Upload
doandan
View
233
Download
4
Embed Size (px)
Citation preview
Standalone Grinding Cement Industry
M/s HEMAVATHI CEMENT INDUSTRIES
PRE-FEASIBILITY REPORT
On
Establishment of Standalone Grinding Cement Industry (102 TPD)
At
KIADB Industrial Growth Centre, Survey no 52-P, Plot No. 246 & 247, Nagathavalli Village, Kasaba Hobli, Hassan Taluk-573201,
Hassan District Karnataka.
For
M/s. Hemavathi Cement Industries Hassan
Environmental Consultants
M/s. Aqua Tech Enviro Engineers,
(Environmental Engineers & Consultants)
# 3391, 6th Main, 3rd Cross, RPC Layout,
Vijayanagar II Stage, Bangalore – 560 040
Tele Phone: 080: 23141679
Fax: 080:23148166
E-mail: [email protected]
Standalone Grinding Cement Industry
M/s HEMAVATHI CEMENT INDUSTRIES
CONTENTS Sl. No. Particulars Page No.
Chapter-1 Executive Summary
1.1 Introduction 1
1.1.1 Preamble 1
1.1.2 Site Location 1
1.1.3 Project at a Glance 2
1.1.4 Project Setting 2
Chapter-2 Introduction of Project Proponent
2.1 Introduction of Project Proponent/ Project 3
2.2 Need for the project and its importance to the country and/region
3
2.3 Demand Supply gap 3
2.4 Domestic / Export markets 3
2.5 Employment generation due to the project 4
Chapter-3 Project Description
5-19
3.1 Location 5
3.2 Basis of selecting the Proposed Site 7
3.3 Size/Magnitude of Operation 7
3.4 Equipment Details 7
3.5 Raw materials, Sources & Transportation 8
3.6 Description of the Process 10
3.7 Products Manufactured 13
3.8 Water Requirement 13
3.9 Power Requirement 13
3.10 Stack Details 14
3.10.1 Working principle of Reverse jet Bag filter 14
3.11 Water and Wastewater Management 15
3.11.1 Water consumption and Wastewater generation details 15
3.11.2 Design details for septic tank 16
3.12 Solid Waste Disposal System 18
3.13 Schematic Representation of the Feasibility Drawing Which Give Information Of EIA Purpose
19
Chapter-4 Site Analysis
4.1 Connectivity 20
4.2 Land Form, Land Use & Ownership 21
Standalone Grinding Cement Industry
M/s HEMAVATHI CEMENT INDUSTRIES
4.3 Topography 22
4.4 Existing Land-Use Pattern 23
4.5 Existing Infrastructure 23
4.6 Soil Classification 24
4.7 Climatic data from secondary source 24
4.8 Social Infrastructure Available 28
Chapter-5 Planning Brief
5.1 Planning concept 29
5.2 Population projection 29
5.3 Land use planning 29
5.4 Assessment of infrastructure demand 29
5.5 Amenities/facilities 29
Chater-6 Proposed Infrastructure
6.1 Industrial area 30
6.2 Residential area 30
6.3 Green belt 30
6.4 Connectivity 30
6.5 Drinking water management 30
6.6 Sewerage System 30
6.7 Industrial Waste Management 30
6.8 Solid Waste Management 31
6.9 Power requirement & supply/ source 31
Chapter-7 Rehabilitation & Resettlement Plan
32
Chapter-8 Project Schedule & Cost Estimates
32
8.1 Time Schedule 32
8.2 Estimated Project Cost 32
Chapter-9 Analysis of Proposal
33
TABLES & FIGURES
TABLES
3.1 Capital Investment of the project 7
3.2 Raw material consumption for GGBS & Cement Manufacturing per day
10
3.3 Flue Gas Stacks 14
3.4 Water Consumption and Wastewater Generation pattern 15
3.5 Solid Waste Generation and Disposal 18 4.1 Connectivity from the Project Site 20
4.2 Land Use Planning 21
Standalone Grinding Cement Industry
M/s HEMAVATHI CEMENT INDUSTRIES
4.3 Existing Land-Use Pattern 23
4.4 Meteorological Data of Koppal for the Year 2014 24
4.5 List Of infrastructural facilities in the surroundings 28
8.1 Time Schedule for the Project 32
8.2 Capital Investment on the Project 32
FIGURES
1.1 Location map 2
3.1 Maps Showing Project Boundary & Project Site Location 5
3.2 Project location shown on Map 6
3.3 Google Map Showing Distance Between Udupi Power Plant to Hassan Railway Station
9
3.4 Google Map Showing Distance Between M/s. Zuari Cements to Hassan Railway Station
9
3.5 Google Map Showing Distance Between Puducherry Railway Station to Hassan Railway Station
9
3.6 Manufacturing process Flow chart for producing OPC cement from Clinker
13
3.7 Reverse Jet Bag Filter 14
3.8 Water Balance Chart 16
4.1 Google Map Showing the Site Connectivity 20
4.2 Site Photographs 21
4.3 Land Use Map 22
4.4 Topo map showing the Project Site 23
4.5 Wind rose Diagram 27
Standalone Grinding Cement Industry
1
Chapter-1 EXECUTIVE SUMMARY
1.1 INTRODUCTION 1.1.1 PREAMBLE
Amendment of the Environmental Impact Notification No. S.O. 60(E) dated
27.01.1994, issued by the MoEF, Govt. of India has made mandatory under
Schedule-I of EIA notification for 30 different activities to obtain NOC (No
Objection Certificate) from the State Pollution Control Board and Environmental
Clearance from the Ministry of Environment & Forests, Govt. of India. This
amendment to the EIA Notification is effective from 14.09.2006.
As per the amended EIA notification dated 14th September, 2006 the cement plants
less than 1.0 million tonnes/annum production capacity & all standalone grinding
units will fall under category B schedule 3(b). The proposed project capacity is 102
TPD, Therefore this project comes under category B schedule 3(b) and therefore
necessitates Environmental Clearance.
1.1.2 SITE LOCATION:
The proposed project lies at KIADB Industrial Growth Centre, Plot No. 246 & 247
(Survey no 52-P) of Nagathavalli Village, Kasaba Hobli, Hassan Taluk-573201,
Hassan District Karnataka. The project is located at an aerial distance of 3 Km
from Hassan towards North direction. The locations falls at Latitude:
12°58'15.98"N; Longitude: 76°07’06.82"E; MSL 974m. The Google image appended
provides the topographical features of the area surrounding the project site.
Standalone Grinding Cement Industry
2
Fig 1.1 PROJECT SITE LOCATION MAP
1.1.3 PROJECT AT A GLANCE
1.1.4 PROJECT SETTING Site Bearings
Sl.No. Particulars Direction w.r.t. project site
1 Hassan North
2 SH 57 East
Sl. No. Details
1 Project Establishment of Standalone Grinding Cement Industry of 102 TPD Capacity
2 Project developers M/s. Hemavathi Cement Industries
3 Location of the site KIADB Industrial Growth Centre, Plot No. 246 & 247 (Survey no 52-P) of Nagathavalli Village, Kasaba Hobli, Hassan Taluk-573201, Hassan District Karnataka.
4 Constitution of the Organization
Partnership
5 Total Plot Area 3969 sq. m
6 Project cost Rs. 1,47,00,000/-
(Rupees One Crore forty seven Lakhs only.)
Project Site
Standalone Grinding Cement Industry
3
Chapter-2 INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION
2.1 INTRODUCTION OF PROJECT PROPONENT/ PROJECT M/S. Hemavathi Cement Industries Intends to Establishment of Standalone
Grinding Cement Industry of 102 TPD Capacity at KIADB Industrial Growth Centre,
Plot No. 246 & 247 (Survey no 52-P) of Nagathavalli Village, Kasaba Hobli, Hassan
Taluk-573201, Hassan District Karnataka. The Location Map of the Project site is
appended in the Figure 1.1.
2.2 NEED FOR THE PROJECT AND ITS IMPORTANCE TO THE COUNTRY
AND/REGION
The market for cement manufacturing has growth potential due to the central
government liberalization policies and new schemes for housing, road projects.
Cement demand growth is anticipated to be about 9 to 10% increase mainly
through National Highway road projects, Housing Projects (1.3 million houses in
rural & 0.7 million in urban areas). Continuous demand for exports to China and
other South-East Asian countries along with the increased requirement of the
domestic sector.
Karnataka ranks 7th in terms of production of cement in the country. There are 16
Cement industries in Karnataka producing around 11 million tons per annum of
cement production.
Establishment of M/s. Hemavathi Cement Industries will able to meet the cement
demand locally and provide employment opportunities to the local people.
2.3 DEMAND SUPPLY GAP Demand for cement is ever increasing due to large scale infrastructure projects
that are being undertaken across the country and demand for cement in particular
is always felt and therefore to meet the demand of the market M/s. Hemavathi
cement industries intends to establish Cement manufacturing industry.
2.4 DOMESTIC / EXPORT MARKETS This new project is proposed to meet the domestic markets demand.
Standalone Grinding Cement Industry
4
2.4 EMPLOYMENT GENERATION DUE TO THE PROJECT Man power requirement for the proposed project during construction phase will be
about 50, operation phase will be about 15 workers. The establishment of the
proposed cement industry will also lead to indirect employment generation.
Standalone Grinding Cement Industry
5
Chapter-3
PROJECT DESCRIPTION
3.1 LOCATION
The proposed Project is KIADB Industrial Growth Centre, Plot No. 246 & 247
(Survey no 52-P) of Nagathavalli Village, Kasaba Hobli, Hassan Taluk-573201,
Hassan District Karnataka.
Fig-3.1: Maps Showing Project Boundary & Project Site Location Note: Latitude: 15°22'26.13"N; Longitude: 76°14’30.30"E.
Standalone Grinding Cement Industry
6
Fig 3.2 Project location shown on Map.
Standalone Grinding Cement Industry
7
3.2 BASIS OF SELECTING THE PROPOSED SITE
The proposed site is in KIADB Industrial growth center. It is well connected with
roads with easy access for raw materials and transportation of finished product.
The site is 3 km from the Hassan, 3.5 km from Hassan railway station, 0.1 km from
SH 57. There are no forest area, water bodies & ecological sensitive areas within 5
km from the project site. Under such circumstances the site selected for the
proposed project is environmentally feasible to put up cement plant.
3.3 SIZE/MAGNITUDE OF OPERATION
The proposed project is establishment Standalone grinding cement Industry of 102
TPD Capacity.
The total capital investment on the project is Rs. 1.47 Crores, the details of which
are appended in the following table.
Table 3.1: Capital Investment on the Project
Sl. no.
Description Cost in Rupees
1 Land Rent advance Value 5,00,000/-
2 Plant and machinery 1,42,00,000/-
TOTAL 1,47,00,000/-
Rupees One Crore forty seven Lakhs Only.
3.4 EQUIPMENTS DETAILS The list of machinery and equipments proposed to be used are listed below
1. Hoppers
2. Ball Mill
3. Screw Conveyer
4. Elevator
5. Dust Collector- Bag Filter
6. Silo- 50 tons
Standalone Grinding Cement Industry
8
3.5 RAW MATERIALS, SOURCES & TRANSPORTATION.
The Raw materials required for this project are Clinkers, Fly ash and Gypsum. Raw
materials like clinker will be procured from M/s. Zuari Cements & M/s. Bharati
Cements, Kadapa district, Andra Pradesh which is about 442 Km from Hassan
railway station. The fly ash will be procured from Udupi Thermal Power Plant 206
km from Hassan railway station. The Gypsum will be purchased from Saravana
fertilizers Ltd., Puducherry, Tamil Nadu about 565 km from Hassan railway station.
90% of the Raw materials & products will be transported through railway wagons
from Hassan railway station which is about 3.5 km from project site. 10%
transportation will be through roadways.
Sl.No
Raw Materials
Source of Raw Materials
Raw material procurement Distance
Mode of Transportation
Distance of railway station from project site
1 Clinkers M/s. Zuari Cements & M/s. Bharati Cements, Kadapa district, Andra Pradesh.
442 Km Industry having Railway sidings (Wagons)
Hassan Railway station, 3.5 Km
from site 2 Fly ash Udupi Power
Plant 206 Km Railways
3 Gypsum Saravana fertilizers Ltd., Puducherry
565 km Railways
Standalone Grinding Cement Industry
9
Fig: 3.3 Google Map Showing Distance between Udupi Power Plant & Hassan Railway Station
Fig: 3.4 Google Map Showing Distance between M/s. Zuari Cements Kadapa, AP,
& Hassan Railway Station
Standalone Grinding Cement Industry
10
Fig: 3.5 Google Map Showing Distance between Puducherry Railway Station & Hassan Railway Station
Table 3.2 Raw Material Consumption Cement Manufacturing
Sl.No Particulars In Tons/day
1 Clinkers 80
2 Fly ash 20
3 Gypsum 2
Total 102
3.6 DESCRIPTION OF THE PROCESS
1. PROJECT DESCRIPTION WITH PROCESS DETAILS
The most common raw materials used for cement production are Limestone, Chalk
and Clay. The major component of the raw materials, the Limestone or Chalk Is
usually extracted from a quarry adjacent to or very close to the plant. Limestone
provides the required Calcium oxide and some of the other oxides, while Clay,
Shale and other materials provide most of the Silicon, Aluminum and iron oxides
required for the manufacture of Portland cement. The raw materials are selected,
crushed, ground and proportioned so that the resulting mixture has the desired
Standalone Grinding Cement Industry
11
fineness and chemical composition for delivery to the pyro-processing systems. It
is often necessary to raise the content of silicon oxides or iron oxides by adding
quartz sand and iron ore respectively. The quarried material is reduced in size by
processing through a series of crushers. Normally primary size reduction is
accomplished by a jaw or gyratory crusher, and followed by secondary size
reduction with a roller or with a hammer mill. The crushed material is screened
and stones are returned
After primary and secondary size reduction, the raw materials are further reduced
in size by grinding. The grinding differs with the pyro-processing process used. In
dry processing, the materials are ground into a flow able powder in horizontal ball
mills or in vertical roller mills. In a ball (or tube) mill, steel alloy mills (or tubes)
are responsible for decreasing the size of the raw material pieces in a rotating
cylinder referred to as a rotary mill. Rollers on a round table fulfill this task of
communition in a roller mill. Utilizing waste heat from the kiln exhaust, clinker
cooler hood or auxiliary heat from a standalone air heater before pyro-processing
may further dry the raw materials.
2. Clinker Production (Pyro-Processing):
Clinker is produced by pyro-processing in large kilns. This kilns systems evaporate
the inherent water in raw meal, calcine the carbonate constituents (calcinations),
and form cement minerals (clinkerization). The ground raw material fed, into the
top of the kiln moves down the tube countercurrent to the flow of gases and
towards the flame-end of the rotary kiln, where the raw material is dried,
calcined and enters into the sintering zone. In the sintering (or clinkering) zone,
the combustion gas reaches the temperature of 3300-3600 o F. while many
different fuels can be used in the kiln, coal has been the primary fuel in a wet
rotary kiln the raw meal typically contains approximately 36% moisture. These
kilns were developed as an upgrade of the original long dry kiln to improve the
chemical uniformity in the raw meal. The water (due to the moisture content of
raw meal) is first evaporated in the kiln at the lower temperature zone. The
evaporation step makes a long kiln necessary. In a dry rotary kiln, feed material
Standalone Grinding Cement Industry
12
with much lower moisture content (0.5%) is used, thereby reducing the need for
evaporation and reducing kiln length. Once the clinker is formed in the rotary kiln,
it is cooled rapidly to minimize the formation of a glass phase and ensure the
maximum yield of alite (Tri-calcium silicate formation). An important component
for hardening properties of cement. The main cooling technologies are either the
grate cooler or the tube or planetary cooler. In the grate cooler, the clinker is
transported over a reciprocating grate through which air flows perpendicular to
the flow of clinker. In the planetary cooler, (a series of tubes surrounding the
discharge end of the rotary kiln), the clinker is cooled in a countercurrent air
stream. The cooling air is used as secondary combustion air for the kiln.
3. M/s. Hemavathi Cement Industries Production Process Starts from bringing
Clinker fed to Silos and further cement manufacturing process carried out in
the industry is as under.
1. Cement Manufacturing Process
After cooling, the clinker can be stored in the clinker dome, silos and bins or
outside. The material handling equipment is used to transport clinkers from the
clinker cooler to storage and then to finish mills similar to that used to transport
raw materials (e.g., belt conveyors, deep bucket conveyors and bucket elevators).
To produce powdered cement, the nodules of cement clinker are ground to the
consistency of face powder. Grinding of cement clinker together with additions (3-
5% gypsum to control the settling properties of the cement) can be done in ball
mills, ball mills in combination with roller presses, roller mills or roller presses.
Traditionally, ball mills are used in finish grinding, while many plants are vertical
roller mills. In ball or tube mills, the clinker and gypsum are fed into one of a
horizontal cylinder and partially ground cement exists from the other end.
Packing & Dispatch:
The cement produced as described above will be tested for quality control and
packed in 50 kg bags transported in closed trucks. Process Flowchart is shown in
figure-3.6
Standalone Grinding Cement Industry
13
Figure- 3.6 Manufacturing process Flow chart for producing OPC cement from
Clinker
3.7 PRODUCTS MANUFACTURED The products manufactured Portland Puzulona Cement (PPC) and Ordinary
Portland Cement (OPC).
3.8 WATER REQUIREMENT
Total fresh water consumption for the proposed terminal will be 11 KLD. And
water will be sourced from the KIADB water supply source.
3.9 POWER REQUIREMENT The power requirement for the proposed project is 100 KVA and it will be
augmented from CESCOM (Chamundeshwari Electricity Supply Company Limited).
GYPSUM Fly ash CLINKER
BALL MILL
CEMENT
PACKING
DRIER
(Optional)
DISPATCH
Standalone Grinding Cement Industry
14
3.10 STACK DETAILS Table 3.3: Flue Gas Stacks
Sl. No.
Stack Attached To
Stack Height, m
Stack Top Diameter,m
Specifications
1 Bag filter connected to Ball Mill
5 m AGL
0.2 No. of bags- 25 bags Bag size 130 mm 3000mm long
2 DG Set 100 KVA, 1 No.
3 m ARL - -
Fig- 3.7 Reverse Jet Bag Filter
3.10.1 WORKING PRINCIPLE OF REVERSE JET BAG FILTER
The vacuum pressurized dusty air or gas enters into the filter body through a hole
below the casing. The motion of the air is towards the bags and the dust particles
coming with the pressurized air accumulate on the outer surface of the filter of
the bag. The clean air that enters the bag passes through the venturi to reach the
clean air chamber and leaves out the system through exhaust mechanism.
The porosity of the bags becomes lower because of the formation of a cake layer
of dust on the outer surface of the filters. The porosity of the bags are kept within
set limits by means of a reverse pressure mechanism meant for balancing the
pressure difference between the clean and filthy gas chambers.
Through the periodic signal generated by the timer unit, the solenoid valves are
energized at some intervals for periods to last less than 0,1 sc. and the highly
pressurized air is forced into the blowpipes. The air, thus pressurized, is sprouted
Standalone Grinding Cement Industry
15
through the holes on the blowpipes in the venturis. The pressurized and highly
accelerated air, while passing through the venturi, creates a secondary current
several times stronger than itself. In other words, the highly, pressurized and
accelerated air in the venturi is combined with the air in the clean air chamber to
create sudden but shortly lasted pressure increases in the clean air chamber. It is
this momentary pressure that creates a reverse effect to clean the pores between
the fibres of the bags. The designated flow rate does not fluctuate as a result of
this reverse effect because only a given group of filters are subjected to this
process of cleaning at a time. The efficiency of the filters reaches 99% after
formation of cake layers of dust on the outer surfaces of the filters. Bag cleaning,
therefore, should not damage the cake layers.
3.11 WATER AND WASTEWATER MANAGEMENT 3.11.1 WATER CONSUMPTION AND WASTEWATER GENERATION DETAILS Total fresh water consumption for the proposed terminal will be 11 KLD water will
be sourced from the KIADB water supply source.
Waste water generation quantity will be 0.6 KLD. It will be treated in septic tank
& soak pit.
There will be no disposal of untreated water on land so impact on groundwater
quality due to proposed activity is not anticipated.
Break up of water consumption and wastewater generation along with disposal
mode in given in Table 3.4. The water balance chart for the project is provided in
the Fig. 3.9
Table 3.4: Water Consumption and Wastewater Generation Pattern
Sl.
No
.
Description Quantity in KLD Disposal Mode
Water
Consumption
Waste water
generation
1. Domestic 0.7 0.6 Treated in Septic
Tank and Discharged
to soak pit. 2 Gardening 5 -
3 Industrial Purpose* 5 -
Total 10.7 or say
11
0.6 KLD
* Utilized for Dust suppression by sprinkling
Standalone Grinding Cement Industry
16
Figure 3.8: Water Balance Chart
3.11.2 Design Details for Septic Tank
The septic tank is designed as per the I.S 2470 Part-I & Part-II
ASSUMPTIONS
Total quantity of wastewater generated = 0.6 m3/day. However, the septic tank
and soak pit are designed for sewage inflow of 0.8 m3/day
Note:
Assuming
rate of deposited sludge as 30 L/capita/year
detention time as 24 hours
KIADB WATER SUPPLY SOURCES
Total water requirement is 11 KLD
Domestic use is 0.7 KLD Gardening is 5 KLD
Waste water generation
0.6 KLD
Dust Suppression by
Sprinkling, 5 KLD
Septic Tank & Soak Pit
Standalone Grinding Cement Industry
17
period of cleaning as one year
The volume of sludge deposited = (12 x 30 x 1)/1000 = 0.36 m3
Therefore the total capacity of tank required
= Volume of sewage + Volume of sludge
= 0.8 + 0.36 = 1.16 m3
Now assuming 1.5 m SWD, we have
The floor area of the tank = 1.16/1.5 = 0.8 m2
Let us assume length is thrice the width
3 B2 = 0.8 m2
B = 0.5 m
L = 3 x 0.5
= 1.5 m
However from the practical point of view keep minimum, proposed to provide a
septic tank of size 1.5 m x 0.5 m x 1.8 m (1.5 + 0.3 free board) depth with inlet
and outlet chambers, baffles, sludge withdrawal pipe with valve and covered with
RCC slab with air vent etc. complete.
Design details for soak pit
The soak pit is designed as per IS 2470 Part – I and Part – II
The soak pit is designed by assuming the percolating capacity of the soaking media
as 1,250 L/m3/day.
Therefore, Volume of soaking media required for soak pit= 800/1,250 = 0.64 m3
Let the depth of the soak pit be 1.5 m.
Therefore, area of soak pit = 0.64/1.5 = 0.42 m2
Therefore, diameter = 0.7 m
Therefore provide soak pits of 0.7 m dia and 1.5 m depth
Standalone Grinding Cement Industry
18
3.12 SOLID WASTE DISPOSAL SYSTEM Details of the solid waste and its quantity, disposal system are mentioned in Table
3.5.
Table 3.5: Solid Waste Generation and Disposal
Total no. of workers 15
Assuming per capita solid waste generation rate as 0.25 kg/capita/day
Quantity of solid waste generated 4 kg/day
Organic solid waste : 60 % of the total waste 2.4 kg/day
Inorganic solid waste : 40 % of the total waste 1.6 kg/day
The solid Wastes generated will be collected, composted in compost pits and the
product will be used as manure for landscape development.
Standalone Grinding Cement Industry
19
3.13 SCHEMATIC REPRESENTATION OF THE FEASIBILITY DRAWING WHICH GIVE INFORMATION OF EIA PURPOSE
Standalone Grinding Cement Industry
20
Chapter-4 SITE ANALYSIS
4.1 CONNECTIVITY The well laid road network is available till the project site. State highway 57 apart
from this the railway connectivity from most of the parts which is about 3.5 km.
The major connectivity to the project is provided with distance and site bearing in
table 4.1 as under.
Table 4.1: Connectivity from the Project Site
Sl. No.
Road Distance from the project site (km) aerial distance
Direction w.r.t. project
site
1 Hassan 3 North
2 Hassan Railway Station 3.5 North East
3 SH- 57 0.1 East
4 Nearest Air strip, Mysore 100 South east
Fig: 4.1 Google Map Showing the Site Connectivity.
Project site
SH-57
Mysore Road
Standalone Grinding Cement Industry
21
4.2 LAND FORM, LAND USE & OWNERSHIP
The proposed site is in KIADB Industrial growth center. The surrounding places of
site are small industries and minor agricultural land. The site is well connected
with roads.
Table 4.2 Land Use Planning
Sl.No. Details Area in sq.mt.
1 Total plot area 3969
2 Green belt area 1192
3 Paved area 993
4 Built up area 1140
5 Open area 644
Figure 4.2 Site Photographs
Standalone Grinding Cement Industry
22
Fig 4.3 Land Use Map
4.3 TOPOGRAPHY
The M/s. Hemavathi Cement Industries is located at Latitude: 12°58'15.98"N;
Longitude: 76°07'06.82"E, 974 above MSL; Google map is appended as Fig.3.1. The
topo map of the area is provided in fig 4.4
Standalone Grinding Cement Industry
23
Fig- 4.4 Topo Map Showing the Project Site
4.4 EXISTING LAND USE PATTERN
Table 4.3: Existing Land-Use Pattern
Sl. No. Particulars Details
1 Agriculture Minor Activities
2 National park, forest No National park is located near the project site
3 Water bodies No water Bodies within 5 kms
4 Land Allotment KIADB Industrial Growth center 4.5 EXISTING INFRASTRUCTURE
The proposed site is well connected with roads Apart from this there are other
infrastructure is electricity to the place from CESCOM.
Project Site
Standalone Grinding Cement Industry
24
The list of existing infrastructure at the project site is
1. Portable water for the workers will be augmented from KIADB Water supply
sources.
2. Power supply from CESCOM
4.6 SOIL CLASSIFICATION
The soils of the district display a wide diversity and are quite fertile. The main soil
types are Red soil, Red sandy soil, mixed soil and Silty clay soil. The soils in the
western taluks are derived from granites, laterites and schists. These soils are
shallow to medium in depth and the color changes with depth from red at the
surface and red and yellow mottles at depth. The soils are suitable for coffee,
cardamom, areca, paddy and sugarcane crops.
4.7 CLIMATIC DATA FROM SECONDARY SOURCE
Table 4.4 Meteorological Data of Hassan for the Year 2014
Month Temperature 0C
Relative humidity %
Precipitation rate (inches)
Atmospheric pressure (mb)
Wind speed (m/s)
Wind direction (from)
Inversion / mixing height (m - max)
Cloud cover (tenths)
Min Max Min Max Ave Min Max Min Max Min Max
Jan 12.7 27.8 36 65 0 940 957 0 5.1 NE 652 2 10
Feb 15.2 30.3 42 59 2 938 955 0 4.6 NE 594 2 10
Mar 18.2 32.7 33 63
7 944 956 0 6.2 NE & NW
681 2 10
Apr 20.1 32.9 33 71 58 943 954 0 5.8 SW 783 2 7
May 21.1 31.1 32 55 97 944 952 0 5.7 SW 783 2 10
June 19.4 26.6 40 59 84 941 950 0 8.6 SW 1324 2 10
July 19 24.6 46 74 167 942 952 1.5 9.2 SW 1563 3 10
Aug 18.8 25.2 50 79 94 942 951 1.5 9.4 SW 1421 3 10
Sept 18.4 26.3 31 76 85 943 953 1 8.2 SW 1210 2 10
Oct 18.5 27.2 34 69 152 946 954 0 6.5 NE 762 2 10
Nov 16.9 26.8 38 58 51 948 956 0 7.6 NE 1051 2 10
Dec 14.0 26.5 37 56 9 949 956 0 7.6 NE 1057 2 10
Standalone Grinding Cement Industry
25
1. TEMPERATURE
The mean maximum temperature is observed at (32.9°C) in the month of April and
the mean minimum temperature at (12.7°C) is observed in the month of January.
In the summer season the mean minimum temperature is observed during the
month of March (18.2°C). During the monsoon the mean maximum temperature is
observed to be 26.6°C in the month of June with the mean minimum temperature
at 18.4°C during September. By the end of September with the onset of post
monsoon season (October - November), day temperatures drop slightly with the
mean maximum temperature at 31.6°C in October and mean minimum
temperature is observed at 17.2°C in November. The values are presented in table
4.4
2. RELATIVE HUMIDITY
Minimum and maximum values of relative humidity have been recorded. The
minimum humidity is observed to be at 31% in the month of September and the
maximum is 79% in the month of August. The mean minimum values of humidity
during summer, monsoon, post-monsoon and rainy seasons are 32%, 31%, 34% &
36% during the months of May, September, October and January respectively.
Similarly the maximum values are 79%, 76%, 74%, 71% in the months of August,
September, July & April during the summer, monsoon, post monsoon & winter
seasons. The values are presented in table 4.4.
3. RAINFALL
The monsoon in this region usually occurs twice in a year i.e. from June to
September and from October to November. The maximum annual rate of
precipitation over this region an average 19 inches
4. ATMOSPHERIC PRESSURE
The maximum and the minimum atmospheric pressures are recorded during all
seasons. In the summer season, the mean maximum and minimum pressure values
are observed to be 956 mb in the month of March and 944 mb in the months of
April & May. During monsoon season, the maximum pressure is 953 mb and
minimum 942 mb. The maximum pressure during the post-monsoon season is
observed to be 956 mb in November and minimum pressure is 946 mb in the month
Standalone Grinding Cement Industry
26
of October. During the winter season the minimum atmospheric pressure is 946 mb
in February and the maximum is 957 mb in the month of January. The values are
presented in table 4.4
5. WIND
The data on wind patterns are pictorially represented by means of wind rose
diagrams for the entire year as figure 4.4
Predominant wind directions
Season Period Wind direction
Summer March to May South West
Monsoon June to September South West
Post monsoon October to November North East
Winter December to February North East
6. INVERSION HEIGHT
The maximum inversion heights at the project site for all the months of the year is
as given in the table 3.1. The maximum mixing height of 1563 m is observed during
the month of July and the minimum inversion height is 594 m in the month of
February.
7. CLOUD COVER
The minimum cover measured in the unit of tenths is 2 and the maximum observed
cloud cover is 10.
Standalone Grinding Cement Industry
27
FIG 4.4 WIND ROSE DIAGRAM
Standalone Grinding Cement Industry
28
4.8 Social Infrastructure Available
Infrastructure is the basic physical and organizational structures needed for the
operation of a society or enterprise or the services and facilities necessary for an
economy to function.
The term typically refers to the technical structures that support a society, such
as roads, water supply, sewers, electrical grids, telecommunications and so forth
and can be defined as "the physical components of interrelated systems providing
commodities and services essential to enable, sustain or enhance societal living
conditions.
Viewed functionally, infrastructure facilitates the production of goods and
services, and also the distribution of finished products to markets, as well as basic
social services such as schools and hospitals; for example, roads enable the
transport of raw materials to a factory
Table-4.5 List of infrastructural facilities in the surroundings
Sl. No.
Hospital Distance from the industry
Direction w.r.t. the industry
1 Hassan Institute of medical science, Hassan
4 North-west
2 Hemavathi Hospital 5 North-west
3 Hassan Public School 5 North-west
4 Hassan railway station 3.5 North-East 5 Malnad College of
Engineering 5.3 North
Standalone Grinding Cement Industry
29
Chapter-5
PLANNING BRIEF
5.1 PLANNING CONCEPT
M/S. S.S.R Cement Industries proposed to set up GGBS & Cement manufacturing
Industry at KIADB Industrial Growth Centre, Survey no 52-P, Plot No. 246 & 247, of
Nagathavalli Village, Kasaba Hobli, Hassan Taluk-573201, Hassan District
Karnataka. The proposed capacity is 100 TPD.
5.2 POPULATION PROJECTION
The total Population of Hassan district as of census 2011 is 17,76,42.
5.3 LAND USE PLANNING
Table 5.1 Land Use Planning
Sl.No. Details Area in sq.mt.
1 Total plot area 3969
2 Green belt area 1192
3 Paved area 993
4 Built up area 1140
5 Open area 644
5.4 ASSESSMENT OF INFRASTRUCTURE DEMAND
There is existing Railway station at about 3.5 km for receiving & dispatch of
materials.
The road network SH-57 which connects many places in Karnataka.
Interior roads are already available for dispatch of material for local
consumers.
Locally available man power will be utilized
The transport vehicle will be hired based on requirement.
5.5 AMENITIES/FACILITIES
Proper site services such as with Drinking water, safety equipments & first Aid will
be provided to the workers.
Standalone Grinding Cement Industry
30
Chapter-6
PROPOSED INFRASTRUCTURE
6.1 Industrial area (Processing area)
The proposed site is in KIADB Industrial Growth Centre Hassan district. The total
plot area is 3969 Sq.m.
6.2 Residential Area (Non processing area)
The non-processing area is green belt and open area which is about 1836m2
6.3 GREEN BELT
The green belt area is about 1192 m2 about 30% of total plot area.
6.4 CONNECTIVITY
The site is well connected with roadways. State highway 57 about 0.1 km from site
apart from this the railway connectivity from most of the parts which is about 3.5
km.
6.5 DRINKING WATER MANAGEMENT
The Potable water required for the workers will be augmented through KIADB
Water supply sources.
6.6 SEWERAGE SYSTEM
The sewage generated from the working people in the project is planned to
discharge to proposed Septic Tank and soak pit designed as per the IS 2470 Part II
(1985). The overflow if any during the operation phase would be planned dispose
to the nearest sewer network either through pumping or through tanker.
6.7 INDUSTRIAL WASTE MANAGEMENT
No trade effluent will be generated from the project.
Standalone Grinding Cement Industry
31
6.8 SOLID WASTE MANAGEMENT
There is no solid waste is expected to be generated from the project except the
domestic waste (About 4 Kg/day). The solid Wastes generated will be collected,
composted in compost pits and the product will be used as manure for landscape
development.
6.9 POWER REQUIREMENT & SUPPLY/SOURCE
The power requirement for the proposed project is 100 KVA and it will be
augmented from CESCOM. 100 KVA DG set will be installed for emergency power
supply during power failure
Standalone Grinding Cement Industry
32
Chapter-7 REHABILITATION & RESETTLEMENT PLAN
M/s. Hemavathi Cement Industries proposed to Establish Cement manufacturing
unit. The proposed project site is in KIADB Industrial Growth Centre hence
Rehabilitation and Resettlement in not envisaged.
Chapter-8
PROJECT SCHEDULE & COST ESTIMATES
8.1 TIME SCHEDULE
The Industry will be operational by March 2016
Table 8.1 The Time Schedule for the Project are as Under
Sl. No. Descriptions Time Schedule
1. Levelling & compound wall Construction
November-december 2015
2. Statutory Approval October-November 2015
3. Plant & Machinery Building construction January - February 2016
8.2 ESTIMATED PROJECT COST
Total capital investment on the proposed Project is detailed as under
Table 8.2: Capital Investment on the Project
Sl. no.
Description Cost in Rupees
1 Land 5,00,000/-
2 Plant and machinery 1,42,00,000/-
TOTAL 1,47,00,000/-
Rupees One Crore Forty seven Lakhs Only.
Standalone Grinding Cement Industry
33
CHAPTER-9
ANALYSIS OF PROPOSAL
The proposed project is establishment Cement manufacturing industry. The
following are the benefits of the project.
1. Substantial Socio-economic benefits due to development of the ancillary
units in support to the proposed project.
2. Good Techno-commercial viability due to availability of required basic raw
materials like Clinker Slag and Gypsum.
3. Skilled, Semi-skilled and unskilled manpower are expected to get
employment from local population in these areas to meet the manpower
requirement during construction and Operational phase.
4. Infrastructural facilities will be improved due to the project.
5. Secondary employment will be generated thereby benefiting locals.
6. Thus a significant benefit to the socio-economic environment is likely to be
created due to the project.