    PRE-BORING WORK

    PRIOR TO

    DIAPHRAGM WALL CONSTRUCTION

  • 8/11/2019 Preboring Works to DWall with Air-lift & RCD Core Barrer - 17.6.14.pdf

    2/18

    CONTENTS

    OBJECTIVE

    PRE-BORE METHODOLOGY ------------------------------------------------------ 3

    A) AIR-LIFT METHOD -------------------------------------------------------------- 4

    Guide Wall and Casing Installation ---------------------------------------------- 4

    Pre-boring --------------------------------------------------------------------------- 5

    Pre-coring --------------------------------------------------------------------------- 6Backfilling -------------------------------------------------------------------------- 8

    Diaphragm Wall Soil Excavation ----------------------------------------------- 10

    Pre-boring P3 & P4 --------------------------------------------------------------- 11

    Pre-boring P5 & P6 --------------------------------------------------------------- 12

    Diaphragm Wall Rock Coring --------------------------------------------------- 13

    B) RCD(REVERSE CIRCULATION METHOD) ------------------------------- 15

    APPENDIX A - LAYOUT PLAN OF PRE-BORING

    - ENLARGE LAYOUT OF PRE-BORING

  • 8/11/2019 Preboring Works to DWall with Air-lift & RCD Core Barrer - 17.6.14.pdf

    3/18

    Objective: To remove hard strata prior to diaphragm wall construction

    1. Pre-boring Methodology

    Pre-boring is selected to ease the excavation for diaphragm wall at hard strata / high rock level in these

    area prior to diaphragm wall excavation. It entails the process since inception of guide wall

    construction, pre-casing installation, coring and backfill with LSS(Liquefied Soil Stabilizer) and lean

    concrete at above rock bed and within rock bed zone for backfilling respectively.

    Based on current available bore-log information, pre-boring of 1000mm diameter along Dwall

    alignment, please see Appendix A have been selected for such works. Thus, 2 pre-boring methodology

    will be used to carry out, namely; Air-lift and RCD(Reverse Circulation Drill) methods.

    A) Air-lift method:Using a boring rig attach with kally-bar mounted with a self-collecting box core

    barrel to perform pre-boring with air supply to create suction effect to clear out drilling

    fragments from pile toe. The air-lift method of clearing the drilling from pile toe are air-lifted into

    collection box situated above the core barrel, thus every interval of an hour may be required to

    retrieve its kally-bar to empty those loose rock fragment being collected in the collection box or

    deemed at the operator opinion that the collection box is fully filled.

    B) RCD method: Using a boring rig attach with RCD rod instead of kally-bar, mounted with core

    barrel with air supply to create suction effect to clear out drilling fragments. The RCD method

    tends to be a one-time process to continuously clean out the drillings from pile toe.

    The above 2 methodology of pre-boring are similar with the used of casing installed by either vibro-

  • 8/11/2019 Preboring Works to DWall with Air-lift & RCD Core Barrer - 17.6.14.pdf

    4/18

    A) Air-lift method

    Casing Installation

    1. Construct the guide wall for diaphragm wall alignment accordingly to pre-bore location layout,

    catering for the outer casing diameter of 1050mm.

    2. Only applying for pre-bore location, its guide wall internal face to internal face width shall be

    constructed as in Figure 1 to suit the casing installation for pre-boring works.

    3. Pre-arrange with marking of each diaphragm wall(D-wall) joints on guide wall top for initial casing

    setting out for pile 1 and 2 at every joint of D-wall.

    4. Pre-excavate by means of backhoe or excavator to depth of guide wall if necessary at site discretion

    for the initial insertion of casing setting/positioning. Commence pile 1 casing installation by vibro

    hammer or casing-driving adapter of the boring rig into ground. Check the verticality of casing

    during installation by spirit level. Drive casing until some refusal from ground. Commence boring

    at pile 1 while pile 2 may continue to start installation of casing into hard strata by mean of vibro

    Figure 1 / Section A A (N.T.S)

    P1 P2

  • 8/11/2019 Preboring Works to DWall with Air-lift & RCD Core Barrer - 17.6.14.pdf

    5/18

    Pre-boring

    1. Pre-bore to clear out materials with boring bucket within casing at pile 1 until hard strata/rock top

    level as shown below Figure 2; similarly for P2 casing and its pre-boring works as well as for all the

    intended pre-boring location are apply.

    P1 P2

  • 8/11/2019 Preboring Works to DWall with Air-lift & RCD Core Barrer - 17.6.14.pdf

    6/18

    Pre-Coring

    1. Replace boring bucket with Roller Bit Core Barrel, Figure 3 next page; to continue rock head

    coring. The core barrel is fitted with a conceal pipe within its wall, and connected to the suction

    channel to supply air from a compressor unit, so as to create a suction-effect within the suction

    channel to air-lift the crush strata beneath the roller bit at pile toe level into the collection box

    located above the roller bit.

    Suction channel for

    hard strata fragment

    clearing from pile toe

    Suction channel forhard fragment clearingfrom pile toe

    Figure 3 Roller Bit Core Barrel

    Note: Hard strata level shall be

    recorded in the Confirmation of GIIIRock Level and witness by all and in-

    charge person to sign-off as in

    Appendix B.

  • 8/11/2019 Preboring Works to DWall with Air-lift & RCD Core Barrer - 17.6.14.pdf

    7/18

    Enlarge Details on Core Barrel Process

    Suction

    channel

    Air supply inletfrom compressor

    Collection box collection point of fragment chiptransported by air-lift within core barrel during coring

    Rock fragments

    sink into

    collection box

  • 8/11/2019 Preboring Works to DWall with Air-lift & RCD Core Barrer - 17.6.14.pdf

    8/18

    Backfilling

    1. Once the desire depth of that D-wall panel is reached, retrieve core barrel and kelly-bar. Moved off

    boring rig to pile 2 continue pre-boring works in similar manner described earlier.

    2. While pile 1 is prepared with the lowering of tremie pipe, G20 shall be used for the backfilling from

    pile toe to the earlier hard strata/rock level. Remaining from hard strata/rock level to guide wall

    toe/base shall be backfilled with LSS/Grade7 lean concrete as shown below;

    P1 P2

    LSS / G7

  • 8/11/2019 Preboring Works to DWall with Air-lift & RCD Core Barrer - 17.6.14.pdf

    9/18

    in jumping manner at the construction manager discretion so as to provide a continuous pre-boring

    within site constraint.

    4. Pre-bore and cast in similar manner to the rest of the pile. In event of more pre-bore holes are

    requires to carry out at others location other-than those shown in Appendix A, upon further

    information are obtained from the probing soil investigation, new location to be pre-bored shall be

    added and revised for information.

  • 8/11/2019 Preboring Works to DWall with Air-lift & RCD Core Barrer - 17.6.14.pdf

    10/18

    Diaphragm wall Soil Excavtion

    1. Commence grabbing or use cutter with Bentonite slurry, if available to pre-excavate out those

    earlier backfilled LSS/G7 lean concrete and remaining soil shown below until earlier hard strata /

    rock head again;

    Re-excavate earlier

    LSS & soil

    Earlier hard strata /

    rock head level

  • 8/11/2019 Preboring Works to DWall with Air-lift & RCD Core Barrer - 17.6.14.pdf

    11/18

    Pre-boring P3 & P4

    1. Installed casing into excavated trench to setout remaining pre-bore location P3 and P4 on guide wall

    top. Repeat using roller bit to desintegrate the hard strata / rock bed again at P3 & P4.

    P2

    P2

    P1

    P1 P3P4

    P3P4

  • 8/11/2019 Preboring Works to DWall with Air-lift & RCD Core Barrer - 17.6.14.pdf

    12/18

    Pre-boring P5 & P6

    1. Upon hard strata / rock bed are cleared. No backfilling of G20 is required for these last pre-bore

    piles but to retrieve casing for the cutter for further excavation with Bentonite slurry.

    P6P5

  • 8/11/2019 Preboring Works to DWall with Air-lift & RCD Core Barrer - 17.6.14.pdf

    13/18

    Diaphragm Wall Rock Coring

    1. After casing removal, position cutter for excavation as shown below with Bentonite slurry;

  • 8/11/2019 Preboring Works to DWall with Air-lift & RCD Core Barrer - 17.6.14.pdf

    14/18

    2. Continue excavation rock bed until desire Dwall design depth is reached. Proceed to desanding,

    lower steel cages and casting.

  • 8/11/2019 Preboring Works to DWall with Air-lift & RCD Core Barrer - 17.6.14.pdf

    15/18

    B) RCD method

    In RCD methodology, the pre-boring procedures and coring of hard strata / Rock bed drilling

    arrangement is similar described as in air-lift method, but for RCD method, RCD drilling section of

    pipe are used instead of kally-bar; core barrel is connected to RCD pipe with supply of air into RCD

    pipe to create suction-effect within RCD pipe to air-lift the drilling chippings/fragments with

    bentonite slurry within core barrel via RCD pipe into collection tank at ground level as shown below;

    Air Flush &

    Drill chips

  • 8/11/2019 Preboring Works to DWall with Air-lift & RCD Core Barrer - 17.6.14.pdf

    16/18

    APPENDIX A

    PRE-BORED PILES LAYOUT