31
Social Monitoring Report This report has been submitted to ADB by the Wuhan Project Management Office and is made publicly available in accordance with ADB’s public communications policy (2005). It does not necessarily reflect the views of ADB. Project Number: 37597 July 2007 PRC: Wuhan Wastewater and Stormwater Management Project Prepared by Tongji University Shanghai, PRC For Wuhan Project Management Office

PRC: Wuhan Wastewater and Stormwater Management Project · Social Monitoring Report This report has been submitted to ADB by the Wuhan Project Management Office and is made publicly

  • Upload
    others

  • View
    0

  • Download
    0

Embed Size (px)

Citation preview

Page 1: PRC: Wuhan Wastewater and Stormwater Management Project · Social Monitoring Report This report has been submitted to ADB by the Wuhan Project Management Office and is made publicly

Social Monitoring Report

This report has been submitted to ADB by the Wuhan Project Management Office and is made publicly available in accordance with ADB’s public communications policy (2005). It does not necessarily reflect the views of ADB.

Project Number: 37597 July 2007

PRC: Wuhan Wastewater and Stormwater Management Project

Prepared by Tongji University

Shanghai, PRC

For Wuhan Project Management Office

Page 2: PRC: Wuhan Wastewater and Stormwater Management Project · Social Monitoring Report This report has been submitted to ADB by the Wuhan Project Management Office and is made publicly

Resettlement Monitoring and Evaluation Report(No.1)

1

Resettlement Monitoring and Evaluation Report

(No.1)

Wuhan Wastewater and Stormwater

Management Project

Supported by ADB (Loan No.:2240-PRC)

School of Economics and Management

Tongji Uniersity

Shanghai China

July, 2007

Page 3: PRC: Wuhan Wastewater and Stormwater Management Project · Social Monitoring Report This report has been submitted to ADB by the Wuhan Project Management Office and is made publicly

Resettlement Monitoring and Evaluation Report(No.1)

2

Monitoring and Evaluation Organization:

School of Economics and Management

Tongji University

Address:Siping Road 1239, Shanghai

Postcode: 200092

Page 4: PRC: Wuhan Wastewater and Stormwater Management Project · Social Monitoring Report This report has been submitted to ADB by the Wuhan Project Management Office and is made publicly

Resettlement Monitoring and Evaluation Report(No.1)

3

Monitoring and Evaluation Director: Wu Zongfa

Monitoring and Evaluation Personnel:Wu Zongfa, Tao Tao

Report Compiler: Wu Zongfa, Tao Tao

Page 5: PRC: Wuhan Wastewater and Stormwater Management Project · Social Monitoring Report This report has been submitted to ADB by the Wuhan Project Management Office and is made publicly

Resettlement Monitoring and Evaluation Report(No.1)

4

CONTENTS 1 GENERAL ........................................................................................................................1

2 MONITORING AND EVALUATION OF RESETTLEMENT........1

2.1 TARGET AND TASK...............................................................................................................1 2.2 PRINCIPAL INDICATORS OF MONITORING AND EVALUATION........................................2 2.3 SURVEY OF RESETTLERS’ LIVING STANDARDS...............................................................2 2.4 PUBLIC CONSULTATION ......................................................................................................2 2.5 RESETTLERS’ OPINIONS......................................................................................................3 2.6 OTHER INDICATORS TO BE MONITORED AND EVALUATED ...........................................3 2.7 MONITORING AND EVALUATION SCHEDULE ...................................................................3 2.8 APPROACHES OF INDEPENDENT MONITORING AND EVALUATION ...............................4

3 MONITORING OF RESETTLEMENT ORGANIZATIONS.........4

4 IMPLEMENTATION PROGRESS OF RESETTLEMENT.............5

4.1 THE WASTEWATER MANAGEMENT PROJECT ..................................................................5 4.2 THE STORM WATER MANAGEMENT PROJECT.................................................................6 4.3 UPDATED PROJECT PLAN ...................................................................................................8

5 RESETTLEMENT IMPLEMENTATION BY WJICC......................24

6 RESETTLEMENT IMPLEMENTATION BY WMDC......................24

7 CONCLUSION AND SUGGESTION............................................................25

7.1 CONCLUSION ......................................................................................................................25 7.2 SUGGESTION.......................................................................................................................26

Page 6: PRC: Wuhan Wastewater and Stormwater Management Project · Social Monitoring Report This report has been submitted to ADB by the Wuhan Project Management Office and is made publicly

Resettlement Monitoring and Evaluation Report(No.1)

1

1 General

Wuhan Wastewater and Storm Water Management Project comprises two components: (a) The Wastewater Management Project t comprises 5 sub-projects, which are: (1) Wuchang Erlangmiao WWTP Expansion and Upgrading Project; (2) Hanyang Nantaizi Lake WWTP Expansion and Collection System Project; (3) Hankou Huangpu Road WWTP Upgrading Project; (4) Caidian WWTP and Collection Systems Project; (5) Dongxihu Wastewater Collection Systems Project. (b) The Storm Water Management Project comprises 4 sub-projects, which are: (1) Yangsigang Pump Station and Storm Water Box Culvert Project (Yangsigang Sub-project); (2) Three Gates Connection Project (Three Gates Sub-project); (3) Changqing Pump Station Expansion Project (Changqing Sub-project); (4) Luojiagang Canal and Luojia Road Pump Station Expansion Project (Luojiagang Sub-project).

Wuhan ADB Financed Wastewater and Storm Water Management Project Resettlement Plan was

approved by Asian Development Bank in 2006.

2 Monitoring and Evaluation of Resettlement

2.1 Target and Task

To make periodical monitoring and evaluation on land acquisition and resettlement in order to make sure that resettlement target is realized. To propose evaluation opinions and suggestions on the holistic resettlement and rehabilitation status of affected people’s living level through exterior independent monitoring and evaluation so that project administration department can get warnings in advance. To propose opinions and suggestions on problems appeared in resettlement.

School of Economics and Management, Tongji University, is retained to be the exterior

independent monitoring and evaluation unit. School of Economics and Management, Tongji

University, will supervise and evaluate the resettlement work by investigation into affected

people’s living level according to related rules, monitor the implementation of the resettlement

policy, investigate the progress of the resettlement, monitor and evaluate the investement of the

land acuisition and resettlement, submit resettlement monitoring and evaluation report to Wuhan

Urban Construction Foreign Fund Office and ADB.

Page 7: PRC: Wuhan Wastewater and Stormwater Management Project · Social Monitoring Report This report has been submitted to ADB by the Wuhan Project Management Office and is made publicly

Resettlement Monitoring and Evaluation Report(No.1)

2

2.2 Principal Indicators of Monitoring and Evaluation

(I) Principal Indicators of Monitoring (i) Progress: include progresses of preparation and implementation of land acquisition and

resettlement; (ii) Quality: include project quality, degree of affected people’s satisfaction on resettlement; (iii) Investment: include payoff and application status of fund; (iv) Payment of Resettlement Compensation.

(II) Principal Indicators of Evaluation (i) Economic Status: Status of households’ economic progress before and after resettlement,

including household’s possession status of production material and livelihood material, status of asset or income;

(ii) Environmental Status: Residential environment before and after resettlement, including infrastructure changes of transportation, education, healthcare, and commercial service;

(iii) Employment Status: Occupation changes, employment ratio, and helps supported to different object, especially poor households, minority households;

(iv) Community Development: Status of community economy, environment, interpersonal relations, and public voice after affected people are relocated in new community;

(v) Status of Disadvantaged Groups

2.3 Survey of Resettlers’ Living Standards

The necessary data can be obtained by periodical survey, random interview and site visits, based

on which statistical analysis and evaluation are performed.

Questionnaire of livelihood level is consisted of every indicator measuring production and

livelihood level, whose change before and after resettlement reflects progress status of production

and livelihood level. Whether designed indicators accurately reflect changes of affected people’s

production and livelihood change will be checked up in the sample-based survey. Indicators will

be improved according to realistic conditions so that acquired information can completely and

really reflect affected people’s production and livelihood level.

2.4 Public Consultation

Economic and Management College of Tongji University will participate in the public

consultation conferences held by the villages and townships aperiodically. By this method, the

institution can evaluate the effectiveness the public participation and the cooperative attitude of

the resettlers towards the RP implementation. Such activities will be conducted during and after

the resettlement implementation.

Page 8: PRC: Wuhan Wastewater and Stormwater Management Project · Social Monitoring Report This report has been submitted to ADB by the Wuhan Project Management Office and is made publicly

Resettlement Monitoring and Evaluation Report(No.1)

3

2.5 Resettlers’ Opinions

Economic and Management College of Tongji University will often interview the district s

resettlement offices and villagers to know the opinions collected from the resettlers and interview

the resettlers who have grievances. The institution will report the opinions and suggestions from

affected individuals and collectives to the Project Resettlement Office, and provide advice for

improvement, so that the resettlement implementation can be more smooth and effective.

2.6 Other Indicators to be Monitored and Evaluated

Economic and Management College of Tongji University will monitor the following activities in the process of implementation:

(1) Relocation of resettlement;

(2) House rehabilitation;

(3) Production arrangement and rehabilitation;

(4) Support to vulnerable groups;

(5) Re-construction of special facilities;

(6) Payment and amount of the compensation;

(7) Resettlers’ transfer;

(8) Employment of laborers;

(9) Training;

(10) Schedule of the items above mentioned;

(11) Organizational efficiency for the resettlement;

(12) Use of compensation of the collective-owned land;

(13) Resettlers’ incomes, expenditures, and assets;

(14) Employment of the surplus laborers and income increase of them.

2.7 Monitoring and Evaluation Schedule

Conduct first monitoring in July 2007, submit first Resettlement Monitoring and Evaluation Report. Conduct second monitoring in January 2008, submit second Resettlement Monitoring and Evaluation Report. Conduct third monitoring in August 2008, submit third Resettlement Monitoring and Evaluation Report. Conduct fourth monitoring in January 2009, submit fourth Resettlement Monitoring and Evaluation Report. Conduct fifth monitoring in August 2009, submit fifth Resettlement Monitoring and Evaluation Report. Conduct sixth monitoring in January 2010, submit sixth Resettlement Monitoring and Evaluation Report.

Page 9: PRC: Wuhan Wastewater and Stormwater Management Project · Social Monitoring Report This report has been submitted to ADB by the Wuhan Project Management Office and is made publicly

Resettlement Monitoring and Evaluation Report(No.1)

4

Conduct seventh monitoring in August 2010, submit seventh Resettlement Monitoring and

Evaluation Report.

2.8 Approaches of Independent Monitoring and Evaluation

2.8.1 Checkout

Monitoring and evaluation group will discuss work status of resettlement with Wuhan Urban

Construction Use of Foreign Capital Office, WMWC, Wuhan Jianxing Infrastructure Construction

Company, correspongding project management departments of Dongxihu and Caidian projects

and related department of affected comunity, and principally spot-check implementation status of

Resettlement Plan of Wuhan Wastewater and Storm water Management Project.

2.8.2 Sample Survey

To spot-check occupied land quantity of affected people and quantity of dismantled houses,

randomly sample households from seriously affected villages to check, and consult affected

households’ opinions and suggestions about resettlement investigation, and collect basic materials

of sample households for next step’s monitoring on payment of compensation.

2.8.3 Interview and Observation

The monitoring and evaluation group called at each resettlement implementation organizations,

resettlement work staff, affected residents in order to get the basis condition of the affected

community and the progress status of resettlement of Wuhan Wastewater and Storm Water

Management Project. Monitoring and evaluation group interviewed key information providers,

reviewed the land acquisition and resettlement status of each sub-projects.

2.8.4 Monitoring and Evaluation of Resettlement Organizations

Monitoring and evaluation the policy implementation and the efficiency of the land acquisition

and resettlement work of the related personnel.

3 Monitoring of Resettlement Organizations

Wuhan ADB Financed Wastewater and Storm Water Project Management Regulation was issued

by Wuhan Urban Construction Fund Office on August 6, 2006, which defines the responsibilities

of each organizations.

Wuhan Urban Construction Fund Office is the owner institution of the project. Wuhan Construction Use of Foreign Capital Project Management Office is responsible for the day-to-day

Page 10: PRC: Wuhan Wastewater and Stormwater Management Project · Social Monitoring Report This report has been submitted to ADB by the Wuhan Project Management Office and is made publicly

Resettlement Monitoring and Evaluation Report(No.1)

5

management.

Wuhan Urban Construction Fund Office is the body corporate of the Storm Water Management

Project. Wuhan Jianxing Infrastructure Construction Company is the implementation organization.

Wuhan Municipal Drainage Company is the body corporate of the Wastewater Management

Project. It is also the implementation organization of the Wastewater Management Project in the

main urban erea.

Corresponding project management departments have been assigned as the Wastewater Management Project implementation organizations of Dongxihu and Caidian sub-projects.

Wuhan Dongxihu District Government established Wuhan ADB Financed Three Gates

Connection Wastewater and Storm Water Management Project Coordination Leading Group on

April 16, 2007, which in charge of the implementation of the project.

Opinions of monitoring and evulation group: The responsibility of each sub-project

implementation organizations has been defined. Sub-project implementation organizations take

charge in the concrete resettlement implementation work. Reasonable organizations, clear work

division are the precondition of the resettlement implementation.

4 Implementation Progress of Resettlement

4.1 The Wastewater Management Project

Table 1 Progress of the Land Requisition Procedures (By June 30, 2007)

Item Nantaizi Lake

Wastewater Project

of Hanyang

District

Dongxihu District Caidian District

Feasibility study Completed Completed Ongoing

Feasibility study

pre-examination by the land

departments

Ongoing Being prepared Being prepared

Feasibility study approval by Development

Completed Completed Being prepared

Page 11: PRC: Wuhan Wastewater and Stormwater Management Project · Social Monitoring Report This report has been submitted to ADB by the Wuhan Project Management Office and is made publicly

Resettlement Monitoring and Evaluation Report(No.1)

6

&Reform Committee

Invite public bidding of the

preliminary design

Being prepared Completed

Peliminary design Being prepared Completed

Land acquisition survey Ongoing Completed

Approval of peliminary design Completed Being prepared

Approval procedures for land requisition

(one approved letter and one

certificate)

Ongoing Being prepared

Approval of land requisition Ongoing Being prepared

Invite public bidding of the

detailed design

Being prepared

Project start Being prepared

Resettlement negotiations Being prepared

4.2 The Storm Water Management Project

Table 2 Progress of the Land Requisition Procedures (By June 30, 2007)

Item Luojiagang

Sub-project

Yangsigang

Sub-project

Three Gates

Connection

Project

Changqing

Sub-project

Feasibility study Completed Completed Completed Completed

Feasibility study pre-examination

by the land departments

Being

prepared

Being

prepared

Ongoing Being

prepared

Feasibility study approval by Development

&Reform Committee

Completed Completed Ongoing Completed

Invite public bidding of the

preliminary design

Being

prepared

Ongoing Being

prepared

Peliminary design Being Completed Completed

Page 12: PRC: Wuhan Wastewater and Stormwater Management Project · Social Monitoring Report This report has been submitted to ADB by the Wuhan Project Management Office and is made publicly

Resettlement Monitoring and Evaluation Report(No.1)

7

prepared

Land acquisition survey Being

prepared

Being

prepared

Being

prepared

Approval of peliminary design Completed Ongoing

Approval procedures for land requisition

( one approved letter and one

certificate)

Ongoing Completed Ongoing

Approval of land requisition

Invite public bidding of the

detailed design

Project start

Resettlement negotiations

Opinions of monitoring and evulation group: As a result of the land acquisition and resettlement work of this project is ongoing, the land acquisition and resettlement procedures should be conducted by the related implementation units quickly according to the domestic procedures, make the land acquisition and resettlement work implement smoothly.

Page 13: PRC: Wuhan Wastewater and Stormwater Management Project · Social Monitoring Report This report has been submitted to ADB by the Wuhan Project Management Office and is made publicly

Resettlement Monitoring and Evaluation Report(No.1)

8

4.3 Updated Project Plan

The plans have been updated. The updated plan of Wastewater Management Project is given in table 3, the updated plan of Stormwater Management Project is given in table 4.

Table 3 Updated Plan of Wastewater Management Project Project Item 2006 2007 2008 2009 2010 ADB Financied Prject 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

PPTA Disclosure the Information of Land Acquisition and Assettlement

Updated

PPTA Assettlement Updated

PPTA(2006) Peliminary and Construction Buleprint Design

Updated(2006-2007,4)

PPTA(2006-2007,3) Invite Public Bidding Updated(2007,3-2008,1)

PPTA(2006-2009,4) WWTP Construction Updated (2007,3-2009,4)

PPTA(2010,1-2010,2)

Erlangmiao

Testing Operation Updated (2010,1-2010,2)

Disclosure the Information

Page 14: PRC: Wuhan Wastewater and Stormwater Management Project · Social Monitoring Report This report has been submitted to ADB by the Wuhan Project Management Office and is made publicly

Resettlement Monitoring and Evaluation Report(No.1)

9

of Land Acquisition and Assettlement

Assettlement

PPTA2006-2007,1 Peliminary and Construction Buleprint Design

Updated 2007,1-2007,4)

PPTA(2007,4-2008,1) Invite Public Bidding Updated(2007,4-2008,1)

PPTA(2007,2-2008,4) WWTP Construction Updated(2008,2-2009,4)

PPTA(2009,1-2009,2)

Huangpu Road WWTP

Testing Operation Updated (2010,1-2010,2) PPTA(2006-2007,4) Disclosure the Information

of Land Acquisition and Assettlement

Updated (2006-2007,4)

PPTA(2006-2009,1) Aesettlement Updated (2006-2009,1)

PPTA(2006-2007,1) Peliminary and Construction Buleprint Design

Updated (2007,1-2008,2)

PPTA(2006-2008,3) Invite Public Bidding Updated (2006-2008,3)

PPTA(2006-2009,4)

Nantaizi Lake

WWTP Construction Updated (2008,1-2009,4)

Page 15: PRC: Wuhan Wastewater and Stormwater Management Project · Social Monitoring Report This report has been submitted to ADB by the Wuhan Project Management Office and is made publicly

Resettlement Monitoring and Evaluation Report(No.1)

10

PPTA(2010,1-2010,2) Testing Operation

Updated (2010,1-2010,2) PPTA(2008,1-2010,2) Pipeline Network and

Pump Station Construction Updated (2008,1-2010,2) PPTA(2006-2007,4) Disclosure the Information

of Land Acquisition and Assettlement

Updated (2007,4-2008,2)

PPTA(2007,1-2008,2) Aesettlement Updated (2007,4-2008,3)

PPTA(2006-2008,1) Peliminary and Construction Buleprint Design

Updated (2007,2-2008,2)

PPTA(2006-2008,4) Invite Public Bidding Updated (2008,1-2008,3)

PPTA(2007,3-2009,4) WWTP Construction Updated (2008,2-2010,2)

PPTA(2010,1-2010,2) Testing Operation

Updated (2010,3-2010,4) PPTA(2009,1-2010,2)

Caidian

Pipeline Network and Pump Station Construction Updated (2008,4-2010,2)

PPTA(2007,3-2008,1) Disclosure the Information of Land Acquisition and Assettlement

Updated (2007,1-2007,3)

PPTA(2008,1-2009,2)

DongxiAesettlement Updated (2007,3-2008,1)

Page 16: PRC: Wuhan Wastewater and Stormwater Management Project · Social Monitoring Report This report has been submitted to ADB by the Wuhan Project Management Office and is made publicly

Resettlement Monitoring and Evaluation Report(No.1)

11

PPTA(2006-2007,2) Peliminary and Construction Buleprint Design

Updated (2006-2007,3)

PPTA(2008,1-2009,1) Invite Public Bidding Updated (2007,3-2008,2)

PPTA(2008,4-2010,2)

hu

Pipeline Network and Pump Station Construction

Updated (2008,1-2009,4)

Page 17: PRC: Wuhan Wastewater and Stormwater Management Project · Social Monitoring Report This report has been submitted to ADB by the Wuhan Project Management Office and is made publicly

Resettlement Monitoring and Evaluation Report(No.1)

12

0 2 4 6 8 10 12 14 16 18

Time

Disclosure the Information of LA&A

Assettlement

Peliminary and Construction Buleprint Design

Invite Public Bidding

WWTP Construction

Testing Operation

Pro

ject

Item

PPTA Plan of Erlangmiao Project

0 2 4 6 8 10 12 14 16 18

Time

Disclosure the Information of LA&A

Assettlement

Peliminary and Construction Buleprint Design

Invite Public Bidding

WWTP Construction

Testing Operation

Pro

ject

Item

Updated Plan of Erlangmiao Project

Page 18: PRC: Wuhan Wastewater and Stormwater Management Project · Social Monitoring Report This report has been submitted to ADB by the Wuhan Project Management Office and is made publicly

Resettlement Monitoring and Evaluation Report(No.1)

13

0 2 4 6 8 10 12 14

Time

Disclosure the Information of LA&A

Assettlement

Peliminary and Construction Buleprint Design

Invite Public Bidding

WWTP Construction

Testing Operation

Pro

ject

Item

PPTA Plan of Huangpu Road WWTP Project

0 2 4 6 8 10 12 14 16 18

Time

Disclosure the Information of LA&A

Assettlement

Peliminary and Construction Buleprint Design

Invite Public Bidding

WWTP Construction

Testing Operation

Pro

ject

Item

Updated Plan of Huangpu Road WWTP Project

Page 19: PRC: Wuhan Wastewater and Stormwater Management Project · Social Monitoring Report This report has been submitted to ADB by the Wuhan Project Management Office and is made publicly

Resettlement Monitoring and Evaluation Report(No.1)

14

0 2 4 6 8 10 12 14 16 18

Time

Disclosure the Information of LA&A

Assettlement

Peliminary and Construction Buleprint Design

Invite Public Bidding

WWTP Construction

Testing Operation

Pipeline & Pump Station Construction

Pro

ject

Item

PPTA Plan of Nantaizi Lake Project

0 2 4 6 8 10 12 14 16 18

Time

Disclosure the Information of LA&A

Assettlement

Peliminary and Construction Buleprint Design

Invite Public Bidding

WWTP Construction

Testing Operation

Pipeline & Pump Station Construction

Pro

ject

Item

Updated Plan of Nantaizi Lake Project

Page 20: PRC: Wuhan Wastewater and Stormwater Management Project · Social Monitoring Report This report has been submitted to ADB by the Wuhan Project Management Office and is made publicly

Resettlement Monitoring and Evaluation Report(No.1)

15

0 2 4 6 8 10 12 14 16 18

Time

Disclosure the Information of LA&A

Assettlement

Peliminary and Construction Buleprint Design

Invite Public Bidding

WWTP Construction

Testing Operation

Pipeline & Pump Station Construction

Pro

ject

Item

PPTA Plan of Caidian Project

0 2 4 6 8 10 12 14 16 18 20

Time

Disclosure the Information of LA&A

Assettlement

Peliminary and Construction Buleprint Design

Invite Public Bidding

WWTP Construction

Testing Operation

Pipeline & Pump Station Construction

Pro

ject

Item

Updated Plan of Caidian Project

Page 21: PRC: Wuhan Wastewater and Stormwater Management Project · Social Monitoring Report This report has been submitted to ADB by the Wuhan Project Management Office and is made publicly

Resettlement Monitoring and Evaluation Report(No.1)

16

0 2 4 6 8 10 12 14 16 18

Time

Disclosure the Information of LA&A

Assettlement

Peliminary and Construction Buleprint Design

Invite Public Bidding

Pipeline & Pump Station Construction

Proj

ect I

tem

PPTA Plan of Dongxihu Project

0 2 4 6 8 10 12 14 16

Time

Disclosure the Information of LA&A

Assettlement

Peliminary and Construction Buleprint Design

Invite Public Bidding

Pipeline & Pump Station Construction

Pro

ject

Item

Updated Plan of Dongxihu Project

Page 22: PRC: Wuhan Wastewater and Stormwater Management Project · Social Monitoring Report This report has been submitted to ADB by the Wuhan Project Management Office and is made publicly

Resettlement Monitoring and Evaluation Report(No.1)

17

Table 4 Updated Plan of Storm Water Management Project Project Item 2006 2007 2008 2009 2010 ADB Financied Prject 1 2 3 4 1 2 3 4 1 2 3 4 1 2 3 4

PPTA(2006) Disclosure the Information of Land Acquisition and Assettlement

Updated(2007.1-2008,1)

PPTA(2006-2007,1) Aesettlement Updated(2007,1-2008,1)

PPTA(2006) Peliminary and Construction Buleprint Design

Updated(2006-2007,3)

PPTA(2006-2007,1) Invite Public Bidding Updated(2007,3-2007,4)

PPTA(2006-2008,1)

Three Gates Connection Project

Pipeline Network and Pump Station Construction

Updated (2007,3-2010,3)

PPTA(2006) Disclosure the Information of Land Acquisition and Assettlement

Updated (2007,3-2007,4)

PPTA(2007,1-2007,2) Aesettlement Updated (2007,3-2007,4)

PPTA(2006) Peliminary and Construction Buleprint Design

Updated (2006-2007,3)

Changqing Pump Station Invite Public Bidding PPTA(2007,2-2007,4)

Page 23: PRC: Wuhan Wastewater and Stormwater Management Project · Social Monitoring Report This report has been submitted to ADB by the Wuhan Project Management Office and is made publicly

Resettlement Monitoring and Evaluation Report(No.1)

18

Updated (2007,3-2007,4)

PPTA(2007,4-2009,1)

Pipeline Network and Pump Station Construction

Updated (2008,1-2010,2)

PPTA(2006) Disclosure the Information of Land Acquisition and Assettlement

Updated (2007,4-2008,1)

PPTA(2007,1-2008,1) Aesettlement Updated (2007,4-2009,4)

PPTA(2006) Peliminary and Construction Buleprint Design

Updated (2006-2007,4)

PPTA(2007,2-2007,4) Invite Public Bidding Updated (2007,4-2009,2)

PPTA(2007,4-2009,4)

Yangsigang Pump Station

Pipeline Network and Pump Station Construction

Updated (2008,1-2009,4)

PPTA(2006) Disclosure the Information of Land Acquisition and Assettlement

Updated (2008,1-2008,2)

PPTA(2007,1-2008,2) Aesettlement Updated (2008,3-2009,4)

PPTA(2006)

Luojia Road Pump Station

Peliminary and Construction Buleprint Design

Updated (2007,4-2008,2)

Page 24: PRC: Wuhan Wastewater and Stormwater Management Project · Social Monitoring Report This report has been submitted to ADB by the Wuhan Project Management Office and is made publicly

Resettlement Monitoring and Evaluation Report(No.1)

19

PPTA(2007,2-2007,4) Invite Public Bidding Updated (2008,2-2008,4)

PPTA(2007,4-2009,3)

Pipeline Network and Pump Station Construction

Updated (2008,3-2010,4)

Page 25: PRC: Wuhan Wastewater and Stormwater Management Project · Social Monitoring Report This report has been submitted to ADB by the Wuhan Project Management Office and is made publicly

Resettlement Monitoring and Evaluation Report(No.1)

20

0 1 2 3 4 5 6 7 8 9

Time

Disclosure the Information of LA&A

Assettlement

Peliminary and Construction Buleprint Design

Invite Public Bidding

Pipeline & Pump Station Construction

Pro

ject

Item

PPTA Plan of Three Gates Connection Project

0 2 4 6 8 10 12 14 16 18 20

Time

Disclosure the Information of LA&A

Assettlement

Peliminary and Construction Buleprint Design

Invite Public Bidding

Pipeline & Pump Station Construction

Pro

ject

Item

Updated Plan of Three Gates Connection Project

Page 26: PRC: Wuhan Wastewater and Stormwater Management Project · Social Monitoring Report This report has been submitted to ADB by the Wuhan Project Management Office and is made publicly

Resettlement Monitoring and Evaluation Report(No.1)

21

0 2 4 6 8 10 12 14

Time

Disclosure the Information of LA&A

Assettlement

Peliminary and Construction Buleprint Design

Invite Public Bidding

Pipeline & Pump Station Construction

Pro

ject

Item

PPTA Plan of Changqing Pump Station Project

0 2 4 6 8 10 12 14 16 18

Time

Disclosure the Information of LA&A

Assettlement

Peliminary and Construction Buleprint Design

Invite Public Bidding

Pipeline & Pump Station Construction

Pro

ject

Item

Updated Plan of Changqing Pump Station Project

Page 27: PRC: Wuhan Wastewater and Stormwater Management Project · Social Monitoring Report This report has been submitted to ADB by the Wuhan Project Management Office and is made publicly

Resettlement Monitoring and Evaluation Report(No.1)

22

0 2 4 6 8 10 12 14 16

Time

Disclosure the Information of LA&A

Assettlement

Peliminary and Construction Buleprint Design

Invite Public Bidding

Pipeline & Pump Station Construction

Pro

ject

Item

PPTA Plan of Yangsigang Pump Station Project

0 2 4 6 8 10 12 14 16

Time

Disclosure the Information of LA&A

Assettlement

Peliminary and Construction Buleprint Design

Invite Public Bidding

Pipeline & Pump Station Construction

Pro

ject

Item

Updated Plan of Yangsigang Pump Station Project

Page 28: PRC: Wuhan Wastewater and Stormwater Management Project · Social Monitoring Report This report has been submitted to ADB by the Wuhan Project Management Office and is made publicly

Resettlement Monitoring and Evaluation Report(No.1)

23

0 2 4 6 8 10 12 14 16 18 20

Time

Disclosure the Information of LA&A

Assettlement

Peliminary and Construction Buleprint Design

Invite Public Bidding

Pipeline & Pump Station Construction

Pro

ject

Item

PPTA Plan of Luojia Road Pump Station Project

0 2 4 6 8 10 12 14 16 18 20

Time

Disclosure the Information of LA&A

Assettlement

Peliminary and Construction Buleprint Design

Invite Public Bidding

Pipeline & Pump Station Construction

Pro

ject

Item

Updated Plan of Luojia Road Pump Station Project

Page 29: PRC: Wuhan Wastewater and Stormwater Management Project · Social Monitoring Report This report has been submitted to ADB by the Wuhan Project Management Office and is made publicly

Resettlement Monitoring and Evaluation Report(No.1)

24

5 Resettlement Implementation by WJICC

The main resettlement implementation work by Wuhan Jianxing Infrastructure Construction Company is the Storm Water Management Project. Now the land acquisition and resettlement implementation work of Three Gates Connection Sub-project is ongoing. Interview Record, Interviewee: Zhang Wei (Director of WJICC), etc.

Time: AM. June 6, 2007 The implementation work of Three Gates Connection Project is being prepared. Preliminary design of this project is reported to Wuhan City Development and Reform Committee for approval. The “approval letter and certificate” are being conducted. Dongzheng Evulation Office Company is commissioned to conduct the spot preliminary survey. The land acquisition and housing demolition agreements will be decided after negotiating with the affected people in compliance with relevant laws, legislations and policies of Wuhan City and People’s Republic of China, as well as in accordance with ADB principles and policies of involuntary resettlement. Area involved of this project preliminary investigation includes Jinkou Village, the development zone, the golf course, Jinyinhu ecological park, Jiangjunlou Office, Machi Resident Committee, etc. The compensation negotiation has not been conducted with the affected units for the land acquisition procedures have not been formally approved. According to the fund management of the land acquisition and resettlement, Wuhan Jianxing Infrastructure Construction Company will subscribe the compensation agreements with the affected person and Foreign Capital Office Clearing Center will distribute the fund to the affected person after the compensation agreements were approved by Wuhan Use of Foreign Capital Office. Three persons assigned by our company are in charge of the land acquisition and resettlement work of Three Gates Connection Project. They all have related land acquisition and resettlement work experience, have taken charge in ongong World Bank Financed Wuhan City Transportation Project. The land acquisition and resettlement work of remaining sub-projects financed by ADB is being prepared.

6 Resettlement Implementation by WMDC

Interview Record, Interviewee: Zhou Te, etc.

Time: PM. June 6, 2007, Place: Wuhan Municipal Drainage Company

Page 30: PRC: Wuhan Wastewater and Stormwater Management Project · Social Monitoring Report This report has been submitted to ADB by the Wuhan Project Management Office and is made publicly

Resettlement Monitoring and Evaluation Report(No.1)

25

The land acquisition and housing demolition of Hanyang District Nantaizi Lake Sub-project charged by Wuhan Municipal Drainage Company is under way. 140 mu land will be occpuied in plan, a 7.8 km of sewage collection system and two pump stations will be constructed. The quantity of housing demolition is still in investigation. Temporary occupied land of the pipeline and the pump station is small relatively. The temporary occupied land acquisition work does not start and the site selection has not been finalized. Land acquisition procedures of plant area are being processed. No new land will be occupied for Wuchang Erlangmiao WWTP Second-stage Engineering. Wuchang Erlangmiao WWTP First-stage Engineering occupied the reserved land in 1999, only 180 mu of which was used. No new land will be occupied for Huangpu Road WWTP Second-stage Engineering. The engineering content is upgrading current wastewater treatment technics. The staff engaged in the land acquisition and housing demolition of the project all have practical experience. They have land acquisition and resettlement experience in the use of foreign investment projects,. Comment: Wuhan Municipal Drainage Company pay great attention to the land acquisition and resettlement work of this project. The personnel with related knowledge and experience are assigned for this project. Land acquisition and resettlement work of Nantaizi Lake Sub-project is ongoing.

7 Conclusion and Suggestion

7.1 Conclusion

(1) Wuhan City Fund Management Office pays great attention to Wuhan ADB financed city project. Wuhan ADB Financed Wastewater and Storm Water Project Management Regulation was issued specially, which define the responsibilities of each organizations. (2) Wuhan City Construction Use of Foreign Capital Project Management Office assigns particular people with abundance experience to take charge in the coordination work of land acquisition and resettlement. (3) Wuhan Jianxing Infrastructure Construction Company and Wuhan Municipal Drainage Company assign special people for land acquisition and resettlement work. (4) Some earlier preparations is being conducted for the land acquisition and resettlement work of this project. Large-scale land acquisition and resettlement work has not been done.

Page 31: PRC: Wuhan Wastewater and Stormwater Management Project · Social Monitoring Report This report has been submitted to ADB by the Wuhan Project Management Office and is made publicly

Resettlement Monitoring and Evaluation Report(No.1)

26

(5) The land acquisition and resettlement implementation progress of this project is behind schedule compared to the land acquisition and resettlement plan approved by ADB.

7.2 Suggestion

(1) Further strengthen the connection with Wuhan City Construction Use of Foreign Capital Project Management Office and the two sub-projects of Dongxihu District and Caidian District. (2) Further accelerate the transaction of land acquisition procedures according to the project progress, accelerate the land acquisition and resettlement progress. (3) Further strengthen public participation of the land acquisition and resettlement work.