PPP Infrastructure Project Motorway BAB 8 Facts Project Description The PPP Infrastructure Project BAB A8 in the section Ulm-Elchingen and Augsburg West includes the responsibilities of expansion, maintaining, operating and financing on a length of 57 km. The motorway A8 Ulm-Augsburg-Munich is one of the most important road axis in Europe. The above mentioned section of the previous four-lane motorway A8 will be extended on a length of approx. 41 km to six lanes plus shoulder while maintaining the traffic. The contract also includes the construction of 79 bridges, culverts and other civil engineering works and the maintenance and operation of further 29 bridge constructions. Three PWC car park toilet facilities will be built along the motorway and the filling station and service area Burgauer See will be extended. PROJECT DATA: New road surface: 1.2 million m³ Earthworks: 4.2 million m³ Concrete for road pavement: 380,000 m³ 79 bridge structures Noise protection facilities: Barriers: 9.4 km Walls: 3.6 km Barrier Wall Combination: 4.8 km Concession: 30 years City/Country Ulm - Augsburg / Germany Client Autobahndirektion Südbayern, München Contract Value € 562,00 Mio. Construction Period 06/2011 - 09/2015 (52 Months) .

PPP Infrastructure Project Motorway BAB 8FILE/A8.pdf · 2016. 7. 7. · PPP Infrastructure Project Motorway BAB 8 Facts Project Description The PPP Infrastructure Project BAB A8 in

  • Upload
    others

  • View
    3

  • Download
    0

Embed Size (px)

Citation preview

Page 1: PPP Infrastructure Project Motorway BAB 8FILE/A8.pdf · 2016. 7. 7. · PPP Infrastructure Project Motorway BAB 8 Facts Project Description The PPP Infrastructure Project BAB A8 in

PPP Infrastructure Project Motorway BAB 8

Facts Project DescriptionThe PPP Infrastructure Project BAB A8 in the section Ulm-Elchingen and Augsburg Westincludes the responsibilities of expansion, maintaining, operating and financing on a lengthof 57 km.The motorway A8 Ulm-Augsburg-Munich is one of the most important road axis in Europe.The above mentioned section of the previous four-lane motorway A8 will be extended on alength of approx. 41 km to six lanes plus shoulder while maintaining the traffic. Thecontract also includes the construction of 79 bridges, culverts and other civil engineeringworks and the maintenance and operation of further 29 bridge constructions. Three PWCcar park toilet facilities will be built along the motorway and the filling station and servicearea Burgauer See will be extended.

PROJECT DATA:New road surface: 1.2 million m³Earthworks: 4.2 million m³Concrete for road pavement: 380,000 m³79 bridge structures

Noise protection facilities:Barriers: 9.4 kmWalls: 3.6 kmBarrier Wall Combination: 4.8 km

Concession: 30 years

City/Country

Ulm - Augsburg / Germany

Client

Autobahndirektion Südbayern, München

Contract Value

€ 562,00 Mio.

Construction Period

06/2011 - 09/2015 (52 Months)

.