Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
1
PRE-FEASIBILITY REPORT
Name of the project: Road Metal& Building stone quarry of Sri.M/S Lakshmi Venkateswara Stone Crushers, M.G.Partnor: Sri B.S.Narayanareddy
1 Name and address of the proponent:
Sri.M/S Lakshmi Venkateswara Stone Crushers M.G.Partnor: Sri B.S.Narayanareddy, Lakshmipuram (V), Yellampalli (Po), Bagepalli Taluk, Chikkaballapura District, Karnataka State
2 Location of the project(Coordinates of the area and Topo sheet No)
A.13°55’27.6”N 77° 37’01.0”E B.13°55’27.2”N, 77°37’02.6”E C.13°55’25.5”N, 77°37’02.9”E D.13°55’25.2”N, 77°37’01.2”E 57 G/9Velidadakala (V),
3 Category of the project as per the Schedule under EIA notification
1(a)of the Schedule, Category B2
4A Details of application filed before the concerned granting authority
Existing project hence Not Applicable
Survey No: 318/P,350/7 &11
Extent: 1.000 Ha.,
Village: Velidadakala
Mandal: Somandepalli
District: Anantapur
State: Andhra Pradesh
4B Details of grant made in case of existing project
Grant order details Granted vide proceedings no.852/Q1/2017, dated.11.09.2007 of Director / Deputy Director of Mines & Geology, Kurnool. Proceedings No. 852/Q3/RM/2007 dt:28.07.2016 of Assistant Director Mines & Geology, Ananthapuramu
Period of Lease 10 years
w.e.f. 28.07.2016
Survey No: 318/P,350/7 &11
Extent: 1.000Hects.,
Village: Velidedakala
Mandal: Somandepalli
District: Anantapur
State: Andhra Pradesh
2
1. EXECUTIVE SUMMARY: This relates to a quarry project to produce road metal, rough
stone/boulders for the use in construction activity.Due to recent
introduction of stone crushing units, the major activity of production of
stone aggregate shifted to Industry from the place of quarry
site.Presently boulders of about150mm size are produced in the quarry
and are transported to crushing Industry where the boulders are reduced
torequired sizes.Presently 40mm size is used for metal soling in road
works and alsoin flooring foundations.The next sizeshaving in demand in
the market are 20mm, 12mm, 6mm and stone dust.A mix of 20mm and
12mm is normally used in concrete making in building structures and
also making cement roads. The 6mm and stone dust are used for upper
layers of blacktop roads.Thus entire produce is put to use in building
construction and road laying activity.For development of any area, Stone
metal is pre-requisite.Andhra Pradesh is endowed with huge reserves of
granite throughout the state. Though geologically there are different rock
types likegranite, charnockite, dolerite, gabbro, syeniteetc.for all these
the general terminology under usage is granite, which is hard rockwith
hardness of 5.5 to 7 in Moh’s scale of hardness.The other rock types like
limestone,dolomite arealso predominant in the state. Due to their
chemical weatheringcharacter and low hardness they are normally not
preferred in concrete mixing.Besides, the other widely occurringrock type
in A.P. is quartzite. Although it is also useful in concrete mix, due to its
high hardness (7 Moh’s scale) its crushing cost is relatively high.Hence it
is not preferred unless local availability compels to use it.
The present project is a Stone metal quarry in operation at least for the
last one decade. As per the recent amendments brought to the EIA
3
notification of 2006 vide amendment, dated 07.10.2014for mining of in
less than 5 ha area also under the net of obtaining E.C. especially due
to the observation of the National Green Tribunal, the present proposal
is made for seeking Environmental Clearance (EC).
The area under operation covers by a quarry lease granted by the
Dy.Director of Mines and Geology, under the provisions of A.P.Minor
Mineral Concession Rules 1966.The said grant gives right of quarrying
to the proponent subject to the terms and conditions of the lease
agreement entered with the Government. The required seigniorage fee
is paid to the department for the material dispatched from the quarry site.
The quarrying activity is manual using mild explosives with controlled
blasting, without affecting the surrounding environment. In fact the
activity is far away from the habitations. The material so quarried is
dispatched to the stone crushing units, which have already got E.C.
Broadly speaking,in the metal quarrying activity there is very little scope
for Environmental Pollution and waste generation. The small amount of
dust generated is suppressed by way of using water sprinklers. The
workers employed in the activity are supplied with nose and ear masks
to protect them from possible airand noise pollution. Since the
operations are mostly confined to rocky areas of the hill slopes, there is
no possibility of land degradation due to this activity. Wherever possible
by way of plantations, greenery is maintained. Above all as this material
is essential for the developmental activity, mining is inevitable. By way of
taking appropriate measures, it is possible to control dust emissions in
the mine.
2. INTRODUCTION OF THE PROJECT/ BACKGROUND
INFORMATION:
4
The project under operation is called mining project which falls under
category B2 under schedule specified under notification issued vide S.O.
1533 MOEF dated 14-9-2006 read with amendments issued under S.O
2601 dated 7-10-2014 of MOEF&Climate change. Even though the said
notification envisages necessity of obtaining E.C. only for new projects,
keeping in view of the notices issued by the department of Mines and
Geology, present application is filed for seeking E.C.
The project is to produce building stone/road metal stone from the
quarry lease granted areas. The material obtained by way of using small
quantities of mild explosives under controlled blasting.
i) Brief note on use of explosives:
The quarrying activity requires dislodging of rock mass from the parental
rock which is quite hard. In order to mine this rock material, usage of
explosives and blasting is inevitable. .Forthis purpose to operate by
himself, the proponent requires explosive license under the Indian
Explosives Act 1884. Since the small quarry operators cannot afford to
establish individual explosive Magazines, they are resorting to outsource
the blasting operation to an agency which holds the license to use
explosives and undertakes the blasting operations in the quarry by
appointing qualified blasters.
The quarry operator gets blast holes drilledin the spacing and burden
suggested by the out sourced agency. The drill holes of 32 mm dia. are
drilled to an average depth of 2.0m with a spacing of 1.5 m and burden
of 1.0 m. The maximum numbers of holes at one go of blasting will be
20-25. Once the drill holes are kept ready, the licensed blaster of the
outsourcing agency takes over for further operations. The holes are
charged with 25mm. dia. A based slurry explosives. Stemming is done
5
with locally available clay. The holes are connected with millisecond
delay detonators for ensuring maximum fragmentation and fired by using
a dynamo type exploder. Before firing the shots, the entire area of a
minimum 500 meters radius is cleared of men and machinery and all
possible entry points for men or animals are posted with well-informed
guards and the final firing with a dynamo exploder is done after
clearance is obtained from all the points. After a lapse of sufficient time,
the blasted face is inspected and all clear signals is given to the guards.
Whistles and Red flags are used for the operations.
Extra precautions are taken when a certain quarry is closer to a highway,
habitations etc. The explosive charge is reduced and thick mattings are
laid over the surface concerned.
On blasting, it is natural that large boulders are occasionally produced.
These cannot be handled easily for loading and also the crushers cannot
crush them. Therefore the secondary blasting is resorted to by drilling
Jack hammer holes and using small diameter explosives like kelvex,
superdyne etc. by taking the same precautions as per primary blasting
ii)Brief description of nature of the project:
The product produced from this project is stone of about 150 mm
size, a feed to the stone crusher, to produce stone aggregate of
40mm, 20mm,12mm, 6mm sizes for the use in concrete and other
road works. The final product in the process is stone dust which can
also be used as filling material, in place of ordinary sand in cement
mix and also as top fine layer in block top roads.
iii) Need for the project and its importance to the country and
or region:
6
As civilization grows, there is need for the improvement of
infrastructural facilities. For the development of infrastructure
facilities, huge consumption of stone aggregate and road metal is
imminent. For every tone of cement consumed, the stone aggregate
required would be 3tones. Government is committed to housing to
poor people in the present welfare state. In this context requirement
fof huge quantities of stone aggregates and cement are imminent.
The requirement of stone aggregate in A.P. is 90 million tones basing
on cement consumption figures,apart from this the stone aggregate
is also used in road making where cement is not used. Besides,
dueto shortage of river sand, presently, rock sand is contemplated to
be its substitute. Hence, the requirement of stone for making rock
sand increases exponentially and there is need to go for further
production of the rock boulders. Hence, there is every need to
encourage the mining projects of this type. Moreover, the quarrying
activity of the area over considerable time make the area fit for tree
growth after exhaustion of the deposit. If the activity takes place
below ground level the mine pit helps to act as water reservoirs and
thereby improves ground water level in the surrounding areas. Hence
the activity can be considered to be environmental friendly. More so
in the nearby vicinity a new A.P. capital with huge out lay of about
more than INR 100000crores is contemplated. At least 20% of this
component goes for raw material such as stone aggregate, sand and
cement. Therefore, there is every need to encourage this type of
project
7
iv) Demand, Supplyand Gap:
As explained supra there is increasing demand for this stone
especially due to the new capital under way for A.P and the present
area is located in very close proximity. Therefore there is going to be
more demand than present supply of the material, since present
supply is only catering the needs of existing construction activity.
v) Imports vs. Indigenous production:
There is no scope of import of this type ofconstruction material as
there is enough scope to exploit the vast reserves of hard rock. In
fact, some of the small islands surrounding our country are importing
such construction material as they cannot indulge any more in
excavation of the exposed hard rock there.
vi)Export Possibility:
There is good possibility to export this material,provided the port
network facilitates.
vii) Domestic / export Markets:
This material, as explained earlier, so as to cater to the
developmental needs of Vijayawada which is one of the fast
developing cities in India and more so to the new State Capital which
is coming up in nearby area with huge investments. Hence there is
very bright future for the domestic consumption.
viii)Employment Generation (Direct and Indirect) due to
the project:
8
This project provides employment to about 15persons per day
directly and about equal number indirectly.
3. PROJECT DESCRIPTION:
i) Type of project including interlinked and interdependent
projects, if any:
This is interlinked project with stone crushing projects. The activity is
by way of manual mining using small quantities of explosives under
controlled blasting to split/ loosen the rock mass from the parent
rock. The rock boulders so produced will be of size range between
0.2cum to 0.75 cum and same will be reduced in size to small
boulders about 150mm bymanualbreaking and would be used as
stone crusher feed.
Ii) Location (map showing general location, specific
location, and project boundary & project site layout) with
coordinates:
The lease area is located along the southwestern slopes of the
hills(Δ731) and is 2.0 km SW of Velidadakala (v) Somandepalli (M)
Anantapur (Dist.). The location map of the area demarcated on
revenue sketch is annexed to the lease grant order apart from
locating the area on Survey of India Toposheet No. 57G/9
iii) Detailsof alternate sites considered and the basis
ofselecting the proposed site, particularly the environmental
considerations gone into should be highlighted:
Minerals are site specific unlike other products. There is no
alternative than mining of the mineral where ever they occur by way
of shifting the other projects toelsewhere, even if they are located on
9
the top of mineral bed.We can re-locate any project to anywhere, but
not the mineral deposits, which are god given gifts to the humankind.
iv) Size or magnitude of operation:
This is a very small project spread over anextent of 1.ha. The
probable annual production is about 17911m cubetons which can
give employment opportunities to about 15persons directly and
another10 persons indirectly. This project is alabour
intensiveindustry though the capital out lay of the project is very
low, when compared to projects of high investments.
v) Project description with process details (a schematic
diagram/ flow chart showing the project layout, components of
the project etc. should be given):
Schematic Diagram/Flow Chart:
Parent rock
↓
Producing of rock aggregates with sizes of0.25 to 0.75m by line
drilling and controlled blasting.
↓
Breaking up of the bigger size blocks to ≈150mm size rock
aggregates by manual hammering
↓
The ≈150mm size rock material shall be sent as crusher feed
↓
From crusher the resulting end products arewith 40mm, 20mm,
12mm size road metal and rock dust.
10
vi)Raw material required along with estimated quantity, likely
source, marketing area of final product/s, and mode of transport
of raw material and finished Product:
The estimated resource of rock material in the lease area, as crusher
feed, is of the order of about.3 million tons.The transportation of the
raw material is by way of tippers from the quarry to the stone
crushing units and loading is by using raw material loader
(Poclain).The marketing area is-nearby Towns like Hindupur,
Penukonda, Dharmavaram, Gorantla, Palasamudram, Somandepalli,
and neighboring villages. The final finished product from the crusher
will be transported to the consumer points by tippers.
vii) Resource optimization/ recycling and reuse envisaged inthe
project, if any, should be briefly outlined:
The estimated resource of the raw material in the lease hold area of
extent 1hais of the order of about0.3million tons.Because it is a basic
construction material for roads and buildings, it cannot be retrieved
and recycled.
In fact, the stone dust generated wasconsidered to bea waste in the
past. But of late, due to the shortage of filling material the stone dust
is being used as alternative filling material for leveling thelow lying
areas. Further, recently due to the shortage of soil in brick making,
concrete bricks aremade by using baby chips and stone dust as an
alternative. Hence the dust generated is also has good market along
with other produce in the stone crushing unit.
vii i ) Availability of water, its source, Energy/ power requirement
and source should be given:
At mine site, water is used for:
11
Wet drilling
Water sprinkling on quarry roads and approach roads for dust
suppression.
The metal quarry requires about 10KLD of water.This includes water
for drilling(about 1-1.5 KLD), dust suppression(6.0-7 KLD) and
domestic purposes (1.0- 1.5 KLD).
For drinking purpose of the persons working in the quarry potable
water supply is out sourced. Whereas for sprinkling purposes water
will be tapped from the nearby boreholes on contract basis by tankers.
There is no need for power supply since the operations are conducted
only duringday times.
The requirement of fuel for running the vehicles and machinery will be
procured from the nearby petrol bunks.
ix) Quantity of wastes to be generated (liquid and solid)and
scheme for their Management/disposal:
The stone metal quarrying is on the hill slopes occupied by sheet
rocks and boulderswhich do not have soil cover,hencethere will not
be any scope waste generation.
x) Schematic representations of the feasibility drawingwhich
give information of EIA purpose:
This is a very small mining project with an extent of 1.0 ha and does
not have any major Environmental Impact. However, the minor
environmental impacts such as air pollution by dust emissions and
noise pollution by mining activity are contained by water sprinkling on
the quarry roads and by provided ear & nose masks to the persons
working in the mine respectively.
12
Topo map of the mining project with 5 Km radius from the project with
site location showing and its adjoining areas isenclosed. As such there
is no impact on the human habitation, water bodies and nearby forest
due to this mining activity. The dust emissions due to blasting are
minimal and settle in a short time.The dust in the muck pile will be
suppressed by sprinkling water. No solid waste and liquid effluents will
be generated during mining activity. The river Chitravathi is at a
distance of 14 Km east of the site.As there are no waste materials
generated, there is no possibility of dumping the pollutants in
neighboring rivers, nalas and tanks.
4. SITE ANALYSIS:
i) Connectivity:
The site has good connectivity as National Highway (NH 44)
connecting Hyderabad with Bangaloreis at about 2.0kmsin East..The
nearest rail headHindupuram of South Central Railway is at22 Km
distances. A black topped road connects the quarry site with the
National Highway.
ii) Land Form, Land Use and Land Ownership:
The lease area is located along the southern slopes of the
hills(Δ731)Southern Eastoccurring 2.0 kmSWfromVedidakala The
land forms observed on the hill are domal,elephant back, sheetrock,
pediment slope, split boulder, strewn boulder and stray boulder. All
around the hill the country is with adulatory topography covered with
black and deep back soils of high fertility nature. In the surrounding
area paddy, chilies’ and pulses are grown. The quarry land belongs
to the Govt. of Andhra Pradesh.
13
iii)Topography (along with map):
The lease area is along the southern slopes of massive hills(Δ 731)
the elevation difference between the ground level to highest point of
the lease area is7m. The MSL of the base point of the quarry area is
640m.The location of the lease area is marked on Survey of India
ToposheetNo.57G/9, which depicts the altitudes and other
Topographic features with in 5 Km radius of the site.
iv)Existing land use pattern (agriculture, non-agriculture, forest,
water bodies(including area under CRZ)), shortest distances
from the periphery of the project to periphery of the forests,
national park, wild lifesanctuary, eco sensitive areas, water
bodies ( distance from the HFL of the river), CRZ. In case of
notified industrial area, a copy of the Gazette notification should
be given:
Except for the hill tracks, the surrounding plain country with highly
fertile nature is used for cultivation for the crops like Groundnut ,
Jowar , Red Gram, Horse Gram, maize etc. As such there are no
major water bodies nearby except for the ChitravathiRiver at a
distance of15km in East. The minor village irrigation velidadakala
irrigation tankare at 2 km northeastThe project is located at 1.0 km
west of Errakonda R F. There are no National parks, wild life
sanctuaries and eco-sensitive areas in nearby.There are no notified
Industrial areas in nearby.
14
v)Existing Infrastructure:
Since it is small mine no permanent structures are built.However, need based temporary structures are constructed for providing basic emanates to the work force.
vi)Soil classification:
There is no soil in the quarry area as it is a rocky exposure all over
the quarry area.
vii ) Climatic data from secondary sources:
The area falls in semi arid region and experiences maximum
temperature of 43°C in summer during April & May, while minimum
temperature of 18°Cin winter during December & January. The
average rain fall is of the order of 650 mm/year.The area experiences
maximum rain fall due to SW monsoon during June–September. It
also receives rain fall due to NE monsoon during November and
December.
viii)Social Infrastructure available:
The surrounding villages are well developed and are well connected
to the major Cities like Banglore,Anantapur,Hindupurand towns like
Penukonda,Gorantla, Puttaparthi, etcarewell-maintained black topped
wide roads.The towns which are nearby are equipped with good
educational, hospital and communication facilities.
15
5. PLANNING BRIEF:
i) Planning Concept (type of industries, facilities, transportation etc) Town and county Planning/Development authority Classification: This quarry operation exists for more than a decade and hence it is in
the knowledge of the Town and County Planning Departments. As
such, medical, educational and transport facilities are well developed
in nearby Cities and Towns and they can be made use of by the
working personnel in the mine.
ii)Population Projection:
The population of the vil lages fall ing within 5 Km radius as
indicated below:
Vil lage Population
Peddireddipal l i 950
Velidedakala 880
Jangalapall i 860
Cherlopal l i 900
(source:Censes 2011)
iii)Land use planning (breakup along with green belt etc):
This is a small quarry which is located on a hill slope and hence there
is no scope for green belt development until the operation is
completed. However, after the quarrying operations are over the
degraded area due to quarrying shall developed as a green belt area
by reclamation. The reclamation of the quarry pit is by refilling.
iv)Assessment of Infrastructure Demand (Physical &Social):
16
There are well developed infrastructural facilities in the nearby areas of the lease hold. Hence, there is no need to go for any such projects within the lease area or in nearby area.
v)Amenities/Facilities:
Since the area is inclose proximitywith the developed cities and
towns, the educational, medical and communication facilities
available there can make use of. Besides, need based
facilities/services arealso provided by the proponent.
Vi). Proposed Infrastructure:
i)Industrial Area (Processing Area): There are no demarcated specified industrial zones in the
area.However depending on the market demand a number of stone
crushing units wereestablished within the reasonabledistances.
ii)Residential Area (Non Processing Area):
No residential constructions are proposed in the area since there are
good number of villages (within 5 km distance) which can be make use
for staying by the quarry workers.
iii)Green Belt:
After the closure of the quarry development of green belt is proposed
after reclamation.
iv)Social Infrastructure:
The area is very well accessible.
v)Connectivity (Traffic and Transportation Road/
Rail/Metro/Water ways etc):
17
The quarry area is at about 2.0 kmdistance from the National Highway
No NH44and is also at a distance of about90 Km from Ananthapur.
Therefore, it has very good road and rail connectivity.
vi)Drinking Water Management (Source & Supply of water):
All the nearby villages are having potable water source from the local
bodies and hence there is no problem for potable water supply.
vii)Sewerage System:
The project as such is devoid of human habitation and hence no
need to have the linkage with sewerage system.
viii)Industrial Waste Management:
No industrial waste management is required since no waste
materialis generated.
ix)Solid Waste Management:
No solid waste management since there is no solid waste is
generated in the quarry operations.
x)Power Requirement & Supply / source: No power requirement,since the operations are confined to day time
only.
CONCLUSIONS:
In the light of the above explanations, in order to meet the basic
requirements of mankind such as Rods, buildings and infrastructure