Upload
frederick-french
View
217
Download
2
Embed Size (px)
Citation preview
Prague 24 Aug 2003 University of Zagreb 1
Observational Methodand Eurocode 7
Antun Szavits-Nossan
University of Zagreb, Croatia
Prague 24 Aug 2003 University of Zagreb 2
Observational Method in Eurocode 7 (1995) Acceptable limits of behaviour shall be
established before construction commences; It shall be shown that there is an acceptable
probability that the actual behaviour will be within these limits;
… A plan of contingency actions shall be devised
which can be adopted should the monitoring reveal behaviour outside these limits.
Prague 24 Aug 2003 University of Zagreb 3
What is the acceptable probability ? Eurocode 7 does not refer to acceptable
probability any further. The acceptable probability determines the
degree of conservatism for the initial design prior to construction. The higher the chosen probability, the more conservative will be the initial design.
The lower bound of acceptable probability corresponds to the design based on characteristic values from Eurocode 7(a cautious estimate of ground conditions).
Prague 24 Aug 2003 University of Zagreb 4
… continued
Eurocode 7 implicitly requires a margin of conservatism for the design based on characteristic values, because the actual behaviour may step outside acceptable limits. If this happens, there should be provisions for the application of planned contingency actions. The required margin of conservatism is, however, not specified.
Prague 24 Aug 2003 University of Zagreb 5
How conservative should one be?
Peck (1969) lists eight ingredients of the complete application of the observational method, and one of them is: ‘(c) establishment of the design based on a working hypothesis of behaviour anticipated under the most probable conditions.’(Which should correspond to characteristic values of Eurocode 7).
Prague 24 Aug 2003 University of Zagreb 6
… continued
Powderham (1994) supports a moderately conservative initial design based on more probable conditions and introduces the progressive modification of design through the application of the observational method, which proved to be a very efficient approach.
Muir Wood (2000) suggests a conservative initial design for tunnels based on a simplified economical analysis.
Prague 24 Aug 2003 University of Zagreb 7
Initial design: constant probability (Muir Wood 2000)
Prague 24 Aug 2003 University of Zagreb 8
… continued
The relative cost of contingency actions is defined as:
contingency actions cost for 0initial design construct. cost for 1
pk
p=
==
Prague 24 Aug 2003 University of Zagreb 9
Probability distribution (Muir Wood)
Prague 24 Aug 2003 University of Zagreb 10
Triangular probability distribution
Prague 24 Aug 2003 University of Zagreb 11
Initial design: triangular probability
Prague 24 Aug 2003 University of Zagreb 12
Construction cost
Probability distribution
Initial design Contingency actions
Constant
Muir Wood (2000)
Triangular
(this study)
f( )p g( )p
Ap (1 )kA p-
11
2p
Aæ ö- ÷ç - ÷ç ÷çè ø
12p
kA-
f( )p g( )p
Prague 24 Aug 2003 University of Zagreb 13
Minimal cost and optimal probability for adequate design
Total estimated cost
Minimal cost
Solution for both the constant and the triangular distribution
f( ) (1 )g( )C p p p= + -
min 0dC
Cdp
® =
minCp = -
k1
12
(k : relative cost of contingency actions)
Prague 24 Aug 2003 University of Zagreb 14
Optimal probability of adequate design
= -pk1
12
Prague 24 Aug 2003 University of Zagreb 15
Conclusions
Eurocode 7 provides no guidance for the selection of the acceptable probability on which to base the initial design when using the observational method.
Many agree that the initial design should be more conservative than the Peck proposal based on most probable conditions.
The optimal degree of conservatism for the initial design depends on the relative cost of contingency actions (k).
This may be the way to acceptable probability.
Prague 24 Aug 2003 University of Zagreb 16
References
Eurocode 7 (1995). ENV 1997-1 Eurocode 7, Geotechnical design, Part 1: General rules (together with the United Kingdom National Application Document). British Standards Institution, London.
Muir Wood, A. (2000). Tunnelling: Management by design. E & FN Spon, London.
Peck, R. B. (1969). Advantages and limitations of the Observational Method in applied soil mechanics. Géotechnique, 44 (4), 619-636.
Powderham, A. J. (1994). An overview of the observational method: development in cut and cover bored tunnelling projects. Géotechnique, 19 (2), 171-187.