28
Proposed installation of Unit II – 60 KLPD Molasses based Ethanol Plant alongwith 2 MW Co-generation Power Plant in Existing Distillery Plant At Village Bhadson, Umri Road, Tehsil Indri, District Karnal (Haryana) Pre - feasibility Report M/s. Piccadily Agro Industries Limited 1 PRE - FEASIBILITY REPORT 1.0 EXECUTIVE SUMMARY (I) INTRODUCTION In line with the ambitious programme of Govt. of India like “MAKE IN INDIA” and to become self-dependent on fuel within the country, M/s. Piccadily Agro Industries Limited has planned for proposing installation of Unit II – 60 KLPD Molasses based Ethanol Plant along with 2 MW Co-generation Power Plant in Existing Distillery Plant at Village Bhadson, Umri Road, Tehsil Indri, District Karnal (Haryana). Molasses will be transported through pipelines from own sugar mill located next to Distillery & nearby Sugar Mills. The company has an existing 90 KLPD Molasses/Grain Based Distillery along with 3 MW Co-generation Power Plant at Village Bhadson, Umri Road, Tehsil Indri, District Karnal (Haryana). As per EIA Notification dated 14 th Sep., 2006 as amended from time to time; the project falls in Category ‘A’, Project or Activity - 5(g). Table - 1 Salient Features of the Project S. NO. PARTICULARS DETAILS A. Nature & Size of the Project Proposing installation of Unit II 60 KLPD Molasses based Ethanol Plant along with 2 MW Co-generation Power Plant in Existing Distillery Plant B. Category of the Project As per EIA Notification dated 14 th September, 2006 and as amended from time to time; the project falls in Category ‘A’, S. No. - 5(g). C. Location Details Village Bhadson Tehsil Indri District Karnal State Haryana Latitude 29° 54’ 04.21” N to 29° 54’ 32.93” N Longitude 76° 58’ 40.83” E to 76° 59’ 05.25” E Toposheet No. 53 C/13 & 53 G/1 D. Area Details Total Plant Area Existing plant area: 70 Acres/28.3 Ha No additional land is required for the proposed expansion, as the same will be done within the existing plant premises

PRE - FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...Based Distillery at Village Bhadson, Tehsil Indri, District Karnal (Haryana). Environmental Clearance for

  • Upload
    others

  • View
    4

  • Download
    0

Embed Size (px)

Citation preview

Page 1: PRE - FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...Based Distillery at Village Bhadson, Tehsil Indri, District Karnal (Haryana). Environmental Clearance for

Proposed installation of Unit II – 60 KLPD Molasses based Ethanol Plant alongwith 2 MW Co-generation Power Plant in

Existing Distillery Plant

At Village Bhadson, Umri Road, Tehsil Indri, District Karnal (Haryana)

Pre - feasibility Report

M/s. Piccadily Agro Industries Limited 1

PRE - FEASIBILITY REPORT

1.0 EXECUTIVE SUMMARY

(I) INTRODUCTION

In line with the ambitious programme of Govt. of India like “MAKE IN INDIA” and to

become self-dependent on fuel within the country, M/s. Piccadily Agro Industries Limited

has planned for proposing installation of Unit II – 60 KLPD Molasses based Ethanol Plant

along with 2 MW Co-generation Power Plant in Existing Distillery Plant at Village Bhadson,

Umri Road, Tehsil Indri, District Karnal (Haryana).

Molasses will be transported through pipelines from own sugar mill located next to

Distillery & nearby Sugar Mills.

The company has an existing 90 KLPD Molasses/Grain Based Distillery along with 3 MW

Co-generation Power Plant at Village Bhadson, Umri Road, Tehsil Indri, District Karnal

(Haryana).

As per EIA Notification dated 14th Sep., 2006 as amended from time to time; the project

falls in Category ‘A’, Project or Activity - 5(g).

Table - 1

Salient Features of the Project

S. NO.

PARTICULARS DETAILS

A. Nature & Size of the Project Proposing installation of Unit II – 60 KLPD Molasses based

Ethanol Plant along with 2 MW Co-generation Power Plant in

Existing Distillery Plant

B. Category of the Project As per EIA Notification dated 14th September, 2006 and as

amended from time to time; the project falls in Category ‘A’,

S. No. - 5(g).

C. Location Details

Village Bhadson

Tehsil Indri

District Karnal

State Haryana

Latitude 29° 54’ 04.21” N to 29° 54’ 32.93” N

Longitude 76° 58’ 40.83” E to 76° 59’ 05.25” E

Toposheet No. 53 C/13 & 53 G/1

D. Area Details

Total Plant Area

• Existing plant area: 70 Acres/28.3 Ha

• No additional land is required for the proposed

expansion, as the same will be done within the existing

plant premises

Page 2: PRE - FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...Based Distillery at Village Bhadson, Tehsil Indri, District Karnal (Haryana). Environmental Clearance for

Proposed installation of Unit II – 60 KLPD Molasses based Ethanol Plant alongwith 2 MW Co-generation Power Plant in

Existing Distillery Plant

At Village Bhadson, Umri Road, Tehsil Indri, District Karnal (Haryana)

Pre - feasibility Report

M/s. Piccadily Agro Industries Limited 2

Greenbelt / Plantation Area 23 acres/9.3 ha i.e. 33% of the total plant area has already

been developed.

E. Environmental Setting Details (with approximate aerial distance & direction from plant site)

1. Nearest Village Bir Majra (~ 1.0 km in WNW direction)

2. Nearest Town & City Town - Kurukshetra (~ 12 km in NW direction)

Karnal District Headquarter (~ 25 km in South direction)

3. Nearest National Highway /

State Highway

NH-1 (~ 6 km in WSW direction)

4. Nearest Railway station Nilokheri Railway Station (~ 9 km in SW direction)

Kurukshetra Railway Station (~ 12 km in NW direction)

5. Nearest Airport Chandigarh (~ 88 km in NNW direction)

6. Archaeological Important Site None within 10 km radius

7. National Parks, Wild Life

Sanctuaries, Biosphere

Reserves, Tiger/ Elephant

Reserves, Wildlife Corridors etc.

within 10 km radius

No National Park, Wild Life Sanctuary, Biosphere Reserve,

Tiger / Elephant Reserve, Wildlife Corridors etc. falls within 10

km radius of the plant site.

8. Reserved Forests (RF) /

Protected Forests (PF) etc.

within 10 Km. radius

Bir Seonti Reserved Forest (~ 7.5 km in North direction)

No Protected Forest falls within 10 km radius study area.

9. River / Water Body (within 10 km

radius)

• Chautang Nadi – Seasonal (~2.5 km in West direction)

• Sirsa Branch Canal (~ 3.0 km in South direction)

• Khand Nala - Seasonal (~ 7.5 km in NNW direction)

• Western Yamuna Canal (~ 5.5 km in SW direction)

F. Cost Details

Total Cost of the Project Rs. 47.0 Crores

Cost for Environment

Management Plan

o Capital Cost - Rs. 10 Crores

o Recurring Cost - Rs. 1.0 Crores / annum

G. Basic Requirements for the project

Main Raw Material – Molasses 282 to 300 MT/day

Source:- Sugar Mills

Water Requirement 526

Source:- Ground Water

Power Requirement

1.2 MW

Source: - 2 MW Co-gen Power Plant & D.G Set (for

emergency).

Man Power Requirement 60

Source:- Unskilled / Semi-Skilled - Local Area; Skilled

H. Product Mix Ethanol

I. Working Days Working days - 330 Days per Annum

Page 3: PRE - FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...Based Distillery at Village Bhadson, Tehsil Indri, District Karnal (Haryana). Environmental Clearance for

Proposed installation of Unit II – 60 KLPD Molasses based Ethanol Plant alongwith 2 MW Co-generation Power Plant in

Existing Distillery Plant

At Village Bhadson, Umri Road, Tehsil Indri, District Karnal (Haryana)

Pre - feasibility Report

M/s. Piccadily Agro Industries Limited 3

1.1 Environment Management Plan

Particulars Details

Air Management

Emissions � A stack of 35 m height equipped with ESP/Bag Filter will be installed with the

boiler of 25 TPH capacity to control the particulate and gaseous emissions

due to combustion of fuel.

� CO2 generated during the fermentation process will be collected by utilizing

CO2 Scrubbers and sold to authorized vendors.

� All the roads are asphalted to control the fugitive dust emissions

� Proper servicing & maintenance of vehicles is being/will be carried out.

� Green Belt around the periphery and within premises already exists and the

same will be maintained after proposed expansion, modernization &

installation.

Monitoring Ambient air quality and stack emission will be regularly monitored to ensure that

ambient air quality standards and suggested limits on stack emission loads would

be met honestly at all the time.

Water Management

Management � The project will be based on “Zero Effluent Discharge”.

� Fresh water requirement of the project will be met by Ground Water &

Recycled water. Efforts will be made to conserve as much water as possible

by recycling and reuse.

� Spent wash generated during Molasses operation will be concentrated in

Multi-effect evaporator and then used for Bio-composting.

� Record of wastewater returned back to process for utilization in

Fermentation/cooling tower and to gardening will be kept.

� Process condensate from MEE will be treated and recycled back in the

process.

Monitoring Regular monitoring of water quality will be carried out.

Noise Management

Management � Personal Protective Equipment like earplugs and earmuffs will be provided to

the workers exposed to high noise level.

� D.G sets will be provided with acoustic to control the noise level within the

prescribed limit.

� Proper maintenance, oiling and greasing of machines at regular intervals will

be done to reduce generation of noise.

Page 4: PRE - FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...Based Distillery at Village Bhadson, Tehsil Indri, District Karnal (Haryana). Environmental Clearance for

Proposed installation of Unit II – 60 KLPD Molasses based Ethanol Plant alongwith 2 MW Co-generation Power Plant in

Existing Distillery Plant

At Village Bhadson, Umri Road, Tehsil Indri, District Karnal (Haryana)

Pre - feasibility Report

M/s. Piccadily Agro Industries Limited 4

� Green Belt of inside the plant premises and at the plant boundary has been

developed.

Monitoring Regular monitoring of noise level will be carried out and corrective measures in

concerned machinery will be adapted accordingly to the possible extent.

Solid & Hazardous Waste Management

Management

� Spent Wash generated during the process, will be first treated in Bio-Digester

(Bio-Methanation) and after that will be concentrated in Multi-effect

evaporator and concentrate is used for bio composting.

� Ash from the Boiler will be used in bio-composting & also given to nearby

brick manufacturers.

� Yeast sludge & Digesters sludge will be finally disposed as Mixing with Press

Mud.

� The company will utilize the spent wash for manufacturing bio-compost

within the premises, with proper labelling and marketing of the finished

compost, in sealed bags, bearing the name and seal of our industry and the

composition of the bio-compost.

� The company will not sell compost in open tractors/ trolleys.

Green Belt Development / Plantation

Management � Green belt development in and around the plant site helps to attenuate the

pollution level.

� Out of the total plant area approx. 33% land is already developed as green belt

and it will be maintained in future also.

� Green belt has been developed as per Central Pollution Control Board (CPCB)

guidelines.

� Native species have been planted in consultation with the local DFO.

Odour Management

Management � The remedial measures will be taken such as better house-keeping by regular

steaming of all fermentation equipments and same will be followed in future.

� Temperature will be kept under control during fermentation to avoid in-

activation/killing of yeast and staling of fermented wash will be avoided.

2.0 INTRODUCTION OF THE PROJECT/ BACKGROUND INFORMATION

(i) Identification of Project and Project Proponent

Piccadily Agro Industries Ltd. (PAIL), a Public Limited Company was incorporated in the

year 1994. It is spread over an area of 168 Acres of Land. It started its operation in the

Page 5: PRE - FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...Based Distillery at Village Bhadson, Tehsil Indri, District Karnal (Haryana). Environmental Clearance for

Proposed installation of Unit II – 60 KLPD Molasses based Ethanol Plant alongwith 2 MW Co-generation Power Plant in

Existing Distillery Plant

At Village Bhadson, Umri Road, Tehsil Indri, District Karnal (Haryana)

Pre - feasibility Report

M/s. Piccadily Agro Industries Limited 5

year 1996 - 97 for manufacture of White crystal sugar with installed capacity of 2500

TCD along with in-house facilities for 6 MW Co-generation of power at Umri-Indri Road,

Tehsil Indri, District Karnal, (Haryana).

The company there after started expansion & modernization of the Sugar Mill and

enhanced the crushing capacity to 5000 TCD w.e.f. 02/12/2004 i.e from crushing season

2004 - 2005.

The company further expanded its business & set up a Distillery Unit with an installed

capacity of 60 KLPD in year 2007, which has further been expanded to 90 KLPD.

Piccadily Agro Industries Ltd. (PAIL) is having an existing 90 KLPD Molasses/ Grain

Based Distillery at Village Bhadson, Tehsil Indri, District Karnal (Haryana).

Environmental Clearance for the same has been obtained from MoEF, New Delhi vide

Letter No. J-11011/495/2008- 1A II (I) dated 23rd October, 2008 and amendment on dated

25th May, 2016.

(ii) Brief description of nature of the project

In line with the ambitious programme of Govt. of India like “MAKE IN INDIA” and to

become self-dependent on fuel within the country, M/s. Piccadily Agro Industries

Limited has planned for proposing installation of Unit II – 60 KLPD Molasses based

Ethanol Plant along with 2 MW Co-generation Power Plant in Existing Distillery Plant at

Village Bhadson, Umri Road, Tehsil Indri, District Karnal (Haryana).

Molasses will be transported through pipelines from own sugar mill located next to

Distillery & nearby Sugar Mills.

M/s. Piccadily Agro Industries Limited has an existing 90 KLPD Molasses/Grain Based

Distillery at Village Bhadson, Umri Road, Tehsil Indri, District Karnal (Haryana).

As per EIA Notification dated 14th September, 2006 and as amended from time to time;

the project falls in Category ‘A’, S. No. - 5 (g).

(iii) Need for the project and its importance to the country and or region

Advancement in science and technology has created so many products that have

enhanced the quality of human life in every passing year. The human race is largely

dependent on industrialization for up gradation in quality of life. Progress of the nation

is judged through its economic growth which is largely dependent on industrial

productivity. In Indian economy (which is agro based) many industries are dependent

over agricultural produce for production of luxury and need based commodities.

Alcohol has assumed a very important place in the Country’s economy. It is a vital raw

material for a number of chemicals. It has been a source of revenue by way of excise

Page 6: PRE - FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...Based Distillery at Village Bhadson, Tehsil Indri, District Karnal (Haryana). Environmental Clearance for

Proposed installation of Unit II – 60 KLPD Molasses based Ethanol Plant alongwith 2 MW Co-generation Power Plant in

Existing Distillery Plant

At Village Bhadson, Umri Road, Tehsil Indri, District Karnal (Haryana)

Pre - feasibility Report

M/s. Piccadily Agro Industries Limited 6

duty levied by the State Government on alcohol liquors. The use of alcohol for the

purpose of potable liquor is as high as its use for industrial purposes.

According to analysts, the Indian Ethanol industry is expected to witness accelerating

growth in coming years. Ethanol is an alcohol fuel that is added to petrol in some

countries to lower cost to the consumer, reduce consumption of oil, and lessen the

environmental impact of transportation. Mixed fuels are rated by the amount of

ethanol contained; for example, common blends are E10, which contains 10% ethanol,

and E15, which contains 15% alcohol. Another common blend is E85, also known as flex

fuel, in which the ethanol ranges from 51% in winters to 83% in summers.

In addition, though ethanol reduces air particulate pollution, its production results in

fairly high greenhouse gas emissions and negates any the environmental benefit of the

shift from fossil fuel.

The biggest concern with the addition of ethanol to India's fuel supply is that it will take

up scarce land set aside for grazing and other crops to grow fuel. With the demand

likely to be huge, there is bound to be a shift in land use from food crops to fuel crops.

Agriculture will become even more intensive. Without adequate reforms and education

in the agricultural sector to increase productivity, the shift to fuel crops will result in

food price inflation. The savings from reduced oil imports will be spent instead on

subsidies and higher food prices.

Furthermore, technology can improve at two ends - energy efficiency at the EV end and

greater storage capacity at the EVB end. The latter would translate into better

performing vehicles without the consumer having to regularly upgrade his EV.

In the path of company’s growth and development this proposed project will serve as

yet another milestone.

(iv) Demand- Supply Gap

Not required in this Project. This depends on excise Department.

(v) Import vs. Indigenous Production

Indian market could not meet present alcohol demand. So they import alcohol 5-7% of

total demand. As far as ethanol production is concerned, Indian market play a vital role

at both domestic & international level. So they require producing more alcohol to meet

the demand.

(vi) Export Possibility

Export of ethanol is currently governed by Govt. policy.

Page 7: PRE - FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...Based Distillery at Village Bhadson, Tehsil Indri, District Karnal (Haryana). Environmental Clearance for

Proposed installation of Unit II – 60 KLPD Molasses based Ethanol Plant alongwith 2 MW Co-generation Power Plant in

Existing Distillery Plant

At Village Bhadson, Umri Road, Tehsil Indri, District Karnal (Haryana)

Pre - feasibility Report

M/s. Piccadily Agro Industries Limited 7

(vii) Domestic / Export Markets

Sales and Marketing division has always been a key focus area for our company. Over

the years we have reached a number of key customers through our initiatives. We have

a thrust on institutional Buyers which is a paradigm shift from the tradition of selling to

wholesale market.

(viii) Employment Generation (Direct and Indirect) due to the project

For smooth functioning of the plant, the company needs a team of 60 persons. These

persons are responsible towards their respective department such as Process Plant,

Boiler Operating Plant and administrative block.

3.0 PROJECT DESCRIPTION

(i) Type of Project including interlinked and independent projects, if any.

There are no interlinked projects related to this project.

ii) Location (map showing general location, specific location, and project boundary & project

site layout) with coordinates

Page 8: PRE - FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...Based Distillery at Village Bhadson, Tehsil Indri, District Karnal (Haryana). Environmental Clearance for

Proposed installation of Unit II – 60 KLPD Molasses based Ethanol Plant alongwith 2 MW Co-generation Power Plant in

Existing Distillery Plant

At Village Bhadson, Umri Road, Tehsil Indri, District Karnal (Haryana)

Pre - feasibility Report

M/s. Piccadily Agro Industries Limited 8

Figure - 1: Location Map

Page 9: PRE - FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...Based Distillery at Village Bhadson, Tehsil Indri, District Karnal (Haryana). Environmental Clearance for

Proposed installation of Unit II – 60 KLPD Molasses based Ethanol Plant alongwith 2 MW Co-generation Power Plant in Existing

Distillery Plant

At Village Bhadson, Umri Road, Tehsil Indri, District Karnal (Haryana)

Pre - feasibility Report

M/s. Piccadily Agro Industries Limited 9

(ii) Key Plan

Figure - 2: Key Plan

Page 10: PRE - FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...Based Distillery at Village Bhadson, Tehsil Indri, District Karnal (Haryana). Environmental Clearance for

Proposed installation of Unit II – 60 KLPD Molasses based Ethanol Plant alongwith 2 MW Co-generation Power Plant in Existing

Distillery Plant

At Village Bhadson, Umri Road, Tehsil Indri, District Karnal (Haryana)

Pre - feasibility Report

M/s. Piccadily Agro Industries Limited 10

(iv) Details of alternative sites consideration and basis of selecting the proposed site,

particularly the environmental considerations gone into should be highlighted.

The proposed installation of Unit II will be done within the existing Distillery plant premises

and no additional land will be required; therefore, no alternative site has been considered.

(v) Size or magnitude of operation

M/s. Piccadily Agro Industries Limited has planned for proposing installation of Unit II – 60

KLPD Molasses based Ethanol Plant along with 2 MW Co-generation Power Plant in Existing

Distillery Plant at Village Bhadson, Umri Road, Tehsil Indri, District Karnal (Haryana). Molasses

will be transported through pipelines from own sugar mill located next to Distillery & nearby

Sugar Mills. The company has an existing 90 KLPD Molasses/Grain Based Distillery at Village

Bhadson, Umri Road, Tehsil Indri, District Karnal (Haryana).

(vi) Project Description with Process Details

Project Description

S. No. Units Capacity

1. Ethanol Plant 60 KLPD

2. Co-Generation Power Plant 2.0 MW

Process Description

A. Molasses Based Operation

Alcohol is produced from carbohydrates by fermentation with yeast. Yeasts are

unicellular, uninucleate fungi that can reproduce by budding, fission or both. They have

been used for centuries to brew alcoholic beverages and are the most commonly used

micro-organism in the industrial production of alcohol by fermentation. Ethanol

production by fermentation comprises four steps:

• Yeast propagation from yeast slant from the laboratory.

• Fermentation to produce fermented wash containing alcohol.

• Recovery, enrichment and purification of alcohol from fermented wash to produce

95.5 V/V alcohols.

• Production of absolute alcohol by dehydration of 95.5% V/V alcohol to produce

absolute alcohol.

A proper choice of appropriate technology in each of these steps governs the efficient

and viable operation of fermentation alcohol plant.

Page 11: PRE - FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...Based Distillery at Village Bhadson, Tehsil Indri, District Karnal (Haryana). Environmental Clearance for

Proposed installation of Unit II – 60 KLPD Molasses based Ethanol Plant alongwith 2 MW Co-generation Power Plant in Existing

Distillery Plant

At Village Bhadson, Umri Road, Tehsil Indri, District Karnal (Haryana)

Pre - feasibility Report

M/s. Piccadily Agro Industries Limited 11

Yeast Propagation

Yeast, for the production of alcohol is characterized by high selectivity of the yeast

species, low production of by-products (side products), high ethanol yield, high

fermentation rate, good tolerance towards both high ethanol concentration and high in

organics in the fermenting substrate, high temperature tolerance, land high genetically

stability. Although finding a strain that has all these characteristics is difficult, a proper

selection and development of the best possible strain is needed. Sacharomy-cervisiae is

the commonly deployed yeast strains in alcohol fermentation of sugars. The purity and

sterility of yeast culture used as inoculums have great influence on the alcohol yield and

longevity of yeast in fermenter. Flocculating yeasts are deployed for continuous

fermentation particularly with yeast recycle system. The selectivity of yeast is also

essential to maintain the required metabolic reaction pathways specific to conversion of

sugars to alcohol. The side products are higher alcohols, acids, etc. which naturally

reduce the alcohol yields and final quality of alcohol. It is, therefore, customary to

propagate yeast from laboratory strain in increasing volumes under sterile and aerobic

conditions protecting the same from other wild yeasts and moulds during their growth.

This is done in 3 or four stages starting from a 1 lit inoculums developed in laboratory

from a well preserved yeast culture slant.

Yeast will be developed in plant from fresh slant to laboratory flash culture and then in 3

stage S.S. yeast propagation vessels (VO1, VO2 and VO3) which operate in series but in

batch mode. When enough bio mass strength is developed, it is pitched Into Fermenter

(VO4).

Fermentation

The yeast propagation is only at the start and stabilization of the fermenter. When once

the continuous fermentation is on, the yeast propagation is stopped and only a periodic

continuous addition of small make up of fresh culture from yeast vessel is done to

maintain the activity of yeast in the active yeast count in the fermenter. The yeast vessels

are fitted with jacket for sterilizing and cooling the medium in situ. Sterile air is supplied

to these vessels through compressor (G-01) and the sterilization-system comprising a

series of fine filters followed by HEPA filters. Molasses from the molasses tank T-01 in the

yard are pumped to transfer pump (P-02) into tipper type molasses weighing system W-

01 and weighed molasses feed tank (T-03) from where molasses feed pump it to yeast

vessels (when necessary) or to fermenter (V-04) through a static mixer type molasses

diluter. Main fermenter could be one or two stages depending on the control system

envisaged based on the final designs. The heat of fermentation is extracted by

circulating the fermenter contents through wort coolers (EO1 & EO3). Temperature in

the fermenter is to be maintained at 32 – 34°C. Carbon dioxide evolved during

Page 12: PRE - FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...Based Distillery at Village Bhadson, Tehsil Indri, District Karnal (Haryana). Environmental Clearance for

Proposed installation of Unit II – 60 KLPD Molasses based Ethanol Plant alongwith 2 MW Co-generation Power Plant in Existing

Distillery Plant

At Village Bhadson, Umri Road, Tehsil Indri, District Karnal (Haryana)

Pre - feasibility Report

M/s. Piccadily Agro Industries Limited 12

fermentation is vented out through scrubber (C-03) to recover entrained alcohol vapors.

Dilute molasses are fed to the fermenter continuously. The final fermented wash is

transferred by wash pump (P-05) to yeast separation system comprising hydrocolones F-

01 & F-02 and centrifuge F-03. The sludge and dead yeast are purged into sludge tank and

yeast cream is returned to the fermenter (V-04) while clear fermented wash is collected

in wash tank V-02. Sludge from sludge tank is fed to the bottom of Analyzer Column (C-

01) in the distillation section. Part of spent wash from a selected tray in the column C-01

is returned to fermenter V-04 after cooling the same to as near to ambient temperature

as possible. Anti-foam oil is added from T-04 whenever necessary when the level in the

fermenter rises beyond a limit due to foaming because of runaway fermentation rate.

The operations in the fermenter can be controlled closely through automation. Process

water is taken into scrubber water tank from where it is fed to scrubber (C-03) and

overhead water tank (T-12) by water pump (P-10). All process water in the fermentation

section is supplied by gravity from this overhead tank (T-12).

RS/AA /ETHANOL/ENA Spirit Distillation

Fermented wash from wash holding tank T-01 is pumped by wash feed pump P-01 to the

top of degassing column (C-2) after preheating the same in beer heater E-02 and spent

wash heat exchanger E-01. The vapors along with non-condensable gases from the top of

degassing column (C-02) are rectified in Heads column (C-03), to expel the high volatiles,

technically know as heads. Bottom liquid from the degasser flows into analyzer column

(C-01) where alcohol is stripped from the liquid. The liquid from bottom of analyzer

column (C-01) is completely stripped of alcohol and is pumped out by spent wash

discharge pump P-02 through heat exchanger E-01 where it preheats the fermented wash

before it enters degassing column. Part of spent wash from a tray, few numbers above

the bottom tray is cooled and returned to the fermenters as a measure of water saving

and reduction of effluent discharge.

The dilute alcohol vapors from near the top of analyzer column (C-01) are condensed first

in beer heater (E-02) while exchanging heat with wash feed and then in analyzer

condenser (E03). Degasser and analyzer operate under vacuum. The condensate from E-

02 and E-03 is collected in Rectifier Feed Tank V-02. The vapors for stripping alcohol are

generated from analyzer column bottom liquid in the analyzer column re-boiler (E-04) by

using the rectified column top vapors, as discussed subsequently.

Vapors from the top of heads column (C-03) are condensed in heads column condenser

(E-06) and then in head column vent condenser (E-07). Part of the condensate is

returned to column C-03 as reflux while a small portion is taken out as an impure spirit

cut. Liquid from bottom of C-03 is also taken into Rectified feed tank V-02.

Page 13: PRE - FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...Based Distillery at Village Bhadson, Tehsil Indri, District Karnal (Haryana). Environmental Clearance for

Proposed installation of Unit II – 60 KLPD Molasses based Ethanol Plant alongwith 2 MW Co-generation Power Plant in Existing

Distillery Plant

At Village Bhadson, Umri Road, Tehsil Indri, District Karnal (Haryana)

Pre - feasibility Report

M/s. Piccadily Agro Industries Limited 13

Dilute alcohol water mixture from rectifier feed tank (V-02) are pumped by rectifier feed

pump (P-04) through rectifier feed pre-heater E-11 in to rectifying column (C-04). Rectifier

and its associated equipment work under pressure so that these vapors can supply the

necessary heat for generating the vapors

The condensate from E-04 is then pumped as Reflux to rectifying column C-04. Rich

alcohol vapors at a concentration of 95.5% v/v from top of rectifying column (C-04) are

condensed first in Analyzer (E-04) and then in Reflux Vent Condenser (E-05). The liquid

from E04 and E-05 are collected in Rectifier Reflux Tank (V-01). Part of the liquid from E-

05 may be drawn off as impure spirit. The impure spirit cut will be maintained as little as

possible to maintain aldehyde levels to meet the required limits in Absolute Alcohol.

Liquid from the reflux tank (V-01) is pumped by Product Pump (P-03) partly as product

and partly as reflux to the top of the Rectifying Column (C-04). The necessary rectifying

vapors to C-04 are generated by boiling the C-04 bottom liquid in Rectifier Column Re-

boiler E-08 using medium pressure steam. Some side streams are drawn from rectifier

column as light and heavy fractions of higher alcohols called fusel oils and cooled in fusel

oil coolers E-09 and E-10 and are mixed with water and allowed to separate out in fuel oil

separator F-01. All vents from E-03, E-07, V-02 and E-05 are connected to Vent Gas

Absorber (C-05) where the vent gases are scrubbed with water to recover entrained

alcohol. The scrubber water is used for washing the fusel oils in fusel oil separator to

recover alcohol from the fusel oil fractions. The absorber vent is connected to vacuum

pump (G-01) which is used to create vacuum in the analyzer and degasser.

The products Rectified Spirit and Impure Spirit, are cooled in product coolers and

collected in the respective receiver tanks prior to pumping the same through respective

transfer pumps into storage tanks in the excise godown. Impure spirit, is however,

returned to Ethanol plant along with the rectified spirit feed, subject to maintaining, the

Absolute Alcohol quality required for blending with petrol.

Fuel Grade Ethanol

Absolute alcohol is manufactured by dehydration of Rectified Spirit. The process

adopted here is based on Pressure Swing Adsorption (PSA) system using Molecular

Sieves (3-A). The flow scheme is shown in above referred flow diagram.

Rectified spirit, after preheating by waste hot streams, is vaporized and superheated in E-

03 and E-04 by using medium pressure steam at 6 Kg/cm2g pressure. Hot vapors at

kg/cm² g pressure and 130° C temperature pass through PSA column S-01A/S-01B where

the water vapors are retained while water free alcohol is released as vapors. The vapors

are condensed in E-07 and E-08 and collected as Absolute Alcohol. When the molecular

sieve bed is saturated with water the alcohol vapors are shifted to the other tower and

Page 14: PRE - FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...Based Distillery at Village Bhadson, Tehsil Indri, District Karnal (Haryana). Environmental Clearance for

Proposed installation of Unit II – 60 KLPD Molasses based Ethanol Plant alongwith 2 MW Co-generation Power Plant in Existing

Distillery Plant

At Village Bhadson, Umri Road, Tehsil Indri, District Karnal (Haryana)

Pre - feasibility Report

M/s. Piccadily Agro Industries Limited 14

the first tower is taken for regeneration. Regeneration is done first by pressure releasing

and creating vacuum and then by elutriating with dehydrated alcohol vapors from the

tower in dehydration operation. The vapors are condensed in E-06 and E-05 and the vent

vapors are recovered through scrubber C-02. Vacuum can be created vacuum by P-04.

(Eductor may also be considered for this duty). Product is cooled in E-09 and transferred

to Absolute Alcohol receiving tank and then on to storage tank.

Figure 3: Molasses Based Distillery Process

B. Effluent Handling Section

Effluent discharged from the distillation process, commonly known as Spent Wash, is one

of the most polluting effluents with very high values of BOD and COD. It is first treated in

a Bio-methanation System, which not only reduces the effluent load, but also produces

methane rich biogas. Biogas is a high calorific value fuel and is used as fuel for boiler to

produce power and steam to run distillery plant. The production of extra power from

biogas improves the economics of the ethanol project. The effluent after Bio-

methanation is being/will be concentrated in Multi-effect evaporator and then used for

Bio-composting.

1) Bio-methanation Process

Bio-methanation involves conversion of organic compounds present in the effluent, using

a consortium of bacteria under anaerobic conditions. During their life cycle, the bacteria

Page 15: PRE - FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...Based Distillery at Village Bhadson, Tehsil Indri, District Karnal (Haryana). Environmental Clearance for

Proposed installation of Unit II – 60 KLPD Molasses based Ethanol Plant alongwith 2 MW Co-generation Power Plant in Existing

Distillery Plant

At Village Bhadson, Umri Road, Tehsil Indri, District Karnal (Haryana)

Pre - feasibility Report

M/s. Piccadily Agro Industries Limited 15

break down these organic compounds into methane and carbon dioxide. The bacteria,

being living organisms, require specific conditions to prosper. This is achieved by

controlling the following parameters:

Temperature

Acidity

Organic Loading

Nutrient Balance

The existing bio-methanation system uses a specially designed CSTR, called bio-digester,

to convert organic matter into useful energy in the form of biogas. The biological process

of conversion takes place at mesophilic temperature in a controlled atmosphere,

ensuring maximum conversion efficiency and production of biogas.

Following are the salient features of the process:

• Pre - Settling

Before entering the bio digester, the spent wash from the distillery unit is received

into a spent wash pit to enable settling of suspended solids. The pre-settling system

ensures consistent operation by reducing the solid build up in the bio digester. The

settled solids are removed periodically from the pit for further disposal.

• pH Control

Spent wash pH is adjusted to 6.5-7.0 by recycling part of the treated effluent.

• Mixing in Bio digester

Mixing is done by recirculation of biomass, using a specially designed mixing system

and is further enhanced by gas propagation. Efficient mixing helps micro organisms to

reach fresh nutrients in a favourable living condition and convert organic matter into

methane and carbon dioxide. Various sample points are provided in the biodigester to

measure the concentration of sludge. Drain points are provided to drain the sludge

from the bio digester. The sludge is settled in the parallel plate clarifier, which is

recycled to increase solid retention time in the bio digester. Supernatant liquid from

the clarifier is sent for further treatment. Excess biomass and sludge is removed from

the bottom of the bio digester regularly and sent to sludge drying beds for disposal.

• Gas Collection & Handling

Biogas produced in the bio digester is collected from the top of the digester and flows

to the gas holder. The gas holder acts as an intermediate gas storage and pressure

control device. Biogas is transferred to a biogas power plant to produce power. A flare

unit is provided for excess gas burning.

Page 16: PRE - FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...Based Distillery at Village Bhadson, Tehsil Indri, District Karnal (Haryana). Environmental Clearance for

Proposed installation of Unit II – 60 KLPD Molasses based Ethanol Plant alongwith 2 MW Co-generation Power Plant in Existing

Distillery Plant

At Village Bhadson, Umri Road, Tehsil Indri, District Karnal (Haryana)

Pre - feasibility Report

M/s. Piccadily Agro Industries Limited 16

• Safety Systems

For safe operation, flame arresters are provided on gas lines to protect the bio

digester from backfire & pressure relief valves are provided on bio digester to protect

from excess pressure or vacuum.

• Control Systems

Controlling pH ensures the smooth and safe operation of the system. Temperature,

volatile acidity and alkalinity are also controlled, using various control features

provided.

• Type of Bacteria

Anaerobic digestion of organic compounds is carried out, using different bacteria.

Three main groups of bacteria, used in the process are indicated below:

� Hydrolyzing bacteria ( Solubilising bacteria)

� Acetogenic bacteria ( Acetate forming bacteria)

� Methanogenic bacteria ( Methane forming bacteria)

2) Multi-Effect Evaporation

Direct spent wash will be concentrated in a multistage vacuum evaporator from 5-7% to

30-35% solids. The total process is under vacuum and the vapours generated in the system

are compressed in a TVR to economize steam consumption. Condensate water generated

from the evaporation system will be recycled back in the process. The concentrated

effluent is used in Bio-composting

3) Bio Compost Plant

The composting process consists of converting the spent wash into useful manure. This is

done with the help of specialized microbial culture or using fresh compost as seed for the

micro-organisms. The raw materials required for composting are concentrated spent

wash from multi effect evaporator, bacterial culture, Press mud from the sugar factory,

ash from boiler

Composting is a biological oxidation process for decomposing organic material by a

mixed microbial population in a suitably warm and moist environment under aerobic

conditions. The degradation converts the material to a stable organic fertilizer which is

also a soil improver. The aerobic composting process involves arranging the press mud

(filler material) in 300 to 400 m long windrows of triangular section of about 1.5 m height

by 3.0 m. width on impervious ground usually with the help of front end loaders. The

windrows are sprayed with a measured quantity of spent wash, in the ratio of 3.5:1 (spent

wash to press mud). The ratio will vary depending on the moisture content of the filler

materials. The spraying of spent wash is done when the moisture content of the press

Page 17: PRE - FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...Based Distillery at Village Bhadson, Tehsil Indri, District Karnal (Haryana). Environmental Clearance for

Proposed installation of Unit II – 60 KLPD Molasses based Ethanol Plant alongwith 2 MW Co-generation Power Plant in Existing

Distillery Plant

At Village Bhadson, Umri Road, Tehsil Indri, District Karnal (Haryana)

Pre - feasibility Report

M/s. Piccadily Agro Industries Limited 17

mud drops to 50%. The moisture content is not allowed to exceed 65% as at that moisture

anaerobic condition start prevailing which is detrimental to the composting process. The

windrows are inoculated with the seed material after the first spray. About 1 Kg. of bio

culture is required per ton of press mud. From ambient temperature at start up the

temperature rises to 65 Deg. C. by the second week and continues up to the 4th week.

The total duration for completion of the reactions is about 6 weeks by which time the

temperature returns to ambient. A further 2 weeks is allowed for curing. Carbon to

nitrogen ratio is the deciding factor to determine the completion of the bio composting

process. Specialized mixing machines called aero-tillers, traveling along the length of the

windrows are used to mix and aerate the decomposing mass, about once in three days.

This results in increased spent wash absorption, oxygen supply for proper growth of

micro-organisms and dissipation of heat, which is liberated due to metabolic activity of

micro-organisms. The moisture content during composting is maintained at 50-60% by

periodic spraying of the spent wash. Adequate holding capacity (min. 30 days) is to be

provided for the spent wash in lined lagoons to cater to any demand mismatch. The

lagoons should be duly lined and pitched by stone/bricks with cement mortar to prevent

leachate. Composting is to be carried out on a raised impervious floor protected by bunds

with provision for leachate collection and surface runoff and it’s pumping to the holding

lagoon. Pipe network is laid for automatic spraying of spent wash.

C. Power Co-generation 2 MW

OPERATIONS

The unit proposes to set-up boiler and power turbine.

In this proposed expansion project a 25 TPH boiler will be installed and based on

Bagasse/Rice Husk/Coal and Biogas as available fuel options. This Boiler will operate

mainly to feed steam to Molasses based operations and 2 MW power generations from

Turbine.

Proposed 2 MW co-generation plant consists of a high pressure water tube steam boiler

extraction cum condensing steam turbine. Fuel in the steam boiler will be burnt with the

help of air in the boiler furnace. Water will be circulated in the boiler drum and tubes thus

getting heated by the flame burning in the boiler furnace. Water comes out of the boiler

drum located at the top of the boiler as steam. Flue gases rise in the boiler furnace and

come in contact with the steam coming out of boiler drum. Steam after coming in

contact with flue gases gets heated up further thus getting superheated. Super heated

steam leaves the boiler in a pipe. Flue gases after super heating the steam pass through

economizer where they pre-heat the boiler feed water before it enters the boiler drum.

After economizer, flue gases pass through air pre-heaters where they heat the air which

Page 18: PRE - FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...Based Distillery at Village Bhadson, Tehsil Indri, District Karnal (Haryana). Environmental Clearance for

Proposed installation of Unit II – 60 KLPD Molasses based Ethanol Plant alongwith 2 MW Co-generation Power Plant in Existing

Distillery Plant

At Village Bhadson, Umri Road, Tehsil Indri, District Karnal (Haryana)

Pre - feasibility Report

M/s. Piccadily Agro Industries Limited 18

is fed to the boiler furnace for burning the fuel. After air pre heaters flue gases pass

through Bag Filter/ESP where the dust particles are collected.

High pressure superheated steam from boiler will be passed through a steam turbine,

which will be used for distillery process operations. While passing through the turbine,

the high pressure and temperature steam rotates the turbine rotor and an electric

alternator mounted on the same shaft. Electric power will be generated by the

alternator. This electric power generated will be consumed in house i.e. for running the

distillery and utilities like boilers auxiliaries etc.

Figure 4: Process Flow Chart for Cogeneration Power Plant

(vii) Raw material required along with estimated quantity, likely source, marketing area of final

products, mode of transport of raw material and finished product.

(a) Raw Material Requirement

The raw materials required for the Molasses based distillery can be broadly categorized

as follows:

• Molasses

• Enzymes & Chemicals

• Steam

• Water

• Fuel

• Power etc.

Page 19: PRE - FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...Based Distillery at Village Bhadson, Tehsil Indri, District Karnal (Haryana). Environmental Clearance for

Proposed installation of Unit II – 60 KLPD Molasses based Ethanol Plant alongwith 2 MW Co-generation Power Plant in Existing

Distillery Plant

At Village Bhadson, Umri Road, Tehsil Indri, District Karnal (Haryana)

Pre - feasibility Report

M/s. Piccadily Agro Industries Limited 19

Details regarding quantity of raw materials required their source along with distance &

mode of transportation for proposed project are given in Table below.

Table 2

RAW MATERIAL REQUIREMENT FOR MOLASSES BASED DISTILLERY

S.

No.

Particulars Total

Requirement

Source and mode of transportation

1. Molasses 282 to 300 MT/day Own sugar mills through pipelines/

road

2. Chemicals

Sodium Hydroxide (Caustic) 600 kg/day Nearby market

NH2-CO- NH2 (Nutrients) 50 kg/day

Enzymes As per

requirement

Antifoam Agent 100 Kg/day

Yeast (Active Dry Yeast/Distiller’s

Yeast)

Own Propagation

(b) Fuel Requirement

S. No. Fuel

Total requirement for proposed 25 TPH Boiler

Source

1 Biogas 32000m3/day Own plant through pipelines

2 Bagasse 84 ton/day Own plant through conveyor belt

Rice Husk 100 Ton/Day Nearby area

Note: 10 - 15% Auxiliary Fuel will be used such as Coal.

(viii) Resources optimization/ recycling and reuse envisaged in the project, if any, should be

briefly outlined.

Water as a resource will be recycled at each possible step of the process and latest

technology and methodology will be adopted to conserve and reuse the resources.

(ix) Availability of water it’s source, energy /power requirement and source should be given.

(a) Water Requirement and Source

Total fresh water requirement for proposed 60 KLPD Ethanol Plant will be 526 KLPD.

Source of Water: Ground Water

Page 20: PRE - FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...Based Distillery at Village Bhadson, Tehsil Indri, District Karnal (Haryana). Environmental Clearance for

Proposed installation of Unit II – 60 KLPD Molasses based Ethanol Plant alongwith 2 MW Co-generation Power Plant in Existing

Distillery Plant

At Village Bhadson, Umri Road, Tehsil Indri, District Karnal (Haryana)

Pre - feasibility Report

M/s. Piccadily Agro Industries Limited 20

TABLE – 3 (A)

TOTAL WATER INPUT

S. No Section Water quantity (KLD)

1 Process Water in Fermentation 455

2 DM Water for RS Dilution 575

3 DM Water for Boiler Feed 480

4 Soft Water for analyzer flash tank 104

5 Soft Water for Make for vacuum pump and others 30

6 Soft water makeup for cooling tower 290

7 Water in Molasses 56

8 Other Domestic Use (Provisional) 10

9 Miscellaneous Washing (Provisional) 10

TOTAL WATER INPUT 2010

TABLE – 3 (B)

TOTAL WATER OUTPUT

S. NO SECTION Water quantity (KLD)

1 Steam Condensate 364

2 Water in Spent wash 590

3 Spent lees(rectifier) 575

4 Spent Lees ( Pre-rectifier) 76

5 CT Evaporation & Blowdown 290

6 Domestic Consumption 10

7 Boiler Blowdown 65

8 Vacuum Pump Sealing/Purge 30

9 Miscellaneous Washing (provisional) 10

TOTAL WATER OUTPUT 2010

TABLE – 3 (C)

RECYCLING & UTILIZING STREAM

S. No. SECTION Water quantity (KLD)

1 Lees recycle for RS dilution 495

2 Steam Condensate recycle for boiler 364

3 Spent lees(Rect) cooling tower Make up 80

4 Process condensate recycle to process& CT 520

5 Vacuum Pump water recirculation 25

TOTAL RECYCLING/RE-UTILIZATION OF WATER PER DAY 1484

TOTAL FRESH WATER INPUT 526

� Hence, fresh water Requirement is 526 KLD

� Water requirement for first run would be 2010 KLD

Page 21: PRE - FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...Based Distillery at Village Bhadson, Tehsil Indri, District Karnal (Haryana). Environmental Clearance for

Proposed installation of Unit II – 60 KLPD Molasses based Ethanol Plant alongwith 2 MW Co-generation Power Plant in Existing

Distillery Plant

At Village Bhadson, Umri Road, Tehsil Indri, District Karnal (Haryana)

Pre - feasibility Report

M/s. Piccadily Agro Industries Limited 21

Figure 5: Water Balance of 60 KLPD Molasses Based Ethanol Plant

Page 22: PRE - FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...Based Distillery at Village Bhadson, Tehsil Indri, District Karnal (Haryana). Environmental Clearance for

Proposed installation of Unit II – 60 KLPD Molasses based Ethanol Plant alongwith 2 MW Co-generation Power Plant in Existing

Distillery Plant

At Village Bhadson, Umri Road, Tehsil Indri, District Karnal (Haryana)

Pre - feasibility Report

M/s. Piccadily Agro Industries Limited 22

(b) Power Requirement and Source

The total power requirement of the plant will be 1.2 MW which will be sourced from proposed

2.0 MW Co-Generation Power Plant.

(c) Steam Requirement

The total steam requirement of the plant will be 18.5 TPH. The source will be proposed 25 TPH

boilers.

The steam requirement for different purposes is given below:

TABLE – 4

STEAM REQUIREMENT

S. No. Purpose Steam Required (TPH)

1. Multi-pressure Distillation 8.5

2. Multi Effect Evaporator 8.0

3. Boiler Deaeration 2.0

Total 18.5

(d) Boiler Details

One Boiler with 25 TPH capacity is proposed to be installed. Others details regarding this are

mentioned in the table given below

TABLE – 5 BOILER DETAILS

S. No. Details Proposed

1. Type of Fuel Bagasse/Rice Husk/Coal and Biogas

2. Capacity of Boiler 25 TPH

3. Stack Height 51 m

4. Pollution Control Equipment Measures ESP/Bag Filter

(e) Details regarding the D.G. Sets

1 D.G. sets of 500 KVA will be installed for the power backup. Details regarding the D.G. Sets

are mentioned in the table given below:

TABLE – 6 DETAILS REGARDING THE D.G.SETS

S. No. Details

1. Type of Fuel HSD

2. Capacity 500 KVA

3. Stack Height (above roof level) As per CPCB/SPCB norms

4. Pollution Control Equipment Measures Adequate stack height/ Acoustic

Page 23: PRE - FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...Based Distillery at Village Bhadson, Tehsil Indri, District Karnal (Haryana). Environmental Clearance for

Proposed installation of Unit II – 60 KLPD Molasses based Ethanol Plant alongwith 2 MW Co-generation Power Plant in Existing

Distillery Plant

At Village Bhadson, Umri Road, Tehsil Indri, District Karnal (Haryana)

Pre - feasibility Report

M/s. Piccadily Agro Industries Limited 23

(x) Quantity of waste to be generated (liquid and solid) and scheme for their

management/disposal

o The project will be based on “Zero Effluent Discharge”.

o Spent wash generated during Molasses operation will be concentrated in Multi-effect

evaporator and then used for Bio-composting.

o Process condensate from MEE will be treated and recycled back in the process.

o Record of wastewater returned back to process for utilization in Fermentation/cooling

tower and to gardening will be kept.

o The sewage generated from the sanitary blocks is being/will be treated in septic tanks

and applied on to soak pits and used for irrigation.

o Spent Wash generated during the process will be first treated in Bio-Digester (Bio-

Methanation) and after that will be concentrated in Multi-effect evaporator and

concentrate is used for bio composting.

o Ash from the Boiler will be used in bio-composting & also given to nearby brick

manufacturers.

o Yeast sludge & Digesters sludge will be finally disposed as Mixing with Press Mud.

o The company will utilize the spent wash for manufacturing bio-compost within the

premises, with proper labelling and marketing of the finished compost, in sealed bags,

bearing the name and seal of our industry and the composition of the bio-compost.

o The company will not sell compost in open tractors/ trolleys.

o Used oil & grease generated from plant machinery / Gear boxes & D.G. Set is being / will

be partly used in oiling & greasing as lubrication of external parts of machinery & partly is

being / will be sold to the CPCB authorized recycler.

4.0 SITE ANALYSIS

(i) Connectivity

The plant site is located about at Bhadson Village; umri road, block Indri, Dist Karnal,

Haryana. The plant site is well connected to NH 1 (Approx 6 km in SW direction from

the plant site). Nearest town/city to the plant site is Kurukshetra (~ 12 km in NW

direction) & Karnal District Headquarter (~ 25 km in South direction). Nearest railway

station is Nilokheri Railway Station (~ 9 km in SW direction) & Kurukshetra Railway

Station (~ 12 km in NW direction) and nearest airport is Chandigarh Airport, which is ~

88 km in NNW direction from the plant site. The site is suitably located with respect to

availability of raw material, water, road network, skilled/semi skilled/unskilled and

professional manpower etc. All communication facilities such as telephone, telefax &

internet are available in the vicinity of the plant site.

Page 24: PRE - FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...Based Distillery at Village Bhadson, Tehsil Indri, District Karnal (Haryana). Environmental Clearance for

Proposed installation of Unit II – 60 KLPD Molasses based Ethanol Plant alongwith 2 MW Co-generation Power Plant in Existing

Distillery Plant

At Village Bhadson, Umri Road, Tehsil Indri, District Karnal (Haryana)

Pre - feasibility Report

M/s. Piccadily Agro Industries Limited 24

(ii) Land from Land use and Land ownership

Total plant area is 70 acres/ 28.32 ha. Since, the proposed installation of Unit II will be

done within the existing plant premises, thus, no additional land is required. Hence,

land ownership will be considered as Industrial type.

(iii) Topography

The topography of the area is almost flat.

(iv) Existing land use pattern (agriculture, non-agriculture, forest, water bodies (including

area under CRZ)), shortest distances from the periphery of the project to periphery of

the forests, national park, wild life sanctuary, eco sensitive areas, water bodies

(distance from the HFL of the river), CRZ. In case of notified industrial area, a copy of

the Gazette notification should be given

Environmental Settings of the Area

S. NO. PARTICULARS DETAILS

1. Nearest Village Bir Majra (~ 1.0 km in NW direction)

2. Nearest Town & City Town - Kurukshetra (~ 12 km in NW direction)

Karnal District Headquarter (~ 25 km in South direction)

3. Nearest National Highway / State

Highway

NH-1 (~ 6 km in WSW direction)

4. Nearest Railway station Nilokheri Railway Station (~ 9 km in SW direction)

Kurukshetra Railway Station (~ 12 km in NW direction)

5. Nearest Airport Chandigarh (~ 88 km in NNW direction)

6. National Parks, Wild Life

Sanctuaries, Biosphere Reserves,

Tiger/ Elephant Reserves, Wildlife

Corridors etc. within 10 km radius

No National Park, Wild Life Sanctuary, Biosphere Reserve,

Tiger / Elephant Reserve, Wildlife Corridors etc. falls

within 10 km radius of the plant site.

7. Reserved Forests (RF) / Protected

Forests (PF) etc. within 10 Km.

radius

Bir Seonti Reserved Forest (~7.5 km in North)

No Protected Forest falls within 10 km radius study area.

8. River / Water Body (within 10 km

radius)

• Chautang Nadi (~2.5 km in West direction)

• Sirsa Branch Canal (~ 3.0 km in South direction)

• Khand Nala (~ 7.5 km in NNW direction)

• Western Yamuna Canal (~ 5.5 km in SW direction)

9. Soil Type Sandy Loams

10. Seismic Zone Zone - III [as per IS 1893 (Part-I): 2002]

(v) Existing Infrastructure

Total plant area is about 70 Acres/28.3 ha. Proposed installation of Unit II will be done

within the existing plant premises.

Page 25: PRE - FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...Based Distillery at Village Bhadson, Tehsil Indri, District Karnal (Haryana). Environmental Clearance for

Proposed installation of Unit II – 60 KLPD Molasses based Ethanol Plant alongwith 2 MW Co-generation Power Plant in Existing

Distillery Plant

At Village Bhadson, Umri Road, Tehsil Indri, District Karnal (Haryana)

Pre - feasibility Report

M/s. Piccadily Agro Industries Limited 25

(vi) Soil classification

The soils in Gharaunda and SE half of Karnal blocks are young, stratified with no

profile development. They are sandy to fine sandy loams. The soils in SE half of

Nilokheri, SW extremity of Karnal block touching Nilokheri, eastern portion of

Nissang, Western half of Gharaunda block are heavily textured varying from sandy

loam at the surface to clayey loam at about one meter depth.

(vii) Climatic data from secondary sources

The climate of the district is characterized by the dryness of the air with an intensely

hot summer and a cold winter. The year may be divided in to four seasons. The cold

season starts by late November and extends to the middle of March. It is followed

by hot season which continues to the end of June when the southwest monsoon

arrives over the district. July to September is the southwest monsoon season. The

post monsoon season period is from October to December.

The normal annual rainfall of the district, based on the record for the period 1978-

2005 is 696mm recorded in 33 rainy days in a year. About 82.39% of the annual

rainfall is recorded during the southwest monsoon from June-September. August is

the wettest month of the year with an average of 8.4 rainy days and 214 mm rainfall.

During the period 1978-2005, deficient to scanty rainfall was recorded in 10 years.

Maximum rainfall of 1404 mm and minimum rainfall of 255 mm were observed in the

years 1998 and 1987 respectively.

(viii) Social Infrastructure available

Nearest habitation is at Bir Majra village. The nearest town is Kurukshetra, which is

approx. 12 km distance from the plant site. The nearest major city is Karnal which is

District Headquarter also and is about 25 km from the plant site.

At Kurukshetra Town & Karnal City schools, Hospital, dispensaries, colleges, places of

worship, Railway station, Markets & other facility etc are available. Electrical power

supply in most of surrounding villages is available.

Telephone, Medical facilities are available in the nearby towns. Almost all the

villages in the buffer zone are electrified. L.T. power is being supplied for drawing

water from a large number of tube wells sunk around the important village of the

buffer zone, for irrigation purpose. Most of the tanks and ponds as well as the river

water are being utilized for irrigation.

Page 26: PRE - FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...Based Distillery at Village Bhadson, Tehsil Indri, District Karnal (Haryana). Environmental Clearance for

Proposed installation of Unit II – 60 KLPD Molasses based Ethanol Plant alongwith 2 MW Co-generation Power Plant in Existing

Distillery Plant

At Village Bhadson, Umri Road, Tehsil Indri, District Karnal (Haryana)

Pre - feasibility Report

M/s. Piccadily Agro Industries Limited 26

5.0 PLANNING BRIEF

(i) Planning Concept (type of industries, facilities, transportation etc.) Town and country

Planning/ Development authority classification.

The existing unit is Distillery industry. Transportation of raw material and final product

is being / will be done via existing road and cement concrete road has been developed

within the existing plant premises.

(ii) Population Projection

M/s Piccadily Agro Industries Limited has also organised various activities in nearby

villages under corporate social responsibility (CSR) programme which leads to better

living standards of villagers.

(iii) Land use planning (breakup along with green belt etc)

Total Plant area is 70 Acres/28.3 ha. This project is for proposed installation of Unit II

which will be done within the existing plant premises. No additional land will be

required. About 33 % of the total project area is being/will be covered under green belt

& plantation in order to reduce dust & noise pollution levels & to increase aesthetic

beauty of the area.

(iv) Assessment of infrastructure demand (Physical & Social)

Piccadily Agro Industries Limited has assessed the demand of infrastructure (Physical

& Social) in nearby area of the plant site and development activities are being

undertaken under corporate social responsibilities program for rural development

initiatives for the upliftment of the nearby communities from time to time.

(v) Amenities/Facilities

Piccadily Agro Industries Limited has developed and will further develop the

Amenities/Facilities in nearby area of the Plant site as per requirement of local people

of the nearby area under corporate social responsibilities programs.

6.0 PROPOSED INFRASTRUCTURE

(i) Industrial Area (Processing Area)

No additional infrastructure will be required for the project as the project is of proposed

installation of Unit II 60 KLPD Ethanol Plant and is already set up in the existing plant

premises.

(ii) Residential area (Non Processing area)

No residential area is envisaged. The local labor will be preferred to provide employment

opportunities.

Page 27: PRE - FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...Based Distillery at Village Bhadson, Tehsil Indri, District Karnal (Haryana). Environmental Clearance for

Proposed installation of Unit II – 60 KLPD Molasses based Ethanol Plant alongwith 2 MW Co-generation Power Plant in Existing

Distillery Plant

At Village Bhadson, Umri Road, Tehsil Indri, District Karnal (Haryana)

Pre - feasibility Report

M/s. Piccadily Agro Industries Limited 27

(iii) Green Belt

Out of the total plant area i.e. 70 Acres/28.3 ha, 23 acres/9.3 ha (~33%) has already been

developed under greenbelt / plantation area. The same will be maintained in order to

reduce dust & noise pollution levels & to increase aesthetic beauty of the area.

(iv) Social Infrastructure

The project has resulted in growth of the surrounding areas by increased direct and

indirect employment opportunities in the region including ancillary development and

supporting infrastructure.

(v) Connectivity

The site is well connected with communication facilities like telephone, fax, and wireless

as such, no constraints are envisaged in this aspect as the Tehsil and District headquarters

are near to the site.

(vi) Drinking Water

5 m3/ day water will be required for drinking purpose which will be sourced from Ground

Water.

(vii) Sewage Treatment System

The sewage generated from the sanitary blocks will be treated via soak pit. Treated water

will be utilized in process, greenbelt development & dust suppression.

(viii) Industrial Waste management

The Molasses based Ethanol Plant will be based on “ZERO DISCHARGE”.

(ix) Solid Waste Management

� Spent Wash generated during the process, will be first treated in Bio-Digester (Bio-

Methanation) and after that will be concentrated in Multi-effect evaporator and

concentrate is used for bio composting.

� Ash from the Boiler will be used in bio-composting & also given to nearby brick

manufacturers.

� Yeast sludge & Digesters sludge is being/will be finally disposed as Mixing with Press

Mud.

(x) Power requirement and source

The total power requirement of the plant will be 1.2 MW which will be sourced from

proposed 2.0 MW Co-Generation Power Plant & & D.G Sets (for emergency).

Page 28: PRE - FEASIBILITY REPORTenvironmentclearance.nic.in/writereaddata/Online/...Based Distillery at Village Bhadson, Tehsil Indri, District Karnal (Haryana). Environmental Clearance for

Proposed installation of Unit II – 60 KLPD Molasses based Ethanol Plant alongwith 2 MW Co-generation Power Plant in Existing

Distillery Plant

At Village Bhadson, Umri Road, Tehsil Indri, District Karnal (Haryana)

Pre - feasibility Report

M/s. Piccadily Agro Industries Limited 28

7.0 REHABILITATION AND RESETTLEMENT (R & R) PLAN

(i) Policy to be adopted (Central/State) in respect of the project affected persons including

home oustees, land oustees and landless labourers (a brief outline to be given).

The proposal is for installation of Unit II – 60 KLPD Molasses based Ethanol Plant which

will be done within the existing plant premises. No additional land is required. Therefore

there will not be displacement of people and hence Rehabilitation & Resettlement is not

applicable.

8.0 PROJECT SCHEDULE AND COST ESTIMATES

(i) Likely date of start of construction and likely date of completion (time schedule for the

project to be given).

The project will start only after obtaining Environmental Clearance and all other required

clearance and will complete within 2 years of commencement.

(ii) Estimated project cost along with analysis in term of economic viability of the project.

� Total cost of the Project: Rs. 47.0 Crores

� Cost for Environment Protection Measures:

� Capital Cost: Rs. 10 Crores

� Recurring Cost/annum: Rs. 1.0 Crores/annum

9.0 ANALYSIS OF PROPOSAL

(i) Financial and social benefits with special emphasis on the benefit to the local people

including tribal population, if any, in the area.

Proposed project will result in growth of the surrounding areas by increasing direct and

indirect employment opportunities in the region including ancillary development and

supporting infrastructure. Special emphasis on Financial and Social benefits will be given

to the local people including tribal population, if any, in the area.

Development of social amenities will be in the form of medical facilities, education to

underprivileged and creation of self help groups.

Haryana state will get revenues in terms of taxes and local people will get direct &

indirect employment. Business opportunities for local community will be available like

transport of alcohol to market, fly ash transport to Brick manufactures, maintenance &

house-keeping contract work etc.