21
2015 PRE-FEASIBILITY REPORT OF PROPOSED EXPANSION CUM MODIFICATION OF FORMULATION UNIT WITH NEW TECHNICAL GRADE PESTICIDE FACILITIES PROJECT LOCATED AT 5 KM STONE, SAMPLA BERI ROAD, VILLAGE SAMPLA, TEHSIL SAMPLA, DISTT- ROHTAK 124501 (HARYANA) Project Proponent M/s Pioneer Products Limited Submitted to Ministry of Environment & Forests New Delhi September 2015

PRE-FEASIBILITY REPORT OF PROPOSED EXPANSION CUM …environmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 9. 21. · DTU 313.5 29. TBA 201 30. Fipronil Pyrazole 351

  • Upload
    others

  • View
    1

  • Download
    0

Embed Size (px)

Citation preview

Page 1: PRE-FEASIBILITY REPORT OF PROPOSED EXPANSION CUM …environmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 9. 21. · DTU 313.5 29. TBA 201 30. Fipronil Pyrazole 351

2015

PRE-FEASIBILITY REPORT OF

PROPOSED EXPANSION CUM MODIFICATION

OF FORMULATION UNIT WITH NEW

TECHNICAL GRADE PESTICIDE FACILITIES

PROJECT LOCATED AT

5 KM STONE, SAMPLA BERI ROAD, VILLAGE SAMPLA,

TEHSIL – SAMPLA, DISTT- ROHTAK – 124501 (HARYANA)

Project Proponent M/s Pioneer Products Limited

Submitted to Ministry of Environment & Forests

New Delhi

September 2015

Page 2: PRE-FEASIBILITY REPORT OF PROPOSED EXPANSION CUM …environmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 9. 21. · DTU 313.5 29. TBA 201 30. Fipronil Pyrazole 351

Contents 1. Executive Summary ............................................................................................................................... 3

2. Introduction of the project ................................................................................................................... 3

3. Project Description ................................................................................................................................ 6

4. Site Analysis ........................................................................................................................................ 14

5. Baseline Environment ......................................................................................................................... 16

6. Planning brief ...................................................................................................................................... 17

7. Proposed Infrastructure ...................................................................................................................... 17

8. Rehabilitation & Resettlement (R&R) Plan ......................................................................................... 17

9. Project Schedule & Cost Estimates ..................................................................................................... 18

10. Environmental Management Plan .................................................................................................. 18

11. CSR Activities ................................................................................................................................... 21

Page 3: PRE-FEASIBILITY REPORT OF PROPOSED EXPANSION CUM …environmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 9. 21. · DTU 313.5 29. TBA 201 30. Fipronil Pyrazole 351

1. Executive Summary

The agrochemicals industry is a significant industry for the Indian economy. The Indian

pesticides and insecticide industry is fourth largest in the world and the second in the Asia-

Pacific region only after China. Pioneer Product Limited (PPL) is the leading company engaged

in business of agrochemicals in Indian market.

PPL has a formulation-manufacturing unit at 5 KM Stone, Sampla Beri Road, Village Sampla,

Tehsil – Sampla, Dist.- Rohtak – 124501 (Haryana). PPL wants expansion cum modification of

existing Formulation unit by proposing technical grades facilities.

As per EIA Notification dated 14.09.2006 and as amended on 01.12.2009, the project falls in

Category „A‟, S. No. - 5(b).

Table 1.1. Project at a Glance

1. Name of the Industry M/s Pioneer Products Limited

2. Products to be manufactured 15,000 TPA Technical grade pesticides

3. Total Plot Area 30,000 Sq. M

4. Water Requirement 104 KLD

5. Power Requirement 1000 KVA to be supplied by UHBVNL

DG Sets: 2 Nos. (750 KVA & 275 KVA)

6. Manpower Requirement 110 Persons

7. Project cost Rs. 30 Crores

8. Recurring cost/ annum for

environmental pollution control

measures

Rs. 12 Lac/ Annum

2. Introduction of the project

a) Identification of project

The role of the pesticides in the well-being of human race needs no emphasis. Pesticide usage

has become essential in order to maximize agriculture production and reduce public health

pestilence. The rapid changes in cropping patterns, increased fertilization and adoption of

programs for high yielding varieties have all contributed to increased use of pesticides. Further,

pest problems keep on changing with the changing environment. New physiological kinds evolve

as a result of mutations to withstand new conditions in nature. Many pest species develop

resistant strains when the same Pesticide is used far too often. The problems of pest resurgence

and secondary pest out-breaks crop up with the indiscriminate use of pesticides. These associated

problems offer a great scope for revolutionizing the use of pesticides. However, in India though

the overcall pesticide growth figures may appear impressive, the rate of consumption per hectare

Page 4: PRE-FEASIBILITY REPORT OF PROPOSED EXPANSION CUM …environmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 9. 21. · DTU 313.5 29. TBA 201 30. Fipronil Pyrazole 351

of cultivated land is very low in comparison per hectare of cultivated land is very low in

comparison to other countries. India used 180 g of pesticides/ha. as against 10,790g, 1870 g and

1490 g/ha used in Japan, Europe and U.S.A. respectively. India spent just Rs. 2.15/ha. on

pesticides while Japan and U.S.A spent Rs.110/ha and Rs.35/ha respectively during the same

period. India consumed 12 gm. of pesticides per kg. of fertilizer used against 146 gm. in Japan in

and 19 gm in U.S.A in . This is one of the major factors that can be attributed to low per hectare

yields in our country since the crops and especially the high yielding varieties cannot manifest

their production potential in absence of proper pest protection. That the production potential

remains suppressed for want of protection can be exemplified by considering how in wheat, a

crop comparatively resistant to insect pestilence, we have had a “revolution” where as in paddy

which is one of the most heavily infested crops, we have had no break-through. In case of wheat,

the per hectare yield in India rose from 827 kg. to 1338 kg. Corresponding yields of paddy in

India on the other hand was 1826 kg. as against 6185 kg. 5326 kg. , 5105 kg.and 4000 kg. in

Japan, Egypt, USA and USSR respectively.

With in the country itself, there is a great imbalance between different regions with regard to the

use of pesticides. Of the total of approximately Rs.5000 million spent on pesticides in at the farm

level, south contributed for about 45 per cent of the total consumption in the rest of the country.

b) Project proponent

The project is for the Expansion cum modification of existing Formulation unit with New

Technical grade pesticides facilities by Pioneer Products Limited at 5 KM Stone, Sampla Beri

Road, Village Sampla, Tehsil – Sampla, Dist.- Rohtak – 124501 (Haryana).

c) Brief Description of nature of the project

Pioneer Pesticides Limited is a well-known company in agrochemical industry. Banking on their

rich collective experience of over 20 years. To the farmer community it is simply known as PPL.

PPL Group is a popular name in agri-inputs industry over last twenty years. It has been working

extensively with the farming community to help them raise better and healthy crops. Today

PPL‟s reach and impact has crossed geographical boundaries. Through extensive research in

agricultural fields, the company has manufactured many successful products and services. This

has largely helped farmers grow healthy crops and increase their productivity.

Being established among the frontrunners in the agri-inputs Industry, PPL group products

portfolio consists of a wide spectrum of high quality eco-friendly pesticides, fungicides,

herbicides etc. to cater to every arena in the agricultural sector of crops (food and commercial),

horticulture and floriculture, in applications for public health, house-keeping and veterinary

treatment besides loss prevention in warehouses, depots and granaries. Apart from these, the

group has also forayed into the packaging industry on an encouraging note.

PPL lives to its commitment of prompt deliveries and adherence to promised delivery agenda.

The organization works hand in hand with farming community to bring innovation linear to life,

fulfilling its motto of “Yielding Prosperity”.

Page 5: PRE-FEASIBILITY REPORT OF PROPOSED EXPANSION CUM …environmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 9. 21. · DTU 313.5 29. TBA 201 30. Fipronil Pyrazole 351

d) Production details and Product Specification

Manufacturing of Pesticides used for the pest control in the agriculture & public health. The raw

materials and final products are synthetic organic chemicals and will be manufactured with latest

modern technology which will be environment friendly.

e) Need for the project and its importance to the country and its region

Pesticides are essential input for agriculture and the project will provide adequate availability of

the required products at cheaper rates and will also reduce the import quantities.

f) Production Gap

This would thus appear from the above that there is an unabridged major gap between the

demand and supply of pesticides for both public health and agriculture. The investments

involved in setting up of basic manufacturing plants as compared to formulation units if fairly

high. It has been possible for small-scale entrepreneurs to go in for formulation business but

financially not possible to invest in basic manufacturing facilities. In the country basic

manufacturing are mostly with large-scale multinational companies and, in some cases, may be

wholly owned by them. In view of the fact that the present companies of these subsidiaries have

sizeable capacities for the manufacture of basic chemical in their own countries, they are

reluctant to invest money for basic manufacture in India. Also, these companies are reluctant to

transfer technology and losing monopoly sales especially when these products are proprietary.

g) Demand Supply Gap

Since the requirement of Pesticides is increasing @ 10% to 15% every year, there is a huge gap

between the demand and supply.

h) Import vs. Indigenous production

At present more than 50% requirement is fulfilled by Import and there is urgent need to create

indigenous manufacturing facilities to provide better Quality at optimum cost.

i) Export Possibility

All the products have high potential of Export

j) Domestic/ Export Markets

The technical grade pesticides will be consumed internally within the formulation plant and rest

will be sold to many formulators all over the country. At the same time export will be done in

containers.

k) Employment generation (Direct & Indirect) due to the project

Page 6: PRE-FEASIBILITY REPORT OF PROPOSED EXPANSION CUM …environmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 9. 21. · DTU 313.5 29. TBA 201 30. Fipronil Pyrazole 351

Directly 110 people will be employed in the plant after establishment and operation. Indirectly

an equivalent amount of employment will be generated, in terms of man-hour

3. Project Description a) Type of Project

Proposed Industrial project falls under „section 5(b)‟ for Manufacturing of pesticides and their

intermediates in „Category A‟ as per EIA notification dated 14th September 2006 and its

amendment on 1st December 2009.

b) Location (map showing general location, specific location, and project boundary & project site layout) with coordinates

The satellite view of the site can be reveled from the Figure 1.1

Figure 1.1 10 Km Google Map of Project Site

c) Salient features of Site

Page 7: PRE-FEASIBILITY REPORT OF PROPOSED EXPANSION CUM …environmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 9. 21. · DTU 313.5 29. TBA 201 30. Fipronil Pyrazole 351

The proposed plant will be set up outside the limits of Rohtak Town and Country Planning

Board with due approval from authorities. In addition all arrangements will be made to ensure

environment protection inside the factory & surroundings.

d) Details of alternate sites

As this is a expansion project no alternative site has been examined.

e) Size or magnitude of operation

Pesticides are being produced in batch process in three reactor streams. The total plant installed

capacity after operation will be 15,000 TPA. Production of existing products is being reduced

and some new products will be produced (as per market demand).

Table 1.1 Product List with Capacity

Sl. No. Particulars Production

(MT/annum)

HERBICIDE 4200

1 Metribuzin 600

i. Sodium Sulfate (byproduct) 1278

2 Atrazine 600

3 Sulfosulfuron 300

i. Phenol 66.6

4 Glyphosate 1500

5 Clodinafop Propargyl 300

6 Pretilachlor 600

7 Imizathapyr 300

INSECTICIDE 8295.2

8 Acephate 171.2

9 Thiamethoxam 600

10 Fipronil 300

i. NaBr (Byproduct) 100.2

11 Diafenthiuron 600

12 Buprofezin 900

13 Dichlorvos 1500

i. Methyl Chloride (byproduct) 360

14 Lambda Cyhalothrin 300

i. HCl (byproduct) 24

15 Imidacloprid 600

16 Novaluron 300

17 Bifenthrin 300

18 Permethrin 300

i. HCl 25.6

Page 8: PRE-FEASIBILITY REPORT OF PROPOSED EXPANSION CUM …environmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 9. 21. · DTU 313.5 29. TBA 201 30. Fipronil Pyrazole 351

19 Propargite 300

20 Chlorpyrifos 1200

21 Profenofos 900

i. Trimethyl ammonium bromide (byproduct) 819

FUNGICIDE 2400

22 Tricyclazole 600

23 Cymoxanil 300

24 Propiconazole 300

25 Hexaconazole 300

26 Tebuconazole 300

i. Methanol (byproduct) 28.9

27 Difenconazole 300

28 Isoprothiolane 300

TOTAL CAPACITY (TPA) 15000 (approx.)

f) Project description with process details

Manufacturing Process: (Detail in Annexure 6)

a) Raw material required along, likely source, marketing area of final product/s, mode of transport of raw material and finished product.

Table 1.2 List of Raw material

Sr. No Raw Material Quantity

(MTPA)

1. Cyanuric Chloride 260.4

2. NaOH flakes 29.124

3. NaOH lye 455.076

4. Water 17708.7

5. Ethylamine 80.4

6. Potassium Carbonate 426

7. (R-(+)-2-(4-hydroxy phenoxy) propionic acid [DHPPA] (99%) 159.9

8. 5-CHLOR-2,3-Difluro pyridine [DFP] (95%) 125.1

9. Propargyl chloride (65% in toluene) 60

10. Propoxy ethyl chloride 132

11. 2,6-Diethyl Aniline 345

12. CAC 120

13. Phenyl chloroformate 110.7

Page 9: PRE-FEASIBILITY REPORT OF PROPOSED EXPANSION CUM …environmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 9. 21. · DTU 313.5 29. TBA 201 30. Fipronil Pyrazole 351

14. ADP 108.9

15. Triethyl amine 126.3

16. ESPO 204.9

17. 2-Biphenyl carboxylic acid 150

18. Sodium bi carbonate 75

19. Lambda cyhalothric Acid 195

20. 5% EtOH in Hexane 75

21. Tetrabutyl Ammoniumbromide (Catalyst) 6

22. N-chloromethyl-N-Phenyl Carbamoyl Chloride 192

23. Ammonium Bicarbonate 720

24. 1 - isopropyl-3 - t-butyl thiourea 150

25. Sodium salt of 3,5,6-trichloropyridin-2-ol 188.7

26. Diethylphosphorochloridothioate 137.1

27. Phase Transfer Catalyst Tertiary amine acid boric Tampon 0

28. DTU 313.5

29. TBA 201

30. Fipronil Pyrazole 351

31. BrSCN 153

32. Sodium Formate 76.5

33. SO2 117

34. CF3Br 228

35. Tri Chloro Acetic acid 1200

36. Dichloro acetic acid 450

37. H2O2 72

38. CCMP 262.2

39. N-Nitro N-methyl imidazolidine 247.5

40. Catalyst-1 3

41. AMBT 360

42. Hydrazine mono hydrate 120.6

43. HCl 35% 634.5

44. Formic acid 85.8

45. 4-Nitroimino-3-methyl Isoxazole 180

46. 2-Chloro-5-Chloromethyl Thiazole 191.4

47. ATMT 300

48. Sulfuric Acid 388.5

49. Soda ash 685.2

50. Di ethyl 5 ethylpyridine Dicarboxylate 291

51. 2 amino 2,3 dimethyl butane amide 180.9

52. Sodium ethoxide 197.4

53. Orthochlorophenol 112.5

54. Bromine 180.9

55. Trimethylamine 88.5

56. Diethyl thiochloro phosphate 168.9

57. Propylbromide 116.4

58. DMPTC 351

59. Ammonium Hydroxide 488.4

60. Dimethyl sulfate 45

Page 10: PRE-FEASIBILITY REPORT OF PROPOSED EXPANSION CUM …environmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 9. 21. · DTU 313.5 29. TBA 201 30. Fipronil Pyrazole 351

61. Acetic Anhydride 247.8

62. Chrysanthanic Acid 161.7

63. Thionyl Chloride 250.2

64. MPBD 132

65. NaCN 32.7

66. NaOCl 22.5

67. Catalyst-2 30

68. NaNO2 105

69. 1-Cyanoacetyl-3-Ethylurea 234

70. Carbonate Salt 30

71. p-TSA (catalyst) 19.8

72. DMS 55

73. 2,4 Dichloroacetophenone 129.9

74. Acetic Acid 350.1

75. 1,2-Pentane Diol 84.9

76. 1,2,4 Triazole 319.2

77. KOH 210

78. Valeric Acid 139.5

79. MDCB 201

80. AlCl3 246

81. DMSO4 (Catalyst) 908.2

82. 1,2,4 Triazole 319.2

83. 1-(4-Chlorophenyl) 4-4-Dimethyl-3-Pentanoate 202.5

84. Sodium methoxide 48.6

85. Dimethyl Sulfide 55.8

86. Bromoketal 549.9

87. IPE 249.9

88. PE 50.1

89. CMAC 174.6

90. Metaphenoxy benzyl alcohol 153.6

91. CS2 90

92. Diisopropylmalonate 210

93. TMP 169.8

94. Chloral 202.2

95. 2,6 -difluoro benzoyl isocyanate 111.3

96. 2-chloro-4-amino-phenoxy ether 188.7

97. 2,(4 -tert-butyl phenoxy) cyclohexanol 212.1

98. Propargyl alcohol 48

Mode of transportation: Mainly by Road

b) Resource optimization/ recycling and reuse envisaged in the product

All the solvents used will be recovered and recycled for all products. Energy efficient equipment

will be installed at all location. Waste water will also be reused after proper treatment. There will

be no discharge from the site.

Page 11: PRE-FEASIBILITY REPORT OF PROPOSED EXPANSION CUM …environmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 9. 21. · DTU 313.5 29. TBA 201 30. Fipronil Pyrazole 351

c) Availability of water its source, Energy/ power requirement and source should be given

a. Water requirement:

Proposed Fresh Water Consumption: 104.00 KLD

Source: Purchased from outside with the help of tanker.

b. Power requirement The total power requirement for the project will be as follows:

Table 1.3. Power Requirement

Haryana State Electricity Board D.G. Set

(Stand By facility)

1000 KVA to be supplied by UHBVNL 2 Nos. (750 KVA & 250 KVA)

The power requirement of the proposed project will be met with the power supply from State

electricity board. To meet Emergency power requirement of critical operations for ensuring

safety, DG sets will be provided as standby power back up (2DG set of 750 KVA & 250 KVA

capacities will be installed).

c. Steam 800 kg capacity boiler with fuel consumption 100 litre per hr briquettes.

d. Fuel Requirement

Page 12: PRE-FEASIBILITY REPORT OF PROPOSED EXPANSION CUM …environmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 9. 21. · DTU 313.5 29. TBA 201 30. Fipronil Pyrazole 351

The following fuel will be used as mentioned below. The mode of Transport of Fuel to Site will

be Trucks by road.

Table 1.4 Fuel Requirements

Fuel Requirement

Agro waste, Briquettes or FO 4.2 KLD

HSD 200 Lit/day

LDO 200 Lit/hr

e. Manpower Requirement

The total manpower requirement is mentioned below:

Table 1.5 Manpower Requirements

S. No. Details Manpower Requirement

1. Plant Head 1

2. Production Manager 6

3. Store Incharge/keeper 6

4. Quality Incahge 3

5. Lab Assistanat 6

5. Supervisiors 6

6. Skilled Labours 18

7. Guards 10

8. Peon 6

9. Accounts 4

10. Data Entry operators 4

11. Unskilled Labours 30

12. Maintenance Staff 6

Total 110

d) Quantity of wastes to be generated (liquid & solid) and scheme for their management / disposal

a. Solid Wastes The list of the waste generated in the proposed project are as follows:

Page 13: PRE-FEASIBILITY REPORT OF PROPOSED EXPANSION CUM …environmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 9. 21. · DTU 313.5 29. TBA 201 30. Fipronil Pyrazole 351

Table 1.7 Types of Waste generation

S.No Particulars

1. Process Solid waste/ residue

2. Process Wastes/ residue

3. Chemical sludge from waste water treatment

4. Used / Spent Oil

The applicable precautions will be taken in storing and handling of hazardous chemicals. All of

the Hazardous wastes will be disposed off as per guidance of State Pollution Control Board. All

the necessary measures will be taken as per the MSIHC Rule 1989 & Hazardous Waste

(Management & Handling) Rules, 1989 Hazardous Wastes Category As Per Hazardous Waste

The Hazardous Wastes (Management, Handling And Transboundary Movement) Rules, 2008 &

Rules thereafter and these will be strictly followed with. Liquid & solid wastes will be sent for

disposal to authorized TSDF site.

b. Quantity of Effluent generated and its end use

Total 93 KLD to be treated in ETP followed by RO and 79 KLD to be treated in MEE.

DETAILS OF WATER USAGE AND WASTE WATER GENERATION

S. No. Area of

Consumption

Fresh Water

Quantity,

KLD

Waste Water

Generation,

KLD

Effluent Treatment &

Disposal Facilitry

1 Domestic 6 5 To ETP

2 Gardening 4 - -

3 DM Plant 9 1 To MEE

3.1 Boiler 24 2 To ETP

4 Cooling Tower 90 5 To ETP

5 RO Reject - 17 To ETP

6 Floor Washing

and Equipment

Washing

5 5 To ETP

7 MEE Condensate - 75 To ETP

8 Total Water

Consumption &

Waste Water

174 110 Total 93 KLD to be treated in

ETP followed by RO and 79

KLD to be treated in MEE

9 Recycled Water 70 -

10 Fresh Water

Consumption

104 -

Page 14: PRE-FEASIBILITY REPORT OF PROPOSED EXPANSION CUM …environmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 9. 21. · DTU 313.5 29. TBA 201 30. Fipronil Pyrazole 351

4. Site Analysis a) Connectivity

S.N. Particulars Description

1 Village

District

State

Sampla

Rohtak

Haryana

2 Coordinates 76°43'23.95"E

28°45'41.60"N

3 Most Populated Area Kultana (2.60km), W; Ismaila ,3.90

km, E,

Sampla 5.0 km, E.

4 Surface Water Source

within 10 Km

No any surface water source

5 Nearest Densely Populated

Areas

Kultana (2.60km), W; Ismaila ,3.90

km, E,

Sampla 5.0 km, E.

6 Nearest Highway NH-10 at a distance of 4.20 km (E).

7 Nearest Railway Station Sampla (Broad Gauge) 5.0 kms in

E direction

8 Nearest Village Kultana (2.60km), W

9 Nearest Town Rohtak,29.0 km,NW

10 Nearest Airport Indira Gandhi International Airport

– 80 Km (SE)

11 Nearest Forest No Protected Forest

12 Recorded Sensitive Places There is no sensitive area in the

study area.

13 Historical Places There is no historical area in the

study area.

14 Location of National Parks/

Wildlife Sanctuary within

10 Km radius of the project

site

There are no National Parks/

Wildlife Sanctuary in the study

area.

b) Land Form, land use and Land ownership

The general elevation of the area is 221 msl. The area has plain topography and major area

around the project site is dominated by agricultural land.

Page 15: PRE-FEASIBILITY REPORT OF PROPOSED EXPANSION CUM …environmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 9. 21. · DTU 313.5 29. TBA 201 30. Fipronil Pyrazole 351

c) Topography

Page 16: PRE-FEASIBILITY REPORT OF PROPOSED EXPANSION CUM …environmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 9. 21. · DTU 313.5 29. TBA 201 30. Fipronil Pyrazole 351

d) Existing infrastructure Refer to Annexure 2 Site Layout

5. Baseline Environment e) Soil classification

The district area is occupied by Indo-Gangetic alluvium. There are no surface features worth to

mention. Physiographically the area is flat terrain. The area slopes towards northeast to

southwest with an average gradient of 0.19 m/km.The general elevation in the district varies

between 215 m to 222m above MSL. The soils of the district arefine to medium textured. It

comprises sandy loam in Rohtak, Sampla, and Lakhan Majra blocks whereas it is loamy sand

with occasional clay loam in Kalanaur and Meham Blocks. High potassium, medium phosphorus

and low nitrogen occur in the soils. The soils of the district are classified as arid brown

(Solemnized) and sierozem..

f) Climatic data from secondary source The climate of Rohtak district can be classified as subtropical monsoon, mild &dry winter, hot

summer and sub-humid which is mainly dry with very hot summer and cold winter except during

monsoon season when moist air of oceanic origin penetrate into the district. The hot weather

season starts from mid March to last week of the June followed by the south west monsoon

which lasts upto September. The transition period from September to November forms the post

Page 17: PRE-FEASIBILITY REPORT OF PROPOSED EXPANSION CUM …environmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 9. 21. · DTU 313.5 29. TBA 201 30. Fipronil Pyrazole 351

monsoon season. The winter season starts late in November and remains upto first week of

March.

g) Social infrastructure available Project site is well connected with NH-10 (4.20 Km-E). It is also connected with district Rohtak

(29.0 Km- NW) where basic facilities like hospital, school etc. are present in the area.

6. Planning brief (i) Planning concept (type of industries,

facilities, transportation etc) Town

and Country Planning/Development

authority Classification.

The proposed plant will come under medium scale industry well connected with all public transport facilities. Proopsed Plant located at , 5 KM Stone, Sampla Beri Road, Village Sampla, Tehsil – Sampla, Distt- Rohtak – 124501 (Haryana)

(ii) Land use planning (breakup along

with the green belt etc). Total Land : 30,000 m2

Green area : 10,000 m2(proposed) Green belts up to 33 % is proposed.

(iii) Assessment of infrastructure

Demand (Physical & Social).

Will be developed as per requirement.

(iv) Amenities/Facilities. Will be developed as per requirement.

7. Proposed Infrastructure (i) Total Area 30,000 m

2

(ii) Green Belt. 10,000 m2(proposed)

(iii) Social Infrastructure. None

(iv) Connectivity (traffic and

Transportation

Road/Rail/Metro/Water ways etc)

Nearest connectivity NH-10 at a distance of 4.20 km

(E).

(v) Process / Drinking Water

Management (Source & Supply of

water)

Total water requirement of 104 KLD

Source: Outside vendor, through tanker

(vi) Industrial Waste Management. Waste from ETP and other waste will be sent to

waste management facility.

(vii) Solid Waste Management. Will be sent to approved agency/ site for safe

disposal

(viii) Power Requirement & Supply /

source.

1000 KVA will be obtained from state power

corporation. Also 2 DG sets are to be installed.

8. Rehabilitation & Resettlement (R&R) Plan Not Applicable

Page 18: PRE-FEASIBILITY REPORT OF PROPOSED EXPANSION CUM …environmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 9. 21. · DTU 313.5 29. TBA 201 30. Fipronil Pyrazole 351

9. Project Schedule & Cost Estimates a) Project Cost Estimation

The estimated cost of the proposed Project is ~ 30 crore.

b) Cost towards Environmental Protection The estimated cost towards Environmental Protection is 12 lac/annum.

c) Project Implementation Schedule The construction and production from new plant may start after the approval.

Public liability insurance plan policy will be obtained for suitable amount. On site & off site

emergency plans will be prepared and enforced by continuous training to all concern.

10. Environmental Management Plan a) Air Pollution Control Gaseous emission from fuel burning, consist of common pollutants like SO2, NO2, and

PM would be discharged into atmosphere through Stack of suitable height.

Green belt will be developed covering >33% of the total project area, around the plant

boundary as dust preventive barrier.

Odor Control System: All the vents of the batch tanks and solvents are connected to

scrubber to absorb any pollutant / odor producing gases and chemicals. Green belt around

the plant boundary will absorb the odor to some extent.

The operation of centrifuging/ filter will be done in closed equipment to avoid any vapors

coming out in the local atmosphere. The vents of centrifuges / filters will be connected to

scrubbers.

The drying of the product is done in a closed type continuous Fluidized Bed dryer/ Nudge

filter to avoid the exposure of any chemicals to human being.

Volatile organic solvents are carefully handled in a closed system, thereby preventing any

discharge of these chemicals into the air.

Process emission quality will be maintained as per the following standards:

H2S < 45 mg/Nm3

NH3 < 175 mg/NM3

HCl <20 mg/NM3

SO2 <40 mg/NM3

Cl2 <9 mg/NM3

Adequate systems shall be provided to capture the emissions from process plants &

maintain the emission quality as per recommended guidelines with central scrubber

having caustic solution, before venting it in to the atmosphere.

Page 19: PRE-FEASIBILITY REPORT OF PROPOSED EXPANSION CUM …environmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 9. 21. · DTU 313.5 29. TBA 201 30. Fipronil Pyrazole 351

Table 1.11 Name of Equipment

Air Pollution Control Measures

S. No.

Stack Attached

to Fuel Used

Quantity of Fuel

APCM Expected Pollutants

Efficiency of APCE

Stack Height(m)

Flue Gas Stacks

1 Boilers

Agrowaste briquettes / FO (as per

availability)

300 Sm3/Hr HG or 4.2 KLD

FO

- PM, SO2

& NOx - 35

2 Thermic

Fluid Heater

LDO (as per

availability)

25 Sm3/Hr NG or 200

Ltr/Day LDO

- PM, SO2

& NOx - 30

3 DG Sets HSD 200 Ltr/Hr

Adequate Stack Ht.

PM, SO2 & NOx

- 15

Process Stacks / Vents

1

Process Reactor – Vents (5

Nos.)

- - Acid

Scrubber

HCl, HBr, H2S, NH3, NOx & HC

99.5 % 35

2

Process Reactor – Vents (6

Nos.)

- - Gas

Scrubber 99.5 % 35

3

Process Reactor – Vents (6

Nos.)

- - Gas

Scrubber 99.5 % 35

All the above mentioned air pollution control measures shall be practiced to minimize air

pollution in and around plant.

b) Waste Water Management Out of total water requirement of 174 KLD, 104 KLD of fresh water will be required while

the industrial waste water generated (~ 93 KLD) will be treated in the Effluent Treatment

Page 20: PRE-FEASIBILITY REPORT OF PROPOSED EXPANSION CUM …environmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 9. 21. · DTU 313.5 29. TBA 201 30. Fipronil Pyrazole 351

Plant ETP/ MEE. After treatment (~70 KLD) will be recycled back in the system. The

domestic Waste sent to Soak Pit but in later future STP is proposed to be commissioned.

c) Noise Environment Installation of the plant machinery will be done after- due consideration to design noise

levels and noise mitigation measures.

The green belt developed helps in reducing noise levels generated due to plant operations.

There will be no major sources of industrial noise; minor noise generated from the

industrial operations will be controlled by proper maintenance.

Proper mitigation measures will be taken in addition to above for the reduction of noise

levels i.e. use of acoustic enclosures and providing personal protective equipment etc. to

the workers.

Periodical monitoring for noise is being carried out on regular basis.

Proper maintenance, oiling and greasing of machines at regular intervals is done to

minimize generation of noise at source.

The D.G. sets will be provided with acoustic enclosures.

d) Solid Waste Management Minor quantities of construction waste will be generated in the form of packaging

material and construction waste. Proper care will be taken for handling and reduction of

the solid waste generated during construction phase.

During the operation phase the solid waste is being generated in the form of ETP sludge,

etc..

Hazardous solid wastes will be sent to nearby TSDF site.

e) Green Belt Development/Plantation Green belt development in and around the project site will help in to attenuate the pollution level.

Out of the total plant area of 30,000 Sq M,, Approx. ~ 10,000. Sqm (33%) land will be

developed as green belt. Green belt will be developed as per Central Pollution Control Board

(CPCB) Norms. The Avenue plantation will give priority to native species, and the periphery

will be devoted to generation of green belt area.

Green belt development in and around the project site will help in to attenuate the

pollution level.

Native species will be given priority for Avenue plantation.

The periphery will be devoted to generation of green belt area.

f) Hazardous Waste Management

HAZARDOUS WASTES CATEGORY AS PER HAZARDOUS WASTE THE HAZARDOUS

WASTES (MANAGEMENT, HANDLING AND TRANSBOUNDARY MOVEMENT)

RULES, 2008

(As specified under hazardous wastes / management handling rules 1989) amendment rule 2003.

Process wastes/ residue

Chemical sludge containing residue insecticides

Date expired and off-specification insecticides

Page 21: PRE-FEASIBILITY REPORT OF PROPOSED EXPANSION CUM …environmentclearance.nic.in/writereaddata/Online/TOR/0_0... · 2015. 9. 21. · DTU 313.5 29. TBA 201 30. Fipronil Pyrazole 351

All above waste are will be collected and stored at separate identified place and suitably disposed

off to authorized agencies.

11. CSR Activities

The project activity and the management will support the local panchayat by providing of

assistance for the development of public amenities in the region and will help in improving the

overall infrastructure status of the area. Thus the proposed project of PPL will be proved

beneficial to the local economy and society and will not lead to any adverse impact on the

environment.