations.
Dr. Abhay Gupta, Vice President (Engineering) Era Building Systems Ltd. Noida
PEB: A New Technological Wave
Technological improvement over the year has contributed immensely to the enhancement of
quality of life through various new products and services. One such revolution was the pre–
engineered buildings. Though its origin can be traced back to 1960's, its potential has been
felt only during the recent years.
An estimated 70% of all new commercial buildings in the US are pre-engineered! There is
really no dispute in the fact that pre-engineered building systems are the new wave in
construction.
Definition
"Pre-engineered steel buildings" are those which are fully fabricated in the factory after
designing, shipped to site in CKD(completely knocked down) condition; and all components
are assembled and erected at site with nut-bolts, thereby reducing the time of completion.
Pre–engineered means, generally speaking, is any part of a structure that is manufactured
prior to its arrival on the building site. The concept of the pre-engineered building (PEB) is
one where the fabrication is completed in a controlled environment with the latest
technology, and then subsequent erection is carried out.
Though initially only off the shelf products were available in these configurations aided by
the technological development tailor made solutions are also made using this technology in
very short durations.
8/13/2019 Precast concrete.docx
http://slidepdf.com/reader/full/precast-concretedocx 7/22
The designs were ready-made but the building components were either ready-made or
manufactured against specific orders. These buildings were pre-designed or 'pre-engineered'
into standard sizes, spans, bays and heights, and use standard details for fixing cladding,
roofing, gutters, flashing, windows, doors etc taking advantage of industrial practices of
mass production of components economically.
Although PEB systems are extensively used in industrial and many other nonresidential
constructions worldwide, it is relatively a new concept in India. These concepts were
introduced to the Indian markets in the late 1990's with the opening up of the economy;
and a number of multi–nationals setting up their projects. The current pre–engineered steel
building manufacturing capacity is 6.0 lac ton per annum. The industry is growing at the
compound rate of 25 to 30%.
With respect to design of the structure and aesthetic appearance India is way behind. Indian
manufacturers are trying to catch up; comparatively PEB is a new concept in India.
A healthy trend in the form of growth in demand for construction works in residential,
Commercial, Institutional industrual and infrastructure sectors are being seen over the past
decade. Modern Structures are much more complex and sophisticated as compared to
earlier period. One of the major changes which are being felt by all is that the present
structures are taller and thinner. Modern day requirement of structures is that these should
be lighter yet not compromising on functionality. Civil engineering construction has seen a
continual economic competition between steel, concrete and other construction materials.
Currently, the total steel production in the country is about 45Mn Ton against 1280Mn ton of
world. Per capita steel consumption in India is 42kg whereas it is 270kg in China. About
10% of steel goes to the construction industry and amidst it PEB accounts only for the0.5Mn ton. As on date. In the next 5 years, the steel production will be doubled and with
efforts of organisations like BIS and INSDAG, steel intensive construction may rise up to
22Mn ton. Owing to advantages of PEB, several non-conventional segments are also getting
attracted to use PEB and the potential will rise up to 2.2Mn ton which is four to five times of
today's scenario.
Subsequent paragraphs are only a humble attempt to present the various aspects of
conceptual development, technology of design and manufacture; and future growth aspects
of Pre–engineered building Industry in India along with its grey areas.
he Concept: Superiority of PEB over Conventional Construction
Pre–engineered steel buildings use a combination of built-up sections, hot rolled sections
and cold formed elements which provide the basic steel frame work with a choice of singleskin sheeting with added insulation or insulated sandwich panels for roofing and wall
cladding. The concept is designed to provide a complete building envelope system which is
air tight, energy efficient, optimum in weight and cost and, above all, designed to fit userrequirement like a well fitted glove.
8/13/2019 Precast concrete.docx
http://slidepdf.com/reader/full/precast-concretedocx 8/22
These Pre–engineered Steel Buildings can be fitted with different structural accessories
including mezzanine floors, canopies, fascias, interior partitions, crane systems etc. The
building is made water-tight by use of special mastic beads, filler strips and trims. This is a
very versatile building system and can be finished internally to serve any required function
and accessorized externally to achieve attractive and distinctive architectural styles. It ismost suitable for any low-rise building and offers numerous benefits over conventional
buildings.
It is very advantageous over the conventional buildings and is really useful in case of the
low rise buildings. Pre-engineered buildings are generally low rise buildings; however the
maximum eave heights can go up to 25 to 30 meters. Low rise buildings are ideal for
offices, houses, showrooms, shop fronts etc. The application of pre-engineered concept to
low rise buildings is very economical and speedy. Buildings can be constructed in less than
half the normal time especially when complimented with other engineered sub-systems.
Table-1 presents an overview of comparison between RCC, Conventional steel and PEB
structures.
Advantages
8/13/2019 Precast concrete.docx
http://slidepdf.com/reader/full/precast-concretedocx 9/22
Pre-engineered building systems provide real value to clients without sacrificing durability,seismic and wind resistance, or aesthetic appearance. Cost savings begin right at the
drawing preparation stage. Systems engineering and fabrication methods help reduce
interim financing costs through faster construction and minimised field erection expense. Anadded benefit is earlier occupancy of the facility and a head start on day-to-day operations
by the client.
Apart from costs, there is an assurance of factory-built quality and uniformity in design and
fabrication. These systems are also energy efficient; incorporate watertight roofing systems;enable easy disassembly or future expansion and have the lowest life cycle maintenance
costs.
Adding to these; there is no mess of sand and cement; power savings; walkable ceilings;
progressive and non-progressive panel systems for walls. A poor man can be provided witha home created under strict quality control and having a longer life span, with greater safety
against natural disasters like earthquakes and cyclones.
8/13/2019 Precast concrete.docx
http://slidepdf.com/reader/full/precast-concretedocx 10/22
Moreover, It is possible to create the building in required form and shape. And the 'system
approach' renders a holistic way of thinking at one platform for consultants, designers,
architects, and builders. Thus it tends to achieve a perfect harmony among variousstringent specifications and aesthetic requirements in a most economic way.
In nutshell, the benefits may be summarized as under: Increased speed of construction, quicker return on investment
Ensured quality of material, Design and construction
Unlimited architectural possibilities
Enhanced Durability and seismic reliability
Easy construction, maintenance and refurbishing
Increased Life cycle performance and cost competitiveness
Environment–friendly structures
Better value for money
Cleaner and unencumbered sites
Sustainability in construction through reuse of most materials
Suitability for Hilly regions and other geographically difficult areas Hassle Free
Optimized design of steel reducing weight
Better Earthquake & Wind pressure resistant.
Energy efficient roof and wall system using insulations.
Easy integration of all construction materials
The building can be dismantled and relocated easily.
Future extensions, expansion modification can be easily accommodated without
much hassle.
Faster delivery and erection, saving around 30-40% of project time
Column-free large spans, up to 90 m.
Virtually maintenance free
Single-source responsibility
'Systems approach' ensures integrity and safety of all building components
Lighter weight; savings in foundation cost of 10-20 percent
Insulated from sound and heat, as per the requirement
Better rainwater harvesting through gutters and down-take arrangements
Overall economy
Diversified Applications
8/13/2019 Precast concrete.docx
http://slidepdf.com/reader/full/precast-concretedocx 11/22
Almost every conceivable building use has been achieved with PEB; the most common
applications are industrial, institutional and commercial.
In India, Pre-engineered building systems find application primarily in the construction of
Warehouses, & Industrial sheds & Buildings. The recent focus has also shifted to cover Rural
as well as urban, individual and mass housing projects, farmhouses, slum re-organisationprojects and rehabilitation projects, amenity structures like health centres, kiosks, primary
schools, panchayat ghars etc. The pharmaceutical industries and exhibition centres, andfunctional requirements like offices, seminar halls, call centres, supermarkets, showrooms
etc. have also attracted PEB. Earthquake-resistant buildings are the recent applications of
PEB with wide and immediate acceptance.
PEB concept has acted as a catalyst in the infrastructure development of the country. Singlestoried houses for living take minimum time for construction and can be built in any type ofgeographic location like extreme cold hilly areas, high rain prone areas, plain land, extremehot climatic zones etc.
Applications of pre-engineered steel buildings include (but are not limited to) the following: Industrial Buildings & Workshops
8/13/2019 Precast concrete.docx
http://slidepdf.com/reader/full/precast-concretedocx 12/22
Warehouses
Commercial Complexes & Supermarkets
Showrooms
Corporate Office Buildings
Schools
Indoor Stadiums
Outdoor Stadiums with canopies
Fuel Stations
Metro Stations, Bus Terminals, Parking Lots
Highrise Buildings
Customized Housing
Large Exhibition Centers
And many more…
Aircraft Hangers
Labor Camps
Community Centers
Railway Stations & Railway Storage yards
Equipment housing/shelters Telecommunication shelters
"Almost" any low-rise building
There is a great possibility of improving the aesthetic quality with a choice of roofingelements, exterior finishes, weather-sheds, color system and variations in planning as well
as massing. Main Components
There are following major components in a pre-engineered building: Primary or Main frame
Gable End framing or Wind columns
Secondary frame or Purlins, girts etc.
Roof & Wall Sheeting
Bracing system
Crane system
Mezzanine system
Insulations
Attachments like canopies, fascia etc
Doors, Windows, Ventilators
Accessories like Turbo vents, Ridge Vents, Skylights etc.
Main Framing
8/13/2019 Precast concrete.docx
http://slidepdf.com/reader/full/precast-concretedocx 13/22
Main framing basically includes the rigid steel frames of the building. The PEB rigid framecomprises tapered/straight columns and tapered rafters (steel plate fabricated 'I' or 'H'
sections are referred to as built-up members). The frame is erected by bolting the end
plates of connecting sections together.
Secondary frame or Purlins, girts etc.
Purlins, girts and eave struts are also known as secondary cold-formed members. There is
no welding involved in their preparation. They are prepared by press bending the HR steel
coil giving it the desired shape(Z- or C-shape).
Roof & Wall Panels
Metallic plain or color coated profiled steel sheets are used as roof and wall sheeting. The
steel sheets are generally made from Zincalume or Galvalume coils in thickness range of0.47mm to 0.55mm. The base steel is either galvanized having a zinc coating varying from
a minimum Mass of 120 gsm./m2 to a maximum of 275 gsm./m
2 (total of both sides) or a
base steel coating of zinc – aluminum (zinc 45%, aluminum 55%) of total Mass of 150
gsm./m2 (total of both sides) are available with permanent color coating. The color coating
is also available in various options in polyester paint coating like regular modified polyester,silicon modified polyester and super polyester coatings. Special organic coatings like PVF2
(Poly Vinyl Fluoride) are also made available. These various color coatings on the base steelwith galvanized or zinc aluminum coating provides suitable resistance for various kinds of
environment hazards. Metal roofing and siding profiles can be manufactured to any length – limited only by transportation constraints (usually to 12 meters). Lap joints with 150mm to
200mm overlap virtually eliminate water ingress.
Profiling can be carried out at site itself with no limit in lengths. This permits a totally joint-less run of roofing, a major advantage to the designers to create roofing with the minimum
pitch. Machines have been developed which permit rolling at the eaves level so that even
the task of lifting and shifting the rolled profiles in to position is avoided. Standing seamprofiles with a pre-determined height of up-stands can be chosen to accommodate the
expected run-off of water without overflow on to the crest of the profile.
At the initial project planning stage, roof slope is a key consideration for architectsincorporating roof systems into their designs. Slopes as shallow as 1:20 are possible
ensuring sufficient drainage of water and good long term performance of roof panels.
These profile steel sheets are usually categorized into two types depending upon the type offixing arrangement followed. These two types are known as Through Fastened and second
one is Standing Seam.
Installation of this type of roofing & cladding system can provide 30 years or more of
8/13/2019 Precast concrete.docx
http://slidepdf.com/reader/full/precast-concretedocx 14/22
trouble-free service in most environments.
Insulations
These buildings can be properly insulated by providing fibrous insulation slabs/rolls of non-combustible Rockwool, Aluminum foil laminated, placed over a metal mesh bed created
between the purlins, and then the roofing steel sheet fixed over it. The siding walls can alsobe insulated by providing a double skin profile steel sheet wall cladding having RockwoolInsulation slab sandwiched in between and held in position with the help of 'Z' spacers in
between the two profile steel sheets. In similar pattern a double skin insulated roofingsystem can also be erected.
Sandwich Panels
Another alternative is to provide pre-fabricated insulated panels, which comprises two singleskin panels (plain steel sheets zincalume color coated) with polyurethane foam insulation inbetween. These panels are intended for use as thermally efficient roof and wall claddings for
buildings e.g., in high altitude areas and cold storages. In addition to the above sandwichpanels also find extensive use in residential as well as non-residential buildings. The panels
provide sufficient insulation and noise reduction properties. Nowadays large cold storageunits (Potato, Onion, vegetables, processed foods etc.) are also made with this pre-
engineered building technique.
Crane systems
These pre–engineered buildings can be equipped with Overhead EOT cranes, Semi-gantry
cranes, wall mounted cranes, Mono rails and under slung cranes for various material and
equipment handling operations inside. These buildings are being designed for crane
8/13/2019 Precast concrete.docx
http://slidepdf.com/reader/full/precast-concretedocx 15/22
capacities ranging from 1MT to 250MT. The crane runway beams (Gantry Girders) are
simply supported built-up sections with/without cap channels and with maintenance
platforms and ladders. Catwalks for crane maintenance are usually mounted alongside thecrane beams, suspended under rigid frame rafters or elevated above the top of the building
roof. Cranes at various levels can also be provided. PEB vendors generally do not keep thesupply of rail and Crane Bridge with crane in their scope.
Mezzanine systems
Standard mezzanine structure consists of built-up beams that support built-up, hot-rolled orcold-formed mezzanine joists which in-turn support a metal deck. A concrete slab is cast on
the metal deck as a finished surface. Steel checkered plates may also be used as topsurface. These mezzanines are used for office space, storage or equipment supports in
industries. For commercial buildings and highrise structures several types of light weight
panel boards are available as horizontal surface.
Bracing system
Longitudinal cross bracing, used to provide lateral stability to the structure against wind,seismic or other forces, comprises of rods, pipes, angles or cables with an eye bolt and an
adjusting nut at both ends, located near the outer flange of columns or rafters and attachedat the web of the rigid frame.
Paints and finishes
Any desired finish can be achieved as per the architect/client recommendations. Various
choices are synthetic enamel or epoxy based paints, depending upon the environment insideand outside the building.
Accessories, Attachments etc.
As per the functional and architectural requirements, accessories are supplied in ready to fit
condition. Ventilation and lighting systems should be properly designed in consultation with
an expert. High Strength Materials
The standard mild steel used in civil engineering construction have nominal yield stress
values of approximately 250MPa but the PEB industry is using high tensile hot rolled steelplates and coils of 345MPa. Recent revision of IS2062:2006 has incorporated these hightensile grades of steel for structural uses and there are a good number of manufacturers
like TATA, SAIL, etc. who are manufacturing these in India. The new materials like Fe540B
gives yield stress as large as 410MPa in plate thickness lower than 20mm. the galvalume orzincalume roofing and wall sheets have strengths in the range of 550MPa. Steel became
more popular in design and construction of larger structures as well structures with unusual
geometry due to its large strength to weight ratio, viability of economical fabrication, andease of erection.
A typical sample of material specs for a PEB project, as defined and freezed in advance is
enclosed for ready reference. This indicates that the client is assured of the quality ofmaterial that is being supplied.
8/13/2019 Precast concrete.docx
http://slidepdf.com/reader/full/precast-concretedocx 16/22
The design Process & Principles
Pre-engineering of metal buildings can be optimized to meet specific design criteria. LargelyIndian and American practice of design is followed by most of the consultants and PEBvendors in India these days. A brief of design codes used in each of these is attached
herewith:
PEB Design Process in Brief
The Load calculations are done as in the case of a regular frame. Normally, the critical casegoverning the designs would be (DL+WL) or (DL+LL) conditions as the PEB slopes are minor(like 1 in 10). The support conditions are normally hinged, but it is some times beneficial,
on a selective basis to use a fixed condition giving a gussetted base plate and Anchor boltcombination. In Hinged base condition, the section is normally tapered down and providedwith a Bolted connection to the base. All the other Joints would be normally designed as
rigid joints and steel connections are moment connections, transferring the axial, momentand shear values between the sections connected. In the Wind load calculations, the designwind pressures should be arrived at after a careful analysis and combinations of internal and
external pressure coefficients or force coefficients, referring to IS-875 pt.3 latest version.
Proper load combinations with Wind, Earthquake and Crane loads should be investigated.
Any standard structural analysis and design software can be employed for PEB designs, like
STAAD etc. However, couple of good dedicated software is also available for PEB like MBS,Precision Plus etc. Since detailing and connectivity of various components is much moreimportant, owing to CKD nature, it is good to use a high end detailing software that also has
a BIM capability, like TEKLA Structures, which provides a complete integration of complete
analysis, design, detailing, Bill of material preparation and production/dispatch/erectionplanning.
Usually, Checking the Combination Stresses and comparing with the limiting values (in LSD
or WSD) is done using interactive software, which calculates the Exploitation efficiency of
the section, i.e., if the Actual Stress/permitted stress is 0.95, it means that the section isexploited for 95% of its strength. For this, the total weight of the frame is calculated. A no.
of trails are done such that sections are designed with Variables like Flange thk, Web thk,Flange Width, Web Depth, so that the Entire frame becomes theoretically safe, and is of
minimum wt! Checking for defections is the next step. Many times sections need to berevised to hold the theoretical maximum deflections within the permissible ones. Some
Vendors exploit 90% of the section, leaving 10% for probable lapses in manufacturing,transporting, assembling & erection. But the competition has made (forced) people believe
that there are no lapses anywhere! The Next important step is to design the welds between
the flanges and Webs. Here too, Efficiency of the weld plays an important part. Hence, PEBmanufacturer will avoid any weld at the site, because a 4.5 mm weld at the shop may be
better than 6 or 8 mm weld at the site.
Next step is to design the Field joints (Where the parts are assembled at the site). Theresultant forces are known at the joints; design a bolted connection, preferablyperpendicular to the plane of frame, to exploit tensile capacity of bolts for BMs rather thanthe shear capacities. Hence, Number of bolts required for the connection will reduce. These
joints are also placed at Optimum locations! That is the advantage of pre engineering.
The secondary members like Purlins and Girts are designed as per codes for thin Cold
Formed Sections, with or without lip. One can use many span reducing and Lateral
8/13/2019 Precast concrete.docx
http://slidepdf.com/reader/full/precast-concretedocx 17/22
8/13/2019 Precast concrete.docx
http://slidepdf.com/reader/full/precast-concretedocx 18/22
High Engineering Production/Erection Process
The PEB production process primarily consists of FOUR major parallel processing lines, asunder:
1. Built-up members for Primary frame
2. Cold forming for Secondary framing3. Profiling for Roof and Wall sheeting
4. Accessories & Bracings like Gutters, down take pipes, ridge Vents, Skylights, clips
etc.
The flow chart in image explains the parallel processing and then after final inspection,ready for shipment in CKD conditions.
The production & shipment of these components for a PEB structure uses followingprocesses:
1. Plate cutting using Shear/Plasma/Multi-torch through nesting software for optimized
use of plate area.2. H-beam welding on automatic welding machines using SAW or MIG welding process
3. Fabrication for fitments like end plates, stiffeners and connections cleats.
4. Cleaning the surface for painting
5. Slitting HR coils for cold forming operations to make Z and C sections with punching
6. Cutting and threading sag rods and bracing rods
7. Fabrication of Diagonal bracing angles or pipes
8. Profiling the Galvalume/Zincalume sheets for roofing and wall cladding
9. Manufacturing Gutters, down take pipes in press bend
10. Procuring and assigning required matching fasteners for connections
11. Organizing some bought out accessories
12. Quality control tests & inspection; and matching with project wise Bill of Quantitiesas given by the engineering department.
13. Dispatching to project sites as per sequence of erection
Erection
Steel framing members are delivered at site in pre-cut sizes, which eliminates cutting andwelding at site. Being lighter in weight, the small members can be very easily assembled,
bolted and raised with the help of cranes. This system allows very fast construction and
reduces wastage and labour requirement. These buildings can then be provided with roofdecking and wall cladding with metal profile sheets and proper insulation. The framing are
so designed that electrical and plumbing services are part of it and can be very easily
concealed.
However, the erection process is highly technical and needs skilled and trained manpower to
handle heavy construction equipments. Proper training of erection engineers for
understanding of drawings and execution of work is necessary. A qualified and experiencedwork agency should be employed for erection work. Grey Areas: Points of Concern: What Glitters is not always GOLD…????
8/13/2019 Precast concrete.docx
http://slidepdf.com/reader/full/precast-concretedocx 19/22
The evolution of the application of steel in civil engineering practice gives rise to many
issues from the point of view of engineering design, research and development of steel
structures.
Issues of Concern
Fire protection
Although great advances have been made in lighter and more economical fire
protection systems but fire protection remains an issue of greater concern for steel
structures than compared to concrete or other construction materials. The smaller
members and thermal mass associated with steel structures makes it more
vulnerable. The memories of collapse of world trade centre towers in USA due to fire
caused by burning of aviation fuel and sudden rise of temperature leading to
complete destruction of structure might not have faded away. Fire protection adds
up to larger part of structural cost. It would be a challenge to engineers toward
reducing these costs, while assuring adequate resistance to elevated temperatures
expected during a fire.
BucklingBuckling and stability become more critical in Steel structures due to smaller
members and large stress levels.
Micro Cracks
The increasing yield stress, operating stress levels, emphasis on plastic and ultimate
capacity, and use of welded construction have resulted in increased frequency of
initiation of micro cracks and cause of fracture in bridges and industrial structures.
Further development of Micro Cracks and crack growth become a major concern in
areas of seismically vulnerable areas.
Corrosion
Steel has great tendency to corrode when exposed to the environment, which leads
to deterioration, increased maintenance costs, and increased reconstruction costs.
Although Galvanization, paint, and coatings may provide protection against
corrosion, yet they increase the overall fabrication costs of the steel structure
appreciably. In hot and humid regions and industrially polluted severe environments
problem is more pronounced. Therefore, engineers have to continually seek
economically viable solutions to aim at reducing these costs.
Welding
Presently welded constructions are more commonly used, for these provide stiffer,
stronger structures with reduced building weight. Increased steel yield strength
requires new innovative welding methods, because high strength steels pose more
difficulty to weld without affecting adversely the ductility and performance of the
structural system. Recently the use of fully automatic and semi-automatic
submerged arc welding results in increase in welding speed apart from the goodquality. The elimination of any fumes, smoke or any visible arc column gives an ease
of operation and efficiency; better quality & thus encourages its application in
welding industry.
Ductility from seismic considerations
Seismic design is today a must requirement for almost all civil engineering
structures. Although steel is an ideally more suited material from point of view of
seismic design because of its property inherent material strength, stiffness, and
8/13/2019 Precast concrete.docx
http://slidepdf.com/reader/full/precast-concretedocx 20/22
ductility. Weldability may affect the seismic performance and it follows that new
methods to improve inelastic seismic performance of steel structures need to be
investigated.
Meliorations
Critics point to poor aesthetics with a typical 'industrial' or 'warehouse' look; minimal
flexibility regarding location, shape and size of structural members; the need to utilise offthe shelf building shapes and sizes in order to realise cost savings; and a lighter structurewhich does not achieve the longevity of more conventional structural systems.
"The most basic prerequisite of PEB is 'single sourcing' of the entire building. Any slightdeviation from this can deprive the customers of the real advantages. Also, as steel is prone
to corrosion, it would require various protective coatings which may sometimes make PEB
unfeasible economically."
Maintenance
In PEB the maintenance area is the steel roofing & cladding. Installed roofing must beinspected at least once a year. Any exposed metal that can rust or has rusted should be
painted. Leaves, branches, and trash should be removed from gutters, at ridge caps and incorners. Also watch out for discharge from industrial stacks, and particulate matter and highsulphur exhaust from space heaters which could get piled up. The Future Bright Towards the Economic growth
Steel is a preferred material for construction, due to its various advantages like quality,aesthetics, economy and environmental conditions. This concept can have lot of scope in
India, which can actually fill up the critical shortage of housing, educational and health care
institutions, airports, railway stations, industrial buildings & cold storages etc.
Pre-engineered Metal building concept forms a unique position in the construction industry
in view of their being ideally suited to the needs of modern Engineering Industry. It wouldbe the only solution for large industrial enclosures having thermal and acoustical features.The major advantage of metal building is the high speed of design and construction for
buildings of various categories.
The present construction methodology for buildings calls for the best aesthetic look, highquality & fast construction, cost effective & innovative touch. One has to think for
alternative construction system like pre-engineered steel buildings. India has an installed
steel capacity of 35 to 40 million ton & apparent steel consumption is around 27 to 30million ton. In pre-engineered building concept the complete designing is done at the
factory and the building components are brought to the site in knock down condition. These
components are then fixed / jointed at the site and raised with the help of cranes.
8/13/2019 Precast concrete.docx
http://slidepdf.com/reader/full/precast-concretedocx 21/22
8/13/2019 Precast concrete.docx
http://slidepdf.com/reader/full/precast-concretedocx 22/22
will need to develop suitable Codes and specifications for the purpose to meet the
requirements of future generations. There is increased invest more for research and
development for innovative material and construction methodologies.
One has to use the PEB products, with a word of caution, and frame the contract provisions
accordingly. We are fairly close to a day when steel buildings should be the rule, rather thanbeing the exception, if we work together to give the Client, best value for his money.