Upload
emery-harris
View
216
Download
2
Embed Size (px)
Citation preview
PPP Basic Concepts Case Study Application: Indiana Toll Road
Ricardo SanchezFebruary 12, 2013
2
Index
1. tion: concept, grounds for P3s and main players of highway P3s
01Introduction to PPP’s
4
01. Definition of Public-Private Partnerships (PPP)
Contractual arrangements between the public and private sector in which
(i) the private sector assumes most of the risks of financing, constructing (or leasing) and operating and maintaining an infrastructure
(ii) in exchange for the right to future revenues or payments
(iii)for a specified term
5
01. The driving forces of PPPs growth (I)
Increasing demand for investment in highway construction, operation and maintenance projects due to:• Traffic congestion• Aging infrastructure• Population growth• Changing development patterns
Decreased purchasing power of the traditional public funding mechanisms for funding highways (the gas tax) due to:• Increasing fuel efficiency of motor vehicles• Political resistance to increasing the gas tax• Depletion of the Highway Trust Fund
6
01. The driving forces of PPPs growth (I)
Increasing demand for investment in highway construction, operation and maintenance projects due to:• Traffic congestion• Aging infrastructure• Population growth• Changing development patterns
Decreased purchasing power of the traditional public funding mechanisms for funding highways (the gas tax) due to:• Increasing fuel efficiency of motor vehicles• Political resistance to increasing the gas tax• Depletion of the Highway Trust Fund
7
01. The driving forces of PPPs growth (II)
THE CONSEQUENCE:• The private-sector capital becomes an attractive option to
supplement or replace the public funds for highway projects
OTHER BENEFITS THAT BRINGS THE PRIVATE-SECTOR PARTY:• Equity Invested at Risk• Accelerated project completion• Motivated and highly specialized management teams• Cost control and operational efficiency • Innovation and new technology• Improved customer service
WHY SUCH BENEFITS?• Significant risks are allocated to the private sector who is
rewarded for accepting such risks
8
01. Main players in PPPs Projects
Public Sector
Participant
• State Legislatures• Governors• Public Sector Sponsors
(State DOTs)• Conduit Issuer of PABs• US DOT (TIFIA)
Private Sector
Participant
• Concessionaire• Equity investors• DB Contractor• Operator• Commercial Lenders (banks)
• Bondholders
9
01. Advantages of PPPs
• Maximizes the use of each sector’s strength• Reduces public capital investment• Improves efficiencies – quicker completion• Shares risks• Mutual rewards• Improves aggregate overall costs efficiencies• Improves service to community
02TRADITIONAL VS ALTERNATIVE PROJECT DELIVERY METHODS
11
02. Traditional Delivery Method : Design-Bid-Build
Process:• Public sector develops
design • Competitive bids for
construction by private sector based on that design
• Construction work is awarded to the lowest-price bid
• Project financed with public funds
• Public entity inspects compliance of the works with the design
• Public entity operates and maintains the facility
Advantages:• Full control over design by
public sponsor• Low-bid procurement
encourages lowest construction cost
• Ensures competition among private contractors
• Consistent with the institutional framework (state agencies are structured and stuffed to procure highway projects following this traditional method)
Disadvantages:• Impacts on cost and
project schedule: constructor takes advantage of unanticipated design flaws to get additional payments (change orders) or of unanticipated site conditions to get project schedule relief
• Project financed entirely with public funds
• No synergies between design and construction phases
02. Alternative Delivery Methods
12
Increasing participation of private sector in the development of the projects:• Assuming
significant project risks
• Making available private sector funds
Design-Build-Finance-Operate-
Maintain
Design-Build-Operate-Maintain
Design-Build
02. Alternative Delivery Methods
13
Design-Build-Finance-Operate-
Maintain
Design-Build-Operate-Maintain
Design-Build
Design-buildFaster project deliveryDesign, construction and operational efficienciesQuality improvementsEncourages innovation
Design-Build-Operate-Maintain + Encourages delivery of a higher quality project (to reduce life-cycle maintenance and rehabilitation costs)
Design-Build-Finance-Operate-Maintain (toll)+Risk of traffic is transferred to the private entity. The tolls, are used by private entity to repay the private sector funding
Design-Build-Finance-Operate-Maintain (availability) + Risk of financing the project is transferred to the private
sector: funds from private sources (i) Equity & (ii) debt are available. The tolls, are used by public entity to repay the private sector funding.
03PPP Risk Allocation
03. Design-Bid-Build Risk Allocation
PUBLIC SECTOR
Construction Technology upgrades
Finance
Design
Environmental
Change in law
Approval Process
Right of Way
Integration
Traffic & Revenue
Operation & ManagementPRIVATE
SECTOR
Customer acceptance
Unforeseen conditions
PublicSector
03. Design-Build-Finance-Operation-Maintain Risk Allocation
Construction Technology
Customer Acceptance Delay Events
Financing
Environmental
Operation & Maintenance
Competing Facilities
PrivateSector
PublicShared Private
Design
UnforeseenConditions
Approval Process
Oversight
Termination
ROW
Traffic & Revenue
Change in law
04CONTRACTUAL STRUCTURE OF AHIGWAY P3 PROJECT
18
04. Common structure of a highway P3
PROJECTCOMPANY
AUTHORITYUSERS
TOLL COLLECTIO
BACK OFFICE
IT SYSTEMSPROVIDER
OPERATORDB CONTRACTOR
LENDERS
PRIVATESPONSOR
CONCESSION AGREEMENT
REVENUESHARE – UPFRONT PAYMENT
TOLLS
SERVICEEQUITY RETURN
EQUITY CONTRIBUTION&PROVIDES SERVICES
DEBT SERVICE
LOAN FUNDS
PROJECT DESIGN & CONSTRUCTION
LUMP SUM FIXED PRICE
OM&R SERVICES
FIXED PAYMENT
COLLECTION & ENFORCEMENT & BACK OFFICE SERVICES
TRANSACTION PAYMENTS
TOLL SYSTEMS DELOPMENT & INTEGRATION
CONTRACT PRICE
UPFRON PAYMENT
PUBLIC FUNDS
05PPP’s Financing
¿What is Project Finance?
• Financing of a project where creditors have as main and only repayment source the revenues generated by such project.
• Also called non recourse or with limited recourse to the sponsor financing
• As the repayment source is the cash generated by the project, creditors make a careful and deep analysis of the certainty of those revenues in order to minimize the risk of not being repaid.
• Project Finance is generally not applicable to real state or industrial projects where market risks are difficult to mitigate. Applicable to Infrastructure Projects like Toll Roads .
20
Ways to finance an Infrastructure Project• Public Financing:
• Financed by a public entity.
• No private investment is involved (equity).
• Public support varies depending on the project: Revenue Bonds (e.g. NTTA projects) vs full support from state.
21
• Private Financing:• Financed with the
involvement of a private entity.
• Takes the form of a Public Private Partnership (P3).
• Different degrees of private and/or public support.
• The private investor invest equity at risk and expects a return.
22
• The main sources of funding are:• Equity: Provided by the Private Sector• Debt: Funded by the Capital Market (Bonds) or
Bank Loans• Public Support: Usually in the form of direct
subsidy or TIFIA Financing
Civil WorksRight of WayTolling SystemsAdvisors
Public Support
Debt
Equity Debt Interest & Fees
Reserve Accounts
Sources of Funds Uses of Funds
Transaction Cost
¿How is a typical P3 Project Financed?
OPEX & CAPEX
Project
Senior Debt
Equity
Toll collection & other revenues
O&M/Capex Providers
Capital markets/ banks debt service
Federal Government (TIFIA) other Public Entities
Sponsors: dividends payment
Debt like public support
23
P3 Typical Flow of Funds
05PPP Case Study: Indiana Toll Road
25
05. Indiana Toll Road
ITR Ticket System• 133 miles long, connects the Barrier
system to the Ohio Turnpike
• Closed system w/ 14 plazas
• Few viable alternatives, occasionally competes with SH-20 and I-94
• 1.2 billion VMT (40% trucks), 21 million transactions recorded in 2012
• Cars pay $0.06/mi (cash) or $0.03/mi (ETC tag)
• 5-axle trucks pay $0.24/mi
ITR Barrier System• 24 miles long, connects the Chicago
Skyway to the Ticket System
• Open tolling system w/ 8 plazas
• Strong competition with the I-94
• 431 million VMT (10% trucks), 26 million transactions recorded in 2012
• Cars pay $0.07/mi (cash) or $0.02/mi (ETC tag)
• 5-axle trucks pay $0.22/mi
Barrier System
26
05. Existing Traffic & Revenue
385 , 24%
47 , 3%
717 , 45%
436 , 28%
Share of VMT Traveled in 2012VMT in millions
Barrier Cars
Barrier Trucks
Ticket Cars
Ticket Trucks
28, 15%
10, 5%
42, 23%105, 57%
Share of Revenue Collected in 2012Revenue nominal USD, millions
Barrier Cars
Barrier Trucks
Ticket Cars
Ticket Trucks
Light vehicles make up about 70% of the miles traveled on the ITR, making cars the largest market in terms of both number of users and VMT.
Trucks are the most valuable asset to the ITR. 5-axle trucks (the most common variety) pay toll rates 3-4 times higher than cars and demonstrate an inelastic response to toll rate increases.Of the ITR’s $185m annual revenue, two-thirds comes from trucks.
27
05. Trend in Traffic & RevenueThe figures to the right show the average daily traffic on each ITR system in blue bars. Traffic is measured in full-length equivalent trips (FLET), which is calculated as VMT divided by the facility’s length.
The annual revenue (nominal) collected from tolls in each year is shown by the red line.
Note that while traffic has not recovered from the recession, revenue continues to increase as toll rates are increased annually.
0
5
10
15
20
25
30
35
40
0
10,000
20,000
30,000
40,000
50,000
60,000
70,000
80,000
2006 2007 2008 2009 2010 2011 2012
Revenue (mn)Traffic (AADT)
Barrier Traffic & Revenue
Traffic (AADT in FLET) Revenue ($ million)
0
25
50
75
100
125
150
0
5,000
10,000
15,000
20,000
25,000
30,000
2006 2007 2008 2009 2010 2011 2012
Revenue (mn)Traffic (AADT)
Ticket Traffic & Revenue
Traffic (AADT in FLET) Revenue ($ million)
28
Year 1956 1960 1965 1970 1975 1980 1985 1990 1995 2000 2005 2010 2015 2081
ITR Commission INDOT ITRCC
157 miles of JRCP Roadway Completed in
1956
HMA Resurfacing Cycles (1975-1992)
New Interchanges along ITR (1980s)
Lane Expansion & 10-year Bridge Capital
Improvement Plan
ETC Tolling System Implemented (2008)
End of Concession
05. Indiana Toll Road Project History• Publicity financed and constructed during the 1950s.• Began operations in 1956 giving motorists easy access
between the Midwest and the Eastern United States.• Operated by the Indiana Toll Road Commission from its
inception.• INDOT assumes operations in 1981 from ITR Commission.• In 2006, ITRCC took over operation of Toll road.• ETC Tolling System implemented in 2008. • As of 2013, over $300 million has been invested in
improvements to the ITR.
29
05. ITR Privatization Process Indiana Toll Road Privatization Process
January 2005
Governor Mitch Daniels begins his first term after winning the election in November 2004. In his first term he introduced the Major Moves Project, which included a 75 year lease of the Toll Road.
Winter 2005Gov. Daniels entrusted Meyer Brown, Goldman Sachs and Wilbur Smith as the advisors for the structuring of Indiana’s lease, using the Chicago Skyway model as a guide.
Spring 2005 The RFQ is released to the market
Summer 2005
The RFP is released to the market
Fall 2005Four bids were submitted for consideration with the winning bid going to Cintra-MIG, a 50/50 consortium, for $3.8 Billion.
Winter 2006 Legislation was passed for the Major Moves Project.
April 12, 2006
Contract for the ITR lease is signed and three months remained to financial close. (IFA represented the State of Indiana)
June 29, 2006
Financial close and transfer of operation to the Indiana Toll Road Concession Company.
30
05. ITR Risk Allocation Structure
IFA
Construction ETC Implementation
Delay Events
Environmental
Operation & Maintenance
Competing Facilities
ITRCC
PublicShared Private
Design
UnforeseenConditions
Approval Process
Oversight
Termination
ROW
Traffic & Revenue
Change in law
Financing
31
05. ITR PPP Contractual Structure
ITRCC
IFA
Ferrovial Agroman
Lenders
32
05. ITR Concession Agreement (I)• Lease Term: 75 years• Tolling Regime
• Tolls increased every July 1st by the greater of CPI, Nom GDP/capita or 2%
• Car tolls ‘freezed’ at 2006 rates for ETC users up to 2016
• Contract allows for certain toll optimization• IFA does not APPROVED new tolls but reviews
compliance with contractual regulation
33
05. ITR Concession Agreement (II)• Mandatory Expansion Works in Barrier Section
(Widening to 3+3 lanes of x miles)• Implementation of ETC system no later than
June 2008• Capacity Expansions triggered at LOS D in urban
areas and LOS C in rural areas• Performance Based Maintenance Standards
• Example: PavementsMeasurement Value
Length of the measurement stretch
Threshold
Average Entire ITR < 150 inches/mile
Average 1.0 miles < 170 inches/mile
Average 0.1 mile < 190 inches/mile
Average 1.0 mile < 3/8 inch
Average 0.1 mile < 5/8 inch
FNS Minimum - ≥ 30
Concession Lease Aggreement - Pavement Criteria
IRI
Rut
34
05. ITR Financing
Sources of Funds ($ '000) % Uses of Funds ($ '000) %
Bank debt 3,248,341 81.0% Purchase price 3,800,000 94.8%Equity 760,000 19.0% Due Diligence Fees 5,422 0.1%
Development Fees 55,900 1.4%Debt Stablishment Fees 46,728 1.2%Title Fees 291 0.0%Revenue Stabilization Res. 100,000 2.5%
TOTAL 4,008,341 100% TOTAL 4,008,341 100%
06CONCLUSIONS