61
PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA MARCH 2016 SUBMITTED TO ODISHA URBAN INFRASTRUCTURE DEVELOPMENT FUND (OUIDF) (FOR JODA MUNICIPALITY) BY TATA CONSULTING ENGINEERS LIMITED 247 PARK, 4 TH FLOOR, TOWER ‘A’ L.B.S MARG, VIKHROLI (WEST) MUMBAI- 400083

PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

Embed Size (px)

Citation preview

Page 1: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA

MARCH 2016

SUBMITTED TO

ODISHA URBAN INFRASTRUCTURE DEVELOPMENT FUND (OUIDF)

(FOR JODA MUNICIPALITY)

BY

TATA CONSULTING ENGINEERS LIMITED

247 PARK, 4TH FLOOR, TOWER ‘A’ L.B.S MARG, VIKHROLI (WEST)

MUMBAI- 400083

Page 2: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

i

Page No.

SUMMARY i-vii

CHAPTER 1 - INTRODUCTION 1

1.1 Odisha Urban Infrastructure Development Fund

: 1

1.2 Project Objectives : 2

1.3 Authorization : 2

1.4 Scope of the Report : 2

1.5 Structure of the Report : 3

1.6 Acknowledgement : 3

CHAPTER 2: PROJECT DETAILS 4

2.1 Need for the Project : 4

2.2 Profile of Project Area : 4

2.2.1 Profile of Joda ULB : 4

2.2.2 Location of Joda Site : 5

2.2.3 Topography of Land : 5

2.2.4 Climatic conditions (Meteorology) : 6

2.2.5 Area and Population : 6

2.2.6 Population Projections : 6

2.2.7 Population Density : 6

2.3 Current waste management Scenario : 9

2.3.1 Primary Collection : 9

2.3.2 Secondary Collection and Transportation : 10

2.4 Details on waste quantity, composition and waste generation rates

: 11

2.4.1 Waste Quantity, Composition and Waste Generation Rates in Joda

: 11

2.4.2 Gaps in waste collection : 11

2.4.3 Waste Characterization : 11

2.4.4 SWM organization : 12

2.5 Baseline Study Parameters for Study : 12

TABLE OF CONTENTS

Page 3: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

ii

Page No.

CHAPTER 3: PROPOSED SOLID WASTE MANAGEMENT FACILITIES 13

3.1 Technical Profile : 13

3.1.1 Integrated Waste Management : 13

3.1.2 Proposed Scheme for Joda Municipality for Solid Waste Management

: 13

3.2 Waste Collection : 15

3.2.1 Primary Waste Collection : 15

3.2.2 Secondary Collection : 16

3.2.3 Construction and Demolition Waste : 17

3.2.4 E-Waste : 17

3.3 Processing Plant for Municipal wastes : 19

3.3.1 Segregation of hazardous materials : 19

3.3.2 Landfilling : 20

3.4 Process Technology : 20

3.4.1 Technology Alternatives for Waste Processing : 20

3.4.2 Selection of Technology : 21

3.4.3 Waste Management by Composting : 22

3.4.4 Windrow Composting : 22

3.4.5 Aerated Static Pile Composting : 24

3.4.6 In-Vessel Composting : 25

3.4.7 Decentralized Composting : 25

3.4.8 Vermi Composting : 25

3.4.9 Optimization of Windrow Composting Processing Facility

: 26

3.4.10 Broad Specification for the Sanitary Landfilling Facility

: 26

3.4.10.1 Liner System : 26

3.4.10.2 Leachate Collection : 28

3.4.10.3 Leachate pond : 28

3.4.10.4 Leachate Treatment : 28

Page 4: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

iii

Page No.

3.4.11 Infrastructure of Processing and Land filling : 28

3.4.12 Option for Additional Technology Intervention : 29

3.4.13 Reclamation of Existing Dump yard : 29

3.4.14 Alternatives for Management of Medical Waste : 30

3.5 Resources : 32

3.5.1 Manpower : 32

3.5.2 Equipments for handling Waste, Transportation Vehicles, Infrastructure Development

: 32

3.5.2.1 Construction material : 33

3.5.2.2 Power : 33

3.5.2.3 Source of water for utilities, domestic : 33

CHAPTER 4 - SITE SELECTION 34

4.1 Land details : 34

4.2 Major techno-economic feasibility considerations : 34

4.2.1 Joda Site for Dedicated Processing & Land filling Facility

: 34

4.3 Option for Centralized Processing & Land filling for Joda-Barbil Cluster

: 35

4.3.1 Land Area Required : 35

4.3.2 Traffic Problems : 35

4.3.3 Public Resistance : 35

4.3.4 Ownership Issues : 36

4.4 Boundary Wall with Greenbelt and Landscaping : 36

4.5 Suitability of Landfill Site : 36

4.6 Suitability of Joda Landfill Site : 38

4.7 Social Aspects : 38

Page 5: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

iv

Page No.

CHAPTER 5 - ENVIRONMENTAL MITIGATION MEASURES : 40

5.1 Air pollution control measures : 40

5.2 Water pollution control measures : 40

5.3 Solid waste disposal : 41

5.4 Noise : 43

5.5 Ecology of the Area : 43

5.6 Green belt development : 43

5.7 Land use : 43

5.8 Design Environmental Targets : 44

5.9 Environmental Monitoring : 45

CHAPTER 6- REHABILITATION AND RESETTLEMENT (R&R) PLAN : 46

6.1 Joda Site : 46

CHAPTER 7- PROJECT SCHEDULE & COST ESTIMATES : 47

7.1 Project Implementation Schedule : 47

7.2 Project Cost : 47

Page 6: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

v

Page No.

LIST OF FIGURES

2-1 Joda Ward Map : 7

2-2 Joda Site Location Map : 8

2-3 Topographic Land Features within a Radius of 5km from Joda Dump Site : 9

3-1 Proposed Scheme for Waste Collection, Transportation and Processing at Joda Municipality

: 14

3-2 Zone Map for Joda : 18

3-3 Process Scheme for Windrow Composting : 23

3-4 Typical Sectional Profile of Liner Systems & Leachate Collection of Sanitary Landfill

: 27

3-5 A Comparison of Waste Management System in Existing and Proposed Scenario

: 31

Page 7: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

vi

Page No.

LIST OF TABLES

2-1 Population Projection for Joda : 6

2-1 Vehicles for Primary Collection and transportation at Joda : 10

2-3 Manpower for SWM in Joda : 12

3-1 Regulatory Guidelines of Compost Quality : 24

5-1 Environmental Mitigation Measures : 42

Page 8: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

i

SUMMARY

This Summary presents the highlights of the proposed project for setting up of an Integrated

Municipal Solid Waste Processing and Sanitary Landfilling at Joda in the state of Odisha.

Introduction

1. The Implementation of Municipal solid Waste (MSW) Management is an important

component of the Government of India's (GoI) "Swachh Bharat Mission" (SBM) -

component IV. The Government of Odisha has set up a Trust namely "Odisha Urban

Infrastructure Development Fund (OUIDF)" in the Housing & Urban Development for the

purpose of developing and financing of these Projects.

2. OUIDF has grouped 32 Urban Local Bodies (ULBs) into ten (10) clusters for preparation of

DPR for integrated solid waste management. TATA Consulting Engineers Limited (TCE)

has been appointed by OUIDF for preparation of DPR for integrated solid waste

management for Cluster VIII comprising of Joda and Barbil ULBs.

3. The objective of the project is to implement integrated solid waste management system

into action in the identified ULBs and offer the citizens of Joda a clean, healthy and safe

environment.

Project Highlights:

Project Details Integrated Municipal Solid Waste Processing and Sanitary Landfilling.

Site Joda, Keonjhar district – Odisha

Land Area Required Within the existing dump area of about 5.5 acres

Water Source Existing Municipality bore well or PHED supply.

Water Requirement About 20-30 KLD

Electrical Power Source Nearest Substation

Electrical Power Demand 100KVA

Fuels HSD for DG Set power back-up for Admin Bldg.

Employment Opportunity About 20-25 persons (direct)

Capital Investment (INR) About 6.74 Crores for Composting & Land filling (phase I)

Additional Environmental Mitigation Cost (INR)

In the tune of 60 lakhs

Page 9: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

ii

Project Details

4. Joda is a Municipality in Barbil Tehsil of Champua Sub-division in Kendujhar (Keonjhar)

district of Odisha. Joda has a population of 46,681 (as per Census 2011) with 10,697

households within its 14 wards. It is at a distance of about 15km Barbil Municipality.

5. Joda is famous for its rich iron and manganese mine deposits. There are 31 slums and 6

revenue villages under Joda Municipality. The area under the municipality is about 26.5

sq. km. The slum population is about 70 percent.

6. The estimated collection of municipal solid waste is in the tune of 14 TPD from all sources.

7. The primary and secondary waste collection in Joda is primarily outsourced to external

agencies with a central supervisory manpower under the respective Municipalities. Main

infrastructure available for primary collection and transportation are Tricycle, Push Cart

Carriers and tractors.

8. The area acquired by the Municipality for dumpsite is about 5.53 acres. This land is under

the possession of Joda Municipality and is already being used for open dumping of mixed

municipal solid wastes generated within Joda ULB.

9. The study area of Joda is located within 22000’00’’ to 22002’30’’ latitude and 85025’00’’ to

85027’30’’ longitude. The MSL of the site varies between 459 - 465 m. The Dumping site is

located in ward no. 6 near Bachuhutting, which is in the south direction and is beyond 500

m. In the adjacent dumpsite area the principal drainage channel, Sona River is flowing in

the west at a distance of about 50 metres. Railway line in SE railway from Barbil to

Banspani is adjacent to the landfill site in the eastern direction. Bhadrasahi airstrip, which

is used for occasional small business flight operations is at a distance of about 7 km NW

from this site.

10. Ground water in Joda varies from about 3-6 m below ground level in post-monsoon and

winter season.

11. As per the Climatological Normal of IMD of Keonjhar observatory, the highest temperature

recorded is around 41.80C in May and the lowest temperature recorded is 8.20C recorded

in the month of January. The average relative humidity is around 70% and the total annual

rainfall is about 1284 mm. The mean wind speed is 4.8 km per hr. The predominant wind

directions are from W and NE.

12. The population density for Joda is around 1762 per sq km.

Page 10: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

iii

13. After survey and estimation it appears that the total municipal solid waste generation from

all sources in Joda in 2016 is about 14 TPD. This is estimated to go up to 21 TPD in 2032

.

Sl. No.

ULB Waste Generation (TPD)

2018 2022 2027 2032

1. Joda 15 17 19 21

14. Physical characterization of municipal solid waste sampling carried out indicates a waste

composition of 37-45% of compostable matter, recyclables of 12-15% and inert matter of

40-45%.

15. Chemical characterization indicates C/N ratio ranging from 21-31 and calorific value of

mixed dumpsite wastes is found to be in the range of 1180-1310 Kcal/kg.

16. The presence of toxic elements like lead, mercury, chromium, arsenic, cadmium etc. are

found to be in the range of 0.011-8.4 mg/kg which are well within the permissible limits of

Schedule II Class A and Class B of Hazardous Wastes (Management, Handling and

Transboundary Movement) Rules, 2008 vide MoEFCC, GOI notification dated 24th

September, 2008.

17. EIA study for the Processing Plant and Sanitary landfilling would be carried out by

conducting base line study of one dry month.

18. Baseline data would be collected as per stipulated guidelines within the study area of 5 km

radius around the proposed site which shall include micro-meteorology, ambient air

environment, surface and ground water quality, ambient noise quality, land environment,

ecological environment and socio-economic environment.

Proposed Solid Waste Management Facilities

19. The predominance of food waste compounded by horticultural waste would drive the

choice of technology more towards biological processing i.e. composting. Good C/N ratio

and lean calorific value of wastes probably indicate composting as the preferred choice of

technology for waste processing for Joda.

20. Composting of municipal waste can be broadly classified in five (5) categories namely,

wind row composting, aerated static pile composting, in-vessel composting, decentralized

composting and vermin-composting.

Page 11: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

iv

21. The suitable technology of choice for composting in Joda would be windrow composting

due to lower capital investment and operational costs as compared to other composting

technologies combined with large scale success of this technology across India.

22. Processing of waste is necessary for recovery of recyclable materials. The centralized

processing Plant would receive segregated waste in wet, dry and mixed form. The dry

waste processing would utilize manual labour or equipment that separate material into

various streams e.g. fibre, paper, plastic, containers etc. for disposing same to designated

pool of recyclers.

23. The wet waste collected in the segregated form from primary and secondary collection

stations would be pre-processed before sending for wind row composting.

24. The processing facility would be complete with pre-sorting material handling equipment,

various size reduction facilities for metal cans, plastic bottles etc. The processing facility

would also comprise of pollution control equipment and other equipments e.g. fixed

storage bins, truck scale, belt scale etc.

25. The recoverable hazardous items would be disposed of to recycling agencies or sent to

secured land fill after sorting out carefully from the dry and wet waste segregation lines.

The rejects after processing would be stored in a separate place for placing it in a secured

landfill with proper liner systems. There would be leachate collection and treatment system

with evaporation ponds for management of the leachate generated within the landfill

facility.

26. It is estimated that about 40-45% of the total waste generation would be rejects or wastes

in the real term, which need to be land filled in a proper manner. The secured waste

landfill area shall be designed for an initial period of 10-12 years of storage to be later

expanded to 25 years based on area availability. The total landfill area would be divided in

separate phases of 5-7 years each.

27. The processing and land filling facility at Joda would be complete with peripheral access

roads within the site, approach road to the landfill site upto the processing plant, security

office, weigh bridge & control building, water supply facilities, power and lighting system,

communication system, sewage system, fire-fighting system, tyre cleaning system, garage

and workshop, administration office and laboratory, 4 m high compound wall all along the

property line with barbed wire fencing with 3-5 m wide peripheral greenbelt. The coverage

of greenbelt has been estimated to be about 12% of the total area.

Page 12: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

v

28. The physical infrastructure components in the primary and secondary collection and

transportation services include the procurement of tricycles, Household Bins, Community

Bins, Tata Ace tippers and garbage compactors for transportation of MSW from various

wards.

29. With the increase in population the waste generation would also increase which would in

turn require larger number infrastructure components for collection and transport of the

waste.

30. The available landfill area can accommodate additional space for waste storage, if the

rejects fraction of the recyclable wastes in the tune of about 15% is subjected to RDF

technology for manufacture of RDF pellets.

31. The existing dump material in Joda is scattered indiscriminately. As soon as the layout for

the proposed processing and landfilling shall be finalized, an area shall be demarcated to

store the waste already dumped and strewn around the site.

32. It is estimated that about 3000-4000 TPD of waste has been dumped so far in last 10

years in the dumpsite. The ULB has to take initiatives to remove the already dumped

mixed waste and store at a designated area within the facility.

33. The manpower would be ensured for smooth functioning of the activities involved in waste

collection, transportation, processing and land filling operations of designated Contractor

Agencies or BOO-BOOT operators as applicable on a day to day basis.

Site Selection and Social Aspects

34. The site is presently used for dumping of mixed wastes. The site has Authorizations from

OSPCB to set up waste processing facility.

35. Considering Joda and Barbil as cluster towns it would be more convenient if a suitable

land for siting a centralized waste processing and sanitary landfilling facility catering to

both the ULBs could be found out.

36. No central site for waste processing and land filling for Joda and Barbil could be found out

as this would have required about 15 acres land.

37. There are other disadvantages of central processing and landfill site for this cluster

including the significant reason of waste transportation problems due to heavy traffic on

the road connecting Joda and Barbil, the region being an iron-ore deposit zone.

Page 13: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

vi

38. Keeping in with the provisions of the siting guidelines, the site at Joda more or less

qualifies with the stated conditions critical of which is nearness to human habitations. The

processing and land filling facility would be 500 m away from nearest human habitations.

39. Living conditions of nearby settlements would be improved by setting up of this project

facility and also facilitate prevention of water borne diseases to significant extent. It is

expected that due to coordinated efforts of municipality, NGOs and SHGs the socio-

economic conditions of rag-pickers’ families would also be significantly improved.

40. The setting up of composting and landfilling project would help in direct employment of

about 20 - 25 persons. Apart from this there would be employment of additional

employment of 200 odd as contractual skilled and semi-skilled workers for primary and

secondary waste collection, road sweeping, drain cleaning etc. due to the proposed

integrated solid waste management operation.

Environmental Protection Measures

41. The proposed project shall abide by the design environmental guidelines as laid down in

CPCB manual and MSW Rules (Mgmt. & Handling), 2000 and 2015 (vetted), GOI and

prevailing environmental quality at the respective sites.

42. Environment Protection measures regarding air, water, solid waste, noise, land use due to

the proposed project during construction and operational phases would be accounted.

Internal roads would be bitumen covered to reduce fugitive dust emissions.

43. Leachate generated at various places in the plant would be in the range of 4-4.5 cum/hr.

This would be collected and properly treated in an ETP. Sanitary landfilling would be

adopted for rejects generated from processing, ETP sludge and evaporation pond settled

particulates.

44. Site clearing or operational activities would not impact the ecology of the area adversely,

since there are no known rare, endangered or ecologically significant animal and plant

species in the area.

45. The proposed project would be developed on the existing waste disposal site. Hence, no

change in the land use of the site due to the proposed project would be anticipated.

46. Monitoring for air quality parameters as per NAAQS 2009 and surface water quality would

be carried out on a six monthly basis. The ground water quality monitoring in 5 permanent

Page 14: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

vii

monitoring wells within a perimeter of 50 m from the landfill would be carried out quarterly

once.

Rehabilitation and Resettlement (R&R) Plan

47. Proposed project site in Joda is located in ward No. 6 near Bachuhutting. This land is

under the possession of Joda Municipality and is already being used for open dumping of

mixed municipal solid wastes generated within Joda ULB. There are no settlements within

the acquired site. All R&R issues have been already settled by Joda Municipality.

48. The Joda municipality is in possession of Authorization Order from OSPCB to use the land

as dumping ground for MSW. The Joda Municipality is also in possession of the

authorization to set up a waste processing and disposal facility vide OSPCB letter dated

5th December 2013 with a validity of the authorization up to 31st March 2018.

Project Schedule & Cost Estimates

49. The whole project is estimated to be completed in about 12 months following approval of

DPR and 6.5 months from obtaining environmental clearance whichever is later. It is

envisaged that the proposed facility would be operational from January 2018.

50. The estimated CAPEX for the centralized composting and landfilling plant facility would be

about Rs 6.74 Crores for the year 2015- 2016, although this will be operational from 2018.

The cost for environmental monitoring would be around 8 lakhs per annum. However, the

additional estimated cost of EMP for addressing environmental concerns arising due to

setting up of this project would be in the tune of 60 lakhs comprising of ETP for leachate

treatment and permanent groundwater monitoring wells.

Page 15: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

1

CHAPTER 1 - INTRODUCTION

Municipal Solid Waste Management (MSWM) refers to a systematic process that

comprises of storage, collection, transportation, processing and disposal of solid

refuse residuals in an engineered sanitary landfill.

Effective solid waste management has the following benefits:

- It prevents contamination of water and soil;

- Reduces waste sent to the landfill, which may have negative impacts on

groundwater and air quality;

- Reduce emissions from energy consumption, as waste when recycled

requires less energy than making goods from virgin materials thereby

reducing the energy demand and pressure on non renewable sources;

- Contributes to Climate Change by reducing methane emissions from landfills.

Waste prevention and recycling (including composting) divert organic wastes

from landfills, reducing the methane released when these materials

decompose.

- Reduction in quantum of waste by diverting it to recycling and other

processing unit reduces the landfill costs;

- An effective waste management implies the concept of 3Rs e.g. reduce,

reuse and recycle waste matter leading to introduction of more and more of

waste matter into the value chain leading to economic benefits;

- Waste management being a labour intensive activity, it helps in employment

generation.

The Implementation of Municipal solid Waste (MSW) Management is an important

component of the Government of India's (GoI) "Swachh Bharat Mission" (SBM) -

component IV.

1.1 Odisha Urban Infrastructure Development Fund

The Government of Odisha has set up a Trust namely "Odisha Urban Infrastructure

Development Fund (OUIDF)" in the Housing & Urban Development for the purpose

of developing and financing Infrastructure Projects under taken by Urban Local

Bodies, Statutory Bodies, Public Sector Undertakings and Private Investors and

attract inter alia, investments, professional advice from institutions for financing

Infrastructure Projects.

Page 16: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

2

1.2 Project Objectives

The current system of Solid Waste Management (SWM) in most of the ULBs in

Odisha is that door to door collection of waste, collection from market and from

community bins, transportation and disposal at the dump yard is being carried out

without any processing or treatment. This has led to environmental degradation, air

pollution, surface and ground water contamination and poses grave health hazards.

The objective of the project is to implement solid waste management practices into

action in the identified ULBs and offer to the citizens of the state a clean, healthy and

safe environment. As a first step in this direction, OUIDF intends to hire consulting

service providers to design a SWM scheme customized to the requirements of the

identified Clusters. The SWM system would be in line with Integrated Municipal Solid

Waste Management (ISWM) practices and adhering to the local regulations and

professional best practices.

TATA Consulting Engineers Limited (TCE) has been appointed by OUIDF for

preparation of DPR for integrated solid waste management for Cluster VIII

comprising of Joda and Barbil ULBs.

1.3 Authorization

OUIDF with their LoA no. 491/OUIDF (OUIDF - 74/2014) dt. 24-08- 2015 appointed

TCE for preparation of PFR and DPR for integrated solid waste management for

Cluster VIII (Joda and Barbil ULBs). Environmental Clearance for the proposed

projects also needs to be obtained for the respective ULBs from the SEIAA,

Government of Odisha.

1.4 Scope of the Report

This Report presents the present and proposed municipal solid waste management

system at Joda. This Report is prepared for submission of Form-I application to

SEIAA for obtaining Environmental Clearance as per the guidelines of EIA

Notification, 2006 of MoEFCC, GOI.

Page 17: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

3

1.5 Structure of the Report

This Report is presented in seven (7) chapters. The structure of this Report is as per

the guidelines of MoEFCC and Technical EIA Guidance Manual for Common

Municipal Solid Waste Management Facilities, ILFS, September, 2010. Following this

Introduction Chapter, Chapter 2 presents the Project Details; Chapter 3 presents

the Proposed Solid Waste Management Facilities; Chapter 4 presents the Site

Selection; Chapter 5 presents the Environmental Mitigation Measures. Chapter-6

and Chapter-7 highlights the R&R aspects and project cost respectively.

1.6 Acknowledgement

Consultant acknowledges the all round cooperation extended by the authorities of

Joda Municipality in carrying out the basic study. Consultant also acknowledges the

advice and directions provided by OUIDF from time to time for successfully

conducting the study.

Page 18: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

4

CHAPTER 2- PROJECT DETAILS

This Chapter describes the existing waste management scenario, details of waste

quantity, composition and waste generation rates in Joda.

2.1 Need for the Project

At present the MSW disposal is carried out in an unscientific manner by open disposal

of mixed waste. The Implementation of MSW Management is also an important

component of the Government of India's (GoI) "Swachh Bharat Mission" (SBM) -

component IV in 2014.

The Government of Odisha thus proposes to strengthen the MSWM system covering

collection, segregation, recycling, transportation processing and disposal in 32 ULBs

so as to comply with the service level Benchmarks of the GoI and also to meet its goal

of maintaining growth rates without jeopardizing the environment and its natural

resources. The setting up of proposed project at Joda, which is one of the 32 ULBs is

aimed at fulfilling the above objectives.

2.2 Profile of Project Area

The project area consists of Joda Municipality in Keonjhar district of Odisha. Joda is

important due to the presence of iron ore deposits and a concentration of small to large

scale mining industries.

2.2.1 Profile of Joda ULB

Joda is a Municipality in Barbil Tehsil of Champua Sub-division in Kendujhar (Keonjhar)

district of Odisha. It has a tribal population of 30%. Joda is famous for its rich iron and

manganese mine deposits. Both minerals are exported to China and Korea through

Haldia port near Kolkata and Paradip port near Bhubaneswar. Joda got municipal

status in 1993. Joda has a population of 46,681 (as per Census 2011) with 10,697

households. Joda is about 15 kms from Barbil. Joda is located at a distance of 260 km

from state capital Bhubaneswar. The nearest railway station is at Banspani at a

distance of about 4 km from the dumpsite and the Barbil railway station is at a distance

of about 7.1 km from Joda. Ranchi Airport at Jharkhand is located at a distance of

about 256 km by road and Bhubaneswar Airport in Odisha is located at a distance of

266 km from Joda by road. Joda municipality has 14 wards. Sona River, the major

surface water stream passes through Ward Nos. 1,3,4,5 6, 7, 10 and 14. There are 31

Page 19: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

5

slums and 6 revenue villages under Joda Municipality. The area under the municipality

is about 26.5 sq. km. The population projection would be in the tune of 70,000 in 2030.

2.2.2 Location of Joda Site

Project site in Joda is located in ward no. 6 near Bachuhutting within 22000’00’’ to

22002’30’’ latitude and 85025’00’’ to 85027’30’’ longitude in Barbil Tehsil of Champua

Sub-division in Kendujhar (Keonjhar) district of Odisha.

The area acquired by the Municipality for dumpsite is about 6 acres. A survey of the

land area has been carried out in the present study which indicates an available land

area of about 5.53 acres. The site comes under Seismic Zone-II i.e. low damage risk

zone. Occurrence of flood is not envisaged.

This land is under the possession of Joda Municipality and is already being used for

open dumping of mixed municipal solid wastes generated within Joda ULB.

Railway line in SE railway from Barbil to Banspani is however, adjacent to the landfill

site in the eastern direction. Bhadrasahi airstrip, which is used for occasional small

business flight operations is at a distance of 7 km NW from this site. The waste

dumping site for TSL is near Manmora and the area of the dumping site is around 2

acres. The site has been in use for the past 5 years. The nearest settlement of existing

Joda dump site is Bacchu Hutting in the south direction and is beyond 500 m.

The Ward Map and Site Location Map is as shown in Fig 2-1 and 2-2 on pages 7 and 8

respectively.

2.2.3 Topography of Land

The topography of the land area is moderately undulating. The MSL of the site varies

between 459 - 465 m. The Sona River is flowing in the west at a distance of about 50

metres which is the principal drainage channel for storm water in the adjacent area. The

site is surrounded by hills on the NW which are mainly iron ore deposits. The general

elevation of the study area within 5 km radius is varying from 400-720 m above msl. In

the South is the Baitarani Reserved Forest which is mainly occupied by the mining

industry as the area is rich in iron and manganese deposits. The topographical map of

Joda showing the study area within 5 km radius of proposed project site is presented in

Fig 2-3 on page 9

Page 20: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

6

2.2.4 Climatic conditions (Meteorology)

As per the Climatological Normal of IMD of Keonjhar observatory, the highest

temperature recorded is around 41.80C in May and the lowest temperature recorded is

8.20C recorded in the month of January. The average relative humidity is around 70%

and the total annual rainfall is about 1284 mm. The mean wind speed is 4.8 km per hr.

The predominant wind directions are from W and NE.

2.2.5 Area and Population

Joda has a population of 46,681 (as per Census 2011) with 10,697 households. The

Joda ULB is divided into 4 zones. Ward Nos. 1,2,3,4 are in Zone 1, ward Nos. 6, 7, 8

are in Zone 2, ward Nos. 5,9,11 are in Zone 3 and Ward Nos. 12, 13, 14 are in Zone 4.

There are 31 slums and 6 revenue villages under Joda Municipality. As per Census

2011, the slum population is around 33641 with 6728 households. The area under the

municipality is about 26.5 sq. km. The estimated collection of municipal solid waste as

furnished by Joda Municipality is in the tune of 16 TPD from all sources.

2.2.6 Population Projections

The population projection for Joda is as given in Table 2-1.

Table 2-1: Population Projection for Joda

Sl. No. Year Population

1. 2018 52404

2. 2022 55934

3. 2027 60628

4. 2032 65651

2.2.7 Population Density

The population density for Joda is around 1762 per sq km.

Page 21: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

7

Fig 2-1: Joda Ward Map

Page 22: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

8

Fig 2-2: Joda Site Location Map

Page 23: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

9

2.3 Current waste management Scenario

Joda practices waste collection and dumping of same in their respective designated

grounds as stated above on a regular basis. The present estimated collection of

municipal solid waste as furnished by Joda Municipality is in the range of 15-16 TPD

from all sources.

2.3.1 Primary Collection

Primary collection is the practice of waste collection from its very source of generation.

Primary collection includes ‘house to house’ or ‘door to door’ collection, collection of

waste from commercial units like shops, hotels and restaurants. There is no

segregation of waste at source.

PROJECT SITE

22002’30”N

2200’N

85

02

5’E

85

02

7’3

0” E

Fig 2-3: Topographic Land Features within a Radius of 5km from Joda Dump Site

Page 24: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

10

There are efforts for door to door waste collection on a daily basis from all households

except the slum areas. In the slum areas door to door collection is not found to be

possible due to inaccessibility of push carts or tricycles in the narrow lanes. The waste

from the road side bins and door to door collection is done through tricycles and push

carts to secondary collection centre from where the same is transported through

tractors.

In Joda, number of wards covered by door to door collection is 13 out of 14 wards.

Wards 1 to 8 are entirely covered under door to door waste collection system and

Wards 9-14 are having 60-70% coverage for door to door collection and there is no

door to door collection in Ward no. 10. Primary collection and transportation of mixed

wastes to separate designated dumping sites is also carried out by the major industrial

establishments like Tata Steel, SE Railway, for their colony households.

The capacity of community bins are 200 litres each and are made of Plastic and Metal.

Street sweeping for 200 km road length is carried out on a basis of 80 km per day. The

waste generated from cleaning drains is around 2-3 TPD and are transported to the

dumpsite in tractors. The equipments required for road cleaning and drain cleaning is

outsourced.

2.3.2 Secondary Collection and Transportation

Tractors are used for transportation of waste from the collection points to disposal site.

The bins are common for both decomposable and non-decomposable waste. The auto

tippers are found to be in breakdown condition. The capacity of Tractor is 1 ton each.

The tractors owned by the municipality are between 7-9 years old. The total distance

travelled for transportation of waste is around 12-16 trips daily.

Table 2-2: Vehicles for Primary Collection and transportation at Joda

Name of the vehicles

No. of vehicles Condition

Tricycle 30 Good

Auto Tippers 02 Breakdown

Push Cart Carriers 28 -

Tractor 3 Good

Page 25: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

11

2.4 Details on waste quantity, composition and waste generation rates

The waste generation from Joda, collection of same, existing gaps and waste

characterization is dealt with in the following sub-sections.

2.4.1 Waste Quantity, Composition and Waste Generation Rates in Joda

During the present study, the total municipal solid waste generation at Joda is

estimated to be about 14 tons/day for the year 2015-16. This is estimated that waste

generation would go up to about 21 TPD in 2032. Based on the present waste

collection system, which is lifted manually in ‘Jhuris’ (waste baskets) into the tractor-

trailers, the estimated daily waste collection from all sources by 11 trips of tractor-

trailers of 1 ton capacity each is about 11 tons in Joda including drain silt, roadside

litters etc. Excluding drain silt, construction debris, this indicates that a gap of about 3-5

tons/day exists. This gap is accountable by dedicated waste collection practiced in Joda

by Tata Steel for their Colony households and S.E. Railways for their residential

Quarters and dumping in separate designated grounds.

2.4.2 Gaps in waste collection

During the survey, it has been observed that in many of the slum zones, waste

collection is poor and irregular and wastes are mostly dumped by the community

nearby the hutments. The animals comprising of cattle, goats, dogs are found to be

feeding on the vegetable and fish/mutton/chicken wastes.

2.4.3 Waste Characterization

Physical characterization of municipal solid waste sampling carried out in Joda

indicates a waste composition of 37-45% of compostable matter, recyclables of 12-15%

and inert matter of 40-45%. Chemical characterization indicates C/N ratio ranging from

21-31 and calorific value of mixed dumpsite wastes is found to be in the range of 1180-

1310 Kcal/kg. The presence of toxic elements like lead, mercury, chromium, arsenic,

cadmium etc. are found to be in the range of 0.011-8.4 mg/kg which are well within the

permissible limits of Schedule II Class A and Class B of Hazardous Wastes

(Management, Handling and Transboundary Movement) Rules, 2008 vide MoEFCC,

GOI notification dated 24th September, 2008.

Page 26: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

12

2.4.4 SWM organization

The manpower available for primary collection and transportation are labour for Door to

Door Collection, Sweeper & drain cleaners, Drivers, Sanitary Workers, Labourers,

Supervisors.

Table 2-3: Manpower for SWM in Joda

Sl. No.

Manpower Wards managed by Municipality (outsourced to Private Agencies)

1. Door to door collection 16

2. Sweeper & drain cleaners 26

3. Rag Pickers Nil

4. Drivers 18

5. Sanitary Workers 31

6. Labourers 8 (Own)

7. Supervisors 6

2.5 Baseline Study Parameters for Study

EIA study for the Processing Plant and Sanitary landfilling would be carried out by

conducting base line study of one dry month.

The EIA study would include determination of baseline conditions within 5 km radius

study area from the boundary of the project site, assessment of the impacts on the

environment due to the construction and operation of the proposed project and

recommendations on the mitigation measures to be adopted, to minimize the impact

on the environment within acceptable levels. Baseline data would be collected as per

stipulated guidelines within the study area of 5 km radius around the proposed site

which shall include micro-meterology, ambient air environment, surface and ground

water quality, ambient noise quality, land environment, ecological environment and

socio-economic environment.

Page 27: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

13

CHAPTER 3- PROPOSED SOLID WASTE MANAGEMENT FACILITIES

The existing waste management scenario, details of waste quantity, composition and

waste generation rates in Joda has been described in the previous Chapter. This

Chapter presents the proposed solid waste management facilities for Joda ULB.

3.1 Technical Profile

Various activities of the proposed integrated municipal solid waste management in Joda

ULB right from segregated primary collection, secondary collection and transport to the

centralized facility at the respective municipalities, processing technology for waste

composting, landfilling of the rejects generated during secondary segregation and

processing have been described in the sections below.

3.1.1 Integrated Waste Management

A proper and scientific integrated waste management system would upgrade

significantly the living status of the people residing there and also ensure eradication of

some of the major health related problems when combined with 100% compliance to

clean sewerage facilities and pure drinking water supply in all the Wards.

3.1.2 Proposed Scheme for Joda Municipality for Solid Waste Management

The essential steps of an efficient solid waste management system are balanced on

scientific and timely collection both at primary and secondary levels, of waste generated

from each household across all sections of people including the slum areas in each

Ward of the municipality, regular street and drain sweepings, ensuring maximum

segregation at origin followed up by secondary segregation at waste processing facility

and secured land filling of inert and non recyclable waste fraction. Other important

aspect of a sustainable waste processing facility is installing proper monitoring

mechanism from the angle of environmental aspects, economic returns and community

acceptance. The proposed scheme for waste collection, transportation and processing

for Joda Municipality is given in Fig. 3-1 on the next page.

Page 28: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

14

Fig.3-1: Proposed Scheme for Waste Collection, Transportation and Processing at Joda Municipality

Page 29: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

15

3.2 Waste Collection

A two bin system shall be introduced for waste collection at all levels and sources of

generation. The 2-bin system would essentially comprise of (i) principally wet or

moist waste comprising of kitchen waste, food waste etc. which are bio-degradable

and (ii) principally waste papers, plastics, sanitary napkins, rags, cardboards, etc.

many of which are recyclable. The street sweepings and drain cleaning material and

sludge would not be disposed along with the household municipal waste collected.

The silt collected from the drains would be disposed of in low lying lands. The street

litter collected which would be mixed in nature shall be brought to the processing

facility for waste processing and segregation.

3.2.1 Primary Waste Collection

Primary waste would be collected from all households and slum areas within each

ward of the ULB. Joda ULB having 14 wards would be segregated into 4 zones e.g.

Zone-1 comprising of Ward -1, 2, 5,6, 7 and 8; Zone -2 comprising of Wards – 3,4,10

and 14; Zone -3 comprising of Wards – 9 &11 and Zone-4 comprising of Wards – 12

& 13.

Household Collection

For one first time Municipal Authorities in Joda has to provide two (2) separate bins

of color ‘Blue’ and ‘Green’ to each household. The Blue color bin would be meant for

collection of all recyclable or non-biodegradable items which are basically dry in

nature. The Green color bin would be meant for collection of various wastes as

identified above which are wet in nature. The bin sizes can be of 20 litre each. Two

(2) Tata Ace-tipper with dedicated dry and wet waste containers (capacity -1.8 cum)

of green and blue color would visit the major lanes and by-lanes every day morning

at pre-determined time for waste collection. This system and schedule of arrival in

each Ward would be informed to the households at prior by ULB officials through

respective Ward Councilors and Supervisors. For areas where Tata Ace-tipper

cannot enter due to narrow lane access, the tri-cycle with separate dry and wet waste

containers would enter for waste collection at a pre-determined time. It is estimated

that about 60% of the slum population which is nearly 70% of the total population of

Joda shall be covered with tri-cycle as a part of primary collection system.

Page 30: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

16

Balance population would be covered by Tata Ace Tippers for primary collection. In

Slum area the common community bins provided for dry (blue color) and wet waste

(green color) disposal would be 120 litres capacity each.

Collection from Market place and Community Centres

In market place and community centres, a 2-bin collection facility would be

introduced. This shall be based on the size of the market or community Centres. A

3.5 cum bin each for (i) food waste of bio-degradable in nature comprising of fish

chicken and mutton waste, vegetable waste etc. and (ii) for various kinds of non-bio-

degradable and recyclable wastes shall be kept at strategic locations. The vegetarian

and non-vegetarian shops each would be provided with a 120 litres wheeled bins for

storage of wastes and transporting same daily to the centralized 3.5 cum bins located

within the market area. Apart from these, there would be a 2-bin waste of 100 (2x50)

litres located at every 100 metre distance along the lanes within the shopping

centres/shopping plaza. In Melas and festival grounds, two bins with 3.5 cum

capacity each for wet food waste and dry recyclable or inert wastes would be placed

for daily lifting by refuse compactor.

3.2.2 Secondary Collection

Secondary collection includes picking up waste from community bins, waste storage

depots or transfer stations and transporting it to waste processing sites or disposal

wastes. The primary and secondary collection system is essential to avoid

containers’ overflow and waste littering on streets. Separate 3.5 cum bins for dry and

wet waste types shall be provided at a centralized location(s) in each of the four

zones comprising of fourteen (14) Wards of the Joda Municipality. Wastes picked up

by the household collection team would be transported to these intermediate

Centres. The intermediate centre or waste transfer stations are aimed basically for

transfer of primary collected waste into vehicles for transport to the centralized

facility. Here Tata Ace-tippers and tricycles would feed the primary collected material

into separate 3.5 cum metal containers kept for secondary collection of wet bio-

degradable waste and other dry wastes. The metal bins with covers would have

lifting hooks for lifting to refuse compactor trucks and transport same to Central

processing Plant.

Page 31: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

17

The waste collected in designated dry and wet bins located in the market area and

market or shopping Centers or Office/Institutions and served by the waste collection

team within respective domain areas would be separately brought to the centralized

processing facility by refuse compactors. The secondary collection area of

dimensions about 10 m x 7 m would be a designated area with proper low height

guard wall and a raised platform at 1.5-2 m height with a proper ramp up and down

from the road for facilitating the Tata Ace-tippers and tricycles to ride over the

platform and unload the material directly into the bins placed on the ground with

minimal spillage and then get down from the opposite end. The refuse compactor

truck would stand near the bins and lift up same for waste feeding into the

compactors and transportation to the centralized processing facility. This would also

minimize manual handling of the waste to the extent possible.

3.2.3 Construction and Demolition Waste

For Construction and Demolition (C&D) waste in Joda, dedicated metal bins of 3.5

cum capacity with proper markings on them shall be placed at specific locations in

each Zone of the municipality. The C&D waste shall be lifted by hook loaders or

refuse compactors onto the trucks/dumpers and brought to a separate segregation

facility to be identified by the ULB. In this facility after recovery of valuables and re-

useable, the construction wastes shall be utilized for designated low lying land filling

and other construction back filling purpose.

3.2.4 E-Waste

Various electronic wastes belonging to these two categories generated within the

Joda ULB shall be stored separately at the generation place. Such waste can be

arranged to be collected from the sources by the Municipality as a part of special

waste stream or through dedicated e-recycling agencies. For such collection

dedicated bins of adequate capacity may be kept at each zone of the ULB.

Page 32: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

18

Fig 3-2: Zone Map for Joda

Page 33: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

19

3.3 Processing Plant for Municipal wastes

Processing of waste is necessary for recovery of recyclable materials and disposal to

dedicated Vendors so that balance processed waste is suitable for composting. Due

to non-availability of separate dedicated land, the processing Plant for Joda would be

located within the existing dumping yard. The centralized processing Plant would

receive segregated waste in wet and dry form. Only some part of waste in-spite of

best of efforts for at source segregation may be of mixed nature, which needs to be

segregated in a pre-sorting bay. The wet, dry and mixed wastes would be stored in

separate storage pits ready for onward conveyor loading and segregation.

Processing of waste is necessary for recovery of recyclable materials. The

centralized processing Plant would receive segregated waste in wet, dry and mixed

form. The dry waste processing would utilize manual labour or equipment that

separate material into various streams e.g. fiber, paper, plastic, containers etc. for

disposing same to designated pool of recyclers. The wet waste collected in the

segregated form from primary and secondary collection stations would be pre-

processed before sending for wind row composting. The processing facility would be

complete with pre-sorting material handling equipment, various size reduction

facilities for metal cans, plastic bottles etc. The processing facility would also

comprise of pollution control equipment and other equipments e.g. fixed storage bins,

truck scale, belt scale etc. The recoverable hazardous items would be disposed of to

recycling agencies or sent to secured landfilling after sorting out carefully from the

dry and wet waste segregation lines. All avenues would be explored to utilize the

non-biodegradable and non-recyclable carbonaceous waste for use in manufacturing

of RDF pellets or burning in any nearby cement kilns or smelting furnaces. The

ultimate rejects after processing would be stored in a separate place for placing it in a

secured landfill with proper liner systems.

3.3.1 Segregation of hazardous materials

The hazardous materials would contain toxic elements like lead, mercury, chromium,

arsenic, cadmium etc. These materials would be sorted out carefully from the dry

and wet waste segregation lines so that the recoverable items are disposed of to

recycling agencies to the extent possible and balance sent to secured landfilling.

Page 34: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

20

3.3.2 Landfilling

It is estimated that about 40-45% of the total waste generation would be rejects or

wastes in the real term, which if no other use could be found out need to be landfilled

in a proper manner. The secured waste landfill area shall be designed for an initial

period of 10-12 years of storage to be later expanded to 25 years based on land area

availability. The total landfill area would be divided in separate phases of say, 5-7

years life each so that soon after any particular area is filled up the subsequent

phases of land filling can be taken up.

3.4 Process Technology

The processing technology of municipal solid wastes, segregated at source on dry

and wet basis and brought separately to the central facility with an aim so as to utilise

the maximum value of the inherent waste characteristics given the available

processing technologies as discussed below.

3.4.1 Technology Alternatives for Waste Processing

Any technology selected must be in compliance to the basic principles of

sustainability i.e. it should be environmentally compatible, economically feasible and

socially acceptable. Keeping in line with these principles, the various technologies

available for processing, treatment of management of municipal waste are basically

of two natures e.g. (i) technologies based principally on utilization of the organic

value of waste viz. composting, bio-methanation and (ii) technologies which aims at

utilizing the calorific value of waste by extracting energy from waste viz. refuse

derived fuel (RDF) manufacturing, pyrolysis, mass incineration and other waste to

energy options.

Waste Processing Methods Important Waste Parameters Desirable Range

Thermal Processing Technologies

Moisture Content (%) <40%

Volatile Matter (%) >40%

Fixed Carbon (%) <15%

Inert (%) <35%

Net Calorific Value (Kcal/kg) >1700

Biological Processing Technologies

Moisture Content (%) >50

Organic Matter (%) >40

C/N Ratio 25-30

Page 35: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

21

3.4.2 Selection of Technology

Looking at the lifestyles of the people after carrying out primary survey in various

Wards, it has been found that major constituent of wastes generated from the

households would be of food wastes, vegetable wastes, fish, chicken and mutton

wastes with a rising proportion of plastics percentage in the higher income groups.

The plastics, paper, metal and other miscellaneous non-organic wastes would be of

26-32%, but all are not fit for recycling. Actual recyclables would not be more than

15% considering only 50% of the material generated in this category is fit for

recycling in other downstream industries. Therefore about another 15% waste would

find its way into the landfill along with the inerts.

The suitability of technologies which are based on some form of burning or

incineration for extracting energy is dependent on the nature of wastes and quantum

of waste generation. For mass incineration and waste to energy options, the MSW

should ideally have moisture content less than 40% and minimum calorific value of

1450 Kcal/kg and an annual average of 1700kcal/kg.

The nature of waste generated in Joda does not comply with the above criteria. The

compostable matter would be in the range of 37-45% and inert matter would be

ranging somewhere between 40-45%. C/N Ratio of the waste is in the range of 21-

31. The balance fraction would be mainly recyclables e.g. paper, plastics, metals,

leather etc. The calorific value of waste would be in the range of 1180-1350 Kcal/kg.

The physical nature of wastes and quantum of generation after field sampling report

suggests that the waste is not rich in calorific value so that it is suitable for waste to

energy option of processing. The waste to energy technologies based on mass

incineration, refuse derived fuel, plasma arc or pyrolysis are highly capital intensive

and would not be suitable for this much quantum of wastes with a lean calorific value

as generated at Joda, even if considered together. The feasible capacity for

consideration of these technologies would not be less than 500 TPD. The

predominance of food waste compounded by horticultural waste would drive the

choice of technology more towards biological processing i.e. composting, bio-

methanation etc. However, bio-methanation is more capital intensive and has its own

complexities of utilization of bio-gas and its distribution network, its demand in the

market and consistency in generation and supply. This probably indicates

composting as the preferred choice of technology for waste processing for Joda.

Page 36: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

22

3.4.3 Waste Management by Composting

Based on the draft guidelines of CPHEEO Manual (Draft), 2014, the composting of

municipal wastes can be broadly classified in five (5) categories namely, wind row

composting, aerated static pile composting, in-vessel composting, decentralized

composting and vermi-composting.

3.4.4 Windrow Composting

Windrow composting process consists of placing the pre-sorted feed stock in long

narrow piles called windrows that are turned on a regular basis by turning machines

or pay loaders for boosting passive aeration. The turning operation mixes the

composting materials and enhances passive aeration. Every 7th day a waste pile is

turned. This process is continued for five (5) weeks and high temperatures of 55-

650C within the windrow is maintained to sanitize the material. The Process Scheme

for Windrow Composting is as shown in Fig 3-3 on the next page. The size and

spacing of windrows depend on the equipment used for turning. The optimum

capacity for wind row composting is 500 TPD. However, in India there have been

several ventures where wind row composting of much smaller capacities in the range

of 10-30 TPD have been implemented. Following wind row composting the material

need to be segregated through a series of sieves and the coarser material which is fit

for compost has to be further cured for about two (2) weeks, when low level of

microbial activity would continue. The completely cured material does not emit any

smell and is ready for bagging as product compost. A major disadvantage of wind

row composting is that the system does not operate efficiently during the monsoon

season. During this time the waste is turned more frequently at an interval of 3-4

days. In the last week during monsoon the waste is kept under a monsoon shed with

provisions for mechanical aeration. In general each wind row material is ready for

curing on the 36th day. On this day, the compost is successively screened through

two stage screening stage of 35 mm and 16 mm screens. Screened material coming

out of coarse segregation by curing of same for another 2 weeks when adequate

oxygen supply and 25-30% moisture content would be maintained. The completely

cured well composted material would not release any foul odor and is ready for final

screening below 4 mm in size and packaging of finished product for marketing.

Page 37: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

23

Fig 3-3-: Process Scheme for Windrow Composting

Page 38: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

24

Table 3-1: Regulatory Guidelines of Compost Quality

Parameters Organic Compost Phosphate Rich

Organic Manure MSW Rules, 2000 FCO Rules, 2009

Arsenic (mg/kg) 10 10 10

Cadmium (mg/kg) 5 5 5

Chromium (mg/kg) 50 50 50

Copper (mg/kg) 300 300 300

Lead (mg/kg) 100 100 100

Mercury (mg/kg) 0.15 0.15 0.15

Nickel (mg/kg) 50 50 50

Zinc (mg/kg) 1000 1000 1000

C/N Ratio 20-40 < 20 < 20:1

pH 5.5-8.5 6.5-7.5 Max 6.7

Moisture % by weight (max)

15-25 25

Bulk density (gm/cm3)

<1 <1.6

TOC 12 7.9

T Nitrogen 0.8 0.4

T Phosphate 0.4 10.4

Total Potassium 0.4 -

Color Dark brown to black -

Odor Absence of foul odor -

Particle size Min. 90% should pass through 4 mm IS seive

Min. 90% should pass through 4 mm IS seive

Conductivity 4.0 8.2

The sum total of phosphorus, nitrogen and potassium nutrients shall not be less than

1.5%.

3.4.5 Aerated Static Pile Composting

Aerated static pile composting is a technology that requires the composting mixture

of pre-processed material to be placed in piles that are mechanically aerated. The

piles are placed over a network of pipes connected to a blower, which supplies the

Page 39: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

25

air for composting. Unlike aerobic windrow composting, the aerated static pile has

direct control over aeration. This is the strength of this system, which can be used to

reduce the fermentation time and also save fuel used by the turning equipment.

Producing compost using this technology usually takes 6 to 12 weeks depending on

preprocessing of feedstock, air movement and temperature control. A controlled air

supply enables construction of large piles, which decreases the need for land.

3.4.6 In-Vessel Composting

In-vessel composting systems enclose the feedstock in a chamber or vessel that

provides adequate mixing, aeration, and moisture. There are several types of in-

vessel systems available - drums, silos, digester bins and tunnels. These vessels can

be single- or multi-compartment units. In some cases the vessel rotates, in others the

vessel is stationary and a mixing or agitating mechanism moves the material around.

Most in-vessel systems are continuous-feed systems, although some operate in a

batch mode. All in-vessel systems require further curing after the material has been

discharged from the vessel. The detention time in the vessel varies from 1 to 2

weeks. A 3 week curing period after the active composting period is required.

3.4.7 Decentralized Composting

Decentralized composting is the composting of source separated organic waste in

limited quantities from households, apartments, neighborhoods, markets, gardens or

from the entire ward. The decentralized composting approach reduces transportation

costs, makes use of low-cost technologies based mainly on manual labour.

Decentralized composting facilities generally handle from very small waste quantities

up to 20 tons per day depending on the size of the community and volume of

compostable waste materials in the waste stream.

3.4.8 Vermi Composting

Vermi-compost is the castings of earthworms. Vermi-composting is the process of

composting the biodegradable fraction of municipal solid waste with the help of

earthworms, resulting in the production of vermi-compost which can be used in

agricultural fields as a soil conditioner and nutrient supply. Vermi-composting is

typically suited for managing smaller waste quantities. It is an ideal technology for

towns which generate up to 50 tonnes of mixed municipal solid waste per day. The

worm species that are commonly considered are Pheretimasp, Eiseniasp & Perionyx

sp. These worms are known to survive in the moisture range of 20-80% and the

temperature range of 20-40°C.

Page 40: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

26

3.4.9 Optimization of Windrow Composting Processing Facility

Considering all the above technologies for composting, it appears that the suitable

technology of choice for composting of processed waste in Joda would be windrow

composting due to lower capital investment and operational costs as compared to

other composting technologies combined with large scale success of this technology

across India.

Distinct Advantage:

Wind row composting systems although involve larger area for building up the waste

piles for 4-5 weeks followed by maturation period of about 2 weeks, but is less

mechanically intensive and robust in approach and reliability. No special processing

equipment or rotating parts is involved. This technology can be conveniently scaled-

up as the waste generation builds up. The land required would be higher but capital

investment and operational costs in terms of energy would be moderate and lower

than other composting options especially in-vessel mechanical composting.

Disadvantages:

The windrow composting system is dependent on temperature of 55-600C and

sensitive to low and high moisture conditions (moisture content is maintained 55-

65%), hence a strict maintenance of conditions would be necessary. Land required

would be higher compared to most of other composting technologies. The process

would be slower in the winter season and little difficult to operate in the rainy season.

Odor would be an issue if turning is inadequate.

3.4.10 Broad Specification for the Sanitary Landfilling Facility

The broad specification of sanitary landfill for scientific dumping of rejects and non-

recyclable materials are provided in the following sections.

3.4.10.1 Liner System

The liner system would essentially comprise of HDPE geo-membrane and geo textile

layers to be laid over compacted clay layer of 900 mm thickness. The clay layer

would be of bentonite clay to be laid over native compacted soil to 95% procter

density. The base area would have sufficient slope to guarantee draining of leachate

and storm water. The composition of the base sealing system has to be in

compliance with the MSW Rules 2000. The permeability of the base layer would be

Page 41: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

27

less than 1 x 10-7 cm/s. In case adequate bentonite clay is not found in the nearby

areas, then geo-synthetic clay liner (GCL), which is bentonite sandwiched between

two layers of geo-textiles would be used as a base layer. The GCL may be further

reinforced with an additional layer of HDPE liner. Above the clay liner or GCL liner a

HDPE geo-membrane liner with standardized thickness of 2 mm and conforming to

ASTM standards would be laid. Above this a protection layer of geo-textile liner with

2000 gm/m2 weight would be laid. Above these layers a drainage layer of 300 mm

thick with filter gravel and ensuring a permeability of greater than 10-2 cm/sec would

be laid. The drainage layer would comprise of 25-50 mm round shaped gravel and

pipes of 200-250 mm diameter with sloping towards the leachate collection sump. A

non-woven geo-textile layer would be laid above the drainage layer as a protection to

the drainage layer and this also helps in maintaining high filtering capacity of the

underlying drainage layer. A typical Sectional Profile of Liner Systems and Leachate

Collection of Sanitary Landfill is shown in Fig 3-4 below.

Fig 3-4: Typical Sectional Profile of Liner Systems & Leachate Collection of Sanitary Landfill

Page 42: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

28

3.4.10.2 Leachate Collection

The basic objective of the leachate collection system is that all the leachate would be

collected and removed from the landfill area into the leachate collection pit through

the underlying drainage layer. The leachate collection system would be designed so

that it can take care of water generated from a storm resulting in maximum rainfall in

24 hours continuously for 72 hours based on a 50 years historical storm data. It is

estimated that total leachate generation from the proposed waste processing and

landfilling facility would be in the range of 4.0-4.5 cum/hr.

3.4.10.3 Leachate pond

This would be essentially a 2-chamber pond with liner system in the bottom and side

walls to hold the leachate without percolating into the soil underneath for treatment of

same.

3.4.10.4 Leachate Treatment

The leachate collected need to assessed with chemical characterization or TCLP test

of leachate. Based on the chemical characteristics of leachate, treatment process

may include biological processes such as activated sludge, aeration,

nitrification/denitirification, chemical processes such as oxidation, neutralization and

other physical processes such as activated carbon adsorption, ultra-filtration etc. One

alternative of treatment would be evaporation of leachate water in shallow ponds for

which large area would be required. The residual salts may be disposed of to the

secured landfill. This alternative would be further explored during the DPR stage and

engineering of the landfill system.

3.4.11 Infrastructure of Processing and Land filling

The processing and land filling facility at Joda would be complete with the following

infrastructure:

i) Peripheral access roads within the site with single lane of 3.5 m width.

Approach road to the landfill site up to the processing Plant would be of

7.0 m width.

ii) Security Office

iii) Weigh bridge & control building

iv) Water Supply facilities

v) Power and lighting system

Page 43: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

29

vi) Communication systemSewage system

vii) Fire-fighting system

viii) Tyre cleaning system

ix) Garage and Workshop

x) Administration Office and Laboratory

xi) 4 m high compound wall all along the property line with barbed wire

Fencing.

3.4.12 Option for Additional Technology Intervention

The available landfill area can accommodate additional space for waste storage, if

the rejects fraction of the recyclable wastes in the tune of about 15% is subjected to

RDF technology for manufacture of RDF pellets. This RDF product pellets can then

be sold out as supplementary fuel in cement kilns, bio-mass based power Plant

boilers, bituminous road construction etc.

3.4.13 Reclamation of Existing Dump yard

The existing dump material in Joda site are scattered indiscriminately. As soon as the

layout for the proposed processing and landfilling for each ULB shall be finalized, an

area shall be demarcated to store the waste already dumped and strewn around the

site. It is estimated that about 3000-4000 TPD of waste has been dumped so far in

last 10 years in the dumpsite. This waste due to degradation over this long period

has been reduced in volume and weight. Considering 60% loss in overall weight of

the dumped wastes, it is estimated that about 2500 tons of degraded waste is lying at

each of the respective sites. The ULB has to take initiatives to remove the already

dumped mixed waste and store at a designated area within the facility. This is

required for undertaking the design & engineering and construction activities of the

proposed processing Plant and landfill facility.

Page 44: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

30

This can be preferably done within the area designated for second phase of land

filling. The soil over which this waste has been dumped so long is also prone to

contamination and this soil need to be excavated out from various depths and

analysed at laboratory for presence of hazardous toxic elements e.g. mercury, lead,

chromium, cadmium etc. Based on the contamination levels a proper soil

management plan need to be drawn up. The waste generated within the ULB during

the construction period of one year or so shall be also stored in the same designated

area. After the processing Plant and landfill facility is made ready and commissioned,

the dumped mixed wastes which could be utilized for recovery of recyclables and

other hazardous materials. The hazardous material of biological nature e.g. syringes

etc. could be disposed of through incinerators located in hospitals for management of

bio-medical wastes. Other wastes which are hazardous in nature but does not have

suitable disposal option would be considered for sending to a centralized RDF facility

within the state or the last preferred option of disposal in a designated area of the

proposed secured landfill in the ULB with adequate additional protection and properly

covered with soil. The organic matter of the balance waste would have been already

degraded significantly under open atmospheric conditions and with exposure to

precipitation and heat of sun. Therefore same can sieved in 16 mm trommels and

mixed with soil for use as manure in the landscaping and greenbelt within the

complex of processing and landfilling facility.

3.4.14 Alternatives for Management of Medical Waste

No bio-medical waste generated in hospitals, primary health centres or medicine

shops shall be accepted in the processing and landfilling facility. Medical wastes

generated in the Joda Municipality is in the tune of 20 tons per month. The

generation of higher bio-medical wastes in Joda is mainly due to presence of Tata

Steel Hospital, where a large number of patients from its employees’ family and

distant areas also turn up for treatment. All these wastes need to be managed

exclusively in dedicated centres of bio-medical waste management facilities

comprising of incinerators. In Joda, the TSL hospital is having facility for bio-medical

waste management. Joda ULB needs to take up this issue with TSL management, so

that this facility is extended to include the management of bio-medical waste

generation from all other health centres within Joda.

Page 45: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

31

Fig 3-5: A Comparison of Waste Management System in Existing and Proposed Scenario

Page 46: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

32

3.5 Resources

The manpower resource for overall supervision of the proposed integrated solid

waste management system at municipal level has been outlined below. The principal

objective of these staff would be to ensure smooth functioning of the activities

involved in waste collection, transportation, processing and landfilling operations of

designated Contractor Agencies or BOO-BOOT operators as applicable on a day to

day basis.

3.5.1 Manpower

For planning an efficient and advanced MSWM system, it is essential to have an

efficient institutional structure besides having adequate infrastructure and equipment.

An effective institutional set-up capable of designing, implementing and monitoring

the MSWM system needs to be established within the local authority. It is therefore

necessary for the urban local body in Joda to have a SWM cell or SWM department

having staff with technical and managerial skills. Solid waste management needs to

be handled by environmental engineers or public health engineers with the support of

mechanical/automobile engineers to handle the workshop facilities. Qualified

engineers would, therefore, be inducted for Joda. The manpower required would be

one (1) sanitation diploma holder as Sanitary officer (S.O.), one (1) Sanitary

Inspector (S.I.), two (2) Sanitary Sub-Inspector (S.S.I) and four (4) Sanitary

Supervisor (S.S.).

3.5.2 Equipments for handling Waste, Transportation Vehicles, Infrastructure

Development

The physical infrastructure components in the primary and secondary collection and

transportation services include the procurement of the following

tools/equipments/vehicles:

- Tricycles

- Household Bins

- Community Bins

- Tata Ace tippers

- Garbage compactors for transportation of MSW from various wards

Page 47: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

33

With the increase in population the waste generation would also increase which would

in turn require larger number infrastructure components for collection and transport of

the waste.

For the primary collection of solid waste, number of tricycles required are 24 and

number of Tata Ace Tippers with containers required are 6.

The number of garbage compactors required for secondary collection are 2.

3.5.2.1 Construction material

The estimated construction materials required are:

Major Items Unit Estimated Quantity

Required

Piling (600mm dia) nos 30

RCC cum 2000

Structural Steelwork ton 70

Sheeting sqm 800

These are to be sourced locally.

3.5.2.2 Power

Power : 100 KVA

Fuel: HSD for DG Set power back-up for Admin Bldg.

3.5.2.3 Source of water for utilities, domestic

There is no major use of water except during construction period of abt. 50 KLD is

envisaged. During operation phase, about 20-30 KLD water would be required for

composting process, drinking, sanitary and miscellaneous purpose.

During construction period tanker water would be sourced from authorized vendors. During

operation phase, water would be sourced from nearby Borewell owned by municipality and

PHED supply.

Page 48: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

34

CHAPTER 4 - SITE SELECTION

This chapter gives an outline of the site selection for the proposed expansion project.

4.1 Land details

There is a land at Joda which has an area of about 6 acres and is presently being used

for open dumping of mixed municipal solid wastes generated within Joda ULB. The

Joda municipality is in possession of Consent to operate from OSPCB as dumping

ground for MSW. The Joda Municipality is also in possession of the authorization to set

up a waste processing and disposal facility vide OSPCB letter dated 5th December

2013 with a validity of the authorization up to 31st March 2018.

4.2 Major techno-economic feasibility considerations

The major considerations for selection site for Joda ULB for waste processing and

landfilling have been discussed below.

4.2.1 Joda Site for Dedicated Processing and Landfilling Facility

In Joda, it may be found that the estimated waste generation in 2015-16 would be in the

tune of 14 TPD. With a timeline of 15 years duration, the total generation of waste in

Joda would be 20 TPD in the year 2030 and 26 TPD in the year 2040. It may be

observed that with an estimated 37-39% compostable waste, 12-14% recyclables and

about 45% inert or non-recyclable material, the waste generation for land filling in 2030

would be about 9 TPD. Topographic survey and Geo technical survey has been carried

out for the acquired site of Joda Municipality. From survey it may be observed that the

land available at Joda is not of regular shape and it would be difficult to set up the Plant

facility ensuring best utilization of land. The landfill area requirement for 15 years would

be about 3.25 acres based on an average 7.7 TPD rejects generation during this

period. Including the processing Plant and other facilities an estimated 6.55 acres land

would be required. The land available in Joda as evident from the survey carried out at

site is 5.53 acres which would be sufficient to build up an integrated processing facility

with all auxiliaries and a secured waste landfilling for 10-12 years only. For another 5

years of waste storage an additional 1 acre of land would be required. But there is

limited scope of expansion of the present land in any direction due to several natural or

man-made constraints. Hence another site with provisions of additional waste storage

for landfilling has to be found out for use after 10 years.

Page 49: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

35

4.3 Option for Centralized Processing and Landfilling for Joda-Barbil Cluster

Considering Joda and Barbil as cluster towns, combined waste generation in the two

ULBs in the base year (2016) would be in the tune of 34 TPD. In the following 15 years,

this waste generation would go up to as high as up to 51 TPD progressively. In 2040

the total estimated waste generation from Joda and Barbil would be in the tune of 70

TPD. Joda and Barbil is separated by road distance of 15 km and it would be more

convenient if a suitable land for siting a centralized waste processing and sanitary

landfilling facility catering to both the ULBs could be found out. The various factors of

setting up a common waste processing and landfilling facility is explored in the following

sections.

4.3.1 Land Area Required

The land area required for setting up such a centralized facility would be about 15 acres

of which about 10 acres would have been used for landfilling of inert wastes or rejects.

Presently, no such vacant land free for use of setting up such a centralized processing

and landfilling facility is available.

4.3.2 Traffic Problems

The Joda-Barbil region being mineralized zone containing iron ore, there is heavy traffic

on this road. Due to economic downturn the mineral based industries is not performing

well at this point of time. But these mineral based industries especially the mining

industry, which is the driving force of all economic activities in this region, in the future

would again witness an upsurge in business activity as the Nation’s economy recovers

from a slump. This would lead to a significant spurt in traffic load on this busy road once

more and may affect adversely the daily waste transportation from the two (2) ULBs to

this centralized facility located somewhere in between or within any one of the two

towns.

4.3.3 Public Resistance

During operational phase, there could be public objection within the Municipality or

outside where the common facility is set up about accepting this nuisance stating

reasons that ‘this waste is generated somewhere else and why should we accept’. This

is called ‘NIMBY’ or Not in My Backyard syndrome. Therefore long-term sustainable

operation would be difficult.

Page 50: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

36

4.3.4 Ownership Issues

Ownership of the Common Facility would also be a concern area even if the facility is

operated by a Private Party. For any problem during the operational phase, the

respective ULBs can always say, that it is not their ‘baby’ and the responsibility lies with

the Municipality where the Facility is located, which may or may not be willing to take

the responsibility on a long-term basis.

Discussions held with the respective ULB officials have also revealed reluctance on

their part citing reasons of operational constraints apart from availability of suitable land.

Under the above circumstances, it would be a better approach if dedicated waste

processing Facility is set up at Joda and Barbil separately to manage their own wastes

at least for the first 10-15 years.

4.4 Boundary Wall with Greenbelt and Landscaping

The processing and sanitary landfill facility at Joda would have a secured compound

wall of 4 metres height with 2 meter barbed wire fencing on top of the wall along the

boundary with peripheral greenbelt of about 3-5 metres width just inside the compound

wall. The nature of the trees to be planted shall be of local species and non-edible type.

The trees should not have roots penetrating more than 30 cms and trees would have

wide leaves. The basic purpose of plantation is to obscure the facility from the

surroundings. The coverage of greenbelt has been estimated to be about 15% of the

total area.

4.5 Suitability of Landfill Site

The set guidelines for assessing the suitability of landfill site are outlined below:

a. Lake or Pond: No landfill should be constructed within 200 m of any lake or pond.

Because of concerns regarding runoff of waste water contact, a surface water

monitoring program should be established if a landfill is sited less than 200m from a

lake or pond.

b. River: No landfill should be constructed within 100 m of a navigable river or stream.

The distance may be reduced in some instances for non-meandering rivers but a

minimum of 30 m should be maintained in all cases.

c. Flood Plain: No landfill should be constructed within a 100 year flood plain. A

landfill may be built within the flood plains of secondary streams if an embankment

is built along the stream side to avoid flooding of the area. However, landfills must

Page 51: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

37

not be built within the flood plains of major rivers unless properly designed

protection embankments are constructed around the landfills.

d. Railway lines – No landfill facility shall be constructed within 300 metres of

centerline of the facility.

e. Highway: No landfill should be constructed within 200 m of the right of way of any

state or national highway. This restriction is mainly for aesthetic reasons. A landfill

may be built within the restricted distance, but no closer than 50 m, if trees and

berms are used to screen the landfill site.

f. Habitation: A landfill site should be at least 500 m from a notified habitated area. A

zone of 500 m around a landfill boundary should be declared a No-Development

Buffer Zone after the landfill location is finalised.

g. Public parks: No landfill should be constructed within 300 m of a public park. A

landfill may be constructed within the restricted distance if some kind of screening is

used with a high fence around the landfill and a secured gate.

h. Critical Habitat Area: No landfill should be constructed within critical habitat areas.

A critical habitat area is defined as the area in which one or more endangered

species live. It is sometimes difficult to define a critical habitat area. If there is any

doubt then the regulatory agency should be contacted.

i. Wetlands: No landfill should be constructed within wetlands. It is often difficult to

define a wetland area. Maps may be available for some wetlands, but in many

cases such maps are absent or are incorrect. If there is any doubt, then the

regulatory agency should be contacted.

j. Ground Water Table: A landfill should not be constructed in areas where water

table is less than 2m below ground surface. Special design measures have to be

adopted, if this cannot be adhered to.

k. Airports: No landfill should be constructed within the limits prescribed by regulatory

agencies (MOEF/ CPCB/ Aviation Authorities) from time to time. Minimum distance

of landfill facility from any Airport shall be 20 km away. However, for airstrips of

occasional use no such stipulation is provided.

l. Water Supply Well: No landfill should be constructed within 500 m of any water

supply well. It is strongly suggested that this locational restriction be abided by at

least for down gradient wells. Permission from the regulatory agency may be

needed if a landfill is to be sited within the restricted area.

m. Coastal Regulation Zone: A landfill should not be sited in a coastal regulation

zone.

Page 52: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

38

n. Unstable Zone : A landfill should not be located in potentially unstable zones such

as landslide prone areas, fault zone etc.

o. Buffer Zone : A landfill should have a buffer zone around it, up to a distance

prescribed by regulatory agencies.

Keeping in line with the above referred guidelines, the existing dumping site at Joda of

about 6 acres more or less comply to the applicable siting criteria, the most critical of

them being nearness to any human settlements. Nearest civilian airport at Ranchi or

Bhubaneswar for regular flight operations is more than 240 km away.

4.6 Suitability of Joda Landfill Site

The nearest settlement of existing Joda dump site is Bacchu Hutting in the south

direction and is beyond 500 m. The Sona river is flowing in the west at a distance of

about 50 metres. There is no critical or endangered habitat of any flora or fauna near

the Joda site. Railway line in SE railway from Barbil to Banspani is however, adjacent to

the landfill site in the eastern direction. Bhadrasahi airstrip, which is used for occasional

small business flight operations is at a distance of 7 km NW from this site. Ground

water table is varying from 3.2-5.5 m below ground level.

4.7 Social Aspects

The proposed project would be developed on the existing waste disposal site. Hence,

no change in the landuse of the site due to the proposed project would be anticipated.

However, during field survey it has been reported in nearby settlements of dumping site

that water is getting contaminated and water borne diseases are prevalent diseases.

This is due to untreated and uncollected solid waste. These also obstruct storm water

runoff, resulting in the forming of stagnant water bodies that become the breeding

ground of disease. From the proposed project the degraded environment would be

improved by establishing a scientific Integrated Municipal Solid Waste Management

Facility.

The project would provide employment opportunities to the local people. About 15- 20

people would get opportunities to earn their livelihood through this project due to setting

up of the proposed project facility. Apart from this there would be employment

generation of additional 120-130 people for primary and secondary waste collection and

transportation to the centralized facility. Due to proposed project the physical

infrastructure facilities would improve and social infrastructure facilities would come up

in nearby areas. It also would promote sustainable agriculture by producing compost.

Page 53: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

39

Safe working practices also would be followed by Rag Pickers and NGOs or SHGs

would be found to be actively involved with this issue. For improving the solid waste

management services it is essential to adopt modern methods of waste management

having a proper selection of technology which can work in the area successfully.

Simultaneously, measures would be taken for institutional strengthening and internal

capacity building.

Effective provision of MSW management services would require coordinated efforts by

various stakeholders. The main stakeholders comprise ULBs, citizens, private operators

and NGOs. The roles of each stakeholder are presented in the matrix below.

Stakeholder Role

Citizens

- Carry out segregation of waste at household level - Handover the segregated waste to the primary collection crew at

the pre-notified time - Pay user fee for the door-to-door collection service offered - Discontinue throwing waste into the streets

Regulating Authorities

- Inform the residents about the proposed MSW Management Plan - Ensure that the residents co-operate and follow all the principles - Appoint primary collection crew for door-to-door collection service - Monitor performance of service providers, wherever required

Private Operator

- Carry out their roles and responsibilities as per the contractual arrangement

- Ensure that the MSW is handled in the manner set out in the contractual arrangement and is not disposed in any other manner whatsoever.

- Obtain compliance certificate from the authorities concerned

Municipality

- Set out MSW Management Plan - Monitor the works being performed by the private operator - Ensure compliance by citizens - Make payments to the private operator

NGOs

- Print pamphlets/hand-slips announcing the project scheme - Conduct awareness campaigns in the community ward-wise in

each ULB of the proposed SWM system and benefits thereof - Conduct safety awareness with respect to safe handling and work

practices of MSW management amongst rag-pickers and waste collection workers.

Page 54: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

40

CHAPTER 5 - ENVIRONMENTAL MITIGATION MEASURES

In consideration to the prevailing site features and the proposed Integrated Municipal Solid

Waste Management Facilities, outlined in earlier Chapters, it is necessary to ensure that

the proposed plant and facilities would be adequately designed with necessary

environment protection measures. This Chapter accordingly outlines the environment

protection measures for the proposed Integrated Municipal Solid Waste management at

Joda site comprising of Compost Plant and Sanitary Landfill. During project implementation

period special emphasis would be made on measures to minimize leachate or effluent

generation and dust control at source. The sources and types of pollution with broad level

mitigation measures has been outlined in the following sections.

5.1. Air pollution control measures

Air environment including Ambient Air Quality and odour generation due to the proposed

project during construction and operational phases would be accounted. The principal

sources of air pollution are construction activities, truck movement with construction

materials and municipal solid waste, loading and unloading of materials, vehicular exhaust.

The impact is generally confined to the project area and is expected to be negligible

outside the project site boundaries. The pollutants their sources and mitigation measures to

be adopted are presented in Table 5-1 on page 50.

5.2. Water pollution control measures

The water demand for the project which would be in the range of 20-30 KLD. No surface

water would be tapped. The source of water would be the adjacent existing borewell owned

by the Municipality, alternatively from the nearby PHED supply in the case of Joda.

The main wastewater generation sources during construction phases would be equipment

washed water and other surface run-off with suspended solids loading and sewage from

temporary sanitary facilities with BOD loading.

Page 55: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

41

During construction activity the surface run-off would be diverted to working pit to arrest the

suspended solids if any and the settled water would be reused for construction purposes,

and for sprinkling on roads to control the dust emission, etc.

During operation phase, the wastewater would be from drinking and sanitary use, leachate

from compost plant and secured land fill area. The domestic wastewater would be treated

in septic tank followed by soak pit. Maximum leachate generation from the operating cell of

landfill pit and other areas including compost pads would be in the range of 4 – 4.5 cum/hr.

Leachate generated at various places in the plant would be collected in a pond and

properly treated in an ETP. The treated leachate would be sprayed on windrow to maintain

suitable temperature and moisture. Leachate generated during precipitation period would

be stored in evaporation pond.

Based on the rainfall intensity of the plant area, seperate storm water drainage system

would be properly designed. Storm water would be collected in a centralized pit to arrest

the silt particulates and clear water would be used locally for landscaping and fountains.

Surplus water would be released into public drains or adjacent nala. The pollutants their

sources and mitigation measures to be adopted are presented in Table 5-1 on page 50.

5.3. Solid waste disposal

During the construction phase, the solid waste would be different types of raw materials

such as coarse aggregate, fines aggregate, bricks, steel etc being used during construction

stage. The solid waste generated during this period would be predominantly inert in

nature.

During operation phase no solid waste would be generated as such except ETP sludge or

particulates settled in evaporation ponds of nominal quantity. Appropriate management of

solid rejects from different processing activity would be undertaken. Sanitary landfilling

would be adopted for rejects generated from processing, ETP sludge and evaporation

pond settled particulates. The total generation of solid waste would be in the range of 8-10

TPD. The pollutants their sources and mitigation measures to be adopted are presented in

Table 5-1 on page 50.

Page 56: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

42

Table 5-1: Environmental Mitigation Measures

Sl. No.

Pollution Sources Pollutants Emitted Mitigation Measures

Air Pollution Mitigation Measures

1. Construction activities

SO2, NOX, Particulates, Odour etc.

- Dust suppression by water sprinkling.

- Bitumen covered internal roads.

- Wheel Washing Bay at the entry

point.

- Vehicles carrying of construction

materials and waste to be covered

with tarpaulin / plastic sheet.

- Proper ventilation and moisture in

the compost plant and windrow area

to be maintained and herbal

insecticides to be sprayed around

odour generation areas at regular

intervals.

- Secured landfill except the current

waste handling area rest to be

covered by polyethylene sheets

- Green belt would be provided along

the internal roads and plant

boundary

2. Vehicular Movement

3. Loading and unloading

of Trucks

4. DG Set

5. Processing of waste

Water Pollution Mitigation Measures

6 Domestic Waste

Suspended Solids, BOD etc

- Septic Tank/Soak Pit.

- ETP for recycling.

- Impermeable liner in the landfill pit.

- Storm water drainage system for

recycling

7 Leachate from Windrow Compost Plant

8 Leachate from landfill

Solid Waste Management

9. Construction

Construction materials e.g. coarse aggregate, fines aggregate, bricks, steel etc

- Recycled or used for filing/ levelling of low-lying areas within the site or transported outside.

10.

ETP sludge or evaporation pond

ETP sludge or

evaporation pond

settled particulates

- Sanitary Landfilling

Page 57: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

43

5.4. Noise

Noise pollution would be resulted from transportation and during construction phase. To

reduce noise pollution, high-grade machinery would be used. There would not be any

major noise-causing activity during operational phase. DG set operation would have

proper in-built noise control measures.

5.5. Ecology of the Area

Site clearing or operational activities would not impact the ecology of the area adversely,

since there are no known rare, endangered or ecologically significant animal and plant

species in the area. There is no wildlife sanctuary located within 10km radius of the

project site. In fact the scientific processing and landfilling would have a beneficial impact

on the surrounding terrestrial and aquatic ecology.

5.6. Green belt development

In order to arrest wind borne fugitive dusts around the plant boundary with about 3-5 m

wide green coverage based on locally available plant species. An area of 10-12% would

be earmarked for development of greenbelt/greenery along the boundary, roads, and in

open places available. The green belt developed would help to capture the fugitive

emissions, attenuate the noise generation and improve the aesthetics. All open spaces,

where tree plantation may not be possible, would be covered with shrubs and grass to

prevent erosion of topsoil. Apart from green belt all around the site, also on the top of

capped landfills greenery would be developed.

5.7. Land use

The proposed project would be developed on the existing waste disposal site. Hence, no

change in the landuse of the site due to the proposed project would be anticipated. With

the site development for the proposed plant, green belt would be developed and other

aesthetic changes would be made at the plant site, thereby creating overall positive

impact on the aesthetics of the site.

Joda Municipality has obtained authorization from OSPCB for setting up waste

processing and landfilling facility in the respective lands.

Page 58: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

44

5.8. Design Environmental Targets

The proposed project shall abide by the following design environmental norms and

prevailing environmental quality.

Ambient Air Quality

Sulphur dioxide : 80 μg/m3 (24 hours)

Particulate Matter : 100 μg/m3 (24 hours)

Noise Level

Residential Area : Within 55 dBA at the boundary from the noise source

Ambient (Outside the plant) same as of pre-project level

Water Quality

The disposal of treated leachate shall follow the following standards, namely: -

S.No Parameters Standards (mode of

disposal) Inland Surface water

i pH 5.5-9

ii Suspended Solids mg/l (max) 100

iii Dissolved solids (inorganic) mg/l, max. 2100

iv Biochemical oxygen demand mg/l Max. 30

v Chemical oxygen demand, mg/l Max. 250

vi Ammonical nitrogen (as N), mg/l, max. 50

vii Total Kjeldahl nitrogen (as N),mg/l, max. 100

viii Arsenic (as As), mg/l, max 0.2

ix Mercury (as Hg), mg/l, max 0.01

x Lead (as Pb), mg/l, max 0.1

xi Cadmium (as Cd), mg/l, max 2

xii Total Chromium (as Cr), mg/l, max. 2

xiii Hexavalent chromium (as Cr+6), mg/l, Max. 0.1

xiv Copper (as Cu), mg/l, max. 3

xv Zinc (as Zn), mg/l, max. 5

Page 59: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

45

S.No Parameters Standards (mode of

disposal) Inland Surface water

xvi Nickel (as Ni), mg/l, max 3

xvii Cyanide (as CN), mg/l, max. 0.2

xviii Chloride (as Cl), mg/l, max. 1000

xix Fluoride (as F), mg/l, max 2

xx Phenolic compounds (as C6H5OH) mg/l, max. 1

xxi Dissolved phosphates (as P), mg/l Max. 5

xxii Nitrate Nitrogen mg/l 10

xxiii Iron (as Fe) mg/l 3

5.9. Environmental Monitoring

Monitoring for air quality parameters as per NAAQS 2009 and surface water quality

would be carried out on a six monthly basis. The ground water quality monitoring in 5

permanent monitoring wells within an area of 50m from periphery would be carried out

quarterly once. Programs would be conducted on a regular basis for monitoring safety

and health protection of workers with specific reference to improving rag pickers quality

of life, health concerns, etc.

Page 60: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

46

CHAPTER 6- REHABILITATION AND RESETTLEMENT (R&R) PLAN

This Chapter presents the R&R Plan for Joda ULB.

6.1 Joda Site

Proposed project site in Joda is located in ward No. 6 near Bachuhutting. The land area

is around 5.53 acres. This land is under the possession of Joda Municipality and is

already being used for open dumping of mixed municipal solid wastes generated within

Joda ULB. There are no settlements within the acquired site. All R&R issues have been

already settled by Joda Municipality.

The Joda municipality is in possession of Authorization Order from OSPCB to use the

land as dumping ground for MSW. The Joda Municipality is also in possession of the

authorization to set up a waste processing and disposal facility vide OSPCB letter dated

5th December 2013 with a validity of the authorization up to 31st March 2018.

Page 61: PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID …€¦ · PRE-FEASIBILITY REPORT FOR MUNICIPAL SOLID WASTE MANAGEMENT FOR JODA ... (ULBs) into ten ... dry and mixed form

47

CHAPTER 7- PROJECT SCHEDULE & COST ESTIMATES

This Chapter presents the project implementation schedule and cost estimates for

Joda ULB.

7.1 Project Implementation Schedule

The whole project is estimated to be completed in about 12 months following approval of

DPR and 6.5 months from obtaining environmental clearance whichever is later. It is

envisaged that the proposed facility would be operational from January 2018.

7.2 Project Cost

The estimated CAPEX for the centralized composting and landfilling plant facility would be

about Rs 6.74 Crores for the year 2015- 2016, although this will be operational from 2018.

The capital investment of primary and secondary waste collection and transportation from

the whole of Joda municipality limits is not included in same. Land filling costs have been

estimated for about first 10 years only. The cost for environmental monitoring would be

around 8 lakhs per annum. The proposed project is entirely a capital investment for

environmental improvement of the status of municipal waste management of Joda town.

However, the additional estimated cost of EMP for addressing environmental concerns

arising due to setting up of this project would be in the tune of 60 lakhs comprising of ETP

for leachate treatment and permanent groundwater monitoring wells.

The estimated cost is inclusive of the following:

- Composting plant & secured land filling facilities

- Greenbelt

- Boundary wall

- Other civil works and

- Miscellaneous Expenses.