36
FAST TRACK CONSTRUCTION FAST TRACK CONSTRUCTION OF PROJECTS OF PROJECTS Case Study - Tapovan Vishnugad Hydro Power Project By P&S Department, Dated 24.07.2009

PPT Fast Track Construction of Projects

  • Upload
    alex-b

  • View
    646

  • Download
    26

Embed Size (px)

Citation preview

Page 1: PPT Fast Track Construction of Projects

FAST TRACK CONSTRUCTION FAST TRACK CONSTRUCTION OF PROJECTSOF PROJECTS

Case Study - Tapovan Vishnugad Hydro Power Project By P&S Department, Dated 24.07.2009

Page 2: PPT Fast Track Construction of Projects

◦ ExperiencesAspects for timely execution of projects Case Studies of TVHPP

◦ Conclusions◦ Recommendations

PESENTATIONPESENTATION BRIEF BRIEF

Page 3: PPT Fast Track Construction of Projects

◦Geological Investigations◦ Land Acquisition◦ Shifting of Structures◦ Infrastructure Inputs◦ Resistance to blasting◦ Use of Latest Technology◦ Timely decisions in coherent manner

KEY ASPECTS FOR TIMELY KEY ASPECTS FOR TIMELY EXECUTIONEXECUTION

Page 4: PPT Fast Track Construction of Projects

INVESTIGATION PHASEINVESTIGATION PHASEProper and adequate investigation averts delays during execution stage by:• Choosing best methodology of execution.• Avoiding geological surprises.• Making realistic designs and estimates

thereby avoiding contractual complicacies in later stages.• Proper investigations backed the decision

of deployment of TBM at TVHPP thereby crashing the construction period.

Page 5: PPT Fast Track Construction of Projects

o Knowledgeable & Trained Land Acquisition team.

o Effective R&R Policy Implementation.

o Creation of Infrastructureo Use of Latest Technology to

reduce execution time and mitigate environmental concerns

CONSTRUCTION PHASECONSTRUCTION PHASE

Page 6: PPT Fast Track Construction of Projects

LAND ACQUISITIONLAND ACQUISITION◦ Liaison with State Departments helps

in speedy approval of land acquisition and other proposals. ◦ Liasion office has been established in

Dehradun (State capital) to expedite the proposals. ◦ Know How of land acquisition

procedures to the executives engaged in ground work is crucial.◦ Trained Patwaris were hired to help

in ground works.

Page 7: PPT Fast Track Construction of Projects

R&R WORKSR&R WORKS◦ Community development works were finalized in consultation with local bodies.◦Medical camps helped in developing good-will.◦ Community development works helped villagers in terms of facilities and job.◦ Co-operative societies of the same village were involved for CD works of a village. ◦ Job preference to PAPs/locals created conducive environment for project works.

Page 8: PPT Fast Track Construction of Projects

R&R WORKSR&R WORKS

◦ Shifting of Structures to ensure unhindered progress of work and to avoid inconvenience to population using the structures.◦ Crucial structures like Temples, Govt. Inter College, Ayurvedic hospitals, suspension bridges and houses were to be shifted from Barrage area.

Page 9: PPT Fast Track Construction of Projects

SHIFTING OF STRUCTURESSHIFTING OF STRUCTURES◦ Public was educated about the need of

shifting.◦ All Govt. bodies and local bodies like

Panchayat, Youth club, Mahila Mangal Dals etc were taken into confidence.◦ Alternative arrangements were made prior

to shifting of original structures.◦ Due respect was paid to local population’s

sentiments with the structures especially Temples.◦ Special care taken to maintain the original

architecture of ancient temples to be shifted. ◦ Works of construction of new structures

and removal/shifting of old ones was entrusted to PAPs.◦ It was ensured that the services extended

through these structures continued without break.

Page 10: PPT Fast Track Construction of Projects

RELOCATED ANCIENT RELOCATED ANCIENT TEMPLETEMPLE

Page 11: PPT Fast Track Construction of Projects

INFRASTRUCTURE INPUTSINFRASTRUCTURE INPUTS

Approach Roads: ◦ Agencies like BRO & PWD are

available at the start of the project to commence approach works.◦ Our experience –

They are not good at maintaining schedules.After the award of main packages, the approach roads should be included in main packages. All approach roads should be concrete paved to avoid problems during monsoon season especially for hill roads.

Page 12: PPT Fast Track Construction of Projects

INFRASTRUCTURE INPUTSINFRASTRUCTURE INPUTSConstruction Power: ◦ Construction power is crucial for

execution especially when we are using technologies like TBM & Road Header.◦ Augmentation of Power network was

done from Srinagar to Joshimath. ◦ Un-reliability of power was

hampering progress.◦ To tackle the voltage fluctuations in

peak hours, OLTC transformer is installed.◦ Contract should have provision for

DG- supply to tackle power interruptions.

Page 13: PPT Fast Track Construction of Projects

INFRASTRUCTUREINFRASTRUCTUREBefore the completion of land

acquisition activities, residences and offices are accommodated in hired buildings.

As an early solution Pre-fabricatedoffices and porta-cabins are being used as site offices.

Phased construction taken up for Township. Phase -1 of prefab structures for office & Bachelor accommodation has been started.

Page 14: PPT Fast Track Construction of Projects

Use of Latest Technology to reduce execution time

CONSTRUCTION PHASECONSTRUCTION PHASE

Page 15: PPT Fast Track Construction of Projects

◦ Location & No. of Adits:Normally 12 km long tunnel needs 2 intermediate adits due to lead distance and ventilation considerations.Deployment of TBM obviated the need of 2nd

adit and this HRT needs only 1 intermediate adit resulting in time & cost savings.

◦ Selection of Excavation methodology:Mechanized tunneling such as TBM and Road header have been used.A conference was held in Delhi and decision to deploy TBM was taken after elaborate discussions with TBM suppliers.TBM gives 3-5 times the progress rate of conventional excavation.TBM & Road Header cause less vibration and pollution and provide much safer working environment.

USE OF LATEST USE OF LATEST TECHNOLOGYTECHNOLOGY

Page 16: PPT Fast Track Construction of Projects

◦ Selection of latest Equipment:Drill Jumbos being used for drill & blast and rock bolting operations provide better progress & efficiency.High capacity excavators and dumpers for faster excavation and mucking.Grabs are being used for excavation of cut off wallRaise climber being used for inclined Pressure Shaft excavation.Raise Borer deployed for pilot bore and reaming of surge shaft excavation.

USE OF LATEST USE OF LATEST TECHNOLOGYTECHNOLOGY

Page 17: PPT Fast Track Construction of Projects

◦ Raise Borer deployed for Surge shaft pilot boring and reaming. ◦ Offers higher progress rate, pilot

bore completed in 3 days and reaming completed in 12 days.◦ Excavation of Surge Shaft close to

populated area by this technology caused practically no disturbance to adjacent population.

USE OF LATEST USE OF LATEST TECHNOLOGYTECHNOLOGY

Page 18: PPT Fast Track Construction of Projects

RESISTANCE TO BLASTINGRESISTANCE TO BLASTINGThe project faced a major obstacle by

people alleging that the blasts for excavation are causing cracks in their houses. This was motivated by experience of nearby Vishnuprayag HPP. To tackle the issue:◦ Local administration taken into

confidence,◦ Frequent interaction & communication

with villagers and representatives,◦ An investigation on impact of blasts on

the structures in project vicinity carried out by independent agency which gave us clean chit.◦ Committees of villagers have now been

involved in blast monitoring.

Page 19: PPT Fast Track Construction of Projects

TIMELY DECISION IN TIMELY DECISION IN COHERENT MANNERCOHERENT MANNER

Speed of project depends on the speed of decision making

Page 20: PPT Fast Track Construction of Projects

Decision to change the alignment of Decision to change the alignment of Chormi Adit approach road. New Chormi Adit approach road. New alignment:alignment:Is 3.5 km long against earlier planned of 8.5 km.At least 20 ha land acquisition is avoided, resulting in direct saving of approx Rs. 25 Cr. and also saving of land acquisition time. Also serves as approach road to SFT outfall resulting in time & cost saving.Provides much shorter approach between 2nd and 3rd adit of HRT thereby improving the accessibility and ease of supervision.Gives the much required space for muck disposal in the vicinity of Barrage & HRT excavation

Page 21: PPT Fast Track Construction of Projects

APPROACH TO CHORMI APPROACH TO CHORMI ADITADIT

Proposed alignment - 1

Alignment - 2

Chormi (2nd ) Adit Portal

Intake (3rd ) Adit Portal

Barrage Site

Page 22: PPT Fast Track Construction of Projects

The decision to introduce third adit The decision to introduce third adit near Intake end of HRTnear Intake end of HRT

◦ The decision resulted in: Early opening of front – Before the opening of front of 2nd adit approx. 1 km excavation of HRT from this new adit is achieved.Considerable gain in time & cost.

Page 23: PPT Fast Track Construction of Projects

Construction of Part of Third adit Construction of Part of Third adit through separate contract through separate contract

◦ Construction of part of third adit was awarded to M/s Highway & Hydel on 31.08.06.◦ Main HRT package was awarded to

M/s L&T AM JV on 28.11.06◦ Thus awarding this small contract

helped in early start of work.◦ Before the mobilization of HRT

agency:Approach up to the adit was completed.Open excavation was completed.Part of slope protection works were completed.

Page 24: PPT Fast Track Construction of Projects

Decision to shift the location of TBM Decision to shift the location of TBM adit adit

◦ Earlier location involved major support works with huge amount of overburden to be removed.◦ The overburden was likely to disturb

the NH 58 which is lifeline of Joshimath Town.◦ A calculated risk was taken by

shifting the Portal location closer to ridge line.◦ The decision involved well good co-

ordination in Site & Engineering.◦ Decision involved a lot of survey &

geological appraisals and need of agencies for these purposes was felt.

Page 25: PPT Fast Track Construction of Projects

Decision to shift the location of TBM Decision to shift the location of TBM adit adit

Earlier Location

Final Location

HRT

Page 26: PPT Fast Track Construction of Projects

TBM assembly in Two PhasesTBM assembly in Two Phases

◦ Against the area requirement of 15X235m for TBM assembly, area available was 10X70m.◦ An innovative decision to assemble TBM

in 2 phases was taken.◦ First- Adit was excavated up to 130m

chainage◦ After part assembly of TBM up to BU #

11, TBM was pushed up to the face and TBM excavation was started.◦ At Ch. 294m, TBM was stopped and

Assembly up to BU # 21 was completed.◦ Full fledged excavation was then

started.◦ This was ventured for the first time in

the world.

Page 27: PPT Fast Track Construction of Projects

Decision to change the alignment of Decision to change the alignment of approach road to Surge Shaft Top. approach road to Surge Shaft Top. New alignment:New alignment:◦ Involved only 200m length (against

1km) of fresh construction thereby resulting in cost saving.◦ This shorter length involved very small

blasting and hence found no hindrance to work.◦ The road is being used by the villagers

too thus the strengthening of road is giving goodwill to NTPC among PAPs.◦ The strengthening works were

executed through PAPs resulting in improved relation with the village.◦ Pilot hole and reaming of Surge Shaft

completed well within scheduled time besides cost saving.

Page 28: PPT Fast Track Construction of Projects

APPROACH TO SURFGE APPROACH TO SURFGE SHAFTSHAFT

Proposed Alignment 1

Existing Road to Shelong Village

Alignment - 2

Page 29: PPT Fast Track Construction of Projects

Decision to include approach road to Decision to include approach road to Pressure Shaft Intermediate adit in PH Pressure Shaft Intermediate adit in PH package:package:◦ BRO and PWD were unable to take up

the work due to other priorities in the district.◦ Decision to include road in PH

package resulted in:Utilization of equipment and mobilization of agency saving NTPC from idling claims.Saved a lot of time of award & mobilization.Started Pressure shaft excavation from intermediate adit before schedule.

Page 30: PPT Fast Track Construction of Projects

SELECTION OF GOOD SELECTION OF GOOD

CONTRACTOR CONTRACTOR

WITH WORKABLE RATESWITH WORKABLE RATES

Page 31: PPT Fast Track Construction of Projects

Experience with SSJV - ZVSExperience with SSJV - ZVS◦ SSJV-ZVS emerged as L1 and got the

Barrage & De - Silting Basin package of TVHPP.◦ Due to unprecedented rise in rates of Steel

& Cement, the rate of concreting items became unworkable.◦ Situation got aggravated by coinciding

financial meltdown of Satyam group.◦ Barrage package is suffering.◦ A better formula to compensate for such

unusual price hikes of steel & cement should be developed.◦ Employer bears the market fluctuations

where Cement & Steel are provided by the employer.

Page 32: PPT Fast Track Construction of Projects

◦ When it comes to Fast Track Execution of Hydro Projects, speed of decision making is crucial◦ Investment in geological

investigations give high returns.◦ Geologists are the insurance policy

of project.◦ Hydro Projects are generally

constructed in scarcely/less populated areas where even small group of people can affect the progress.◦ This necessitates good liaison with

state & local bodies and better R&R policies

CONCLUSIONSCONCLUSIONS

Page 33: PPT Fast Track Construction of Projects

◦ Selection of good contractor with workable rates is a must.◦ Efficient construction methodology

and latest technologies reduce construction time.◦ Innovations should be encouraged.◦ Capturing of best practices through

initiatives like this is also important.◦ And the most important…A highly motivated and enthusiastic

team of professionals.

CONCLUSIONSCONCLUSIONS

Page 34: PPT Fast Track Construction of Projects

Following can help in fast track project implementation:

Effective R&R policy and implementation.Accommodations to be constructed in early phases of project.Mechanism for compensating unusual hike in rates of steel & cement.We should be open to revisions in construction methodology even at the cost of revision in TS.Designers should pay regular visit to sites.

RECOMMENDATIONSRECOMMENDATIONS

Page 35: PPT Fast Track Construction of Projects

◦ Following can help in fast track project implementation:Agency for survey and geological investigation should be available during construction phase.Dispute resolution mechanism is a must for Hydro.TOC should be accompanied with Engg. Team & designers for effective implementation of their suggestions.Construction power network should choose alignment involving least land acquisition & Forest patches rather than choosing shortest route.

RECOMMENDATIONSRECOMMENDATIONS

Page 36: PPT Fast Track Construction of Projects