Upload
others
View
1
Download
0
Embed Size (px)
Citation preview
Pre-Feasibility Report
Gare Palma Sector-II Coal Mine (Mand Raigarh Coalfield) at Raigarh (D), Chhattisgarh (S) by MAHAGENCO
RamkyEnviro Engineers Ltd., Hyderabad
Table of Contents
Chapter Contents Page
No.
1 Executive Summary 1
2 Introduction of the Project 2
2.1 Identification of Project and Project proponent 2
2.2 Brief Description of nature of the project 3
2.3 Need for the project and its importance to the Country and or Region 3
2.4 Domestic and Export Market 3
2.5 Employment Generation (Direct and Indirect) due to the Project 3
3 Project Description 3
3.1 Type of the project including interlinked and interdependent projects 3
3.2 Location 4
3.3 Details of alternative sites 8
3.4 Size or Magnitude of Operation 8
3.5 Project Discription and Project Details 8
3.5.1 Sequence of Opencast mining 9
3.5.2 Sequence of Underground Mining 12
3.6 Availability of water its source, Energy/ Power Requirement and Source
12
3.6.1 Water Source 12
3.6.2 Energy/Power Source 13
3.7 Quantity of Wastes Generated (Liquid and Solid) and Scheme for their Management /Disposal
13
3.8 Schematic Representations of the Feasibility which give Information of EIA Purpose
14
4 Site Analysis 14
4.1 Connectivity 14
4.2 Topography 14
4.3 Existing Land Use Pattern 15
4.4 Existing Infrastructure 15
4.5 Soil Classification 16
4.6 Meteorological Data 16
4.6.1 Climate 16
4.6.2 Temperature 16
4.6.3 Rainfall 16
4.6.4 Wind Velocity and Wind Direction 16
4.6.5 Relative humidity 17
4.7 Social Infrastructure Available 17
5 Planning Brief 17
5.1 Planning Concept 17
5.2 Population Projection 18
5.3 Land Use Planning 18
5.4 Assessment of Infrastructure Demand 20
5.5 Amenities/ Facilities 20
6 Proposed Infrastructure 20
6.1 Industrial Area 20
6.2 Residential Area 20
6.3 Green Belt 20
6.4 Social Infrastructure 20
6.5 Connectivity (Traffic and transportation Road/Rail/Metro/Water ways etc,)
20
Gare Palma Sector-II Coal Mine (Mand Raigarh Coalfield) at Raigarh (D), Chhattisgarh (S) by MAHAGENCO
RamkyEnviro Engineers Ltd., Hyderabad
6.5.1 Availability of Roads 20
6.5.2 Nearest Railway station 20
6.5.3 Nearest Sea Port 21
6.5.4 Nearest Airport 21
6.6 Water Management 21
6.7 Sewerage System 21
6.8 Solid Waste Management 21
6.9 Energy/Power Source 22
7 Rehabilitation and Resettlement (R & R) Plan 22
8 Project Schedule and Cost Estimation 22
8.1 Likely Date of Start and Date of Completion 22
8.2 Cost Estimation of the Project 22
9 Analysis of Proposal 23
9.1 Socio-economic Benefits 23
List of Tables
Table
No
Contents Pg. No
2.1 Details of End Use Plants 3
3.1 Overall Reconciliation of Reserves in the Block as per Geological Report
8
3.2 Mineable reserves 9
3.3 Land used for Mining purposes (Ultimate land use pattern) 9
3.4 Waste Generation in MCum 13
4.1 Existing land use details of total and applied mining Lease area (Ha) 15
5.1 Overall Reconciliation of Reserves in the Block as per GR 18
5.2 Land use plan during mining (Ha) 19
8.1 Total Estimated Capital Investment 22
List of Figures
Figure No Contents Pg. No
3.1 Index Map Showing the Project Site 5
3.2 Topographical Map of the Area site 6
3.3 Key plan of the site 7
Gare Palma Sector-II Coal Mine (Mand Raigarh Coalfield) at Raigarh (D), Chhattisgarh (S) by MAHAGENCO
RamkyEnviro Engineers Ltd., Hyderabad 1
Pre-Feasibility Report
1. Executive Summary
S.No. Description Details
1. Name of the Project Gare Palma Sector -II Coal Mine (Block)
2. Name and Address of the
Applicant
(present & permanent
address)
Maharashtra State Power Generation Company LTD.,
(MSPGCL), “Prakashgad”
Plot No. G-9, Anant Kanekar Marg, Bandra (East),
Mumbai, Maharashtra-400051.
3. Location of the Mine The mine is located in Bhalumura, Chitwahi,
Dholnara, Dholesara, Gare, Jhinkabahal, Kunjemura,
Libra, Murogaon, Pata, Radopali, Saraitola, Sarasmal,
Tihlirampur villages under Tamnar Tehsil in Raigarh
District, Chhattisgarh State.
The Mine lease area is 25.83 Sq.Km (2583.48 Ha)
Coordinates of the Mine Lease area are
Latitude 22°06'24.215"N to 22°10'49.891"N
Longitude 83°26'15.433"E to 83°31'12.632"E
4. Production/Estimated
Reserves
Capacity: 23.60 MTPA (OC-22.0 MTPA + UG-1.6
MTPA) with peak capacity of OC will be 23.6 MTPA
before the UG becomes operational.
Geological Reserve : Total:1059.29 MT
O/C : 736.10 MT, U/G:323.19 MT
5. Total area reserved for
Mining
2583.48 Ha
6. Total Water requirement &
Source
The total water requirement of 1995 m3/day for the
mine, residential colony after considering the reuse
of 80% of water reclaimed from colony STP.
The water requirement during initial 3 years for
construction and of mine operation is proposed to
be sourced from Kelo River or Bore Wells.
Subsequently after 3 years onwards Industrial water
from mine sump and settling pond would be used till
the end of life of the mine.Groundwater will be
utilized for drinking purposes. The same will be
drawn from the bore wells.
7. Working hours Three shifts operation with 8 hour shift has been
planned
8. Manpower [Operation] 3400 (Underground + Open cast)
9. Estimated Cost of the
Project
Capital cost: Rs.7642 Crores for mining period of 30
Years
10. Nearest Railway station,
Sea Port, Airport
Raigarh about 27 Km (SSW) on Mumbai-Howrah
main line of SE Railway, Gopalpur port at about 348
Km (SE),Raipur Airport about 207 Km (SW)
11. Existence of Public Road,
Railway Track nearby
Roads from Bajarmura to Ghargoda (approx 11.6 Km)
and Milupara to Tamnar (approx 3 Km) are passing
Gare Palma Sector-II Coal Mine (Mand Raigarh Coalfield) at Raigarh (D), Chhattisgarh (S) by MAHAGENCO
RamkyEnviro Engineers Ltd., Hyderabad 2
through the block.
12. Police station and other
facilities
Raigarhin South (26.22 Km) is having all facilities like
Police station, Fire station Hospital, Bank, Post
Office, School, Workshops etc.
2. Introduction of the project
2.1. Identification of Project and Project proponent
The Gare Palma Sector - II Coal Block lies in the eastern part of the Mand-Raigarh
coalfield inChhattisgarh state. Ministry of Coal, Govt. of India, has allotted this coal block
to Maharashtra State Power Generation Company Limited (MSPGCL) for their captive
consumption in their end use power plants.The block is fully explored but non-producing
one.
Gare Palma Sector - II Coal block was earlier allocated by Ministry of Coal jointly to Tamil
Nadu Electricity Board (TNEB) and Maharashtra State Mining Corporation Limited
(MSMC) on 2nd
August, 2008 under the Government dispensation route. TNEB and MSMC
formed a joint venture company by name “Maha Tamil Colliries Limited”.
The Supreme Court of India, vide its judgment dated 25th
August, 2014 read along with its
order dated September 24, 2014 had cancelled allotment of 204 coal blocks. Subsequent
to the Supreme Court Judgment, the Coal Mines (Special Provisions) Ordinance dated
24th
September, 2014 read with Coal Mines (Special Provision) Second Ordinance, 2014
were promulgated and the Coal Mines (Special Provisions) Rules, 2014 were framed for
auction and allotment of all blocks which were subject to cancellation pursuant to the
Supreme Court Judgment. The Gare Palma Sector - II Coal Mine also appeared in the list
of 204 coal blocks and accordingly, its allotment to the prior allottee namely “MahaTamil
Collieries Limited” was cancelled pursuant to Hon’ble Supreme Court’s Judgment.
Maharashtra State Power Generation Co Ltd. (hereinafter referred to as “The
Company”) has been incorporated under Indian Companies Act 1956 pursuant to
decision of Govt. of Maharashtra to reorganize Erstwhile Maharashtra State Electricity
Board (herein after referred to as “MSEB”). The said reorganization of the MSEB has been
done by Govt. of Maharashtra pursuant to Part XIII read with section 131 of The
Electricity Act 2003. Mahagenco has been incorporated on 31.5.2005 with The Registrar
of Companies, Maharashtra, and Mumbai and has obtained Certificate of
Commencement of Business on 15.09.2005. Mahagenco is engaged in the business of
generation and supply of Electricity and has been vested with generation assets, interest
in property, rights and liabilities of MSEB as per Gazette Notification dated 4th June 2005
issued by Industry, Energy and Labour Dept of Govt. of Maharashtra pursuant to section
131 of Electricity Act 2003.
Gare Palma Sector-II Coal Mine (Mand Raigarh Coalfield) at Raigarh (D), Chhattisgarh (S) by MAHAGENCO
RamkyEnviro Engineers Ltd., Hyderabad 3
2.2. Brief Description of nature of the project
The proposed project involves the mining of coal in an extent of 25.83 Sq.Km (2583.48
Ha) and falls in schedule 1(a) (i) Mining of Minerals of Category ‘A’.
2.3. Need for the project and its importance to the Country and or Region
It has recommended opening up new areas in order to reduce the stress/impact on
existing mining leases and this will also lead to exploring the mineral bodies using drilling
etc. Proper exploration of mineral resources will delineate the quality/quantity and help
to wrap up at the most suitable exploitation strategy with an eye on conserving the
mineral and reducing waste handling.
The coal produced in the Gare Palma Sector II coal mine will be transported to the
existing power palntsand other power plants of MAHAGENCO in Maharashtra.
2.4. Domestic and Export Market
Coal produced from this coal block shall be utilised in the power plants existing at three
locations in Maharashtra and details are given in Table 2.1.The total coal requirement for
already linked power plants as per allotment order and as per specific heat consumption
norms comes to 12.76 MTPA.The balance coal out of the total production of 23.6 MTPA
will be used for other thermal plants of Mahagenco.
Table 2.1
Details of End Use Plants
S. No Specified End Use Plants Address Configuration Capacity
1 Chandrapur Thermal
Power Station (Unit 8 & 9)
Nirman Bhavan, Urja
Nagar, Chandrapur,
Maharashtra
2x500 MW 1000 MW
2 Koradi Thermal Power
Station (Unit 8 & 9 &10)
Koradi Complex,
Chindwara Road,
Nagpur,
Maharashtra
3x660 MW 1980 MW
3 Parli Thermal Power
Station (Unit 8)
Taluka Parli,
Vaijnath, District -
Beed, Maharashtra
250 MW 250 MW
Total 3230 MW
2.5. Employment Generation (Direct and Indirect) due to the Project
The mining project will generate direct& indirect employment. About 3400 people will
get direct employment.
3. ProjectDiscription
3.1. Type of the project including interlinked and interdependent projects
The proposed project is for minig of coal. Lease area is 25.83 Sq.Km (2583.48 Ha) and it is
proposed to produce maximum of 23.6 MTPA (OC - 22.0 MTPA + UG - 1.6 MTPA) with
Gare Palma Sector-II Coal Mine (Mand Raigarh Coalfield) at Raigarh (D), Chhattisgarh (S) by MAHAGENCO
RamkyEnviro Engineers Ltd., Hyderabad 4
peak capacity of OC will be 23.6 MTPA before the UG becomes operational. The mining
lease area is situated at Bhalumura, Chitwahi, Dholnara, Dholesara, Gare, Jhinkabahal,
Kunjemura, Libra, Murogaon, Pata, Radopali, Saraitola, Sarasmal, Tihlirampur Villages,
under TamnarTaluk, inRaigarh District, Chhattisgarh.
No interlinked or Interdependent Project.
3.2. Location
District and State Raigarh, Chhattisgarh.
Taluka Tamnar
Village Bhalumura, Chitwahi, Dholnara, Dholesara, Gare,
Jhinkabahal, Kunjemura, Libra, Murogaon, Pata,
Radopali, Saraitola, Sarasmal, Tihlirampur
Area 25.83 Sq.Km (2583.48 Ha)
Ownership/Occupancy A combination of Govt. Land and Private land
Existence of Public Road,
Railway nearby
Roads from Bajarmura to Ghargoda (approx 11.6 Km)
and Milupara to Tamnar (approx 3 Km) are passing
through the block.
Toposheet no, Latitude &
Longitude
Topo Sheet No :F44L7, F44L8, F44L11, F44L12 (New)
Latitude - 22°06'24.215"N to 22°10'49.891"N
Longitude - 83°26'15.433"E to 83°31'12.632"E
Nearest Railway station, Sea
Port
Raigarh about 27 Km (SSW) on Mumbai-Howrah main
line of SE Railway,Gopalpur port at about 348Km
(SE),Raipur Airport about 207 Km (SW)
Police station and other
facilities
Raigarh in South (26.22 Km) is having all facilities like
Police station, Fire station Hospital, Bank, Post Office,
School, Workshops etc.
The index map of the site is given in Figure 3.1. The location map is shown with the 10
Km radius from the periphery of the Mining lease Area in Figure 3.2 and Key plan of the
site area in Figure 3.3.
The entire Mine Lease Area including 10 Km radiusarea falls in Survey of India (SOI)
Toposheet No. F44L7, F44L8, F44L11, F44L12 (New).
Gare Palma Sector-II Coal Mine (Mand Raigarh Coalfield) at Raigarh (D), Chhattisgarh (S) by MAHAGENCO
RamkyEnviro Engineers Ltd., Hyderabad 5
Figure 3.1
Index Map Showing the Project Site
Gare Palma Sector-II Coal Mine (Mand Raigarh Coalfield) at Raigarh (D), Chhattisgarh (S) by MAHAGENCO
RamkyEnviro Engineers Ltd., Hyderabad 6
Figure 3.2
Topographical Map of the Area site
Gare Palma Sector-II Coal Mine (Mand Raigarh Coalfield) at Raigarh (D), Chhattisgarh (S) by MAHAGENCO
RamkyEnviro Engineers Ltd., Hyderabad 7
Figure 3.3
Key plan of the site
Gare Palma Sector-II Coal Mine (Mand Raigarh Coalfield) at Raigarh (D), Chhattisgarh (S) by MAHAGENCO
RamkyEnviro Engineers Ltd., Hyderabad 8
3.3. Details of alternative sites
The mining project is site specific project as it is related to occurance of Coal. Hence no
alternative sites were studied for purpose.
3.4. Size or Magnitude of Operation
The maximum coal production capacity of the proposed mine is 23.6 MTPA (OC - 22.0
MTPA + UG - 1.6 MTPA) with peak capacity of OC will be 23.6 MTPA before the UG
becomes operational. The mining operations have beenplanned to be started from rise
side (NW side) and to advance towards dipside (south side) and towards eastern side.
The block is surrounded by coal bearing areas on east and south direction.The strategy is
to divide the block into two parts along Kelo river. The twoparts are planned to be mined
in sequence by dovetailing. The western partwhich contains larger reserve will be mined
first by opening at the northwesternportion and advancing the operations towards dip
side (south side)and towards eastern side. It has been assumed that the mining
operations in the block will be started after rehabilitating the villages to the extent
required with time as well as getting the forestry clearance.
3.5. Project Discription and Project Details
Net geological reserves of coal as per Geological Report (GR) are 1059.29 MT comprising
of 736.10 MT (having thickness more than 0.5m proposed for OC mining down upto
seam-VI) and 323.19 MT (having thickness morethan 0.9m proposed for UG mining
below seam-VI). These reserves have been cross checked by Min Mec (RQP) and have
been found in order.
Table 3.1
Overall Reconciliation of Reserves in the Block as per Geological Report
S.No Particulars Reserves (MT)
1 Net geological reserves down upto
seam VI with minimum coal
thickness of >0.5m
> 0.9m thickness 682.57
736.10 <0.9m thickness but
>0.5m thickness 53.53
2 Net Geological Reserves below seam
VI with minimum coal thickness of
>0.9m
>1.5m thiickness 235.95
323.19 <1.5m but >0.9m
thickness 87.24
3 Grand Total 1059.29
The recoverable reserves will be 655.15 MT and the life of the OC mine will be about 29
years at annual production rate of22 MT as per the calendar programme of production.
The underground production is envisaged to start from 12th
year and end in77th
year.
Thus, including 3 years of construction (incline drivage and shaftsinking etc.) the life of
underground mine will be 69 years at production rateof 1.6 MTPA.
Gare Palma Sector-II Coal Mine (Mand Raigarh Coalfield) at Raigarh (D), Chhattisgarh (S) by MAHAGENCO
RamkyEnviro Engineers Ltd., Hyderabad 9
Table 3.2
Mineable reserves
S.No Particulars East West Total
1 Extractable reserves by OC (in East and
West Pits), Mt 47.19 505.98 553.18
2 Extractable reserves by UG (on East and
West side of Kelo river), Mt 95.60 6.37 101.97
Total, Mt 142.79 512.35 655.15
Table 3.3
Land used for Mining purposes (Ultimate land use pattern)
S.No Land Use At the end of 5
th
Year
At the end of OC
mining 29th
Year)
Post mine closure
(end of 80th
Year)
1 Excavation 380.70 2440.55 2440.55
2 Backfill 0.00 2248.77 2440.55
3 Void 380.70 191.78 0.00
4 Surface dump 380.00 0.00 0.00
5 Bund 5.20 5.20 5.20
6 Green belt 36.07 36.07 36.07
7 Top Soil Dump 60.00 0.00 0.00
8 Settling Pond 10.00 5.00 5.00
9 Road diversion 30.30 30.30 30.30
10 Facilities (West Part) 50.94 50.94 5.00
11 Facilities (East Part 38.54 0.00 0.00
12 Under Kelo river 15.42 15.42 15.42
13 Dismantling 0.00 0.00 45.94
14 Disturbed area 987.17 2583.48 2583.48
15 Undistrubed area 1596.31 0.00 0.00
Total 2583.48 2583.48 2583.48
3.5.1 Sequence of Opencast mining
The development works during the first year include making access road to sites of
mining activities, removing and rehabilitating the villages lying over the parts of the
block, obtaining 1st
set of mining equipment, diversion of local roads, top-soil removal,
driving box-cut and taking up other constructionactivities. The mode of transporting the
coal to TPP will be through rail fromthe nearest available siding.
Gare Palma Sector-II Coal Mine (Mand Raigarh Coalfield) at Raigarh (D), Chhattisgarh (S) by MAHAGENCO
RamkyEnviro Engineers Ltd., Hyderabad 10
The mining will begin with an aim of producing 11.80 MTPA from 5th
year and peak
capacity of 23.6 MTPA by 7th
year onwards from Open cast. The total coal production in
the first five years will be 20.30 MT. However, the productionfrom OC will be reduced
from 12th
year onwards with the onset of UG miningoperations such that the total
production from the mine is continued at 23.6MTPA matching with the requirements of
end use plants. The UG mine isproposed to achieve a peak capacity of 1.6 MT of coal
from the 15th
year onwards. Accordingly the production from the OC will be kept steady
at 22 MTPA from 15th
year onwards.
Year 1
The initial mine entry (haul road) will be aligned along SE direction for a distance of
about250m along the Inclines safety barrier after which it will reach 280 mRL at a
gradient of 1:16. The lowest bench to be worked in the 1st
year is 270 mRL which will be
approached by a ramp from 280 mRL bench.The depth of pit will be 10 m to 30 m which
will be worked in 1 to 3 benches.
Coal production during this year will be 0.25 MT. The corresponding OB (5 Mcum) will be
disposed off in Surface Dump over the coal bearing area (to be rehandaled later) in the
dip side of the West Pit. There will be no backfilling activities in this year and no activity
related to UG mining.
2nd
to 3rd
Year
The working benches will be advanced parallel to the already existing benches. The
length of the haul road will become 1072m along the safetybarrier of the incline landing
at 230 mRL. The lowermost levels will go downto about 215 mRL which will be
approached by ramps on the benches. Themining operations will reach the seam IX floor
during the 3rd
year.
Coalproduced in two years will be 4.55 MT @ 1.55 MT and 3.00 MT per yearrespectively
during 2nd
and 3rd
year. The related OB amounting to 44.10 M.Cum (14.10 M.Cum during
2nd
and 30.00 M.Cum during 3rd
year will be disposed of in Surface Dump in the dip side
over the coal bearing area ofWest Pit as during previous year. A maximum depth of
about 82m will beachieved by the end of the 3rd
year. There will be no activity related to
UG mining or coal production in this year.
4th
to 5th
Year
The working benches will be advanced parallel to the already existing benches in the
previous year. The length of the haul road will become 1558 m which will approach the
floor of the Seam VIII having exposed floor from 205 mRL to 230 mRL.
Gare Palma Sector-II Coal Mine (Mand Raigarh Coalfield) at Raigarh (D), Chhattisgarh (S) by MAHAGENCO
RamkyEnviro Engineers Ltd., Hyderabad 11
Coal produced in two years will be 15.50 MT @6.00 MT in 4th
year and 9.50 MT in 5th
year
respectively. The related OB (45 Mcum and 80.00 Mcum) will be disposed of in Surface
Dump proposed tobe located over the coal bearing area (to be rehandaled later) at a
distance of over 500 m from the uppermost bench. The area required for stacking top soil
will be 60 Ha for restricting the height to 6 m and the provision of 60 Ha has accordingly
been made beyond the surface dump. There will be noactivity related to UG mining or
coal production in this year.
6th
to 15th
Year.
The working benches will be advanced parallel to the already existing benches in the
previous years. The SW corner of the advancing working benches will just abut against
the batter of Kelo river.
Thus Coal produced in ten years (6th
to 15th
) will be 229.7 MT. The related OB willbe
disposed of in Surface Dump during a part of the 6th
year (47.07 M.Cum) after which total
OB will be accommodated within the backfill of the West Pit. As the decoaled area on the
northern side of the West Pit will berequired for backfilling the haul road will be shifted
and aligned just alongthe NE batter with its entry mouth located just at the SE end of the
inclinesafety barrier. The mouth will be located at 288 mRL. By the end of the 15th
year,
the length of the haul road will be 3.45 Km and it will reach thelowermost seam VI,
mineable by OC method.
The whole surface dump constructed during the 1st
6 years will be rehandaled and
backfilled into the void during the period from 7th
year and20th
year (both years
including).
16th
to 25th
Year.
The West Pit will be further advanced towards south direction till they abut against the
boundary of the West Pit of the block along the Kelo river. The East Pit will also be
opened from 20th
year.Therefore the coal production and OB generation will take place
from West Pit as well as from East pit from 20th
year onwards. All the OB generated from
West as well as East Pit will be backfilled into the West Pit decoaled area concurrent with
mining. The backfill area will advance upto and abutagainst the NW end batter of the
West Pit by the end of 25th
year. A 100 m high crown dump will have to be created above
the backfill area of West Pitto accommodate the OB generated in the past as will become
surplus from the backfill. The coal extracted upto the end of 25th
year will be 470 MT and
OB generated as 2463.1 MCum from both the pits.
26th
Year to End of OC Mining.
West Pit will finish in 26.5 years keeping intact the shaft pillar near the Kelo river as well
as the area under safety pillars of inclines and facilities located in the northern portion of
the West block.These areas will be mined after the mining of eastern part of the
Gare Palma Sector-II Coal Mine (Mand Raigarh Coalfield) at Raigarh (D), Chhattisgarh (S) by MAHAGENCO
RamkyEnviro Engineers Ltd., Hyderabad 12
blockduring the following years and will be retained till the coal from UG mining in the
western part is exhausted.
The total OB produced from both the Pits will be 2761.1 M.Cum (B) includingTop Soil
(14.64 MCum Bank or 16.84 MCum Loose). The TS will be accommodated over the dip
side coal bearing area of West Pit upto 15th
year end after which whatever TS will be
required to be preserves, it will bestacked over the backfilled area. The height of the TS
stack will be restricted to 6 m. Most of the area 2280.17 Ha in the post mineclosure stage
will be converted into an agriculture area.
3.5.2 Sequence of Underground Mining
Entries for underground mining
Two Inclines (one pair) having cross-section 4.8m x 3m and 2 shafts (Exhaust shaft-1 with
6m dia and Intake shaft-2 with 5m dia), all from surface to the lowermost seam-I
Combined are planned to be located in the NW portion of the western part of block. As
the two inclines are notadequate to supply the intake air to sustain the proposed 1.60
MTPA production, an additional Shaft-2 (dia 5m) as mentioned above, is proposed near
the inclines which can also be equipped with men/materials windingfacilities if required.
Both the inclines are started from a point located at 100m distance from theNW
boundary line of the block. The surface RL at the mouth of inclines will be 299 m AMSL
and the inclines will be driven at a gradient of 1:4.5 parallelto the NE block boundary at a
distance of 100m and 150m respectively.That means that the inclines will be 50m apart.
Coal Production
The production from one continuous miner will be 0.4 MTPA. There will be four
continuous miners will be operational at any time with following capacity. The main
drives in coal connecting to inclines, shafts as well as all dip drives will be also driven with
continuous miners. All the workable seamswill be developed and depillared with
continuous miners along with two shuttle cars in each set of continuous miner.
Accordingly, this mining plan has proposed 1.60 MTPA production from underground
mining which could be easily achieved.
3.6. Availability of water its source, Energy/ Power Requirementand Source
3.6.1 Water Source
The total water requirement will be 1995 cum/day. The requirement of water for dust
suppression, plantation,dump trucks washing workshop etc. is estimated to be about
1546 cum/day.The requirement of potable water for other site services i.e. Canteen,
Restshelter, Offices is estimated at about 1239 cum/day out of which 790 cum/day will
be reclaimed from the STP of colony.
The total water requirement will be met by bore-wells at site during the initial2-3 years
after which the mine water will be used after appropriatetreatment as required.
Gare Palma Sector-II Coal Mine (Mand Raigarh Coalfield) at Raigarh (D), Chhattisgarh (S) by MAHAGENCO
RamkyEnviro Engineers Ltd., Hyderabad 13
3.6.2 Energy/Power Source
The power will be fed to the project by a 11 KV overhead line from theexisting grid sub-
station at Tamnar.
3.7. Quantity of Wastes Generated (Liquid and Solid) and Scheme for their
Management /Disposal
Overburden consists predominantly sandstone with minor amount of
shale,carbonaceous shale, ungraded coal and thin coal bands (<1m in thickness).
There is only one surface dump proposed which will be located over the coal bearing
area in the southern portion of the West pit area. This dump will be spread over a
maximum area of 380 Ha (5th
year) and willaccommodate 218.81 MCum (B) OB waste.
The Dumping will start from 1st
year and continue upto 6th
year, however the exclusive
dumping into thissurface dump will be upto 5th
year after which part (47.07) of the OB
will bebackfilled in 6th
year.
The full height of the dump will be 90 m in 6th
year. No OB will be required to be disposed
over the surface dump after 6th
year.Backfilling will start from 6th
year of the project
operation with a quantity of 87.07 MCum (B). During 6th
year partial backfilling will be
done and then upto final year full backfilling will take place concurrent with mining.
The total topsoil generated will be 14.64 MCum (B) during the life of themine. Unutilised
part of the same will be stacked separately in a soil stackpile located beyond the surface
dump over the coal bearing area withinWest Pit area of 60.00 Ha (max). It will be used for
growing plants along the fringes of the site roads and reclamation of surface dump and
backfilled area.The top soil stockpile will be low height not exceeding 6 m and will
begrassed to retain fertility. Besides this, there would be temporary stacksnear the
excavation area and area to be reclaimed which will be made useof for concurrent filling
without bringing the topsoil to the soil stack near theOB dump.
Table 3.4
Waste Generation in MCum
Year Excavation
Area
Over burden
+ TS removel
Topsoil Generated
from Excavation
Pure OB from
Excavation
Progressive Progressive Progressive Progressive
Const. (0) 0.00 0.00 0.00 0.00
1st
Year 26.16 5.00 0.16 4.84
3rd
Year 103.81 129.97 0.62 43.48
5th
Year 250.73 152.60 1.50 123.50
10th
Year 718.67 675.00 4.31 670.69
Gare Palma Sector-II Coal Mine (Mand Raigarh Coalfield) at Raigarh (D), Chhattisgarh (S) by MAHAGENCO
RamkyEnviro Engineers Ltd., Hyderabad 14
15th
Year 647.69 624.00 3.88 620.11
20th
Year 202.79 495.00 1.22 493.78
25th
Year 322.57 495.00 1.94 493.06
Endof mine 29th
168.13 298.00 1.01 296.99
Closure plan 32nd
0.00 0.00 0.00 0.00
Total 2440.55 2874.57 14.64 2746.45
3.8. Schematic Representations of the Feasibility which give Information of EIA
Purpose
A Detailed schematic representation of the feasibility covering the purpose of EIA will be
given in the Environmental Impact Assessment report.
4. Site Analysis
4.1. Connectivity
Existence of Public
Road, Railway nearby
Roads from Bajarmura to Ghargoda (approx 11.6 Km) and
Milupara to Tamnar (approx 3 Km) are passing through the
block.
Nearest Railway
station, Sea Port,
Airport
Raigarh about 27 Km (SSW) on Mumbai-Howrah main line of
SE Railway, Gopalpur port at about 348 Km (SE),Raipur
Airport about 207 Km (SW)
Police station and other
facilities
Raigarhin South (26.22 Km) is having all facilities like Police
station, Fire station Hospital, Bank, Post Office, School,
Workshops etc.
4.2. Topography
The coal block is characterized by undulating and rolling topography, consisting of hills
interspersed with broad valleys. The general elevation of the ground ranges from 242 m
to 303 m above MSL. The slope is towards south. The hills are relict type and rise about
450 m above MSL. The southerly flowing perennial Mand River with its tributaries
constitute the main drainage of the area. The Kelo River, a tributary of Mahanadi, drains
the eastern part of the coal block.
The topography of Gare Palma Sector II is mostly covered by softer horizon and more
resistant sedimentary rocks stand out as ridges, rising as high as 580 m above MSL
(SilotPahar) in the north west and 600 m above MSL (MorgaPahar) in the north east. The
general ground elevation of the sector II area under investigation varies between 240 m
and 300 m above MSL. The minimum ground level is <246 mRL in the region north of
borehole MMT-131, located in the southern -eastern part of the block and maximum
ground elevation is 304.15 mRL at triangulation station T1/T1. The block exhibits
undulating topography. Kelo River flows from north to south through the south eastern
part of the block. A few ponds are present within the block.
Gare Palma Sector-II Coal Mine (Mand Raigarh Coalfield) at Raigarh (D), Chhattisgarh (S) by MAHAGENCO
RamkyEnviro Engineers Ltd., Hyderabad 15
4.3. Existing Land Use Pattern
The total area of 2583.48 Ha, covering part of the 14 villages is mostly in the form of
private, government and forest land. Summary of the existing land details as per revenue
and forest department records are given in Table 4.1
Table 4.1
Existing land use details of total and applied miningLease area (Ha)
S.
No
Village Private Land Govt. Land Total Area
(Private +
Govt. Land) Agricultu
re
Non
Agricultur
e
Total
Area
Popula
ted
Water
Body
Others Small/
Big
Trees
Total
Area
A. As per Revenue Departments Records
1 Tihlirampur 97.90 62.69 160.59 6.83 21.22 39.09 0 67.15 227.74
2 Dholnara 59.64 0 59.64 6.83 0.38 3.32 2.79 13.31 72.95
3 Murogaon 302.39 0 302.39 8.26 1.30 4.29 23.50 37.35 339.75
4 Libra 121.42 7.62 129.04 2.9 0.44 4.7 15.94 23.97 153.01
5 Kunjemura 199.72 0 199.72 14.22 13.6 8.31 30.17 66.3 266.01
6 Jhinkabahal 3.84 0 3.84 0 0 0 0 0 3.84
7 Radopali 351.68 0 351.68 8.34 5.9 19.96 0.12 34.31 385.99
8 Dolesara 20.75 0 20.75 0 0 1.24 0 1.24 21.99
9 Bhalumura 16.3 0 16.3 0 0 0.70 0.62 1.33 17.62
10 Sarasmal 56.87 9.16 66.03 0 1.33 3.56 15.24 20.13 86.16
11 Pata 316.06 13.17 329.23 13.31 5.53 14.47 15.33 48.64 377.87
12 Chitwahi 142.46 0 142.46 0.25 0.87 8.15 0 9.27 151.73
13 Gare 157.22 0 157.22 10.48 4.24 11.6 1.96 28.28 185.5
14 Saraitola 156.23 13.72 169.95 8.4 1.36 7.97 29.70 47.43 217.38
Total of A 2002.48 106.36 2108.84 79.82 56.17 127.36 135.37 398.71 2507.54
B. As per Forest Departments Record
Government Forest Land *75.94
Grand Total 2583.48
Note: *75.94 Ha of Protected Forest land and 135.37 Ha of Revenue Forest land is
present within the mine lease area, which needs to be diverted for mining purpose after
obtaining forestry clearance from the Ministry of Environment and Forest, Govt. of India
under the Forest (Conservation) Act 1980.
4.4. Existing Infrastructure
The proposed lease area is a virgin block and no mining has been undertaken so far. The
various temporary site services proposed to be constructed will be:
1. Office
2. Store
3. Workshop
4. Water Tank
5. First-Aid Center
6. Rest Shelters etc.,
Gare Palma Sector-II Coal Mine (Mand Raigarh Coalfield) at Raigarh (D), Chhattisgarh (S) by MAHAGENCO
RamkyEnviro Engineers Ltd., Hyderabad 16
4.5. Soil Clasification
Soil formation is mainly related to the parent rock material, surface relief, climate and
natural vegetation, animals, insects and man also play an important role in soil
formation. A major part of the block is covered by a thin layer of soil and alluvium
horizon. The weathering has affected all the strata below soil to varying extent. The
thickness of soil ranges from 0.50m to 15.00m. The entire area of Gare Palma sector-II
Coal Block is mostly covered with soil and at a few places only, outcrops of sandstone &
shale can be seen. The soil is silty clay in texture and red to pale brown in color.
4.6. Meterological Data
4.6.1. Climate
The climate of the study area is of subtropical type, and characterised byan oppressive
hot summer, a mild winter and well distributed rainfall duringthe south western
monsoon season. The year may be divided into fourseasons. The summer season lasts
from March to the middle of June, andthe period from June to September is the south
west monsoon season. October and November constitute the post monsoon season and
the coldseason is from December to February. The nearest meteorological stationof IMD
is at Raigarh.
4.6.2 Temperature
As per the monthly average of daily maximum and minimum temperatures for the period
1996 to 2005, collected from IMD Station, Raigarh, themonthly mean of minimum
temperatures ranges from 12.04°C in January to27.57°C in May. The monthly mean of
maximum temperature ranges from27.56°C in January to 42.08°C in May.
4.6.3 Rainfall
The rainfall does not show any cyclic occurrences and shows wide anderratic variations,
ranging from as low as 144.9 mm in 2004 to 1852.4 mm in2003. The average annual
rainfall for the period 1996 to 2005 was 1216.4mm. The monsoon season is spread over
the months from June toSeptember. However, the total rainfall as per IMD Raigarh is
1429.3 mm.
4.6.4 Wind Velocity and Wind Direction
The wind speed and direction for long term period from 1970-2000 havebeen studied
through the Windrose diagrams supplied by IMD, Raigarh, for8.30 hrs and 17.30 hrs
respectively. An observation of the morningWindrose shows that the predominant wind
direction is from NE between (October to April) and SW betweenMay to September.
As per the evening Windrose, the predominant wind direction is from NEbetween
October and January, NW between February to May and SWbetween June to September.
The general wind speed ranges form 1 to 5Kmphthroughout the year. However winds in
the speed ranging from 6-11Kmph and 12-19 Kmph also occur.
Gare Palma Sector-II Coal Mine (Mand Raigarh Coalfield) at Raigarh (D), Chhattisgarh (S) by MAHAGENCO
RamkyEnviro Engineers Ltd., Hyderabad 17
4.6.5 Relative humidity
The relative humidity varies from 22% in (April) to 78% (August) duringevening and 39%
(April) to 84 % (August) during morning.
4.7. Social Infrastructure Available
Raigarh- 26.22 Km (SW) is having all facilities like Police station, Fire station Hospital,
Bank, Post Office, School, Workshops etc.
5. Planning Brief
5.1. Planning Concept
While Considering, the available reserves, seam disposition, depth, availablestrike length
for opencast mining and feasibility to deploy large sizeequipment in opencast operation,
feasibility of simultaneous undergroundoperation, the optimum capacity of the mine has
been estimated at 23.6 MTPA. Hence the mine has been planned for a targeted
production of 23.6MTPA, out of which 22.0 MTPA (23 MTPA prior to start of UG
Operation) would come through opencast operation and 1.6 MTPA throughunderground.
It may be worthwhile to mention here that the earlier allotee ofthe coal block had also
submitted a mining plan to MOC in which the RQP had assessed the capacity as 23.6
MTPA as above.
Considering the simultaneous operation of OC and UG and that a lag is tobe maintained
for UG working, the target capacity through UG has beenfixed at 1.6 MTPA. The targeted
production through UG mining may bereviewed after 25 years with a view to increase the
production andproductivity based on the then available technology.
As per the practice in vogue for OC mine planning, the minimum coal seamthickness for
mining is adopted as 1m. However, in this specific case ahuge quantity of reserve (53.536
MT) falls in a thickness range between0.5m-0.9m. Giving due consideration to
conservation of resource, The RQP has calculated the Opencastable reserves by assuming
minimum miningseam thickness of upto 0.5m irrespective of the fact that mining of
suchthickness will require extra efforts as well as lower efficiency of equipment.However
the reserves mineable by underground method have beenassumed as upto a minimum
thickness of 1.5m, though the reserves oflower thicknesses have been mentioned
alongside.
The overall reconciliation of reserves in the block is as given in Table 5.1
Gare Palma Sector-II Coal Mine (Mand Raigarh Coalfield) at Raigarh (D), Chhattisgarh (S) by MAHAGENCO
RamkyEnviro Engineers Ltd., Hyderabad 18
Table 5.1
Overall Reconciliation of Reserves in the Block as per GR
S. No Particulars Reserves, MT
Reserves related to OC mining upto Seam VI
1 Net Geological Reserves of coal thickness >0.9mdown
upto seam VI
682.57
2 Net Geological Reserves of coal thickness >0.5m
but<0.9m down upto seam VI
53.54
3 Sub-Total – I (1+2) Net Geological Reserves down upto
seam VI with minimum coal thickness of >0.5m
736.11
Reserves related to UG mining below Seam VI
4 Net Geological Reserves of coal thickness >1.5mbelow
seam VI
235.95
5 Net Geological Reserves of coal thickness >0.9m to<1.5m
below seam VI
87.24
6 Sub-Total- I(4+5) Net Geological Reserves below seam
VI with minimum coal thickness of >0.9m
323.19
7 Grand Total of I & II (OC reserves of coal upto seam-VI
with thickness more than 0.5m and UG reserves of coal
below seam-VI with thickness more than 0.9m
1059.3
5.2. Population Projection
Due to proposed project around 3400 persons will be in the mining activity, they will be
mostly from nearby villages, only few people will be accommodated at the site such as
security persons and emergency staff in rest shelter.
5.3. Land Use Planning
The total land area of the block is required for Mining Lease. Therequirement for
additional land required for mining purpose for approachroad to the block and approach
to railway siding etc. will be assessed afterfinalisation of railway alignment passing
through Gare Palma Coalfield andconsidering limited availability of land, as the block is
surrounded by othercoal blocks. The colony will be located away from the block non
coalbearing area to be identified in consultation with local authorities. The ‘during-
mining’ stage land use is given in Table 5.2.
Gare Palma Sector-II Coal Mine (Mand Raigarh Coalfield) at Raigarh (D), Chhattisgarh (S) by MAHAGENCO
RamkyEnviro Engineers Ltd., Hyderabad 19
Table 5.2
Land use plan during mining (Ha)
Landuse At the end
of 5th
year
At the end
of 25th
year
At the end
OC mining
(29th
year)
OC Post
mine
closure 30th
to 32nd
year
End of OC
and UG
mining (77th
year)
Excavation 380.70 2272.42 2440.55 2440.55 2440.55
Backfill 0.00 1535.00 2248.77 2440.55 2440.55
Void 380.70 737.42 191.78 0.00 0.00
#Surface dump 380.00 0.00 0.00 0.00 0.00
Bund 5.20 5.20 5.20 5.20 5.20
Green Belt 36.07 36.07 36.07 36.07 36.07
*Top Soil Dump 60.00 0.00 0.00 0.00 0.00
##Settling Pond 10.00 5.00 5.00 5.00 5.00
<Road diversion 30.30 30.30 30.30 30.30 30.30
**Facilities (West
Part:CHP, Inclines,
Shaft Pit,Office,
Lamp
room,Attendance
Office, RestRoom,
Parking, First
aidroom, Sub
Station etc.)
50.94 50.94 50.94 50.94 5.00
Facilities (East
Part:Office,
Workshop,magazine
etc)
38.54 0.00 0.00 0.00 0.00
Under Kelo river 15.42 15.42 15.42 15.42 15.42
Dismantling 0.00 0.00 0.00 0.00 45.94
Disturbed area 987.17 2415.35 2583.48 2583.48 2583.48
Undisturbed 1596.31 168.13 0.00 0.00 0.00
Total 2583.48 2583.48 2583.48 2583.48 2583.48
* Top soil dump will be over the backfilled area towards the end of mine life.
** Main colony will be located away from the ML area.
# The OB dump lying over the coal bearing area will be fully rehandled andbackfilled by
20th year.
## The settling ponds in 5th
year will comprise of 5 Ha for mine water and 5 Ha for surface
dump but the later will not remain after 20th
year as surface dump willbe rehandaled
and become non-existent.
<Diverted road is for public use.
Gare Palma Sector-II Coal Mine (Mand Raigarh Coalfield) at Raigarh (D), Chhattisgarh (S) by MAHAGENCO
RamkyEnviro Engineers Ltd., Hyderabad 20
5.4. Assessment of Infrastructure Demand
It is obvious to have some of the essential infrastructures to facilitate the employees. For
this purpose it is planned to have office, store, first-aid center, rest shelter etc...
5.5. Amenities/ Facilities
All infrastructure facilities such as education, health facilities and other social facilities
are available at district headquarter due to which the proposed site is facilitated with
adequacy in amenities. As most of the workers are employed from the surrounding
villages, they would be using available medical facilities in the nearest primary health
center.
6. Proposed Infrastructure
6.1. Industrial Area
It is proposed to establish the temporary structures statutory building having the
facilities like Office, first aid center and rest shelter.
6.2. Residential Area
It is proposed to establish only some essential quarters (50% of the employees) within
the mine lease for the Mine Personnel to cater to essential services. Remaining persons
will be accommodated at a suitable site outside the mine lease area.
6.3. Green Belt
Total Unsued land area is 36.07 Ha which would be used for Plantation/Afforestation/
Future expansion.
The species going to be planted would be local species as these are having a better
chance of survival in this region.
6.4. Social Infrastructure
This Project is providing employment to local people directly and indirectly. Indirect
employers are shopkeepers, mechanic, drivers, transporters etc. The lessee will
responsible for providing better social infrastructure benefits such as drinking water,
health care measures, educational facilities, promotion of culture and religious activities
in surroundings.
6.5. Connectivity (Traffic and transportation Road/Rail/Metro/Water ways etc)
6.5.1. Availability of Roads
Roads from Bajarmura to Ghargoda (approx 11.6 Km) and Milupara to Tamnar (approx 3
Km) are passing through the block.
6.5.2. Nearest Railway station
Raigarh about 27 Km (SSW) on Mumbai-Howrah main line of SE Railway
Gare Palma Sector-II Coal Mine (Mand Raigarh Coalfield) at Raigarh (D), Chhattisgarh (S) by MAHAGENCO
RamkyEnviro Engineers Ltd., Hyderabad 21
6.5.3. Nearest Sea Port
Gopalpur port at about 348Km (SE)
6.5.4. Nearest Airport
Raipur Airport about 207 Km (SW)
6.6. Water Management
1995 m3/day water will be required for the mine, residential colony after considering the
reuse of 80% of water reclaimed from colony STP. The water requirement during initial 3
years for construction and of mine operation is proposed to be sourced from Kelo River
or Bore Well.Subsequently after 3 years onwards Industrial water from mine sump and
settling pond would be used till the end of life of the mine.
Groundwater will be utilized for drinking purposes. The same will be drawn from the
bore wells. Detailed hydro geological studies will be carried out to assess the availability
of requisite water for mine operation.
6.7. Sewerage System
Mine discharge: Mine effluent contains silt and coal particles, which will be treated in
two stages at primary sedimentation sump in mine floor and secondary sedimentation
sump at mine surface.The mine discharge, will be used to meet the requirement of
afforestation/plantation, dust suppression, firefighting, and other industrial, domestic
applications. Surplus water meeting the prescribed standards, if any, will be discharged
into nearby surface body.
Washery effluent: Waste water will be collected in slime ponds and circulated back into
the process. Zero effluent discharge will be practiced
Workshop effluent: The workshop effluent will be treated in a proper effluent treatment
plant. Oil and grease will be skimmed using oil trap and stored in leak proof containers
and will be sold to authorized vendors.
Domestic effluent: STP will be provided. Sludge after digestion will be used as manure /
compost.
6.8. Solid Waste Management
Mining waste will be dumped on non-coal bearing area as external dump and rest will be
backfilled as per Mining Plan. Retention wall of adequate dimensions will be constructed
at the base of external dumps. Garland drain and check dam will be made. Proper overall
slope angle will be maintained. Dumps will be gradually reclaimed and rehabilitated using
suitable plant species and grasses.
Gare Palma Sector-II Coal Mine (Mand Raigarh Coalfield) at Raigarh (D), Chhattisgarh (S) by MAHAGENCO
RamkyEnviro Engineers Ltd., Hyderabad 22
6.9. Energy/Power Source
The power will be fed to the project by 11 KV overhead lines from theexisting grid sub-
station at Tamnar.
7. Rehabilitation and Resettlement (R & R) Plan
The Policy of Govt. of Chhattisgarh for resettlement & rehabilitation of
displacedpersons/families, in case of mining projects, shall be followed. R&R Colonywill
be accordingly planned and established.
8. Project Schedule and Cost Estimation
8.1. Likely Date of Start and Date of Completion
The mining operations will be started after obtaining all necessary statutory clearances
from the required departments.
8.2. Cost Estimation of the Project
Capital cost: Rs. 7642 Crores (Approx for the mining period of 30 years).
Table 8.1
Total Estimated Capital Investment
S.No Particulars Total Estimated
Capital
Investment for
the Project
Rs. Crores
MDO’s
Estimated
Capital
Investment
Rs. Crores
MAHAGENCO’s
Estimated
Capital
Investment
Rs. Crores
1 Land Acquisation 1250 - 1250
2 Rehabilitation &
resettlement
434 324 110
3 Buildings
I Service Buildings 130 130 -
Ii Residential Buildings 69 69 -
4 Plant and Machinery
I HEMM 2743 2743 -
Ii CHP 643 643 -
Iii Other P&M 74 74 -
5 Furniture & Fittings 2 2 -
6 Railway Sidings 352 352 -
7 Vehicles 4 4 -
8 Exploration & GR Cost 43 43 -
9 Development
I Capital Outlay in mines 50 50 -
Gare Palma Sector-II Coal Mine (Mand Raigarh Coalfield) at Raigarh (D), Chhattisgarh (S) by MAHAGENCO
RamkyEnviro Engineers Ltd., Hyderabad 23
Ii Roads & Culverts 30 30 -
Iii Water Supply & Sewerage 4 4 -
Iv Diversion of road/
Transmission lines
20 20 -
10 Pre- Operative Expenses 40 40 -
11 Upfront Amount paid to
MOC
151 - 151
Sub Total (A) 6039 4528 1511
12 Coal Washery (B) 550 550 -
Sub Total (A+B) 6589 5078 1511
13 IDC 495 495 -
14 Contigencies (10%) 557 557 -
Total Estimated Capital Cost 7642 6130 1511
9 Analysis of Proposal
9.1 Socio-economic Benefits
As there will be displacement of 1679 families in all fourteen villages, a rehabilitation
programme is required. However, the land and home or bothoustees will be given
rehabilitation and resettlement benefits according tothe Govt. of Chhattisgarh Policies
and prevailing practice in industries in thevicinity. The detailed R&R plan is under
preparation. In addition to theprovisions of the CG R&R Policy 2007, as the proportion of
tribal familiesamong the land losers is significant and in view of project area falling
underscheduled V, a separate Tribal Development Plan (TDP) is essential forvulnerable
group. The company is in the process of making a Tribal Development Plan containing the
profile of community, livelihood pattern, aneed assessment for community development
and a specificcommunication program to engage with the community. The survey is
being done by Asian Institute of Sustainable Development Ranchi (Jharkhand).
The employment will be provided as per the provisions of the Policy of Govt.of
Chhattisgarh. Advisory Committee will be formed by Collector/ RevenueDivisional
Commissioner. The development in the area which ispredominantly backward, will
largely benefit the local population. Preferencewill be given to the local people for gainful
employment in the unskilled and semi-skilled categories as and when the need arises.
Similarly, Due to development activity in the rural and backward area, traders and private
enterprises will grow also in the region, which will provide indirectemployment to the
many local people. The company will arrange medical camps, sports competitions and
awareness programmes for the benefit of local population.