Upload
bayau-fendi-
View
217
Download
0
Embed Size (px)
Citation preview
8/3/2019 Pre Journal FENDI
http://slidepdf.com/reader/full/pre-journal-fendi 1/9
Factors Influence The Selection of Formwork System 1
FACTORS INFLUENCE THE SELECTION OF
FORMWORK SYSTEM
Zakaria.R¹ and Ismail.M.A²*
1Senior Lecturer, Construction Technology and Management Centre (CTMC), Faculty of
Civil Engineering, Universiti Teknologi Malaysia, 81310 Johor Bahru, Johor, Malaysia
2 Master Student, Construction Technology and Management Centre (CTMC), Faculty of
Civil Engineering, Universiti Teknologi Malaysia, 81310 Johor Bahru, Johor, Malaysia
*Corresponding Author: [email protected]
Abstract: A good formwork system enables speedy completion of the concrete structure,
following which other subsequent jobs can be started. However, the current approach in the
selection of formwork systems regularly cannot be specified even though it is crucial in
assuring an optimal and consistent result. The aim of this paper is to highlight factors in
selection of formwork system. It is crucial to identify the selection factors to support the
sustainable construction and indirectly response to sustainable development. The selection
factors have been listed by intensive reviewing of several references, such as journals,
articles, and previous study on formwork system. The questionnaire method is being used
in collecting the data. There are about 34 related respondents have been approached at
several locations in Johor Bharu, Selangor and Kuala Lumpur. The analysis of data is being
done by using Likert Scales. Data validation study is also being conducted in order to
endorse the significance factors in the proposed list of selection factors. Project nature and
budget have been selected as the most effective factors in selecting formwork system. Majority of respondents said that formwork systems do not require high skills in the design,
manufacture, install and monitor the progress of construction projects
Keyword: selection of formwork system; sustainability
1.0 Introduction
Formwork represents a significant part of the cost of concrete structure construction. Most
subsequent jobs including internal finishing and external cladding depend on the
completion of the building structure. A suitable formwork system is thus crucial for
maintaining the smooth flow of the various jobs and a proper working sequence of various
work activities. Typically, the selection of formwork system is made by a senior member of
the contractor‟s organization. The decision is heavily based on that individual‟s experience.
This experience may limit the selection of a system to one that is not optimum.
8/3/2019 Pre Journal FENDI
http://slidepdf.com/reader/full/pre-journal-fendi 2/9
Factors Influence The Selection of Formwork System 2
Building and construction activities worldwide consume 3 billion tons of raw materials
each year or 40 per cent of total global use (Roodman and Lenssen, 1995).In order to
sustain raw materials depletion, using green building materials and products for the
formwork system promotes conservation of declining non-renewable resources
internationally. In addition, integrating green building materials into formwork system can
help reduce the environmental impacts associated with the extraction, transport, processing,
fabrication, installation, reuse, recycling, and disposal of these formwork source materials.
The sustainability elements have to be considered nowadays in selecting the type of
formwork system.it is crucial in such manner to support the sustainable construction.
Sustainable construction is an agenda to response to more effective solutions by
considering recycle, reuse and reduce the usage of raw construction material. Therefore it is
crucial to identify the elements of sustainability that should be incorporated in construction
processes or system. The most system that cannot be avoided in construction is formwork
system that helps to form and cast the shape of the designed concrete. The sustainability
elements have to be considered in selecting the type of formwork system. It is crucial in
such manner to support the sustainable construction. Therefore, accounts on level of
responsive of each element are a must when considering the type of formwork system.
2.0 Research methodology
This research applied three stages in obtaining data needed. The first stage is preliminary
stage whereas the research problem being identified through study and understand the
relation between sustainable and formwork system. In this stage, a list of sustainability
elements in construction development is being listed. This has been done by reviewingseveral references, such as journals, articles, and previous study on sustainability elements.
The related information and data extracted from these references are being simplified into
table of major sustainability concept. From identified elements of sustainability of IBS
formworks, the sustainability elements of those systems have been described as the crucial
elements to be taken into account on the future construction.
8/3/2019 Pre Journal FENDI
http://slidepdf.com/reader/full/pre-journal-fendi 3/9
Factors Influence The Selection of Formwork System 3
The second stage of this research is the data collection using questionnaire method.
There are about 34 related respondents have been approached at several locations in Johor
Bharu, Selangor and Kuala Lumpur. For this stage, the analysis of data is being done by
using Likert Scales, in which being ranked for those elements of interest are as follows:
Strongly disagree = 1
Disagree = 2
Moderate = 3
Agree = 4
Strongly agree = 5
For this research, the software being used to analyse data received from
questionnaires are Microsoft Excel 2007 and Statistical Package for the Social Science
(SPSS version 13.0). The average index is calculated based on the equation as follows;
Where,
αᵢ = constant expressing the weight given to i
ϰᵢ = the frequency of the response for i = 1,2,3,4, and illustrated as follows:
ϰ1= frequency of “extremely not important” response and corresponding to1
ϰ2 = frequency of the “not important” response and corresponding to 2
ϰ3 = frequency of the “moderately important” response and corresponding to 3
ϰ4 = frequency of the “very important” response and corresponding to 4
ϰ5 = frequency of the “extremely important” response and corresponding to 5
The final stage, which is the third stage of this research, is data evaluation. In this stage, the
result from the findings being evaluated in details and several conclusions were being
made. The researcher has come out with several recommendations to enhance the quality of
the future research.
8/3/2019 Pre Journal FENDI
http://slidepdf.com/reader/full/pre-journal-fendi 4/9
Factors Influence The Selection of Formwork System 4
2.1 Research Methodology Flowchart
STAGE 1: PRELIMINARY STUDY
Identify Research
Problem
Identifying the research
Literature review
Formwork system Sustainability
Define inter-relation between
formwork system and sustainability
Identifying preliminary elements of
Construction
Development
Green building
Types
Class
Innovation
Conclusions
Recommendations
Interpretation
Data Collection
[Questionnaires]
Data Validation & Screening
Data Analysis
Findings
STAGE 2: DATA EVALUATION
STAGE 2: DATA COLLECTION
8/3/2019 Pre Journal FENDI
http://slidepdf.com/reader/full/pre-journal-fendi 5/9
Factors Influence The Selection of Formwork System 5
3.0 Results and Discussions
Factors of Selection Mean Rating Scale
Project nature and budget 4.21 very effective
Formwork system availability 4.00 very effective
Installation method 3.94 very effective
Ease the construction 3.94 very effective
Fast track construction process 3.88 very effective
Material use in formwork system 3.76 very effective
Formwork safety and risk assessment 3.68 very effective
Effects on environment and local community 3.62 very effective
Provide site safety to all parties 3.56 very effective
Form durable structure in the construction 3.15 moderately effective
Needs low maintenance, thus provide less cost. 3.09 moderately effective
Need low skill requirement 2.74 moderately effective
Figure 1(a): Selection Factors of Formwork System
Figure 1(b): Comparison Graph for Selection Factors of Formwork System
4.21
4
3.94
3.94
3.88
3.76
3.68
3.62
3.56
3.15
3.09
2.74
0 1 2 3 4 5
Project nature and budget
Formwork system availability
Installation method
Ease the construction
Fast track the construction process
Material use in formwork system
Formwork safety and risk assessment
Effects on environment and local…
Provide site safety to all parties
Form durable structure in the construction
Needs low maintenance, thus provide…
Need low skill requirement
8/3/2019 Pre Journal FENDI
http://slidepdf.com/reader/full/pre-journal-fendi 6/9
Factors Influence The Selection of Formwork System 6
As refer to Figure 1(a) and Figure 1(b), almost 75% (9 over 12) of factors listed have been
chosen to have more than average level of 3.50. The most selected factor as the most
effective factor of selection is „project nature and budget‟ (average score 4.21), while the
lowest score of 2.74 (Formwork system need low skill requirement) being put as the most
ineffective factor.
Project nature and budget have been selected as the most effective factors in selecting
formwork system. This factor can be divided into two, namely the nature of the project
budget and project itself. Project budget means a budget that was held in a project to govern
the financial and levels of specific components involved in the construction. For example,project management must determine how much money should be invested. This is because
the formwork systems are sometimes different from conventional projects. Furthermore,
the formwork systems should meet the design of the site and they need to be modified.
Thus, the modification of the formwork system criteria means the cash flow also has to be
manipulated.
Construction projects sometimes require a different type of formwork and the nature of
the project itself. As for example, the constructions of terraced houses are different to the
construction of skyscrapers that give priority to the architecture. Terraced houses under
construction, formwork systems used are often repetitive and similar in size and design.
however, the artistic aspects of the construction of skyscrapers formwork system
sometimes requires a different and unique to get the desired shape, such as the architectural
drawings.
Meanwhile, there are 3 factors have being selected below the average level of 3.50
which been categorized as moderately effective selection factors. These factors are
inclusive of formwork system need low skill requirement, formwork system form durable
structure in the construction and formwork system need low maintenance therefore
providing less cost for the whole construction.
8/3/2019 Pre Journal FENDI
http://slidepdf.com/reader/full/pre-journal-fendi 7/9
Factors Influence The Selection of Formwork System 7
Majority of respondents said that formwork systems do not require high skills in the
design, manufacture, install and monitor the progress of construction projects. This is
probably because most of the formwork systems, (not including permanent formwork
system) are being used for a while and not one of the components as structural beams and
columns. This causes the formwork system does not require the attention of experts in the
construction aspects as mentioned earlier.
On average, only 3.15, which are below the average level of 3.50 of the respondents,
stated that the formwork system factors contributing to the production of durable structures
in construction. This is because the effect of the formwork system is only slightly lowerthan the properties of the concrete, reinforcement and other factors that are directly
involved.
An average of 3:09 of the respondents stated that the formwork system only requires
little maintenance contribute to the reduction in construction costs. This is because most of
the formwork system used today is made of steel which is less affected by climate change,
human error and other factors as well as reduce maintenance costs because of less damage.
In contrast to conventional formwork system that comes from natural sources such as
timber. These resources are easily damaged by climate change, etc., as well as increased
spending for new formwork system.
4.0 Conclusion
As far as the above concern of questionnaire findings, most of the favourable selection
factors of formwork system are basically common selection factors which have been
practiced in construction area. Based on the discussion of the findings above, this study
found that respondent choose the factor of existence of formwork system will ease the
construction as it is used as supportive structure in making different parts of building like
beams, columns and walls. They also agreed that formwork system will help to accelerate
the construction work schedule. In the meantime, the formwork system will provide site
safety to all parties involved in construction by preventing harmful material like concrete
8/3/2019 Pre Journal FENDI
http://slidepdf.com/reader/full/pre-journal-fendi 8/9
Factors Influence The Selection of Formwork System 8
mixture and imperfect structure from being collapsed to the ground or in the worst case
scenario; get down over personnel surround. The properties of material used as formwork
system also being put into their consideration in selecting formwork system. The method of
installation like precast or in-situ formwork is being among the major factor in selection of
formwork system. Meanwhile, the effects to the environment and local community are also
being emphasized by construction personnel in selecting the best formwork system. It is
crucial to reduce the effect on environment by using green or proper material which has
less toxic. Hazardous formwork system will affect human health and also contaminate
water source. Finally, as the world of construction is a part of a business, the factor of
project nature and budget is the most chosen factors among others is selecting wise
formwork system. Hence, the developer especially contractor are carefully will makeproper budget inclusive of selection of formwork system to prevent loss of money,
manpower and time which become among important keys in construction progress.
5.0 Acknowledgment
The authors would like to thank the consultants and contractors involved for cooperation
and support in providing data for the study.
REFERENCES
1) CIDB, (2010), IBS Industrialized Building Systems (IBS) Roadmap, Construction
Industry Development Board, Pg. 7
2) Knapton, John (2008). World Trade Centre Attack .Retrieved on September 7,
2010, from http://www.john-knapton.com/wtc.htm
3) Sustainable Concrete (2010), Methods of Construction Sustainable Concrete
Design and Construction, Insulated Concrete Formwork (ICF) Retrieved on
September 7, 2010, from http://www.sustainableconcrete.org.uk/
4) Mohan Munasinghe and R. J. Swart (2005) Primer On Climate Change And
Sustainable Development: Facts, Policy Analysis and Applications
London, Cambridge University Press, 101pp.
8/3/2019 Pre Journal FENDI
http://slidepdf.com/reader/full/pre-journal-fendi 9/9
Factors Influence The Selection of Formwork System 9
5) D.M. Roodman and N. Lenssen, A Building Revolution: How Ecology and Health
Concerns are Transforming Construction, Worldwatch Paper 124, Worldwatch
Institute, Washington, D.C., March 1995, p. 5.
6) Badir, Y.F., Kadir, M.R.A. & Ali, A.A.A (1998), “Theory of Classification of
Badir- Razali Building System Classification”, Buletin of Institution of Engineer,
Malaysia.
7) Muhd. Zaimi Abdul Majid, Rosli Mohamad Zin, and Jamiah Salleh, Sistem Fast
Track Wall (FTW), Penerbit UTM Press, 2009
8) Brundtland GH (chairman) (1987). Our Common Future. Oxford: Oxford
University Press.
9) World Commission on Environment and Development. (1987). Our Common
Future. Oxford University Press, Oxford
10) Nazirah Zainul Abidin., (2009). Sustainable Construction in Malaysia –
Developers’ Awareness. World Academy of Science, Engineering andTechnology, 53, 807- 814.
11) Bill Bradley, (2007-2010), Formwork Materials and systems, Retrieved August
21, 2010, from http://www.builderbill-diy-help.com/
12) Lynn M. Froeschle, "Environmental Assessment and Specification of Green
Building Materials," The Construction Specifier , October 1999, p. 53.
13) Ross Spiegel and Dru Meadows, Green Building Materials: A Guide to Product
Selection and Specification, John Wiley & Sons, Inc., New York, 1999.
14) Construction Industry Master Plan (CIMP 2006 – 2015) (2007), Construction
Industry Development Board Publication, Malaysia, Kuala Lumpur