Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
2015
PRE-FEASIBILITY REPORT OF
PROPOSED EXPANSION CUM MODIFICATION
OF FORMULATION UNIT WITH NEW
TECHNICAL GRADE PESTICIDE FACILITIES
PROJECT LOCATED AT
5 KM STONE, SAMPLA BERI ROAD, VILLAGE SAMPLA,
TEHSIL – SAMPLA, DISTT- ROHTAK – 124501 (HARYANA)
Project Proponent M/s Pioneer Products Limited
Submitted to Ministry of Environment & Forests
New Delhi
September 2015
Contents 1. Executive Summary ............................................................................................................................... 3
2. Introduction of the project ................................................................................................................... 3
3. Project Description ................................................................................................................................ 6
4. Site Analysis ........................................................................................................................................ 14
5. Baseline Environment ......................................................................................................................... 16
6. Planning brief ...................................................................................................................................... 17
7. Proposed Infrastructure ...................................................................................................................... 17
8. Rehabilitation & Resettlement (R&R) Plan ......................................................................................... 17
9. Project Schedule & Cost Estimates ..................................................................................................... 18
10. Environmental Management Plan .................................................................................................. 18
11. CSR Activities ................................................................................................................................... 21
1. Executive Summary
The agrochemicals industry is a significant industry for the Indian economy. The Indian
pesticides and insecticide industry is fourth largest in the world and the second in the Asia-
Pacific region only after China. Pioneer Product Limited (PPL) is the leading company engaged
in business of agrochemicals in Indian market.
PPL has a formulation-manufacturing unit at 5 KM Stone, Sampla Beri Road, Village Sampla,
Tehsil – Sampla, Dist.- Rohtak – 124501 (Haryana). PPL wants expansion cum modification of
existing Formulation unit by proposing technical grades facilities.
As per EIA Notification dated 14.09.2006 and as amended on 01.12.2009, the project falls in
Category „A‟, S. No. - 5(b).
Table 1.1. Project at a Glance
1. Name of the Industry M/s Pioneer Products Limited
2. Products to be manufactured 15,000 TPA Technical grade pesticides
3. Total Plot Area 30,000 Sq. M
4. Water Requirement 104 KLD
5. Power Requirement 1000 KVA to be supplied by UHBVNL
DG Sets: 2 Nos. (750 KVA & 275 KVA)
6. Manpower Requirement 110 Persons
7. Project cost Rs. 30 Crores
8. Recurring cost/ annum for
environmental pollution control
measures
Rs. 12 Lac/ Annum
2. Introduction of the project
a) Identification of project
The role of the pesticides in the well-being of human race needs no emphasis. Pesticide usage
has become essential in order to maximize agriculture production and reduce public health
pestilence. The rapid changes in cropping patterns, increased fertilization and adoption of
programs for high yielding varieties have all contributed to increased use of pesticides. Further,
pest problems keep on changing with the changing environment. New physiological kinds evolve
as a result of mutations to withstand new conditions in nature. Many pest species develop
resistant strains when the same Pesticide is used far too often. The problems of pest resurgence
and secondary pest out-breaks crop up with the indiscriminate use of pesticides. These associated
problems offer a great scope for revolutionizing the use of pesticides. However, in India though
the overcall pesticide growth figures may appear impressive, the rate of consumption per hectare
of cultivated land is very low in comparison per hectare of cultivated land is very low in
comparison to other countries. India used 180 g of pesticides/ha. as against 10,790g, 1870 g and
1490 g/ha used in Japan, Europe and U.S.A. respectively. India spent just Rs. 2.15/ha. on
pesticides while Japan and U.S.A spent Rs.110/ha and Rs.35/ha respectively during the same
period. India consumed 12 gm. of pesticides per kg. of fertilizer used against 146 gm. in Japan in
and 19 gm in U.S.A in . This is one of the major factors that can be attributed to low per hectare
yields in our country since the crops and especially the high yielding varieties cannot manifest
their production potential in absence of proper pest protection. That the production potential
remains suppressed for want of protection can be exemplified by considering how in wheat, a
crop comparatively resistant to insect pestilence, we have had a “revolution” where as in paddy
which is one of the most heavily infested crops, we have had no break-through. In case of wheat,
the per hectare yield in India rose from 827 kg. to 1338 kg. Corresponding yields of paddy in
India on the other hand was 1826 kg. as against 6185 kg. 5326 kg. , 5105 kg.and 4000 kg. in
Japan, Egypt, USA and USSR respectively.
With in the country itself, there is a great imbalance between different regions with regard to the
use of pesticides. Of the total of approximately Rs.5000 million spent on pesticides in at the farm
level, south contributed for about 45 per cent of the total consumption in the rest of the country.
b) Project proponent
The project is for the Expansion cum modification of existing Formulation unit with New
Technical grade pesticides facilities by Pioneer Products Limited at 5 KM Stone, Sampla Beri
Road, Village Sampla, Tehsil – Sampla, Dist.- Rohtak – 124501 (Haryana).
c) Brief Description of nature of the project
Pioneer Pesticides Limited is a well-known company in agrochemical industry. Banking on their
rich collective experience of over 20 years. To the farmer community it is simply known as PPL.
PPL Group is a popular name in agri-inputs industry over last twenty years. It has been working
extensively with the farming community to help them raise better and healthy crops. Today
PPL‟s reach and impact has crossed geographical boundaries. Through extensive research in
agricultural fields, the company has manufactured many successful products and services. This
has largely helped farmers grow healthy crops and increase their productivity.
Being established among the frontrunners in the agri-inputs Industry, PPL group products
portfolio consists of a wide spectrum of high quality eco-friendly pesticides, fungicides,
herbicides etc. to cater to every arena in the agricultural sector of crops (food and commercial),
horticulture and floriculture, in applications for public health, house-keeping and veterinary
treatment besides loss prevention in warehouses, depots and granaries. Apart from these, the
group has also forayed into the packaging industry on an encouraging note.
PPL lives to its commitment of prompt deliveries and adherence to promised delivery agenda.
The organization works hand in hand with farming community to bring innovation linear to life,
fulfilling its motto of “Yielding Prosperity”.
d) Production details and Product Specification
Manufacturing of Pesticides used for the pest control in the agriculture & public health. The raw
materials and final products are synthetic organic chemicals and will be manufactured with latest
modern technology which will be environment friendly.
e) Need for the project and its importance to the country and its region
Pesticides are essential input for agriculture and the project will provide adequate availability of
the required products at cheaper rates and will also reduce the import quantities.
f) Production Gap
This would thus appear from the above that there is an unabridged major gap between the
demand and supply of pesticides for both public health and agriculture. The investments
involved in setting up of basic manufacturing plants as compared to formulation units if fairly
high. It has been possible for small-scale entrepreneurs to go in for formulation business but
financially not possible to invest in basic manufacturing facilities. In the country basic
manufacturing are mostly with large-scale multinational companies and, in some cases, may be
wholly owned by them. In view of the fact that the present companies of these subsidiaries have
sizeable capacities for the manufacture of basic chemical in their own countries, they are
reluctant to invest money for basic manufacture in India. Also, these companies are reluctant to
transfer technology and losing monopoly sales especially when these products are proprietary.
g) Demand Supply Gap
Since the requirement of Pesticides is increasing @ 10% to 15% every year, there is a huge gap
between the demand and supply.
h) Import vs. Indigenous production
At present more than 50% requirement is fulfilled by Import and there is urgent need to create
indigenous manufacturing facilities to provide better Quality at optimum cost.
i) Export Possibility
All the products have high potential of Export
j) Domestic/ Export Markets
The technical grade pesticides will be consumed internally within the formulation plant and rest
will be sold to many formulators all over the country. At the same time export will be done in
containers.
k) Employment generation (Direct & Indirect) due to the project
Directly 110 people will be employed in the plant after establishment and operation. Indirectly
an equivalent amount of employment will be generated, in terms of man-hour
3. Project Description a) Type of Project
Proposed Industrial project falls under „section 5(b)‟ for Manufacturing of pesticides and their
intermediates in „Category A‟ as per EIA notification dated 14th September 2006 and its
amendment on 1st December 2009.
b) Location (map showing general location, specific location, and project boundary & project site layout) with coordinates
The satellite view of the site can be reveled from the Figure 1.1
Figure 1.1 10 Km Google Map of Project Site
c) Salient features of Site
The proposed plant will be set up outside the limits of Rohtak Town and Country Planning
Board with due approval from authorities. In addition all arrangements will be made to ensure
environment protection inside the factory & surroundings.
d) Details of alternate sites
As this is a expansion project no alternative site has been examined.
e) Size or magnitude of operation
Pesticides are being produced in batch process in three reactor streams. The total plant installed
capacity after operation will be 15,000 TPA. Production of existing products is being reduced
and some new products will be produced (as per market demand).
Table 1.1 Product List with Capacity
Sl. No. Particulars Production
(MT/annum)
HERBICIDE 4200
1 Metribuzin 600
i. Sodium Sulfate (byproduct) 1278
2 Atrazine 600
3 Sulfosulfuron 300
i. Phenol 66.6
4 Glyphosate 1500
5 Clodinafop Propargyl 300
6 Pretilachlor 600
7 Imizathapyr 300
INSECTICIDE 8295.2
8 Acephate 171.2
9 Thiamethoxam 600
10 Fipronil 300
i. NaBr (Byproduct) 100.2
11 Diafenthiuron 600
12 Buprofezin 900
13 Dichlorvos 1500
i. Methyl Chloride (byproduct) 360
14 Lambda Cyhalothrin 300
i. HCl (byproduct) 24
15 Imidacloprid 600
16 Novaluron 300
17 Bifenthrin 300
18 Permethrin 300
i. HCl 25.6
19 Propargite 300
20 Chlorpyrifos 1200
21 Profenofos 900
i. Trimethyl ammonium bromide (byproduct) 819
FUNGICIDE 2400
22 Tricyclazole 600
23 Cymoxanil 300
24 Propiconazole 300
25 Hexaconazole 300
26 Tebuconazole 300
i. Methanol (byproduct) 28.9
27 Difenconazole 300
28 Isoprothiolane 300
TOTAL CAPACITY (TPA) 15000 (approx.)
f) Project description with process details
Manufacturing Process: (Detail in Annexure 6)
a) Raw material required along, likely source, marketing area of final product/s, mode of transport of raw material and finished product.
Table 1.2 List of Raw material
Sr. No Raw Material Quantity
(MTPA)
1. Cyanuric Chloride 260.4
2. NaOH flakes 29.124
3. NaOH lye 455.076
4. Water 17708.7
5. Ethylamine 80.4
6. Potassium Carbonate 426
7. (R-(+)-2-(4-hydroxy phenoxy) propionic acid [DHPPA] (99%) 159.9
8. 5-CHLOR-2,3-Difluro pyridine [DFP] (95%) 125.1
9. Propargyl chloride (65% in toluene) 60
10. Propoxy ethyl chloride 132
11. 2,6-Diethyl Aniline 345
12. CAC 120
13. Phenyl chloroformate 110.7
14. ADP 108.9
15. Triethyl amine 126.3
16. ESPO 204.9
17. 2-Biphenyl carboxylic acid 150
18. Sodium bi carbonate 75
19. Lambda cyhalothric Acid 195
20. 5% EtOH in Hexane 75
21. Tetrabutyl Ammoniumbromide (Catalyst) 6
22. N-chloromethyl-N-Phenyl Carbamoyl Chloride 192
23. Ammonium Bicarbonate 720
24. 1 - isopropyl-3 - t-butyl thiourea 150
25. Sodium salt of 3,5,6-trichloropyridin-2-ol 188.7
26. Diethylphosphorochloridothioate 137.1
27. Phase Transfer Catalyst Tertiary amine acid boric Tampon 0
28. DTU 313.5
29. TBA 201
30. Fipronil Pyrazole 351
31. BrSCN 153
32. Sodium Formate 76.5
33. SO2 117
34. CF3Br 228
35. Tri Chloro Acetic acid 1200
36. Dichloro acetic acid 450
37. H2O2 72
38. CCMP 262.2
39. N-Nitro N-methyl imidazolidine 247.5
40. Catalyst-1 3
41. AMBT 360
42. Hydrazine mono hydrate 120.6
43. HCl 35% 634.5
44. Formic acid 85.8
45. 4-Nitroimino-3-methyl Isoxazole 180
46. 2-Chloro-5-Chloromethyl Thiazole 191.4
47. ATMT 300
48. Sulfuric Acid 388.5
49. Soda ash 685.2
50. Di ethyl 5 ethylpyridine Dicarboxylate 291
51. 2 amino 2,3 dimethyl butane amide 180.9
52. Sodium ethoxide 197.4
53. Orthochlorophenol 112.5
54. Bromine 180.9
55. Trimethylamine 88.5
56. Diethyl thiochloro phosphate 168.9
57. Propylbromide 116.4
58. DMPTC 351
59. Ammonium Hydroxide 488.4
60. Dimethyl sulfate 45
61. Acetic Anhydride 247.8
62. Chrysanthanic Acid 161.7
63. Thionyl Chloride 250.2
64. MPBD 132
65. NaCN 32.7
66. NaOCl 22.5
67. Catalyst-2 30
68. NaNO2 105
69. 1-Cyanoacetyl-3-Ethylurea 234
70. Carbonate Salt 30
71. p-TSA (catalyst) 19.8
72. DMS 55
73. 2,4 Dichloroacetophenone 129.9
74. Acetic Acid 350.1
75. 1,2-Pentane Diol 84.9
76. 1,2,4 Triazole 319.2
77. KOH 210
78. Valeric Acid 139.5
79. MDCB 201
80. AlCl3 246
81. DMSO4 (Catalyst) 908.2
82. 1,2,4 Triazole 319.2
83. 1-(4-Chlorophenyl) 4-4-Dimethyl-3-Pentanoate 202.5
84. Sodium methoxide 48.6
85. Dimethyl Sulfide 55.8
86. Bromoketal 549.9
87. IPE 249.9
88. PE 50.1
89. CMAC 174.6
90. Metaphenoxy benzyl alcohol 153.6
91. CS2 90
92. Diisopropylmalonate 210
93. TMP 169.8
94. Chloral 202.2
95. 2,6 -difluoro benzoyl isocyanate 111.3
96. 2-chloro-4-amino-phenoxy ether 188.7
97. 2,(4 -tert-butyl phenoxy) cyclohexanol 212.1
98. Propargyl alcohol 48
Mode of transportation: Mainly by Road
b) Resource optimization/ recycling and reuse envisaged in the product
All the solvents used will be recovered and recycled for all products. Energy efficient equipment
will be installed at all location. Waste water will also be reused after proper treatment. There will
be no discharge from the site.
c) Availability of water its source, Energy/ power requirement and source should be given
a. Water requirement:
Proposed Fresh Water Consumption: 104.00 KLD
Source: Purchased from outside with the help of tanker.
b. Power requirement The total power requirement for the project will be as follows:
Table 1.3. Power Requirement
Haryana State Electricity Board D.G. Set
(Stand By facility)
1000 KVA to be supplied by UHBVNL 2 Nos. (750 KVA & 250 KVA)
The power requirement of the proposed project will be met with the power supply from State
electricity board. To meet Emergency power requirement of critical operations for ensuring
safety, DG sets will be provided as standby power back up (2DG set of 750 KVA & 250 KVA
capacities will be installed).
c. Steam 800 kg capacity boiler with fuel consumption 100 litre per hr briquettes.
d. Fuel Requirement
The following fuel will be used as mentioned below. The mode of Transport of Fuel to Site will
be Trucks by road.
Table 1.4 Fuel Requirements
Fuel Requirement
Agro waste, Briquettes or FO 4.2 KLD
HSD 200 Lit/day
LDO 200 Lit/hr
e. Manpower Requirement
The total manpower requirement is mentioned below:
Table 1.5 Manpower Requirements
S. No. Details Manpower Requirement
1. Plant Head 1
2. Production Manager 6
3. Store Incharge/keeper 6
4. Quality Incahge 3
5. Lab Assistanat 6
5. Supervisiors 6
6. Skilled Labours 18
7. Guards 10
8. Peon 6
9. Accounts 4
10. Data Entry operators 4
11. Unskilled Labours 30
12. Maintenance Staff 6
Total 110
d) Quantity of wastes to be generated (liquid & solid) and scheme for their management / disposal
a. Solid Wastes The list of the waste generated in the proposed project are as follows:
Table 1.7 Types of Waste generation
S.No Particulars
1. Process Solid waste/ residue
2. Process Wastes/ residue
3. Chemical sludge from waste water treatment
4. Used / Spent Oil
The applicable precautions will be taken in storing and handling of hazardous chemicals. All of
the Hazardous wastes will be disposed off as per guidance of State Pollution Control Board. All
the necessary measures will be taken as per the MSIHC Rule 1989 & Hazardous Waste
(Management & Handling) Rules, 1989 Hazardous Wastes Category As Per Hazardous Waste
The Hazardous Wastes (Management, Handling And Transboundary Movement) Rules, 2008 &
Rules thereafter and these will be strictly followed with. Liquid & solid wastes will be sent for
disposal to authorized TSDF site.
b. Quantity of Effluent generated and its end use
Total 93 KLD to be treated in ETP followed by RO and 79 KLD to be treated in MEE.
DETAILS OF WATER USAGE AND WASTE WATER GENERATION
S. No. Area of
Consumption
Fresh Water
Quantity,
KLD
Waste Water
Generation,
KLD
Effluent Treatment &
Disposal Facilitry
1 Domestic 6 5 To ETP
2 Gardening 4 - -
3 DM Plant 9 1 To MEE
3.1 Boiler 24 2 To ETP
4 Cooling Tower 90 5 To ETP
5 RO Reject - 17 To ETP
6 Floor Washing
and Equipment
Washing
5 5 To ETP
7 MEE Condensate - 75 To ETP
8 Total Water
Consumption &
Waste Water
174 110 Total 93 KLD to be treated in
ETP followed by RO and 79
KLD to be treated in MEE
9 Recycled Water 70 -
10 Fresh Water
Consumption
104 -
4. Site Analysis a) Connectivity
S.N. Particulars Description
1 Village
District
State
Sampla
Rohtak
Haryana
2 Coordinates 76°43'23.95"E
28°45'41.60"N
3 Most Populated Area Kultana (2.60km), W; Ismaila ,3.90
km, E,
Sampla 5.0 km, E.
4 Surface Water Source
within 10 Km
No any surface water source
5 Nearest Densely Populated
Areas
Kultana (2.60km), W; Ismaila ,3.90
km, E,
Sampla 5.0 km, E.
6 Nearest Highway NH-10 at a distance of 4.20 km (E).
7 Nearest Railway Station Sampla (Broad Gauge) 5.0 kms in
E direction
8 Nearest Village Kultana (2.60km), W
9 Nearest Town Rohtak,29.0 km,NW
10 Nearest Airport Indira Gandhi International Airport
– 80 Km (SE)
11 Nearest Forest No Protected Forest
12 Recorded Sensitive Places There is no sensitive area in the
study area.
13 Historical Places There is no historical area in the
study area.
14 Location of National Parks/
Wildlife Sanctuary within
10 Km radius of the project
site
There are no National Parks/
Wildlife Sanctuary in the study
area.
b) Land Form, land use and Land ownership
The general elevation of the area is 221 msl. The area has plain topography and major area
around the project site is dominated by agricultural land.
c) Topography
d) Existing infrastructure Refer to Annexure 2 Site Layout
5. Baseline Environment e) Soil classification
The district area is occupied by Indo-Gangetic alluvium. There are no surface features worth to
mention. Physiographically the area is flat terrain. The area slopes towards northeast to
southwest with an average gradient of 0.19 m/km.The general elevation in the district varies
between 215 m to 222m above MSL. The soils of the district arefine to medium textured. It
comprises sandy loam in Rohtak, Sampla, and Lakhan Majra blocks whereas it is loamy sand
with occasional clay loam in Kalanaur and Meham Blocks. High potassium, medium phosphorus
and low nitrogen occur in the soils. The soils of the district are classified as arid brown
(Solemnized) and sierozem..
f) Climatic data from secondary source The climate of Rohtak district can be classified as subtropical monsoon, mild &dry winter, hot
summer and sub-humid which is mainly dry with very hot summer and cold winter except during
monsoon season when moist air of oceanic origin penetrate into the district. The hot weather
season starts from mid March to last week of the June followed by the south west monsoon
which lasts upto September. The transition period from September to November forms the post
monsoon season. The winter season starts late in November and remains upto first week of
March.
g) Social infrastructure available Project site is well connected with NH-10 (4.20 Km-E). It is also connected with district Rohtak
(29.0 Km- NW) where basic facilities like hospital, school etc. are present in the area.
6. Planning brief (i) Planning concept (type of industries,
facilities, transportation etc) Town
and Country Planning/Development
authority Classification.
The proposed plant will come under medium scale industry well connected with all public transport facilities. Proopsed Plant located at , 5 KM Stone, Sampla Beri Road, Village Sampla, Tehsil – Sampla, Distt- Rohtak – 124501 (Haryana)
(ii) Land use planning (breakup along
with the green belt etc). Total Land : 30,000 m2
Green area : 10,000 m2(proposed) Green belts up to 33 % is proposed.
(iii) Assessment of infrastructure
Demand (Physical & Social).
Will be developed as per requirement.
(iv) Amenities/Facilities. Will be developed as per requirement.
7. Proposed Infrastructure (i) Total Area 30,000 m
2
(ii) Green Belt. 10,000 m2(proposed)
(iii) Social Infrastructure. None
(iv) Connectivity (traffic and
Transportation
Road/Rail/Metro/Water ways etc)
Nearest connectivity NH-10 at a distance of 4.20 km
(E).
(v) Process / Drinking Water
Management (Source & Supply of
water)
Total water requirement of 104 KLD
Source: Outside vendor, through tanker
(vi) Industrial Waste Management. Waste from ETP and other waste will be sent to
waste management facility.
(vii) Solid Waste Management. Will be sent to approved agency/ site for safe
disposal
(viii) Power Requirement & Supply /
source.
1000 KVA will be obtained from state power
corporation. Also 2 DG sets are to be installed.
8. Rehabilitation & Resettlement (R&R) Plan Not Applicable
9. Project Schedule & Cost Estimates a) Project Cost Estimation
The estimated cost of the proposed Project is ~ 30 crore.
b) Cost towards Environmental Protection The estimated cost towards Environmental Protection is 12 lac/annum.
c) Project Implementation Schedule The construction and production from new plant may start after the approval.
Public liability insurance plan policy will be obtained for suitable amount. On site & off site
emergency plans will be prepared and enforced by continuous training to all concern.
10. Environmental Management Plan a) Air Pollution Control Gaseous emission from fuel burning, consist of common pollutants like SO2, NO2, and
PM would be discharged into atmosphere through Stack of suitable height.
Green belt will be developed covering >33% of the total project area, around the plant
boundary as dust preventive barrier.
Odor Control System: All the vents of the batch tanks and solvents are connected to
scrubber to absorb any pollutant / odor producing gases and chemicals. Green belt around
the plant boundary will absorb the odor to some extent.
The operation of centrifuging/ filter will be done in closed equipment to avoid any vapors
coming out in the local atmosphere. The vents of centrifuges / filters will be connected to
scrubbers.
The drying of the product is done in a closed type continuous Fluidized Bed dryer/ Nudge
filter to avoid the exposure of any chemicals to human being.
Volatile organic solvents are carefully handled in a closed system, thereby preventing any
discharge of these chemicals into the air.
Process emission quality will be maintained as per the following standards:
H2S < 45 mg/Nm3
NH3 < 175 mg/NM3
HCl <20 mg/NM3
SO2 <40 mg/NM3
Cl2 <9 mg/NM3
Adequate systems shall be provided to capture the emissions from process plants &
maintain the emission quality as per recommended guidelines with central scrubber
having caustic solution, before venting it in to the atmosphere.
Table 1.11 Name of Equipment
Air Pollution Control Measures
S. No.
Stack Attached
to Fuel Used
Quantity of Fuel
APCM Expected Pollutants
Efficiency of APCE
Stack Height(m)
Flue Gas Stacks
1 Boilers
Agrowaste briquettes / FO (as per
availability)
300 Sm3/Hr HG or 4.2 KLD
FO
- PM, SO2
& NOx - 35
2 Thermic
Fluid Heater
LDO (as per
availability)
25 Sm3/Hr NG or 200
Ltr/Day LDO
- PM, SO2
& NOx - 30
3 DG Sets HSD 200 Ltr/Hr
Adequate Stack Ht.
PM, SO2 & NOx
- 15
Process Stacks / Vents
1
Process Reactor – Vents (5
Nos.)
- - Acid
Scrubber
HCl, HBr, H2S, NH3, NOx & HC
99.5 % 35
2
Process Reactor – Vents (6
Nos.)
- - Gas
Scrubber 99.5 % 35
3
Process Reactor – Vents (6
Nos.)
- - Gas
Scrubber 99.5 % 35
All the above mentioned air pollution control measures shall be practiced to minimize air
pollution in and around plant.
b) Waste Water Management Out of total water requirement of 174 KLD, 104 KLD of fresh water will be required while
the industrial waste water generated (~ 93 KLD) will be treated in the Effluent Treatment
Plant ETP/ MEE. After treatment (~70 KLD) will be recycled back in the system. The
domestic Waste sent to Soak Pit but in later future STP is proposed to be commissioned.
c) Noise Environment Installation of the plant machinery will be done after- due consideration to design noise
levels and noise mitigation measures.
The green belt developed helps in reducing noise levels generated due to plant operations.
There will be no major sources of industrial noise; minor noise generated from the
industrial operations will be controlled by proper maintenance.
Proper mitigation measures will be taken in addition to above for the reduction of noise
levels i.e. use of acoustic enclosures and providing personal protective equipment etc. to
the workers.
Periodical monitoring for noise is being carried out on regular basis.
Proper maintenance, oiling and greasing of machines at regular intervals is done to
minimize generation of noise at source.
The D.G. sets will be provided with acoustic enclosures.
d) Solid Waste Management Minor quantities of construction waste will be generated in the form of packaging
material and construction waste. Proper care will be taken for handling and reduction of
the solid waste generated during construction phase.
During the operation phase the solid waste is being generated in the form of ETP sludge,
etc..
Hazardous solid wastes will be sent to nearby TSDF site.
e) Green Belt Development/Plantation Green belt development in and around the project site will help in to attenuate the pollution level.
Out of the total plant area of 30,000 Sq M,, Approx. ~ 10,000. Sqm (33%) land will be
developed as green belt. Green belt will be developed as per Central Pollution Control Board
(CPCB) Norms. The Avenue plantation will give priority to native species, and the periphery
will be devoted to generation of green belt area.
Green belt development in and around the project site will help in to attenuate the
pollution level.
Native species will be given priority for Avenue plantation.
The periphery will be devoted to generation of green belt area.
f) Hazardous Waste Management
HAZARDOUS WASTES CATEGORY AS PER HAZARDOUS WASTE THE HAZARDOUS
WASTES (MANAGEMENT, HANDLING AND TRANSBOUNDARY MOVEMENT)
RULES, 2008
(As specified under hazardous wastes / management handling rules 1989) amendment rule 2003.
Process wastes/ residue
Chemical sludge containing residue insecticides
Date expired and off-specification insecticides
All above waste are will be collected and stored at separate identified place and suitably disposed
off to authorized agencies.
11. CSR Activities
The project activity and the management will support the local panchayat by providing of
assistance for the development of public amenities in the region and will help in improving the
overall infrastructure status of the area. Thus the proposed project of PPL will be proved
beneficial to the local economy and society and will not lead to any adverse impact on the
environment.